Professional Documents
Culture Documents
Biswas Cold Storage
Biswas Cold Storage
Biswas Cold Storage
Repair and maintaince of work “BISWAS COLD STORAGE LIMITED” of Present Location-
Borohorishpur, Natore. The Estimate partle completed, Building side, Machinerage and Electfication. The
Estimate complete sa per market rate during the year-2011~2012.
Total Tk. ( Three Crore Thirty Three Lac's Ninty Three Thousand Three Hundred & Ninty Five ) only.
Details Estimated for the Construction of MD. AFSAR ALI S/O. Late. MOHIR UDDIN, Sinner
officer/Manager, Agrani Bank Ltd.Bagatipara Brance, Natore. Owners of Land MOST. NURZAHAN
BEGUM W/O MD.AFSAR ALI, of Present Location- Kanaikhali, P.O + P.S + Dist- Natore. Mouza-
Natore, J.L.No-SA- 204, RS-151, Khation No-SA-1448, RS-343, Plot No- SA-2866,RS-4401. Quantity of
Land Total = 5.50 Decimals. The Estimate complete the rate of L.G.E.D 2012-2013.(Rest Work Estimate)
Item No.02:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c caring etc. all complete as per direction of the E/I.
1 x 35'-8"x 48'-11"x 0-3" = 436.12 cft.
=12.35 m3
@Tk.6163.79 per m3 Tk. =76,122.80
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and labor etc. all
complete as per direction of the E/I.
16 x 7'-0"x 7'-0"x 5'-0" = 3920.00 cft
1 x 35'-8"x 48'-11"x 3'-0" = 5234.92 "
= 9154.92 cft.
= 259.27 m3
@ Tk.642.21 per m3 Tk. =1, 66,505.78
Item No.04:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Item No.05:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 17 x 17'-0"x 2 2 " x 6"=30.10 cft.
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75
=63.85 cft.
=1.80 m3
@ Tk.75943.71 per m3 Tk. =1, 36,698.67
Item No.06:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 17 x 3'-6"x 7'-0" =416.50 sft
W= 12 x 5'-0"x 4'-6" =270.00 sft.
=686.50 sft.
=63.80 m2
@ Tk.6384.61 per m2 Tk. =4, 07,338.11
Item No.07:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both side sand cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
1 Nos @ Tk.60,000.00 Tk. =60,000.00
Item No.08:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.40, 000.00 Tk. =40,000.00
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
SUMMARY
01
First Floor Rest Work Estimated Cost Tk. = 3,50,000.00
Details Estimated for the Construction of Four Storied Residential Building, Owner’s Name- RANENDRA
NARAYAN DAS, S/O:KSHITENDRANATH DAS, of Present Location-Borohirishpur, P.O + P.S + Dist-
Natore. Mouza-Borohirishpur, J.L.No:- RS-224, Khation No:- SA- 624, RS-434, Pro- 2580. Plot No- RS-
852. Quantity of Land Total = 6.50 Decimals. The Estimate completes.The rate of L.G.E.D 2012-2013.
(Ground Floor Rest Work Estimated Cost)
Item No.04:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c charring etc. all complete of the E/I.
Quantity Item No-03
Total = 5845.00 sft
= 543.21 m2
@ Tk.133.57 per m2 Tk. =72,556.55
Item No.05:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 60'-0"x 27'-6" = 1650.00 sft.
Skating: 2 x 390'-0"x 1'-6" = 1170.00 "
Toilet : 4 x 22'-0"x 6'-0" = 528.00"
Kitchen: 2 x 28'-0"x 6'-0" = 336.00"
Stair : 2 x 17'-5"x 3'-6" = 121.94"
Step : 22 x 3'-6"x 0'-10" = 64.14 "
" : 22 x 3'-6"x 0'-6" = 38.50"
= 3908.58 sft.
= 363.25 m2
@ Tk.1319.84 per m2 Tk. = 4, 79,431.88
Item No.06:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both side sand cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.07:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
Item No.08:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. =80,000.00
Item No.09:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 95,000.00
Contingency and unfor seen work L.S Tk.= 4,413.06
Total Tk= 15,00,000.00
Total Tk. (FifteenLac's) only.
Details Estimated for the Construction of (1) MD. ABDUL MANNAN S/O MD. YESAIN
SARDAR (2) MOST: AYASA KHATUN W/O MD. ABDUL MANNAN of Present Location- Vatodara,
P.O + P.S + Dist- Natore. Mouza- Amhati, J.L.No- RS-155, Khation No- RS- 327, Pro-2454, Plot No-RS-
3473. Quantity of Land Total = 3.05 Decimals. The Estimate complete the rate of L.G.E.D 2012-2013.
Item No.01:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total Wall = 1x 225'-0"x 10'-0"= 2250.00 sft.
Deduction Door and window:
D= 11 x 3'-0"x 6'-6" = 214.50 sft
W= 10 x 5'-0"x 4'-6" = 225.00 "
(-) = 439.50 sft
Net work = 1810.50 "
= 168.26 m2
@ Tk.622.14 per m2 Tk. = 1, 04,681.27
Item No.02:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
T.B : 1 x 228'-6"x 10"x 10" = 158.20 cft.
Lintel : 1 x 225'-0"x 5"x 6" = 47.25 "
Fools Slab : 2 x6'-0"x10'-0"x 4" = 39.50 "
" : 1x9'-0"x 4'-0"x 4" = 11.88 "
Sun sheet : 10 x 5'-0"x 1'-6" x 3" = 18.75"
Stair : 1 x 3'-0"x 12'-6"x 0'-10" = 31.23"
Step : 20x1/2x3'-6"x 0'-6" = 17.50 "
Roof Slab : 1 x 35'-9"x 26'-8"x5 " = 400.45 "
=724.76 cft
= 20.52 m3
@ Tk.9163.51 per m3 Tk. = 1, 88,035.22
Item No.03:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing etc.
complete as per direction of the E/I.
Quantity taken Item No-02
724.76 x 1.50 x 490 = 2416.00 kg
2.2046 x 100
Item No.05:
Manufacturing and supplying of Door's and Window's Penal Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Quantity Item No-01
Wall : 1810.50 sft x 2 = 3621.00 sft.
Ceiling: 1x 35'-0"x 26'-0" = 910.00 "
= 4531.00 sft
= 421.09 m2
@ Tk.167.01 per m2 Tk. = 70,326.24
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 4531.00sft
= 421.09 m2
@ Tk.133.57 per m2 Tk. = 56,244.99
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 4x 16'-0"x 6'-6" = 416.00 sft.
Kitchen : 2 x 22'-0"x 6'-6" = 286.00 "
Floor : 1 x 32'-9"x 23'-8" = 775.19 "
Skating: 2 x 225'-0"x 1'-6" = 675.00 "
Stair : 2 x 1'-6"x 15'-0" = 45.00 "
" : 20x 3'-0"x 0'-10" = 49.98 "
" : 20x 3'-0"x 0'-6" = 30.00 "
= 2277.17 sft.
= 211.63 m2
@ Tk.1319.84 per m2 Tk. =2, 79,317.73
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 65,000.00
Item No.10:
Distemper Work at Door, Window's and necessarygrills and etc. all
complete.
L.S Tk. = 55,000.00
Item No.11:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 95, 000.00
Contingency and unfor seen work L.S Tk. =9,346.05
Total Tk.= 15, 00,000.00
Total Tk. (Fifteen Lac's ) only.
Details Estimated for the Construction of Four Storied Commercial & Residential Building of MD.
HAFIZUR RAHAMAN S/O. Late-CHOIYEN UDDIN of Present Location-Village-Nurpur malonchi,
P.O + P.S-Bagatipara, Dist- Natore. Mouza- Kazla, J.L.No- RS-144, Khation No-SA-38, RS-268, Pro-
3209. Plot No:-SA-320, RS-1810.Thana:-Boalia, Dist:- Rajshahi. Quantity of Land Total =4.95 Decimals.
The Estimate complete the rate of L.G.E.D 2012-2013.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
T.B : 1 x 278'-0"x 10"x 10" = 192.90 cft.
Lintel : 1 x 310'-0"x 5"x 6" = 65.10 "
Fools Slab : 2 x9'-8"x4'-0"x 4" = 25.52 "
Sun sheet : 5 x 4'-6"x 1'-6" x 4" = 11.13"
Stair : 1 x 4'-0"x 14'-6"x 0'-10" = 46.64"
Step : 20x1/2x4'-0"x 0'-6" = 20.00"
Roof Slab : 1 x 42'-5"x 34'-2"x5 " = 608.60 "
= 969.89 cft
= 27.46 m3
@ Tk.9163.51 per m3 Tk. = 2, 51,629.98
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing etc.
complete as per direction of the E/I.
Quantity taken Item No-02
969.89 x 1.75 x 490 = 3772.50 kg
2.2046 x 100
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total Wall = 1x 125'-0"x 9'-6"= 1187.50 sft.
= 110.36 m2
@ Tk.622.14 per m2 Tk. = 68,659.37
Item No.04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 80,000.00
Item No.10:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =1,00,000.00
Item No.11:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. =1, 90,000.00
Contingency and unfor seen work L.S Tk. = 11,696.22
Total Tk.= 21, 00,000.00
Total Tk.(Twenty One Lac’s) Only.
Details Estimated for the Construction of Four Storied Commercial & Residential Building of MD.
HAFIZUR RAHAMAN S/O. Late-CHOIYEN UDDIN of Present Location-Village-Nurpur malonchi,
P.O + P.S-Bagatipara, Dist- Natore. Mouza- Kazla, J.L.No- RS-144, Khation No-SA-38, RS-268, Pro-
3209. Plot No:-SA-320, RS-1810.Thana:-Boalia, Dist:- Rajshahi. Quantity of Land Total =4.95 Decimals.
The Estimate complete the rate of L.G.E.D 2012-2013.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
T.B : 1 x 278'-0"x 10"x 10" = 192.90 cft.
Lintel : 1 x 310'-0"x 5"x 6" = 65.10 "
Fools Slab : 2 x9'-8"x4'-0"x 4" = 25.52 "
Sun sheet : 5 x 4'-6"x 1'-6" x 4" = 11.13"
Stair : 1 x 4'-0"x 14'-6"x 0'-10" = 46.64"
Step : 20x1/2x4'-0"x 0'-6" = 20.00 "
Roof Slab : 1 x 42'-5"x 34'-2"x5 " = 608.60 "
= 969.89 cft
= 27.46 m3
@ Tk.9163.51 per m3 Tk. = 2, 51,629.98
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing etc.
complete as per direction of the E/I.
Quantity taken Item No-02
969.89 x 1.70 x 490 = 3664.69 kg
2.2046 x 100
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total Wall = 1x 125'-0"x 9'-6"= 1187.50 sft.
= 110.36 m2
@ Tk.622.14 per m2 Tk. = 68,659.37
Item No.04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Item No.08:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 65,000.00
Item No.09:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 85, 000.00
Contingency and unfor seen work L.S Tk. = 7,025.30
Total Tk.= 15, 00,000.00
Total Tk.(Fifteen Lac’s) Only.
SUMMARY
Details Estimated for the Construction of Four Storied Residential Building of MD.SHAJAHAN
ALI GAGI, S/O. BASHIR UDDIN GAGI of Present Location-Kanaikhali, P.O + P.S+ Dist- Natore.
Mouza- Natore, J.L.No-SA-204, RS-151, Khation No-SA-1509, RS-343. Plot No:-4356, 4357. Quantity of
Land Total = 2.50 Decimals. The Estimate complete the rate of L.G.E.D 2012-2013.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
T.B : 3 x 30'-0"x 10"x 10" = 62.45 cft.
T.B : 4 x 19'-0"x 10"x 10" = 52.73 cft.
Lintel : 3 x 30'-0"x 5"x 6" = 18.90 "
Lintel : 4 x 19'-0"x 5"x 6" = 15.96 "
Fools Slab : 1 x4'-0"x9'-10"x 4" = 12.98 "
Sun sheet : 5 x 4'-6"x 1'-6" x 4" = 11.13"
Stair : 2 x 6'-0"x 3'-6"x 6" = 21.00"
Step : 20x1/2x3'-0"x 6"x10 " = 12.50"
Roof Slab : 1 x 30'-0"x 19'-0"x5 " = 239.40 "
= 447.05 cft
= 12.66 m3
@ Tk.9163.51 per m3 Tk. = 1, 16,010.03
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing etc.
complete as per direction of the E/I.
Quantity taken Item No-02
447.05 x 1.70 x 490 = 1690.00 kg
2.2046 x 100
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total Wall = 1x 125'-0"x 9'-6"= 1187.50 sft.
= 110.36 m2
@ Tk.622.14 per m2 Tk. = 68,659.37
Item No.04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 125'-0"x 12'-0" = 3000.00 sft.
Ceiling: 1x 35'-0"x 24'-0" = 840.00"
= 3840.00 sft
= 356.87 m2
@ Tk.167.01 per m2 Tk. = 59,600.85
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 3840.00 sft
= 356.87 m2
@ Tk.133.57 per m2 Tk. =47,667.12
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 7 x 17'-0"x 3" x 6" = 14.88 cft.
Item No.07:
Manufacturing and supplying of Door's and Window's Penal Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 7 x 3'-6"x 7'-0" = 171.50 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
= 306.50 sft
= 28.48 m2
@ Tk.6384.61 per m2 Tk. = 1, 81,833.69
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 2x 22'-0"x 6'-6" = 286.00 sft.
Kitchen : 1 x 42'-0"x 6'-6" = 273.00 "
Floor : 1 x 35'-0"x 24'-0" = 840.00 "
Skating: 2 x 225'-0"x 1'-6" = 675.00 "
Stair : 2 x 1'-6"x 15'-0" = 45.00 "
" : 20x 3'-6"x 0'-10" = 58.31 "
" : 20x 3'-6"x 0'-6" = 35.00 "
= 2212.31 sft.
