This document contains a production schedule for a film project divided into pre-production, filming week, and post-production sections. Pre-production took place from November 20-24 and included developing character profiles, confirming actors, scriptwriting, storyboarding, and planning locations, music, props, and a weekly blog. Filming was scheduled for November 28-December 1 at various indoor and outdoor locations with different actors and crew each day. Post-production was scheduled from December 4-8 and included test editing, completing the first 3 minutes of the final edit, finishing the full edit, and conducting a peer screening and getting teacher feedback.
This document contains a production schedule for a film project divided into pre-production, filming week, and post-production sections. Pre-production took place from November 20-24 and included developing character profiles, confirming actors, scriptwriting, storyboarding, and planning locations, music, props, and a weekly blog. Filming was scheduled for November 28-December 1 at various indoor and outdoor locations with different actors and crew each day. Post-production was scheduled from December 4-8 and included test editing, completing the first 3 minutes of the final edit, finishing the full edit, and conducting a peer screening and getting teacher feedback.
This document contains a production schedule for a film project divided into pre-production, filming week, and post-production sections. Pre-production took place from November 20-24 and included developing character profiles, confirming actors, scriptwriting, storyboarding, and planning locations, music, props, and a weekly blog. Filming was scheduled for November 28-December 1 at various indoor and outdoor locations with different actors and crew each day. Post-production was scheduled from December 4-8 and included test editing, completing the first 3 minutes of the final edit, finishing the full edit, and conducting a peer screening and getting teacher feedback.
20/11/23 Production schedule & Same day Character Profiles 21/11/23 Actor confirmations & Same day Scriptwriting 22/11/23 Scriptwriting Same day 23/11/23 Storyboarding Same Day 24/11/23 Location Recces, Sound/Music Same day (maybe Saturday as list, Props list & Weekly blog well)
Filming Week
Date Time Location Actors Crew Equipment/
props 28/11/23 2-4pm Henley Me, Seth, Rupert Prop Pills, Prop Syringe, College Gym Kingston Gym Bags, Money, Tripod, Changing Camera Mounted Mic, Room Camera 27/11/23 3pm Home Me, Mum Mum, Tripod, Camera Mounted onwards Marcy Mic, Workbook, Letter, Camera 29/11/23 10:30 am- Braywick Gym Me Emma GoPro, Camera, Bottle 1pm 1/12/23 3-7pm Braywick Cris, Emma, GoPro, Camera, Tripod Leisure Rupert, Olivia Centre Me, Piers
Post Production
Date Activity Completion Date
4/12/23 Test edit 4/12/23 5/12/23 Start first 3 mins of final edit 5/12/23 6/12/23 Finish edit 7/12/23 8/12/23 Peer screening and teacher 8/12/23 feedback