= 205.60 m2
@ Tk.1319.84 per m2 Tk. = 2, 71,359.10
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. =70,000.00
Item No.10:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 60,000.00
Item No.11:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. =1, 20,000.00
Contingency and unfor seen work L.S Tk. = 2,299.03
Total Tk.= 12, 00,000.00
Total Tk.(Twelve Lac’s) Only.
Details Estimated for the Construction of Four Storied Residential Building of “HOJROT AISHA
SIDDIKA (R:) BALIKA MADRASHA” of Present Location-Dayervatuya, P.O + P.S + Dist- Natore.
Mouza-Vita, J.L.No:- RS-144, Khation No:- RS-38,504, Pro-1592. Plot No- RS-2808,2809. Quantity of
Land Total = 6.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Item No.12:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No- 11
Total = 7826.65 sft
= 727.38 m2
@ Tk.133.57 per m2 Tk. = 97,156.14
Item No.13:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 49'-8"x 41'-0" = 2043.15sft
Skating: 1 x 668'-0"x 1'-6" = 1002.00 "
Toilet : 2 x 40'-0"x 7'-0" = 560.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x4'-0"x 0'-10" = 66.64 "
" : 20x 4'-0"x 0'-6" = 40.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x2'-6"x 0'-10" = 41.65 "
" : 20x 2'-6"x 0'-6" = 25.00 "
= 3874.44 sft. = 360.07 m2
@ Tk.1319.84 per m2 Tk. = 4, 75,234.78
Item No.14:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 315'-6"x 9'-6" = 2997.25 sft
Deduction Door and window:
D = 4 x 3'-0"x 6'-6" = 78.00 sft
W = 11 x 5'-0"x 4'-6" = 247.50 "
(-) = 325.50 sft
Net work = 2671.75 "
= 248.30 m2
@ Tk.622.14 per m2 Tk. = 1, 54,477.36
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 4 x 17'-0"x 2.5" x 6" = 7.08 cft
W = 12 x 27'-0"x 2.5"x 6" = 33.74 "
= 40.82 cft
= 1.15 m3
@ Tk.75943.71 per m3 Tk. =
87,335.26
Item No.05:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 4 x 3'-6"x 7'-0" = 98.00 sft
W = 12 x 5'-0"x 4'-6" = 270.00 "
= 368.00 sft
= 34.20 m2
@ Tk.6384.61 per m2 Tk. = 2, 18,353.66
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Quantity Item No-03
Wall : 2671.75 sft. x 2 = 5343.50 sft
Ceiling : 1x 52'-10"x 47'-0" = 2483.15 "
= 7826.65 sft
= 727.38 m2
@ Tk.167.01 per m2 Tk. = 1, 21,479.73
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 7826.65 sft
= 727.38 m2
@ Tk.133.57 per m2 Tk. = 97,156.14
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 49'-8"x 41'-0" = 2043.15sft
Skating: 1 x 668'-0"x 1'-6" = 1002.00 "
Toilet : 2 x 40'-0"x 7'-0" = 560.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x4'-0"x 0'-10" = 66.64 "
" : 20x 4'-0"x 0'-6" = 40.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x2'-6"x 0'-10" = 41.65 "
" : 20x 2'-6"x 0'-6" = 25.00 "
= 3874.44 sft. = 360.07 m2
@ Tk.1319.84 per m2 Tk. = 4, 75,234.78
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 75,000.00
Item No.10:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Contingency and unfor seen work L.S Tk.= 9,762.71
Total Tk = 23,00,000.00
Details Estimated for the Construction of Four Storied Residential Building of “HOJROT AISHA
SIDDIKA (R:) BALIKA MADRASHA” of Present Location-Dayervatuya, P.O + P.S + Dist- Natore.
Mouza-Vita, J.L.No:- RS-144, Khation No:- RS-38,504, Pro-1592. Plot No- RS-2808,2809. Quantity of
Land Total = 6.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 315'-6"x 9'-6" = 2997.25 sft
Deduction Door and window:
D = 4 x 3'-0"x 6'-6" = 78.00 sft
W = 11 x 5'-0"x 4'-6" = 247.50 "
(-) = 325.50 sft
Net work = 2671.75 "
= 248.30 m2
@ Tk.622.14 per m2 Tk. = 1, 54,477.36
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 4 x 17'-0"x 2.5" x 6" = 7.08 cft
W = 12 x 27'-0"x 2.5"x 6" = 33.74 "
= 40.82 cft
= 1.15 m3
@ Tk.75943.71 per m3 Tk. =
87,335.26
Item No.05:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 4 x 3'-6"x 7'-0" = 98.00 sft
W = 12 x 5'-0"x 4'-6" = 270.00 "
= 368.00 sft
= 34.20 m2
@ Tk.6384.61 per m2 Tk. = 2, 18,353.66
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Quantity Item No-03
Wall : 2671.75 sft. x 2 = 5343.50 sft
Ceiling : 1x 52'-10"x 47'-0" = 2483.15 "
= 7826.65 sft
= 727.38 m2
@ Tk.167.01 per m2 Tk. = 1, 21,479.73
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 7826.65 sft
= 727.38 m2
@ Tk.133.57 per m2 Tk. = 97,156.14
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 49'-8"x 41'-0" = 2043.15sft
Skating: 1 x 668'-0"x 1'-6" = 1002.00 "
Toilet : 2 x 40'-0"x 7'-0" = 560.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x4'-0"x 0'-10" = 66.64 "
" : 20x 4'-0"x 0'-6" = 40.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x2'-6"x 0'-10" = 41.65 "
" : 20x 2'-6"x 0'-6" = 25.00 "
= 3874.44 sft. = 360.07 m2
@ Tk.1319.84 per m2 Tk. = 4, 75,234.78
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 75,000.00
Item No.10:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Contingency and unfor seen work L.S Tk.=1,72,762.71
Total Tk = 24,00,000.00
Details Estimated for the Construction of Four Storied Residential Building of “HOJROT AISHA
SIDDIKA (R:) BALIKA MADRASHA” of Present Location-Dayervatuya, P.O + P.S + Dist- Natore.
Mouza-Vita, J.L.No:- RS-144, Khation No:- RS-38,504, Pro-1592. Plot No- RS-2808,2809. Quantity of
Land Total = 6.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 315'-6"x 9'-6" = 2997.25 sft
Deduction Door and window:
D = 4 x 3'-0"x 6'-6" = 78.00 sft
W = 11 x 5'-0"x 4'-6" = 247.50 "
(-) = 325.50 sft
Net work = 2671.75 "
= 248.30 m2
@ Tk.622.14 per m2 Tk. = 1, 54,477.36
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 4 x 17'-0"x 2.5" x 6" = 7.08 cft
W = 12 x 27'-0"x 2.5"x 6" = 33.74 "
= 40.82 cft
= 1.15 m3
@ Tk.75943.71 per m3 Tk. =
87,335.26
Item No.05:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 4 x 3'-6"x 7'-0" = 98.00 sft
W = 12 x 5'-0"x 4'-6" = 270.00 "
= 368.00 sft
= 34.20 m2
@ Tk.6384.61 per m2 Tk. = 2, 18,353.66
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Quantity Item No-03
Wall : 2671.75 sft. x 2 = 5343.50 sft
Ceiling : 1x 52'-10"x 47'-0" = 2483.15 "
= 7826.65 sft
= 727.38 m2
@ Tk.167.01 per m2 Tk. = 1, 21,479.73
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 7826.65 sft
= 727.38 m2
@ Tk.133.57 per m2 Tk. = 97,156.14
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 49'-8"x 41'-0" = 2043.15sft
Skating: 1 x 668'-0"x 1'-6" = 1002.00 "
Toilet : 2 x 40'-0"x 7'-0" = 560.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x4'-0"x 0'-10" = 66.64 "
" : 20x 4'-0"x 0'-6" = 40.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x2'-6"x 0'-10" = 41.65 "
" : 20x 2'-6"x 0'-6" = 25.00 "
= 3874.44 sft. = 360.07 m2
@ Tk.1319.84 per m2 Tk. = 4, 75,234.78
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 75,000.00
Item No.10:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Contingency and unfor seen work L.S Tk.=2,72,762.71
Total Tk = 25,00,000.00
ESTIMATED COST
Details Estimated for the Construction of Four Storied Residential Building of “HOJROT AISHA
SIDDIKA (R:) BALIKA MADRASHA” of Present Location-Dayervatuya, P.O + P.S + Dist- Natore.
Mouza-Vita, J.L.No:- RS-144, Khation No:- RS-38,504, Pro-1592. Plot No- RS-2808,2809. Quantity of
Land Total = 6.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013
SUMMARY
ESTIMATED COST
Details Estimated for the Construction of MD. AFTUB UDDINS/O Late BAZON UDDIN, of
Present Location- North Borgacha, P.O + P.S + Dist- Natore. Mouza- Borgacha, J.L.No-SA- 71, RS-146,
Khation No-SA- 713, Plot No-SA-1989, RS-3957. Quantity of Land Total = 5.00 Decimals.The Estimate
completes. The rate of L.G.E.D 2012-2013
Item No.02:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Boundary Wall: - 2x 200'-0"x 5'-6" = 2200.00 sft.
Parapet Wall: - 2x 180'-0"x 3'-6" = 1260.00 sft.
Garage Wall: - 2x 65'-0"x 10'-0" = 1300.00 sft.
= 4760.00 sft.
= 442.37 m2
@ Tk.167.01 per m2 Tk. = 73,880.21
Item No. 03:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Boundary Wall: - 2x 200'-0"x 5'-6" = 2200.00 sft.
Parapet Wall: - 2x 180'-0"x 3'-6" = 1260.00 sft.
Garage Wall: - 2x 65'-0"x 10'-0" = 1300.00 sft.
= 4760.00 sft.
= 442.37 m2
@ Tk.133.57 per m2 Tk. = 59,087.36
Item No.04:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 2x 13'-0"x 14'-0" = 364.00 sft
Kitchen : 1x32'-0"x6'-0" = 192.00 "
Floor : 1x 37'-6"x 37'-6" =1406.25"
Skating : 1x315'-0"x 1'-6" = 472.50 "
Stair : 20x3'-6"x0'-10" = 58.31 "
Step : 20x3'-6"x 0'-6" = 35.00 "
= 2528.06 sft.
= 234.94 m2
@ Tk.1319.84 per m2 Tk. = 3, 10,083.20
Item No.05:
Required size of Water Reserve 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
1 Nos@ Tk.2, 10,000.00 Tk. = 1, 40,000.00
Item No.06:
Supplying fitting and fixing of collapsible gate and necessary grill's &
Chillachota mating etc. all complete of E/I.
L.S Tk. =80,000.00
Item No.07:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. =90,000.00
Contingency and unfor seen work L.S Tk.= 9,344.31
Total Tk = 9,00,000.00
Total Tk. (Nine Lac's) only.
Details Estimated for the Construction of Four Storied Residential Building, Owner’s Name-
RANENDRA NARAYAN DAS, S/O:KSHITENDRANATH DAS, of Present Location-Borohirishpur, P.O
+ P.S + Dist- Natore. Mouza-Borohirishpur, J.L.No:- RS-224, Khation No:- SA- 624, RS-434, Pro- 2580.
Plot No- RS- 852. Quantity of Land Total = 6.50 Decimals. The Estimate completes. The rate of L.G.E.D
2012-2013.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 14 x 17'-0"x 2 2 " x 6" = 24.79 cft
1
W = 10 x 27'-0"x 2 2 "x 6" = 28.12 "
= 52.91 cft
=1.49 m3
@ Tk.75943.71 per m3 Tk. = 1, 13,156.12
Item No.05:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 14 x 3'-6"x 7'-0" = 343.00 sft
W = 10 x 5'-0"x 4'-6" = 225.00 "
= 568.00 sft
= 52.78 m2
@ Tk.6384.61 per m2 Tk. = 3, 36,979.71
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Quantity Item No-03
Wall : 2356.75 sft x 2 = 4713.50 sft
Ceiling: 1x 40'-0"x 32'-0" = 1280.00 "
= 5993.50 sft
= 557.01 m2
@ Tk.167.01 per m2 Tk. =93,026.24
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 5993.50 sft
= 557.01 m2
@ Tk.133.57 per m2 Tk. = 74,399.82
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 2 x 28'-0"x 6'-0" = 336.00 "
Kitchen : 1 x 38'-0"x 8'-0" = 304.00 "
Stair : 2 x 16'-0"x 1'-6" = 48.00 "
Step : 20x4'-0"x 0'-10" = 66.64 "
" : 20x 4'-0"x 0'-6" = 40.00 "
= 794.64 sft.
= 73.85 m2
@ Tk.1319.84 per m2 Tk. = 97,470.18
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
12 x 6'-0"x 4'-6" = 324.00sft.
=30.11 m2
@ Tk.1547.74 per m2 Tk. =46,602.45
Item No.10:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 90,000.00
Item No.11:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. =1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. =2,50,000.00
Contingency and unfor seen work L.S Tk.= 78,373.23
Total Tk =21,00,000.00
Total Tk. (Twenty OneLac's) only.
Details Estimated for the Construction of MD. AFSAR ALI S/O. Late. MOHIR UDDIN, Sinner
officer/Manager, Agrani Bank Ltd.Bagatipara Brance, Natore. Owners of Land MOST. NURZAHAN
BEGUM W/O MD.AFSAR ALI, of Present Location- Kanaikhali, P.O + P.S + Dist- Natore. Mouza-
Natore, J.L.No-SA- 204, RS-151, Khation No-SA-1448, RS-343, Plot No- SA-2866,RS-4401. Quantity of
Land Total = 5.50 Decimals. The Estimate complete the rate of L.G.E.D 2012-2013.(Rest Work Estimate)
Item No.02:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c caring etc. all complete as per direction of the E/I.
1 x 35'-8"x 48'-11"x 0-3" = 436.12 cft.
=12.35 m3
@Tk.6163.79 per m3 Tk. =76,122.80
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and labor etc. all
complete as per direction of the E/I.
16 x 7'-0"x 7'-0" x 5'-0" = 3920.00 cft
1 x 35'-8"x 48'-11"x 3'-0" = 5234.92 "
= 9154.92 cft.
= 259.27 m3
@ Tk.642.21 per m3 Tk. =1, 66,505.78
Item No.04:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Item No.05:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 17 x 17'-0"x 2 2 " x 6"=30.10 cft.
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75
=63.85 cft.
=1.80 m3
@ Tk.75943.71 per m3 Tk. =1, 36,698.67
Item No.06:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 17 x 3'-6"x 7'-0" =416.50 sft
W= 12 x 5'-0"x 4'-6" =270.00 sft.
=686.50 sft.
=63.80 m2
@ Tk.6384.61 per m2 Tk. =4, 07,338.11
Item No.07:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both side sand cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
1 Nos @ Tk.60,000.00 Tk. =60,000.00
Item No.08:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.40, 000.00 Tk. =40,000.00
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 16 x 17'-0"x 2 2 " x 6" = 28.33 cft
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75 "
= 62.08 cft
=1.75m3
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I
Quantity Item No-03
Wall : 3137.25 sft x 2 = 6274.50 sft
Ceiling : 1x 35'-8"x 48'-11" = 1744.48 "
= 8018.98 sft
= 745.25 m2
@ Tk. 154.13 per m2 Tk. =1, 14,866.67
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 8018.98 sft
= 745.25 m2
@ Tk. 112.32 per m2 Tk. = 83,706.48
Item No.08:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
Item No.09:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 16 x 17'-0"x 2 2 " x 6" = 28.33 cft
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75 "
= 62.08 cft
= 1.75m3
Item No.08:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
Item No.09:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
Item No.02:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Boundary Wall: - 2x 200'-0"x 5'-6" = 2200.00 sft.
Parapet Wall: - 2x 180'-0"x 3'-6" = 1260.00 sft.
Wall: - 2x 65'-0"x 10'-0" = 1300.00 sft.
= 4760.00 sft.
= 442.37 m2
@ Tk.167.01 per m2 Tk. = 73,880.21
Item No. 03:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Boundary Wall: - 2x 200'-0"x 5'-6" = 2200.00 sft.
Parapet Wall: - 2x 180'-0"x 3'-6" = 1260.00 sft.
Wall: - 2x 65'-0"x 10'-0" = 1300.00 sft.
= 4760.00 sft.
= 442.37 m2
@ Tk.133.57 per m2 Tk. = 59,087.36
Item No.04:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 2x 13'-0"x 14'-0" = 364.00 sft
Kitchen : 1x32'-0"x6'-0" = 192.00 "
Floor : 1x 37'-6"x 37'-6" =1406.25"
Skating : 1x315'-0"x 1'-6" = 472.50 "
Stair : 20x3'-6"x0'-10" = 58.31 "
Step : 20x3'-6"x 0'-6" = 35.00 "
= 2528.06 sft.
= 234.94 m2
@ Tk.1319.84 per m2 Tk. = 3, 10,083.20
Item No.05:
Required size of Water Reserve 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
1 Nos@ Tk.2, 10,000.00 Tk. = 1, 40,000.00
Item No.06:
Supplying fitting and fixing of collapsible gate and necessary grill's &
Chillachota mating etc. all complete of E/I.
L.S Tk. = 80,000.00
Item No.07:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Contingency and unfor seen work L.S Tk.= 9,344.31
Total Tk = 9,00,000.00
Total Tk. (Nine Lac's) only.
Details Estimated for the Three Storied Construction of S.M GOLAM AZAM, of Present Location-
Kanaikhali, P.O + P.S + Dist- Natore. Mouza- Natore, J.L.No-SA- 204, RS-151, Khation No-SA-254,
RS-1848,PRO-2242,2243. Plot No- SA-2836,RS-4404. Quantity of Land Total = 5.00 Decimals. The
Estimate complete the rate of L.G.E.D 2012-2013.(Rest Work Estimate)
Item No.05:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 4x32'-0"x 6'-6" = 832.00 sft
Kitchen : 2x35'-0"x 8'-0" = 560.00 "
Floor : 1x 66'-0"x 28'-6" = 1881.00"
Skating : 1x315'-0"x 1'-6" = 472.50 "
Stair : 20x4'-0"x0'-10" = 66.64 "
Step : 20x4'-0"x 0'-6" = 40.00"
= 3852.14 sft.
= 358.00 m2
@ Tk.1319.84 per m2 Tk. = 4, 72,502.72
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 17 x 17'-0"x 2 2 " x 6"=30.10 cft.
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75
=63.85 cft.
=1.80 m3
@ Tk.75943.71 per m3 Tk. =1, 36,698.67
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 17 x 3'-6"x 7'-0" =416.50 sft
W = 12 x 5'-0"x 4'-6" =270.00 sft.
=686.50 sft.
=63.80 m2
@ Tk.6384.61 per m2 Tk. =4, 07,338.11
Item No.08:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
Details Estimated for the Three Storied Construction of MST. JAHANARA KHURSHIDA, W/O.
SAHADATH HOSSAIN,of Present Location- Kandivetua, P.O+P.S & Dist- Natore, Mouza-Vita, J.L.No-
SA-202, RS-144.Khation No:-SA-13, RS-141, PRO-843, Plot No:-SA-769,RS-4636, 4637. Quantity of
Land Total = 5.35 Decimals. The Estimate completed the rate of L.G.E.D 2012-2013.
Details Estimated for the Three Storied Construction of MST. JAHANARA KHURSHIDA, W/O.
SAHADATH HOSSAIN,of Present Location- Kandivetua, P.O+P.S & Dist- Natore, Mouza-Vita, J.L.No-
SA-202, RS-144.Khation No:-SA-13, RS-141, PRO-843, Plot No:-SA-769,RS-4636, 4637. Quantity of
Land Total = 5.35 Decimals. The Estimate completed the rate of L.G.E.D 2012-2013.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Item No.03:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
Outer wall- 1x 135'-6"x 12'-0"x 0'-10" = 1354.45 cft.
M. bed- 1x 51'-2"x 10'-0"x 0'-10" = 426.16 "
Steady- 1x 36'-8"x 10'-0"x 0'-10" = 305.46 "
Drawing- 1x 46'-2"x 10'-0"x 0'-10" = 384.51 "
Dining- 1x 53'-8"x 10'-0"x 0'-10" = 447.07 "
Kitchen- 1x 33'-8"x 10'-0"x 0'-10" = 280.47 "
Toilet- 1x 21'-0"x 10'-0"x 0'-10" = 166.60 "
" 1x 21'-8"x 10'-0"x 0'-10" = 180.51 "
Stair- 1x 45'-8"x 19'-0"x 0'-10" = 722.81 "
= 4268.04 cft.
Deduction Door and window:
D= 3 x 3'-6"x 6'-6"x 0'-10" = 56.85 cft
D1 = 2 x 3'-0"x 6'-6"x 0'-10" = 32.48 "
D2 = 4 x 2'-6"x 6'-6"x 0'-10" = 54.14 "
W= 5 x 5'-0"x 4'-0"x 0'-10" = 83.30 "
W1 = 2 x 3'-0"x 4'-0"x 0'-10" = 19.99"
F/L = 2 x 2'-0"x 1'-6" x 0'-10" = 4.99 "
(-) = 251.75 cft
Net work = 4016.29 "
= 113.74 m3
@ Tk.4243.87 per m3 Tk. = 4, 82,697.77
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 9 x 17'-0"x 3 " x 10" = 31.86 cft
W = 8 x 27'-0"x 3" x 10" = 44.98 "
= 76.84 cft
= 2.17 m3
Item No.05:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 9 x 3'-6"x 7'-0" = 409.50 sft
W= 8 x 5'-0"x 4'-6" = 180.00 "
= 589.50 sft
= 54.78 m2
@ Tk.6384.61 per m2 Tk. = 3, 49,748.93
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I
Outer wall- 2x 135'-6"x 12'-0" = 3240.00 sft.
M. bed- 2x 51'-2"x 10'-0" = 1023.20 "
Steady- 2x 36'-8"x 10'-0" = 733.40 "
Drawing- 2x 46'-2"x 10'-0" = 923.20 "
Dining- 2x 53'-8"x 10'-0" = 1073.40 "
Kitchen- 2x 33'-8"x 10'-0" = 673.40 "
Toilet- 2x 21'-0"x 10'-0" = 420.00 "
" 2x 21'-8"x 10'-0" = 433.40 "
Stair- 1x 45'-8"x 19'-0" = 867.73 "
Ceiling : 1x 54'-0"x 21'-0" = 1071.00 "
= 10458.73 sft.
Deduction Door and window:
D= 3 x 3'-6"x 6'-6" = 68.25 sft
D1 = 2 x 3'-0"x 6'-6" = 39.00 "
D2 = 4 x 2'-6"x 6'-6" = 65.00 "
W= 5 x 5'-0"x 4'-0" = 100.00 "
W1 = 2 x 3'-0"x 4'-0" = 24.00"
F/L = 2 x 2'-0"x 1'-6" = 6.00 "
(-) = 302.25 sft
Net work = 10156.48 "
= 943.91 m2
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 10156.48 sft
= 943.91 m2
@ Tk.133.57 per m2 Tk. = 1, 26,078.05
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Toilet : 2x22'-0"x 6'-6" = 286.00 sft
Kitchen : 1x35'-0"x 8'-0" = 280.00 "
Floor : 1x 50'-9"x 17'-6" = 888.12"
Skating : 2x240'-0"x 1'-6" = 720.00 "
Stair : 20x3'-0"x0'-10" = 49.98 "
Step : 20x3'-0"x 0'-6" = 30.00"
= 2254.10 sft.
= 209.48 m2
@ Tk.1319.84 per m2 Tk. = 2, 76,480.08
Item No.09:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 80,000.00
Item No.10:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
Details Estimated for the Construction of Three Storied Building of “BAHADURPUR PURATONPARA
JAME MOSQUE” of Present Location-Village-Bahadurpur(puratonpara), P.O-Chamary, P.S-singra, Dist-
Natore. Mouza-Bahadurpur, J.L.No:-SA-628,RS-393. Khation No:-RS-408. Plot No-SA-158, RS-764.
Quantity of Land Total = 5.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
3 x 14'-6"x 4'-6" x 8'-0" = 1566.00 cft
6 x 5'-6"x 5'-6" x 8'-0" = 1452.00 "
1 x 6'-0"x 6'-0" x 8'-0" = 288.00 "
2 x 5'-0"x 5'-0" x 8'-0" = 400.00 "
1 x 37'-0"x 39'-6"x 4'-0" = 5846.00"
1 x 8'-0"x 7'-0" x 4'-0" = 224.00 "
= 9776.00 cft.
= 276.86 m3
@ Tk.642.21 per m3 Tk. = 1, 77,802.26
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Total- 1510.00sft x 0'-3" = 377.50 cft.
= 10.69 m2
@ Tk.6163.79 per m3 Tk. = 65,890.91
Item No.05:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
Base : 3 x 14'-6" x 4'-6"x 1'-2" = 227.07 cft
Base : 6 x 5'-6" x 5'-6"x 1'-4" = 241.39 "
Base : 1 x 6'-0" x 6'-0"x 1'-6" = 54.00 "
Base : 2 x 5'-0" x 5'-0"x 1'-4" = 66.50 "
Footing Pillar : 6 x 1'-1" x 1'-1"x 8'-0" = 55.98 "
Footing Pillar : 9 x 1'-1" x 1'-6"x 8'-0" = 116.64 "
Vertical Pillar : 6 x0'-10" x 0'-10"x 12'-0" = 49.96 "
(P.T.O)
Vertical Pillar : 9 x0'-10" x 1'-3"x 12'-0" = 112.45 "
G.B : 1 x 338'-0"x 10"x 15" = 351.94 "
T.B : 1 x 338'-0"x 10"x 10" = 234.53 "
Lintel : 1 x 191'-0"x 10"x 10" = 132.53 "
Sun sheet : 4 x 1'-6"x 5'-0" x 3" = 7.50 "
Roof Slab : 1 x40'-0"x44'-0"x 5" = 739.20 "
Roof Slab : 1 x12-0"x10'-0"x 5" = 50.40 "
Stair : 2 x 5'-0"x 16'-6"x 6" = 82.50 "
Step : 20x1/2x5'-0"x 6"x10" = 20.82 "
= 2543.41 cft
= 72.03 m3
@ Tk.9163.51 per m3 Tk. = 6, 60,047.62
Item No.06:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Quantity taken Item No-05
2543.41 x 1.70 x 490 = 9610.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. = 7, 20,557.80
Item No.07:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
Item No.08:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 2 x 20'-0"x 3" x 10" = 8.33 cft
W= 4 x 30'-0"x 3"x 10" = 24.99 "
= 33.32 cft
= 0 .94 m3
@ Tk.75943.71 per m3 Tk. =
71,387.08
Item No.09:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 2 x 5'-6"x 7'-6" = 82.50 sft
W= 4 x 5'-0"x 4'-6" = 90.00 "
= 172.50 sft
= 16.03 m2
@ Tk.6384.61 per m2 Tk. = 1, 02,345.29
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I.
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No- 11
Total = 6570.00 sft
= 610.59 m2
@ Tk.133.57 per m2 Tk. = 81,556.50
Item No.12:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 45'-0"x 50'-0" = 2250.00sft
Skating: 2 x 191'-0"x 1'-6" = 573.00 "
Maharab: 1 x 25'-0"x 10'-0" = 250.00 "
Stair : 2 x 16'-0"x 5'-0" = 160.00 "
Step : 20x5'-0"x 0'-10" = 83.30 "
" : 20x 5'-0"x 0'-6" = 50.00 "
= 3366.30 sft.
= 312.85 m2
@ Tk.1319.84 per m2 Tk. = 4, 12,911.94
Item No.13:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.15:
Required size of Water Reserve 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Details Estimated for the Three Storied Construction of MST. JAHANARA KHURSHIDA,
W/O. SAHADATH HOSSAIN,of Present Location- Kandivetua, P.O+P.S & Dist- Natore, Mouza-Vita,
J.L.No-SA-202, RS-144.Khation No:-SA-13, RS-141, PRO-843, Plot No:-SA-769,RS-4636, 4637. Quantity
of Land Total = 5.35 Decimals. The Estimate completed the rate of L.G.E.D 2012-2013.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Item No.03:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
Outer wall- 1x 135'-6"x 12'-0"x 0'-10" = 1354.45 cft.
M. bed- 1x 51'-2"x 10'-0"x 0'-10" = 426.16 "
Steady- 1x 36'-8"x 10'-0"x 0'-10" = 305.46 "
Drawing- 1x 46'-2"x 10'-0"x 0'-10" = 384.51 "
Dining- 1x 53'-8"x 10'-0"x 0'-10" = 447.07 "
Kitchen- 1x 33'-8"x 10'-0"x 0'-10" = 280.47 "
Toilet- 1x 21'-0"x 10'-0"x 0'-10" = 166.60 "
" 1x 21'-8"x 10'-0"x 0'-10" = 180.51 "
Stair- 1x 45'-8"x 19'-0"x 0'-10" = 722.81 "
= 4268.04 cft.
Deduction Door and window:
D= 3 x 3'-6"x 6'-6"x 0'-10" = 56.85 cft
D1 = 2 x 3'-0"x 6'-6"x 0'-10" = 32.48 "
D2 = 4 x 2'-6"x 6'-6"x 0'-10" = 54.14 "
W= 5 x 5'-0"x 4'-0"x 0'-10" = 83.30 "
W1 = 2 x 3'-0"x 4'-0"x 0'-10" = 19.99"
F/L = 2 x 2'-0"x 1'-6" x 0'-10" = 4.99 "
(-) = 251.75 cft
Net work = 4016.29 "
= 113.74 m3
@ Tk.4243.87 per m3 Tk. = 4, 82,697.77
Item No.04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I
Outer wall- 2x 135'-6"x 12'-0" = 3240.00 sft.
M. bed- 2x 51'-2"x 10'-0" = 1023.20 "
Steady- 2x 36'-8"x 10'-0" = 733.40 "
Drawing- 2x 46'-2"x 10'-0" = 923.20 "
Dining- 2x 53'-8"x 10'-0" = 1073.40 "
Kitchen- 2x 33'-8"x 10'-0" = 673.40 "
Toilet- 2x 21'-0"x 10'-0" = 420.00 "
" 2x 21'-8"x 10'-0" = 433.40 "
Stair- 1x 45'-8"x 19'-0" = 867.73 "
Ceiling : 1x 54'-0"x 21'-0" = 1071.00 "
= 10458.73 sft. (P.T.O)
Deduction Door and window:
D= 3 x 3'-6"x 6'-6" = 68.25 sft
D1 = 2 x 3'-0"x 6'-6" = 39.00 "
D2 = 4 x 2'-6"x 6'-6" = 65.00 "
W= 5 x 5'-0"x 4'-0" = 100.00 "
W1 = 2 x 3'-0"x 4'-0" = 24.00"
F/L = 2 x 2'-0"x 1'-6" = 6.00 "
(-) = 302.25 sft
Net work = 10156.48 "
= 943.91 m2
@ Tk.167.01 per m2 Tk. =1, 57,642.40
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 10156.48 sft
= 943.91 m2
@ Tk.133.57 per m2 Tk. = 1, 26,078.05
Item No.06:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
NAME OF PROJECT:-
TITLE ~ FOUR (04) STORIED BUILDING.
DESIGN BY:-
MD. MOSTAFA KAMAL
Sub- Assistant Engineer
Naldanga Pourashava, Natore.
Mobile No. 01715973441.
DRAWN BY:-
MD. SAIFUDDIN
Dip-In Civil Engineer
Nichabazar, Natore.
Mobile No. 01712557208.
Details Estimated for the Construction of MD. AFSAR ALI S/O. Late. MOHIR UDDIN, Sinner
officer/Manager, Agrani Bank Ltd.Bagatipara Brance, Natore. Owners of Land MOST. NURZAHAN
BEGUM W/O MD.AFSAR ALI, of Present Location- Kanaikhali, P.O + P.S + Dist- Natore. Mouza-
Natore, J.L.No-SA- 204, RS-151, Khation No-SA-1448, RS-343, Plot No- SA-2866,RS-4401. Quantity of
Land Total = 5.50 Decimals. The Estimate completed the rate of L.G.E.D 2012-2013.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
1
D = 16 x 17'-0"x 2 2 " x 6" = 28.33 cft
1
W = 12 x 27'-0"x 2 2 "x 6" = 33.75 "
= 62.08 cft
= 1.75m3
Item No.09:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 80,000.00
Item No.10:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 90,000.00
Item No.11:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 1, 40,000.00
Contingency and unfor seen work L.S Tk.= 3,453.76
Total Tk =20,00,000.00
Total Tk. (TwentyLac's) only.
Details Estimated for the Construction of MD. AFSAR ALI S/O. Late. MOHIR UDDIN, Sinner
officer/Manager, Agrani Bank Ltd.Bagatipara Brance, Natore. Owners of Land MOST. NURZAHAN
BEGUM W/O MD.AFSAR ALI, of Present Location- Kanaikhali, P.O + P.S + Dist- Natore. Mouza-
Natore, J.L.No-SA- 204, RS-151, Khation No-SA-1448, RS-343, Plot No- SA-2866,RS-4401. Quantity of
Land Total = 5.50 Decimals. The Estimate completed the rate of L.G.E.D 2012-2013.
SUMMARY
Signature of Principal
Details Estimated for the Construction of JAMSHED ALI S/O-MD.KARIM UDDIN MRIDHA, of Present
Location- Kanaikhali, P.O + P.S + Dist- Natore. Mouza- Natore, J.L.No-SA- 204, RS-151, Khation No-SA-
301, RS-181, PRO-5497. Plot No- SA-2839,2840, RS-4366. Quantity of Land Total = 5.00 Decimals. The
Estimate completed the rate of L.G.E.D 2012-2013.
Plinth Area = 1233.00 sft
Second Floor Estimated Cost Tk. = 20, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course
sand (minimum FM 1.80) and 20mm downgraded Stone chips as per
design in base, bed beam, raft foundation, grade beam or anywhere in
below plinth level including cost of reinforcement & its fabrication etc.
all complete as per direction of the E/I.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing
including straightening removing: use if any cranking looking bending
binding with 22 BAG wire etc. all complete supported on mortar blocks
(1:3) with cement & sand metal chairs & hangers as per drawing &
direction etc. complete as per direction of the E/I.
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 350'-0"x 9'-6" = 3325.00 sft
Deduction Door and window :
D= 14 x 3'-0"x 6'-6" = 273.00 sft
W= 7 x 5'-0"x 4'-6" = 157.50 "
(-) = 430.50 sft
Net work = 2894.50 "
= 269.00 m2
@ Tk.622.14 per m2 Tk. =1, 67,355.66
Item No.04:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction
of the E/I.
D = 14 x 17'-0"x 3" x 6" = 29.75 cft
Item No.06:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing
the surfaces, rounding of corners and junctions, curing including cost of
all materials and their carrying etc. complete as per specifications and
direction of the E/I
Quantity Item No-03
Wall : 2894.50 sft x 2 = 5789.00 sft
Ceiling : 1x 37'-7"x 33'-0" = 1240.14 "
= 7029.14 sft
= 653.26 m2
@ Tk. 167.01 per m2 Tk. = 1, 09,100.95
Item No.07:
Distemper work at wall and ceiling two coat over a coat as per
approved color in/c carrying etc. all complete of the E/I.
Quantity Item No-06
Total = 7029.14 sft
= 653.26 m2
@ Tk.133.57 per m2 Tk. = 87,255.93
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as
per approved Choice in/c carrying and finishing etc. all complete of
E/I.
Floor : 1 x 37'-7"x 33'-0" = 1240.14sft
Skating: 2 x 350'-0"x 1'-6" = 1050.00 "
Toilet: 2 x 26'-0"x 8'-0" = 416.00 "
Kitchen: 2 x 30'-0"x 8'-0" = 480.00 "
Stair : 2 x 14'-0"x 3'-6" = 98.00 "
Step : 20x3'-6"x 0'-10" = 58.31 "
" : 20x 3'-6"x 0'-6" = 35.00 "
= 3377.45 sft.
= 313.88 m2
@ Tk.1319.84 per m2 Tk. = 4, 14,271.37
Item No.09:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 60,000.00
Item No.10:
Supplying fitting and fixing of collapsible gate and necessary grill's
etc. all complete of E/I.
L.S Tk. = 80,000.00
Item No.11:
Supplying fitting and fixing of Sanitary, Water Supply and
Electrification work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Contingency and unfor seen work L.S Tk.=4620.59
Total Tk =20,00,000.00
Total Tk. (Twenty Lac's) only.
DETAILS ESTIMATED
Details Estimated for the Construction of “ZINNAPARA TANZILUL KURAN MADRASHA JAME
MOSQUE”of Present Location-Village-Zinnapara, P.O-Dharil, P.S+ Dist.- Natore. Mouza-Zinnapara,
J.L.No:-RS-237. Khation No:-SA-223,RS-131. Plot No-SA-355, RS-479. Quantity of Land Total =10.00
Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Plinth Area =1973.00 sft.
TotalEstimated Cost Tk =25,00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
F-1&F-2 = 8 x 6'-0"x 6'-0" x 8'-0" = 2304.00 cft
F-3 = 2 x 7'-0"x 7'-0" x 8'-0" = 784.00 cft
F-4 = 2 x 8'-0"x 8'-0" x 8'-0" = 1024.00 cft
= 4112.00 cft.
= 116.45 m3
@ Tk.74.39 per m3 Tk. =8,663.03
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
F-1&F2 = 8 x 6'-0"x 6'-0" = 288.00 sft.
F-3 = 2 x 7'-0"x 7'-0" = 98.00 "
F-4 = 2 x 8'-0"x 8'-0" = 128.00 "
Floor =1 x 1973.00 sft. x 1 = 1973.00 "
= 2487.00 sft.
= 231.13 m2
@ Tk.229.63 per m2 Tk. =53,075.26
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
F-1&F-2 = 8 x 6'-0"x 6'-0" x 4'-0" = 1152.00 cft.
F-3 = 2 x 7'-0"x 7'-0" x 4'-0" = 392.00 cft.
F-4 = 2 x 8'-0"x 8'-0" x 4'-0" = 512.00 cft.
Floor =1x1973.00 sft.x 2'-0" = 3946.00 cft.
= 2450.00 cft.
= 69.38 m3
@ Tk.642.21 per m3 Tk. = 44,560.02
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Total- 1x 1973.00 sft x 0'-3" = 493.25 cft.
= 13.97 m3
@ Tk.6163.79 per m3 Tk. = 86,102.78
Item No.05:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base : 8 x 6'-0" x 6'-0"x 1'-4" = 383.04 cft.
Base : 2 x 7'-0" x 7'-0"x 1'-6" = 147.00 "
Base : 2 x 8'-0" x 8'-0"x 1'-7" = 202.24 "
Footing Pillar : 12 x 1'-1" x 1'-6"x 6'-0" = 116.64 "
Vertical Pillar : 12 x0'-10" x1'-3"x 12'-0" = 149.94 "
G.B : 1 x 305'-0"x 10"x 15" = 317.58 "
T.B : 1 x 305'-0"x 10"x 12" = 254.06 "
Lintel : 1 x235'-0"x 10"x 10" = 163.06 "
Sun-sheet : 4 x5'-0"x 2'-0"x 4" = 13.20 "
Roof Slab : 1 x 1973.00 sft. x 6" = 986.50"(P.T.O)
= 2733.26 cft
= 77.40 m3
@ Tk.9163.51 per m3 Tk. = 7,09,324.70
Item No.06:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-05
2733.26 x 1.20 x 490 = 7290.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,46,604.20
Item No.07:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with Portland
cement and sand (minimum FM 1.50) including racking out joints curing
etc. complete as per design including supply carrying & cost of all
materials
1 x 190'-0"x 10"x 9'-6" = 1503.56 cft.
= 42.58 m3
@ Tk.4243.87 per m3 Tk.=1,80,703.98
Item No. 08:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 190'-0"x 10'-0" = 3800.00 sft
Ceiling: 1x 1973.00 sft.x1 = 1973.00 "
= 5773.00 sft
= 536.52 m2
@ Tk.167.01 per m2 Tk. =89,604.90
Item No.09:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-08
Total = 5773.00 sft
= 536.52 m2
@ Tk.133.57 per m2 Tk. = 71,662.97
Item No.10:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 3 x 17'-0"x 4 " x 6" = 8.14 cft
Item No.12:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.13:
Paint Work at Door, Window's and necessary grills and etc. all complete.
L.S Tk. = 60,000.00
Item No.14:
Supplying fitting and fixing of collapsible gate and necessary grill's as per
Approveddesign etc. all complete of E/I.
L.S Tk. = 60,000.00
Item No.15:
Supplying fitting and fixing of Sanitary, Water Supply and other’s work
etc. all complete of the E/I.
L.S Tk. = 45,000.00
Item No.16:
Contingency for unfor Seen work L.S Tk.= 9,909.44
Total Tk =25,00,000.00
Total Tk. (Twenty FiveLac’s) Only.
ESTIMATE COST CERTIFICATE
(Title in questions may be discussed with legal adviser)
This is to certify that the Residential and Commercial Land of DR. MD. NAZMUL HUSSAIN (TUHIN)
S/O. MD. ABDUS SUKUR SARKAR, of present Location- Dhakin Patuapara, Natore and assessed the
present market value (per-haps) below as:-
Total Tk. (Fourteen Lac’s Forty Four Thousand and Five Hundred One) only.
DETAILS ESTIMATED
Details Estimated for thefour storied Residential Construction of 1. MD. SELIM RAZA, S/O. MD.
ABDUR RAZZAK PK. 2.MD. ABDUR RAZZAK PK, S/O. LATE. KOSER PK.of Present Location-
Village-Kusum hate, P.O-Bepathuria, P.S-Gurudaspur, Dist.- Natore. Mouza-Bepathuria, J.L.No:-RS-37.
Khation No:-PRO-185. Plot No:-SA-413, RS-40. Quantity of Land Total =5.00 Decimals. The Estimate
completes. The rate of L.G.E.D 2012-2013.
Plinth Area =2155.77 sft.
TotalEstimated Cost Tk =48,00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Trench = 1 x 408'-0"x 5'-0" x 7'-0" = 14280.00 cft
= 404.41 m3
@ Tk.74.39 per m3 Tk. =30,084.05
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Floor = 1 x 52'-2"x 41'-4" = 2155.77 sft.
= 200.35 m2
@ Tk.229.63 per m2 Tk. =40,140.12
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Floor =1x 2155.77 sft.x 4'-0" = 8623.08 cft.
= 244.21 m3
@ Tk.642.21 per m3 Tk. =1,56,834.10
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor = 1x 21550.77 sft x 0'-4" = 711.40 cft.
= 20.14 m3
@ Tk.6163.79 per m3 Tk. =1,24,138.73
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) custing in/c carring etc. all
complete of E/I.
Wall- = 448'-0"x 0'-10" = 373.18 sft
= 34.68 m2
@ Tk. 585.39 per m3 Tk.=20,301.32
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Lintel : 1 x 485'-0"x 10"x 10" = 336.53cft.
Sun-sheet : 6 x5'-0"x 2'-0"x 4" = 19.80 "
Fools Slab : 3 x 9'-0"x 7'-0"x 4" = 62.37 "
Fools Slab : 1 x 10'-0"x 15'-0"x 4" = 49.50 "
Fools Slab : 1 x 13'-0"x 7'-0"x 4" = 30.03 "
Roof Slab : 1 x 2220.77 sft. x 6" = 1110.38"
= 1608.61 cft
= 45.55 m3
@ Tk.9163.51 per m3 Tk. = 4,17,397.88
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
1608.61 x 1.50 x 490 = 5363.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =4,02,117.74
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with Portland
cement and sand (minimum FM 1.50) including racking out joints curing
etc. complete as per design including supply carrying & cost of all
materials
1 x 485'-0"x 10"x 9'-6" = 3838.04 cft.
= 108.69 m3
@ Tk.5243.87 per m3 Tk.=5,69,956.23
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 590'-0"x 10'-0" = 11800.00 sft
Ceiling: 1x 2250.00 sft. = 2250.00 "
= 14050.00 sft
= 1305.76 m2
@ Tk.167.01 per m2 Tk. =2,18,074.97
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total = 14050.00 sft
= 1305.76 m2
@ Tk.133.57 per m2 Tk. =1,74,410.36
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 14 x 17'-0"x 4 " x 6" = 39.27 cft
Item No.16:
Supplying fitting and fixing of Sanitary, Water Supply,Electrification and
other’s work etc. all complete of the E/I.
L.S Tk. = 3,60,000.00
Item No.17:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.18:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.1,50, 000.0 Tk. = 1,50,000.00
Item No.19:
Required size of Water Reserve 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
1 Nos@ Tk.2, 40,000.00 Tk. = 2,40,000.00
Item No.20:
The structure consists of Brick Boundary wall by (1:4) sand cement in/c
250mm thick superstructure wall by approved sand cement mortar in/c
copping etc. all complete of E/I.
L.S Tk=1,90,000.00
Item No.21:
Contingency for unfor Seen work L.S Tk.= 16,650.86
Total Tk =48,00,000.00
Total Tk. (Forty Eight Lac’s) Only.
DETAILS ESTIMATED
Details Estimated for the four storied Residential Construction of MD. MASHIUR RAHMAN
KHAN,S/O-LATE. KHALILUT RAHMAN KHAN M/O. MST. KAMRUN NESA of Present Location-
Village-Dhakin Borgacha, P.O-Natore, P.S-Natore, Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146.
Khation No:-CS-1018, SA-754,RS-695,PRO-5385. Plot No:-SA-1588,1589 RS-3723. Quantity of Land
Total =5.00 Decimals. The Estimate completes. The rate of L.G.E.D 2012-2013.
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Item No.16:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.1,50, 000.0 Tk. = 40,000.00
Item No.17:
Contingency for unfor Seen work L.S Tk.= 6,672.83
Total Tk =18,00,000.00
Total Tk. ( Eighteen Lac’s) Only.
DETAILS ESTIMATED FOR GROUND FLOOR
Details Estimated for the four storied Residential Construction of MD. MASHIUR RAHMAN KHAN,
S/O-LATE. KHALILUT RAHMAN KHAN M/O. MST. KAMRUN NESA of Present Location-Village-
Dhakin Borgacha, P.O-Natore, P.S-Natore, Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146. Khation
No:-CS-1018, SA-754,RS-695,PRO-5385. Plot No:-SA-1588,1589 RS-3723. Quantity of Land Total =5.00
Decimals. The Estimate completes. The rate of L.G.E.D 2013-2014.
(This Drawing FOUR Storied Foundation)
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor = 1x 24'-0"x 35'-0" x 0'-4" = 277.20 cft.
= 7.85 m3
@ Tk.6163.79 per m3 Tk. =48,385.75
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- = 195'-0"x 0'-5" = 81.90 sft
= 7.61 m2
@ Tk. 585.39 per m3 Tk. =4,454.81
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base :11 x 7'-0"x 7'-0" x 1'-7" = 851.62 cft.
Footing Column :11 x 1'-3"x 1'-6"x 8'-0" = 165.00 "
Vertical Column :11 x 1'-0"x 1'-3"x 12'-0" = 165.00 "
Grade Beam :1 x 195'-0"x 0'-10"x 1'-3" = 203.04 "
Tai-Beam :11 x 1'-3"x 1'-6"x 8'-0" = 165.00 "
Lintel :1 x 230'-0"x 0'-5"x 0'-6" = 48.30 "
Sun-sheet :6 x 5'-0"x 2'-0"x 4" = 19.80 "
Fools Slab :1 x 13'-0"x 5'-0"x 4" = 21.45 "
Fools Slab :1 x 8'-0"x 7'-6"x 4" = 19.80 "
Roof Slab :1 x 24'-0"x 35'-0" x 5" = 352.80 "
= 2011.81 cft
= 56.97 m3
@ Tk.6288.79 per m3 Tk. =3, 58,272.36
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Item No.16:
Required size of soak well 5'-0" & 15'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.80, 000.0 Tk. = 80,000.00
Item No.17:
Contingency for un for Seen work L.S Tk.= 16,672.83
Total Tk =19,00,000.00
Total Tk. (Nineteen Lac’s) only.
DETAILS ESTIMATED FOR GROUND FLOOR
Details Estimated for the Five storied Residential of KHANDAKER ABDUL MANNAN, S/O-MD.
KHANDAKER MAHTAB ALI, of Present Location-Village-Dhakin Borgacha, P.O-Natore, P.S-Natore,
Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146. Khation No:-SA-111,RS-714,PRO-460. Plot No:-
RS-3777 &3778. Quantity of Land Total =2.98 Decimals. The Estimate completes. The rate of L.G.E.D
2013-2014.
Plinth Area =762.79 sft.
Ground Floor TotalEstimated Cost Tk. =32, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base- 12 x 7'-0"x 7'-0" x 10'-0" = 5880.00 cft
= 166.52 m3
@ Tk.74.39 per m3 Tk. =12,387.79
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base 12 x 7'-0"x 7'-0" = 588.00 sft.
Floor 1 x 24'-0"x 35'-0" = 840.00 sft.
= 1428.00 sft.
= 132.71 m2
@ Tk.229.63 per m2 Tk. =30,475.05
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base Column 12 x 7'-0"x 7'-0" x 5'-0" = 2940.00 cft
Floor 1x 24'-0"x 35'-0" x 4'-0" = 3360.00 cft.
=6300.00 cft.
= 178.41 m3
@ Tk.642.21 per m3 Tk. =1, 14,582.29
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor = 1x 24'-0"x 35'-0" x 0'-4" = 277.20 cft. =7.85 m3
@ Tk.6163.79 per m3 Tk. =48,385.75
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- = 195'-0"x 0'-5" = 81.90 sft
= 7.61 m2
@ Tk. 585.39 per m3 Tk. =4,454.81
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base :12 x 7'-0"x 7'-0" x 1'-7" = 929.04 cft.
Footing Column :12 x 1'-3"x 1'-6"x 8'-0" = 180.00 "
Vertical Column :12x 1'-0"x 1'-3"x 12'-0" = 180.00 "
Grade Beam :1 x 195'-0"x 0'-10"x 1'-3" = 203.04 "
Tai-Beam :1 x 195'-0"x 0'-10"x 0'-10" = 135.30 "
Lintel :1 x 230'-0"x 0'-5"x 0'-6" = 48.30 "
Sun-sheet :6 x 5'-0"x 2'-0"x 4" = 19.80 "
Stair : 2 x 4'-0"x 15'-9"x 6" = 63.00"
Step : 20x1/2x4'-0"x 6"x10" = 16.66"
Fools Slab :3 x 5'-6"x 6'-6"x 4" = 35.39 "
Roof Slab :1 x 24'-0"x 35'-0" x 5" = 352.80 "
= 2163.33 cft = 61.26 m3
@ Tk.9568.64 per m3 Tk. =5, 86,174.88
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2163.33 x 2.0 x 490 = 9616.54 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =7, 21,048.16
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x 118'-0"x 10"x 3'-6" = 344.02 cft. =9.75 m3
@ Tk.4243.87 per m3 Tk. = 41,377.73
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 230'-0"x 9'-6" = 2185.00 sft
Deduction Door and window:
D = 9 x 3'-0"x 5'-6" = 148.50 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
(-) = 283.50 sft
Net work = 1901.50 "
= 176.71 m2
@ Tk.622.14 per m2 Tk. =1, 09,938.35
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1901.50 sft = 3803.00 sft
Ceiling: 1x 832.21 sft. = 832.21 "
= 4635.21 sft
= 430.78 m2
@ Tk.167.01 per m2 Tk. =71,944.56
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total = 4635.21 sft
= 430.78 m2
@ Tk.133.57 per m2 Tk. =57,539.28
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 9 x 17'-0"x 4 " x 4" = 16.66 cft
W = 6 x 27'-0"x 4"x 4" = 17.64 "
= 34.30 cft
= 0.97 m3
Item No.13:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 9 x 2'-6"x 6'-6" = 146.25 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
= 281.25 sft
= 26.13 m2
@ Tk.6384.61 per m2 Tk. = 1, 66,829.85
Item No.14:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =70,000.00
Item No.15:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
12 x 6'-0"x 4'-6" = 324.00sft.
=30.11 m2
@ Tk.1547.74 per m2 Tk. =46,602.45
Item No.16:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
SUMMARY
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, over heat water
tank and Electrification other’s work etc. all complete of the E/I.
L.S Tk. = 2, 50,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 58,548.62
Total Tk =18,00,000.00
Total Tk. (Eighteen Lac’s) only.
DETAILS ESTIMATED FOR SECOND FLOOR
Details Estimated for the Five storied Residential of KHANDAKER ABDUL MANNAN, S/O-MD.
KHANDAKER MAHTAB ALI, of Present Location-Village-Dhakin Borgacha, P.O-Natore, P.S-Natore,
Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146. Khation No:-SA-111,RS-714,PRO-460. Plot No:-
RS-3777 &3778. Quantity of Land Total =2.98 Decimals. The Estimate completes. The rate of L.G.E.D
2013-2014.
Plinth Area =762.79 sft.
Second Floor TotalEstimated Cost Tk. =19, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Tai-Beam :1 x 195'-0"x 0'-10"x 0'-10" = 135.30 "
Lintel :1 x 230'-0"x 0'-5"x 0'-6" = 48.30 "
Sun-sheet :6 x 5'-0"x 2'-0"x 4" = 19.80 "
Stair : 2 x 4'-0"x 15'-9"x 6" = 63.00"
Step : 20x1/2x4'-0"x 6"x10" = 16.66 "
Fools Slab :3 x 5'-6"x 6'-6"x 4" = 35.39 "
Roof Slab :1 x 24'-0"x 35'-0" x 5" = 352.80 "
= 671.25 cft
= 19.00 m3
@ Tk.9568.64 per m3 Tk. = 1, 81,804.16
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
671.25 x 2.0 x 490 = 2983.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2, 23,665.34
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 230'-0"x 9'-6" = 2185.00 sft
Deduction Door and window:
D = 9 x 3'-0"x 5'-6" = 148.50 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
(-) = 283.50 sft
Net work = 1901.50 " = 176.71 m2
@ Tk.622.14 per m2 Tk. =1, 09,938.35
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1901.50 sft = 3803.00 sft
Ceiling: 1x 832.21 sft. = 832.21 "
= 4635.21 sft =430.78 m2
@ Tk.167.01 per m2 Tk. =71,944.56
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 4635.21 sft =430.78 m2
@ Tk.133.57 per m2 Tk. =57,539.28
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 9 x 17'-0"x 4 " x 4" = 16.66 cft
W = 6 x 27'-0"x 4"x 4" = 17.64 "
= 34.30 cft =0.97 m3
@ Tk.75943.71 per m3 Tk. = 73,665.39
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 9 x 2'-6"x 6'-6" = 146.25 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
= 281.25 sft
= 26.13 m2
@ Tk.6384.61 per m2 Tk. = 1, 66,829.85
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
12 x 6'-0"x 4'-6" = 324.00sft.
=30.11 m2
@ Tk.1547.74 per m2 Tk. =46,602.45
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, over heat water
tank and Electrification other’s work etc. all complete of the E/I.
L.S Tk. = 2, 50,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 1,58,548.62
Total Tk =19,00,000.00
Total Tk. (Nineteen Lac’s) only.
DETAILS ESTIMATED FOR THIRD FLOOR
Details Estimated for the Five storied Residential of KHANDAKER ABDUL MANNAN, S/O-MD.
KHANDAKER MAHTAB ALI, of Present Location-Village-Dhakin Borgacha, P.O-Natore, P.S-Natore,
Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146. Khation No:-SA-111,RS-714,PRO-460. Plot No:-
RS-3777 &3778. Quantity of Land Total =2.98 Decimals. The Estimate completes. The rate of L.G.E.D
2013-2014.
Plinth Area =762.79 sft.
Third Floor TotalEstimated Cost Tk. =20, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Tai-Beam :1 x 195'-0"x 0'-10"x 0'-10" = 135.30 "
Lintel :1 x 230'-0"x 0'-5"x 0'-6" = 48.30 "
Sun-sheet :6 x 5'-0"x 2'-0"x 4" = 19.80 "
Stair : 2 x 4'-0"x 15'-9"x 6" = 63.00"
Step : 20x1/2x4'-0"x 6"x10" = 16.66 "
Fools Slab :3 x 5'-6"x 6'-6"x 4" = 35.39 "
Roof Slab :1 x 24'-0"x 35'-0" x 5" = 352.80 "
= 671.25 cft
= 19.00 m3
@ Tk.9568.64 per m3 Tk. = 1, 81,804.16
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
671.25 x 2.0 x 490 = 2983.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2, 23,665.34
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 230'-0"x 9'-6" = 2185.00 sft
Deduction Door and window:
D = 9 x 3'-0"x 5'-6" = 148.50 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
(-) = 283.50 sft
Net work = 1901.50 " = 176.71 m2
@ Tk.622.14 per m2 Tk. =1, 09,938.35
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1901.50 sft = 3803.00 sft
Ceiling: 1x 832.21 sft. = 832.21 "
= 4635.21 sft =430.78 m2
@ Tk.167.01 per m2 Tk. =71,944.56
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 4635.21 sft =430.78 m2
@ Tk.133.57 per m2 Tk. =57,539.28
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 9 x 17'-0"x 4 " x 4" = 16.66 cft
W = 6 x 27'-0"x 4"x 4" = 17.64 "
= 34.30 cft =0.97 m3
@ Tk.75943.71 per m3 Tk. = 73,665.39
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 9 x 2'-6"x 6'-6" = 146.25 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
= 281.25 sft
= 26.13 m2
@ Tk.6384.61 per m2 Tk. = 1, 66,829.85
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 70,000.00
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
12 x 6'-0"x 4'-6" = 324.00sft.
=30.11 m2
@ Tk.1547.74 per m2 Tk. =46,602.45
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, over heat water
tank and Electrification other’s work etc. all complete of the E/I.
L.S Tk. = 2, 50,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 2,58,548.62
Total Tk =20,00,000.00
Total Tk. (Twenty Lac’s) only.
DETAILS ESTIMATED FOR FOURTH FLOOR
Details Estimated for the Five storied Residential of KHANDAKER ABDUL MANNAN, S/O-MD.
KHANDAKER MAHTAB ALI, of Present Location-Village-Dhakin Borgacha, P.O-Natore, P.S-Natore,
Dist.-Natore. Mouza-Borgacha, J.L.No:-SA-71,RS-146. Khation No:-SA-111,RS-714,PRO-460. Plot No:-
RS-3777 &3778. Quantity of Land Total =2.98 Decimals. The Estimate completes. The rate of L.G.E.D
2013-2014.
Plinth Area =762.79 sft.
Fourth Floor TotalEstimated Cost Tk. =21, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Tai-Beam :1 x 195'-0"x 0'-10"x 0'-10" = 135.30 "
Lintel :1 x 230'-0"x 0'-5"x 0'-6" = 48.30 "
Sun-sheet :6 x 5'-0"x 2'-0"x 4" = 19.80 "
Stair : 2 x 4'-0"x 15'-9"x 6" = 63.00"
Step : 20x1/2x4'-0"x 6"x10" = 16.66 "
Fools Slab :3 x 5'-6"x 6'-6"x 4" = 35.39 "
Roof Slab :1 x 24'-0"x 35'-0" x 5" = 352.80 "
= 671.25 cft
= 19.00 m3
@ Tk.9568.64 per m3 Tk. = 1, 81,804.16
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
671.25 x 2.0 x 490 = 2983.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2, 23,665.34
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Total= 1x 230'-0"x 9'-6" = 2185.00 sft
Deduction Door and window:
D = 9 x 3'-0"x 5'-6" = 148.50 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
(-) = 283.50 sft
Net work = 1901.50 " = 176.71 m2
@ Tk.622.14 per m2 Tk. =1, 09,938.35
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1901.50 sft = 3803.00 sft
Ceiling: 1x 832.21 sft. = 832.21 "
= 4635.21 sft =430.78 m2
@ Tk.167.01 per m2 Tk. =71,944.56
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 4635.21 sft =430.78 m2
@ Tk.133.57 per m2 Tk. =57,539.28
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 9 x 17'-0"x 4 " x 4" = 16.66 cft
W = 6 x 27'-0"x 4"x 4" = 17.64 "
= 34.30 cft =0.97 m3
@ Tk.75943.71 per m3 Tk. = 73,665.39
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 9 x 2'-6"x 6'-6" = 146.25 sft
W = 6 x 5'-0"x 4'-6" = 135.00 "
= 281.25 sft
= 26.13 m2
@ Tk.6384.61 per m2 Tk. = 1, 66,829.85
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. = 70,000.00
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
12 x 6'-0"x 4'-6" = 324.00sft.
=30.11 m2
@ Tk.1547.74 per m2 Tk. =46,602.45
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, over heat water
tank and Electrification other’s work etc. all complete of the E/I.
L.S Tk. = 2, 50,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 3,58,548.62
Total Tk =21,00,000.00
Total Tk. (Twenty One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the three storied Residential building of MD. ABED ALI, FATHER’S NAME LATE
ABDUL HAMID of Present Location-Village-Naldanga Hat, P.O-Naldanga, P.S-Naldanga, Dist.-Natore.
Mouza-Naldanga, J.L.No:-RS-37. Khation No:-RS-51,PRO-456. Plot No:-RS-1038. Quantity of Land Total
=7.125 Decimals. The Estimate completes. The rate of L.G.E.D 2013-2014.
Plinth Area =2238.17 sft.
Ground Floor TotalEstimated Cost Tk. =66, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-6"x 6'-6" x 8'-0" = 1352.00 cft
Base-F-2 8 x 7'-6"x 7'-6" x 8'-0" = 3600.00 cft
Base-F-3 3 x 8'-0"x 8'-0" x 8'-0" = 1536.00 cft
Base-F-4 6 x 16'-0"x 8'-0" x 8'-0" = 6144.00 cft
=12632.00 cft. =357.74 m3
@ Tk.74.39 per m3 Tk. =26,612.27
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-6"x 6'-6" = 169.00 sft.
Base-F-2 8 x 7'-6"x 7'-6" = 450.00 sft.
Base-F-3 3 x 8'-0"x 8'-0" = 192.00 sft.
Base-F-4 6 x 16'-0"x 8'-0" = 768.00 sft.
Floor 1 x 83'-8"x 26'-9" = 2238.17 sft.
= 3817.17 sft. =354.75 m2
@ Tk.229.63 per m2 Tk. =81,461.24
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 5'-0" = 720.00 cft
Base-F-2 8 x 7'-0"x 7'-0" x 5'-0" = 1960.00 cft
Base-F-3 3 x 7'-6"x 7'-6" x 5'-0" = 843.75 cft
Base-F-4 6 x 15'-0"x 7'-0" x 5'-0" = 3150.00 cft
Floor 1x 83'-8"x 26'-9" x 3'-0" = 6714.51 cft.
= 13388.26 cft.
= 379.16 m3
@ Tk.642.21 per m3 Tk. =2, 43,500.34
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 83'-8"x 26'-9" x 0'-4" = 738.59 cft. = 20.91m3
@ Tk.6163.79 per m3 Tk. = 1, 28,931.07
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 3x 83'-8"x 0'-5" = 105.42sft.
Wall- 9x 26'-9"x 0'-5" = 101.11sft.
= 206.53 sft.
= 19.19 m2
@ Tk. 585.39 per m3 Tk. =4,454.81
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" = 191.52 cft
Base-F-2 :8 x 7'-0"x 7'-0" x 1'-6" = 588.00 "
Base-F-3 :3 x 7'-6"x 7'-6" x 1'-7" = 266.62 "
Base-F-4 :6 x 15'-0"x 7'-0" x 1'-8" = 1052.10 "
Footing C-1 :4 x 1'-3"x 1'-3"x 7'-0" = 43.75 "
Footing C-2 :8 x 1'-1"x 1'-6" x 7'-0" = 90.72 "
Footing C-3 :3 x 1'-3"x 1'-7"x 7'-0" = 41.47 "
Footing C-4 :12 x 1'-3"x 1'-9" x 7'-0" = 183.75 "
Vertical C-1 :4 x 1'-0"x 1'-0"x 10'-0" = 40.00 "
Vertical C-2 :8 x 0'-10"x 1'-3" x 10'-0" = 83.30 "
Vertical C-3 :3 x 1'-0"x 1'-4" x 10'-0" = 39.90 "
Vertical C-4 :12 x 1'-0"x 1'-6" x 10'-0" = 180.00 "
Grade Beam :3 x 83'-8"x 0'-10"x 1'-3" = 261.36 "
Grade Beam :9 x 26'-9"x 0'-10"x 1'-3" = 250.69 "
Tai-Beam :3 x 83'-8"x 0'-10"x 0'-10" = 174.17 "
Tai-Beam :9 x 26'-9"x 0'-10"x 0'-10" = 167.05 "
Lintel :3 x 83'-8"x 0'-5"x 0'-6" = 52.71 "
Lintel :9 x 26'-9"x 0'-5"x 0'-6" = 50.55 "
Sun-sheet :14 x 5'-0"x 1'-6"x 4" = 34.65 "
Stair :2x2 x 16'-0"x 3'-6"x 6" = 112.00 "
Step :2x2x1/2x3'-6"x 10"x6" = 8.75"
Fools Slab :6 x 6'-0"x 8'-0"x 4" = 95.04 "
Roof Slab :1 x 86'-8"x 29'-9" x 5" = 1082.94"
= 5091.04 cft
= 144.18 m3
@ Tk.9568.64 per m3 Tk. = 13, 79,606.51
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
5091.04 x 1.75 x 490 = 19802.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =14, 84,753.96
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x 225'-0"x 10"x 3'-6" = 655.98 cft. = 18.57m3
@ Tk.4243.87 per m3 Tk. = 78,808.66
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 3x 83'-8"x 9'-6" = 2384.59 sft.
Wall- 9x 26'-9"x 9'-6" = 2287.12sft.
=4671.71 sft.
Deduction Door and window:
D = 24 x 3'-0"x 5'-6" = 396.00 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
(-) = 756.00 sft
Net work = 3915.71 sft. = 363.91m2
@ Tk.622.14 per m2 Tk. =2, 26,402.96
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3915.71 sft = 7831.42 sft
Ceiling: 1x 2238.17 sft. = 2238.17 "
= 10069.59 sft = 935.83m2
@ Tk.167.01 per m2 Tk. =1, 56,292.96
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total = 10069.59 sft
= 935.83 m2
@ Tk.133.57 per m2 Tk. = 1, 24,998.81
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 24 x 17'-0"x 4 " x 4" = 44.43 cft
W = 16 x 27'-0"x 4"x 4" = 47.04"
= 91.47 cft
= 2.59 m3
Item No.16:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
“DETAILS ESTIMATE”
Details Estimated for the three storied Residential building of MD. ABED ALI, FATHER’S NAME LATE
ABDUL HAMID of Present Location-Village-Naldanga Hat, P.O-Naldanga, P.S-Naldanga, Dist.-Natore.
Mouza-Naldanga, J.L.No:-RS-37. Khation No:-RS-51,PRO-456. Plot No:-RS-1038. Quantity of Land Total
=7.125 Decimals. The Estimate completes. The rate of L.G.E.D 2013-2014.
Plinth Area =2238.17 sft.
First Floor TotalEstimated Cost Tk. =41, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 10'-0" = 40.00 "
Vertical C-2 :8 x 0'-10"x 1'-3" x 10'-0" = 83.30 "
Vertical C-3 :3 x 1'-0"x 1'-4" x 10'-0" = 39.90 "
Vertical C-4 :12 x 1'-0"x 1'-6" x 10'-0" = 180.00 "
Grade Beam :3 x 83'-8"x 0'-10"x 1'-3" = 261.36 "
Grade Beam :9 x 26'-9"x 0'-10"x 1'-3" = 250.69 "
Tai-Beam :3 x 83'-8"x 0'-10"x 0'-10" = 174.17 "
Tai-Beam :9 x 26'-9"x 0'-10"x 0'-10" = 167.05 "
Lintel :3 x 83'-8"x 0'-5"x 0'-6" = 52.71 "
Lintel :9 x 26'-9"x 0'-5"x 0'-6" = 50.55 "
Sun-sheet :14 x 5'-0"x 1'-6"x 4" = 34.65 "
Stair :2x2 x 16'-0"x 3'-6"x 6" = 112.00 "
Step :2x2x1/2x3'-6"x 10"x6" = 8.75 "
Fools Slab :6 x 6'-0"x 8'-0"x 4" = 95.04 "
Roof Slab :1 x 86'-8"x 29'-9" x 5" = 1082.94 "
= 2633.11 cft
= 74.57 m3
@ Tk.9568.64 per m3 Tk. =7, 13,533.48
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
2633.11 x 1.75 x 490 = 10241.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. = 7, 67,870.18
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 3x 83'-8"x 9'-6" = 2384.59 sft.
Wall- 9x 26'-9"x 9'-6" = 2287.12sft.
=4671.71 sft.
Deduction Door and window:
D = 24 x 3'-0"x 5'-6" = 396.00 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
(-) = 756.00 sft
Net work = 3915.71 sft. = 363.91m2
@ Tk.622.14 per m2 Tk. =2, 26,402.96
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3915.71 sft = 7831.42 sft
Ceiling: 1x 2238.17 sft. = 2238.17 "
= 10069.59 sft = 935.83m2
@ Tk.167.01 per m2 Tk. =1, 56,292.96
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 10069.59 sft
= 935.83 m2
@ Tk.133.57 per m2 Tk. = 1, 24,998.81
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 24 x 17'-0"x 4 " x 4" = 44.43 cft
W = 16 x 27'-0"x 4"x 4" = 47.04 "
= 91.47 cft
= 2.59 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 24 x 2'-6"x 6'-6" = 390.00 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
= 750.00 sft
= 69.70 m2
@ Tk.6384.61 per m2 Tk. = 4, 45,007.31
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk.=1, 20,000.00
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
14 x 6'-0"x 4'-6" = 378.00sft.
= 35.13 m2
@ Tk.1547.74 per m2 Tk. = 54,372.10
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.11:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 2, 00,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 12,140.00
Total Tk =41,00,000.00
Total Tk. (Forty One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the three storied Residential building of MD. ABED ALI, FATHER’S NAME LATE
ABDUL HAMID of Present Location-Village-Naldanga Hat, P.O-Naldanga, P.S-Naldanga, Dist.-Natore.
Mouza-Naldanga, J.L.No:-RS-37. Khation No:-RS-51,PRO-456. Plot No:-RS-1038. Quantity of Land Total
=7.125 Decimals. The Estimate completes. The rate of L.G.E.D 2013-2014.
Plinth Area =2238.17 sft.
Second Floor TotalEstimated Cost Tk. =43, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 10'-0" = 40.00 "
Vertical C-2 :8 x 0'-10"x 1'-3" x 10'-0" = 83.30 "
Vertical C-3 :3 x 1'-0"x 1'-4" x 10'-0" = 39.90 "
Vertical C-4 :12 x 1'-0"x 1'-6" x 10'-0" = 180.00 "
Grade Beam :3 x 83'-8"x 0'-10"x 1'-3" = 261.36 "
Grade Beam :9 x 26'-9"x 0'-10"x 1'-3" = 250.69 "
Tai-Beam :3 x 83'-8"x 0'-10"x 0'-10" = 174.17 "
Tai-Beam :9 x 26'-9"x 0'-10"x 0'-10" = 167.05 "
Lintel :3 x 83'-8"x 0'-5"x 0'-6" = 52.71 "
Lintel :9 x 26'-9"x 0'-5"x 0'-6" = 50.55 "
Sun-sheet :14 x 5'-0"x 1'-6"x 4" = 34.65 "
Stair :2x2 x 16'-0"x 3'-6"x 6" = 112.00 "
Step :2x2x1/2x3'-6"x 10"x6" = 8.75 "
Fools Slab :6 x 6'-0"x 8'-0"x 4" = 95.04 "
Roof Slab :1 x 86'-8"x 29'-9" x 5" = 1082.94 "
= 2633.11 cft
= 74.57 m3
@ Tk.9568.64 per m3 Tk. = 7, 13,533.48
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
2633.11 x 1.75 x 490 = 10241.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. = 7, 67,870.18
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 3x 83'-8"x 9'-6" = 2384.59 sft.
Wall- 9x 26'-9"x 9'-6" = 2287.12sft.
=4671.71 sft.
Deduction Door and window:
D = 24 x 3'-0"x 5'-6" = 396.00 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
(-) = 756.00 sft
Net work = 3915.71 sft. = 363.91m2
@ Tk.622.14 per m2 Tk. =2, 26,402.96
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3915.71 sft = 7831.42 sft
Ceiling: 1x 2238.17 sft. = 2238.17 "
= 10069.59 sft = 935.83m2
@ Tk.167.01 per m2 Tk. =1, 56,292.96
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total = 10069.59 sft
= 935.83 m2
@ Tk.133.57 per m2 Tk. = 1, 24,998.81
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 24 x 17'-0"x 4 " x 4" = 44.43 cft
W = 16 x 27'-0"x 4"x 4" = 47.04 "
= 91.47 cft
= 2.59 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 24 x 2'-6"x 6'-6" = 390.00 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
= 750.00 sft
= 69.70 m2
@ Tk.6384.61 per m2 Tk. = 4, 45,007.31
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk.=1, 20,000.00
Item No.09:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
14 x 6'-0"x 4'-6" = 378.00sft.
= 35.13 m2
@ Tk.1547.74 per m2 Tk. = 54,372.10
Item No.10:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.11:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 50,000.00
Item No.12:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 2, 00,000.00
Item No.13:
Contingency for un for Seen work L.S Tk.= 2,12,140.00
Total Tk =43,00,000.00
Total Tk. (Forty Three Lac’s) only.
DETAIL’S ESTIMATE COST
Details Estimated for the three storied Residential building of MD. ABED ALI, FATHER’S NAME LATE
ABDUL HAMID of Present Location-Village-Naldanga Hat, P.O-Naldanga, P.S-Naldanga, Dist.-Natore.
Mouza-Naldanga, J.L.No:-RS-37. Khation No:-RS-51,PRO-456. Plot No:-RS-1038. Quantity of Land
Total =7.125 Decimals. The Estimate completes. The rate of L.G.E.D 2013-2014.
SUMMARY
Item No.04:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base F-1 : 4 x 6'-0" x 6'-0"x 1'-4" = 191.52 cft.
Base F-2 : 7 x 7'-0" x 7'-0"x 1'-6" = 514.50 "
Base F-3 : 4 x 8'-0" x 8'-0"x 1'-7" = 427.52 "
Base F-4 : 3 x 15'-0" x 7'-0"x 1'-8" = 526.05 "
Footing Pillar : 4 x 1'-3" x 1'-6"x 7'-0" = 52.50 "
Footing Pillar : 7 x 1'-3" x 1'-7"x 7'-0" = 96.77 "
Footing Pillar : 4 x 1'-6" x 1'-6"x 7'-0" = 63.00 "
Footing Pillar : 6 x 1'-3" x 1'-9"x 7'-0" = 91.87 "
Vertical Pillar : 4 x 1'-0" x1'-3"x 12'-0" = 60.00 cft.
Vertical Pillar : 7 x 1'-0" x1'-4"x 12'-0" = 111.72 "
Vertical Pillar : 4 x 1'-3" x1'-3"x 12'-0" = 75.00 "
Vertical Pillar : 6 x 1'-0" x1'-6"x 12'-0" = 108.00 "
G.B : 1 x 503'-0"x 10"x 18" = 628.49 "
T.B : 1 x 503'-0"x 10"x 12" = 418.99 "
Lintel : 1 x 625'-0"x 5"x 6" = 131.25 "
Sun-sheet : 12 x 5'-0"x 2'-0"x 4" = 39.60 "
Roof Slab : 1 x 2937.35 sft. x 6" = 1468.67 "
= 5005.45 cft
= 141.75 m3
@ Tk.6229.11 per m3 Tk. = 8, 82,976.34
Item No.05:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-05
5005.45 x 1.00 x 490 = 11125.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =8, 34,152.50
Item No.06:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 625'-0"x 9'-6" = 5937.50 sft.
Deduction Door and window:
D = 25 x 3'-0"x 5'-6" = 412.50 sft
W = 12 x 5'-0"x 4'-6" = 270.00 "
(-) = 682.50 sft
Net work = 5255.00 sft.
= 488.38m2
@ Tk.622.14 per m2 Tk. =3, 03,840.73
Item No. 07:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2 x 625'-0"x 10'-0" = 12500.00 sft
Ceiling: 1 x 2937.35 sft.x 1'-0" = 2937.35 "
= 15437.35 sft
= 1434.69 m2
@ Tk.167.01 per m2 Tk. = 2, 39,608.90
Item No.08:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-07
Total = 15437.35 sft
= 1434.69 m2
@ Tk.133.57 per m2 Tk. = 1, 91,631.54
Item No.09:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 50,000.00
Item No.10:
Supplying fitting and fixing of Sanitary, Water Supply and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 90,000.00
Item No.11:
Required size of Septic tank 10'-0" long 8'-0" breadth, 7'-0" Height in/c
250mm thick brick wall both sides and cement plaster R.C.C Top man
hole cover etc. all complete of the E/I.
Item No.14:
Contingency for unfor Seen work L.S Tk.= 44,733.98
Total Tk =30,00,000.00
Total Tk. (Thirty Lac’s ) Only.
“DETAILS ESTIMATE”
Details Estimated for the four storied Residential building of 1.MD. SAIFUL ISLAM, FATHER’S NAME
SULTAN AHAMED, 2. MST. SHAMIMA NASRIN,W/O- MD. SAIFUL ISLAM of Present Location-
Village-Ber-gongarumpur, P.O-Nazirpur, P.S-Gurudaspur, Dist.-Natore. Mouza-Dudgari, J.L.No:-RS-33.
Khation No:-RS-17. Plot No:-RS-479. Quantity of Land Total =7.00 Decimals. The Estimate completes.
The rate of L.G.E.D 2013-2014.
Plinth Area =2088.00 sft.
Ground Floor TotalEstimated Cost Tk. =55, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 1 x 5'-6"x 5'-6" x 8'-0" = 242.00 cft
Base-F-2 9 x 6'-0"x 6'-0" x 8'-0" = 2592.00 cft
Base-F-3 4 x 6'-6"x 6'-6" x 8'-0" = 1352.00 cft
Base-F-4 5 x 15'-0"x 7'-0" x 8'-0" = 4200.00 cft
= 8386.00 cft.
= 237.46 m3
@ Tk.74.39 per m3 Tk. =17,664.64
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 1 x 5'-0"x 5'-0" = 25.00 sft.
Base-F-2 9 x 5'-6"x 5'-6" = 272.25 sft.
Base-F-3 4 x 6'-0"x 6'-0" = 144.00 sft.
Base-F-4 5 x 14'-0"x 6'-0" = 420.00 sft.
Floor 1 x 72'-0"x 29'-0" = 2088.00 sft.
= 2949.25 sft.
= 274.09 m2
@ Tk.229.63 per m2 Tk. =62,939.28
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 1 x 5'-0"x 5'-0" x 5'-0" = 125.00 cft
Base-F-2 9 x 5'-6"x 5'-6" x 5'-0" = 1361.25 cft
Base-F-3 4 x 6'-0"x 6'-0" x 5'-0" = 720.00 cft
Base-F-4 5 x 14'-0"x 6'-0" x 5'-0" = 2100.00 cft
Floor 1x 72'-0"x 29'-0" x 4'-0" = 8352.00 cft.
= 12658.25 cft.
= 358.43 m3
@ Tk.642.21 per m3 Tk. =2,30,187.33
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 72'-0"x 29'-0" x 0'-4" = 689.04 cft.
= 19.51 m3
@ Tk.6163.79 per m3 Tk. =1,20,255.54
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 3 x 72'-0"x 0'-5" = 90.72 sft.
Wall- 9x 29'-0"x 0'-5" = 109.62sft.
= 200.34 sft.
= 18.61 m2
@ Tk. 585.39 per m3 Tk. =10,894.10
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :1 x 5'-0"x 5'-0" x 1'-4" = 33.25 cft
Base-F-2 :9 x 5'-6"x 5'-6" x 1'-6" = 408.37"
Base-F-3 :4 x 6'-0"x 6'-0" x 1'-7" = 227.52"
Base-F-4 :5 x 14'-0"x 6'-0" x 1'-8" = 701.40"
Footing C-1 :1x 1'-3"x 1'-3" x 7'-0" = 10.93"
Footing C-2 :11 x 1'-3"x 1'-3" x 7'-0" = 120.31"
Footing C-3 :5 x 1'-3"x 1'-4"x 7'-0" = 58.18 "
Footing C-4=C-5 :7 x 1'-3"x 1'-3" x 7'-0" = 76.56 "
Vertical C-1 :1x 1'-0"x 1'-0" x 10'-0" = 10.00 "
Vertical C-2 :11 x 1'-0"x 1'-0" x 10'-0" = 110.00"
Vertical C-3 :5 x 1'-0"x 1'-1" x 10'-0" = 54.00" (P.T.O)
Vertical C-4=C5 :7 x 1'-0"x 1'-3" x 10'-0" = 87.50"
Grade Beam :3 x 72'-0"x 0'-10"x 1'-3" = 224.91 "
Grade Beam :8 x 29'-0"x 0'-10"x 1'-3" = 241.57 "
Tai-Beam :3 x 72'-0"x 0'-10"x 0'-10" = 149.88 "
Tai-Beam :8 x 29'-0"x 0'-10"x 0'-10" = 160.98 "
Lintel :1 x 495'-0"x 0'-5"x 0'-6" = 103.95 "
Sun-sheet :14 x 5'-0"x 1'-6"x 4" = 34.65 "
Stair :2x2 x 16'-0"x 4'-0"x 6" = 128.00"
Step :2x2x1/2x4'-0"x 10"x6" = 3.33"
Fools Slab :3 x 6'-6"x 5'-0"x 4" = 32.17 "
Roof Slab :1 x 75'-0"x 32'-0" x 5" = 1008.00"
= 3985.46 cft
= 112.87 m3
@ Tk.9568.64 per m3 Tk. = 10,80,012.39
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
3985.46 x 1.75 x 490 = 15501.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =11,62,264.98
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x 225'-0"x 10"x 3'-6" = 655.98 cft.
= 18.57m3
@ Tk.4243.87 per m3 Tk. = 78,808.66
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 495'-0"x 9'-6" = 4702.50 sft.
Deduction Door and window:
D = 18 x 3'-0"x 5'-6" = 297.00 sft
W = 14 x 5'-0"x 4'-6" = 315.00 "
(-) = 612.00 sft
Net work = 4090.50 sft.
= 380.15 m2
@ Tk.622.14 per m2 Tk. =2,36,506.52
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 4090.50 sft = 8181.00 sft
Ceiling: 1 x 75'-0"x 32'-0" = 2400.00 "
= 10581.00 sft
= 983.36 m2
@ Tk.167.01 per m2 Tk. =1, 64,230.95
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total = 983.36 sft
= 983.36 m2
@ Tk.133.57 per m2 Tk. = 1, 31,347.39
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 18 x 17'-0"x 4 " x 4" = 33.32 cft
W = 16 x 27'-0"x 4"x 4" = 47.04 "
= 80.36 cft
= 2.28 m3
Item No.13:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 18 x 2'-6"x 6'-6" = 292.50 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
= 652.50 sft
= 60.64 m2
@ Tk.6384.61 per m2 Tk. = 3,87,162.75
Item No.14:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =1,00,000.00
Item No.15:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
16 x 6'-0"x 4'-6" = 432.00sft.
= 40.14 m2
@ Tk.1547.74 per m2 Tk. =62,126.28
Item No.16:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.18:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 20,000.00
Item No.19:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 1, 90,000.00
Item No.20:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
180'-9" x 4'-8"x 1'-3" = 1055.12 cft
19 x 1'-3"x 2'-0" x 1'-3" = 59.37 cft
= 1114.49 cft.
= 31.56 m3
@ Tk.74.39 per m3 Tk. =2,347.74
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
180'-9" x 4'-8" = 844.10 sft.
19 x 1'-3"x 2'-0" = 47.50 sft.
= 891.60 sft.
= 82.86 m2
@ Tk.229.63 per m2 Tk. =19,027.14
Item No.03:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Trench 1x 180'-9"x 4'-8" x 0'-6" = 422.05 cft.
Pillar 19x 1'-3"x 2'-0" x 0'-6" = 23.75 cft
= 445.80 cft.
=12.62 m3
@ Tk.6163.79 per m3 Tk. =77,787.02
Item No.04:
1st class brick work in approved bonds in superstructure walls or anywhere
in ground flood 1st with cement mortar 1:6 with Portland cement and sand
(minimum FM 1.50) including racking out joints curing etc. complete as
per design including supply carrying & cost of all materials
180'-9"x 3'-4"x 3'-0" = 1805.69 cft.
180'-9"x 2'-11"x 2'-0" = 1055.58 cft.
180'-9"x 2'-6"x 2'-0" = 903.75 cft.
180'-9"x 2'-1"x 1'-6" = 563.94 cft.
180'-9"x 1'-8"x 1'-6" = 452.77 cft.
180'-9"x 1'-3"x 1'-0" = 225.93 cft.
19 x 2'-0"x 6'-0" = 228.00 cft.
19 x 1'-1"x 5'-0" = 102.60 cft.
=5338.26 cft.
= 151.18 m3
@ Tk.4243.87 per m3 Tk. =6, 41,588.26
Item No.05:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1.5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 180'-9"x 11'-0" = 3976.50 sft
Pillar: 19 x 5'-3"x 11'-0" = 1097.25 "
= 5073.75 sft
= 471.53 m2
@ Tk.167.01 per m2 Tk. =78,750.22
Item No.06:
Earth filling work in any kind of soil canals, ponds, drains, foundation
reaches etc by excavating earth, filling baskets, carrying throwing to
desired place & distance in all type of soils, except work & gravels slushy
& organic soil, leveling dressing etc. all complete as per direction of the
E/I.
180'-9" x 15'-0" x 10'-0" = 27112.50 cft
19 x 1'-3"x 2'-0" x 3'-0" = 142.50 cft
= 27255.00 cft.
= 771.66 m3
@ Tk.169.35 per m3 Tk. =1, 30,680.62
Item No.07:
Contingency for un for Seen work L.S Tk.= 19,819.00
Total Tk =9,70,000.00
Total Tk. (Nine Lac’s Seventy Thousand) only.
“DETAILS ESTIMATE”
Details Estimated for the Construction of puritan Bus stand “SONALI BANK” Branch Strong Room Floor
Work Below as: The Estimate completes. The rate of L.G.E.D 2013-2014.
Plinth Area =147.85 sft.
TotalEstimated Cost Tk. = 45,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
1 x 12'-8"x 11'-8" x 0'-6" = 73.92 cft
= 2.09.37 m3
Item No.03:
Contingency for un for Seen work L.S Tk.= 363.88
Total Tk = 45,000.00
Total Tk. (Forty Five Thousand) only.
“DETAILS ESTIMATE”
Details Estimated for the four storied Residential building of MST. RAJEA SULTANA, W/O- MD.
AFSAR ALI, M/O- MST. RAHIMA BEGUM of Present Location-Village-Dhobapukur, P.O-Naldanga,
P.S-Naldanga, Dist.-Natore. Mouza-Dhobapukur, J.L.No:-RS-38. Khation No:-RS-28, Pro-338, Plot No:-
RS-539. Quantity of Land Total = 10.00 Decimals. The Estimate completes. The rate of L.G.E.D 2013-
2014.
Plinth Area = 1402.90 sft.
Ground Floor TotalEstimated Cost Tk. =55, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 1 x 5'-6"x 5'-6" x 8'-0" = 242.00 cft
Base-F-2 9 x 6'-0"x 6'-0" x 8'-0" = 2592.00 cft
Base-F-3 4 x 6'-6"x 6'-6" x 8'-0" = 1352.00 cft
Base-F-4 5 x 15'-0"x 7'-0" x 8'-0" = 4200.00 cft
= 8386.00 cft.
= 237.46 m3
@ Tk.74.39 per m3 Tk. =17,664.64
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 1 x 5'-0"x 5'-0" = 25.00 sft.
Base-F-2 9 x 5'-6"x 5'-6" = 272.25 sft.
Base-F-3 4 x 6'-0"x 6'-0" = 144.00 sft.
Base-F-4 5 x 14'-0"x 6'-0" = 420.00 sft.
Floor 1 x 72'-0"x 29'-0" = 2088.00 sft.
= 2949.25 sft.
= 274.09 m2
@ Tk.229.63 per m2 Tk. =62,939.28
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 1 x 5'-0"x 5'-0" x 5'-0" = 125.00 cft
Base-F-2 9 x 5'-6"x 5'-6" x 5'-0" = 1361.25 cft
Base-F-3 4 x 6'-0" x 6'-0" x 5'-0" = 720.00 cft
Base-F-4 5 x 14'-0"x 6'-0" x 5'-0" = 2100.00 cft
Floor 1x 72'-0"x 29'-0" x 4'-0" = 8352.00 cft.
= 12658.25 cft.
= 358.43 m3
@ Tk.642.21 per m3 Tk. =2,30,187.33
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 72'-0"x 29'-0" x 0'-4" = 689.04 cft.
= 19.51 m3
@ Tk.6163.79 per m3 Tk. = 1,20,255.54
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 3 x 72'-0"x 0'-5" = 90.72 sft.
Wall- 9 x 29'-0"x 0'-5" = 109.62sft.
= 200.34 sft.
= 18.61 m2
@ Tk. 585.39 per m3 Tk. =10,894.10
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :1 x 5'-0"x 5'-0" x 1'-4" = 33.25 cft
Base-F-2 :9 x 5'-6"x 5'-6" x 1'-6" = 408.37 "
Base-F-3 :4 x 6'-0"x 6'-0" x 1'-7" = 227.52 "
Base-F-4 :5 x 14'-0"x 6'-0" x 1'-8" = 701.40 "
Footing C-1 :1 x 1'-3"x 1'-3" x 7'-0" = 10.93 "
Footing C-2 :11 x 1'-3"x 1'-3" x 7'-0" = 120.31 "
Footing C-3 :5 x 1'-3"x 1'-4"x 7'-0" = 58.18 "
Footing C-4=C-5 :7 x 1'-3"x 1'-3" x 7'-0" = 76.56 "
Vertical C-1 :1 x 1'-0"x 1'-0" x 10'-0" = 10.00 "
Vertical C-2 :11 x 1'-0"x 1'-0" x 10'-0" = 110.00 "
Vertical C-3 :5 x 1'-0"x 1'-1" x 10'-0" = 54.00 " (P.T.O)
Vertical C-4=C5 :7 x 1'-0"x 1'-3" x 10'-0" = 87.50 "
Grade Beam :3 x 72'-0"x 0'-10"x 1'-3" = 224.91 "
Grade Beam :8 x 29'-0"x 0'-10"x 1'-3" = 241.57 "
Tai-Beam :3 x 72'-0"x 0'-10"x 0'-10" = 149.88 "
Tai-Beam :8 x 29'-0"x 0'-10"x 0'-10" = 160.98 "
Lintel :1 x 495'-0"x 0'-5"x 0'-6" = 103.95 "
Sun-sheet :14 x 5'-0"x 1'-6"x 4" = 34.65 "
Stair :2x2 x 16'-0"x 4'-0"x 6" = 128.00 "
Step :2x2x1/2x4'-0"x 10"x6" = 3.33 "
Fools Slab :3 x 6'-6"x 5'-0"x 4" = 32.17 "
Roof Slab :1 x 75'-0"x 32'-0" x 5" = 1008.00 "
= 3985.46 cft
= 112.87 m3
@ Tk.9568.64 per m3 Tk. = 10,80,012.39
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
3985.46 x 1.75 x 490 = 15501.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =11,62,264.98
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x 225'-0"x 10"x 3'-6" = 655.98 cft.
= 18.57m3
@ Tk.4243.87 per m3 Tk. = 78,808.66
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 495'-0"x 9'-6" = 4702.50 sft.
Deduction Door and window:
D = 18 x 3'-0"x 5'-6" = 297.00 sft
W = 14 x 5'-0"x 4'-6" = 315.00 "
(-) = 612.00 sft
Net work = 4090.50 sft.
= 380.15 m2
@ Tk.622.14 per m2 Tk. =2,36,506.52
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 4090.50 sft = 8181.00 sft
Ceiling: 1 x 75'-0"x 32'-0" = 2400.00 "
= 10581.00 sft
= 983.36 m2
@ Tk.167.01 per m2 Tk. =1, 64,230.95
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total = 983.36 sft
= 983.36 m2
@ Tk.133.57 per m2 Tk. = 1, 31,347.39
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 18 x 17'-0"x 4 " x 4" = 33.32 cft
W = 16 x 27'-0"x 4"x 4" = 47.04 "
= 80.36 cft
= 2.28 m3
Item No.13:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 18 x 2'-6"x 6'-6" = 292.50 sft
W = 16 x 5'-0"x 4'-6" = 360.00 "
= 652.50 sft
= 60.64 m2
@ Tk.6384.61 per m2 Tk. = 3,87,162.75
Item No.14:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =1,00,000.00
Item No.15:
Supplying, fitting and fixing in thy Aluminum door frames, window,
partitions and curtain wall distortion free glass of approved quality and
shade including cost of fitting fixing all necessary accessories etc.
complete in all respect as per drawing and direction of the E-I-C. (6mm
thick reflection glass)
16 x 6'-0"x 4'-6" = 432.00sft.
= 40.14 m2
@ Tk.1547.74 per m2 Tk. = 62,126.28
Item No.16:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.18:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. = 1, 20,000.00
Item No.19:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 1, 90,000.00
Item No.20:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.01:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Roof 1x 35'-5"x 30'-4" x 0'-4" =354.51 cft.
Floor 1x 14'-10"x 17'-0" x 0'-4" =83.21 cft.
Floor Ver. 1x 37'-0"x 8'-0" x 0'-4" =97.68 cft.
=535.40 cft.
=15.16 m3
@ Tk.6163.79 per m3 Tk. =93,443.05
Item No.02:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 96'-0"x 0'-5" =40.32 sft.
=3.74 m2
@ Tk. 585.39 per m3 Tk. =2,193.58
Item No.03:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x 96'-0"x 10"x 3'-6" =279.88 cft.
=7.92 m3
@ Tk.4243.87 per m3 Tk. =33,634.66
Item No.10:
Supplying fitting and fixing of collapsible gate and necessary grills,
Angle, Truss, Tin as per Approved design etc. all complete of E/I.
L.S Tk. =3, 50,000.00
Item No.11:
Contingency for un for Seen work L.S Tk.= 6,710.22
Total Tk =7,50,000.00
Total Tk. (Seven Lac’s Fifty Thousand) only.
“DETAILS ESTIMATE”
Details Estimated for the Five storied Residential Building of MD. MIZANUR RAHMAN, S/O. MD.
MOFIZ UDDIN, M/O. MST. KHAIRUN NAHAR of Present Location-Village-Mohisdanga vatopara, P.O-
Mohisdang, P.S-Naldanga, Dist.-Natore, and Land Location-Uttor Borgaca, Natore. Mouza-Borgaca,
J.L.No:-RS-146. Khation No:-RS-718, Pro-6004, Plot No:-RS-3913,3968/4071. Quantity of Land
Total(3.45+1.55)=5.00 Decimals. The Estimate completes. The rate of L.G.E.D 2014-2015.
Plinth Area =1480.88 sft.
Ground Floor TotalEstimated Cost Tk. =45, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 10'-0" =1440.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 10'-0" =1960.00 cft
Base-F-3 1 x 14'-0"x 7'-0" x 10'-0" =980.00 cft
Base-F-4 3 x 15'-0"x 8'-0" x 10'-0" =3600.00 cft
=7980.00 cft.
=225.96 m3
@ Tk.74.39 per m3 Tk. =16,809.16
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" =144.00 sft.
Base-F-2 4 x 7'-0"x 7'-0" =196.00 sft.
Base-F-3 1 x 14'-0"x 7'-0" =98.00 sft.
Base-F-4 3 x 15'-0"x 8'-0" =360.00 sft.
Floor 1 x 39'-8"x 37'-4" =1480.88 sft.
=2278.88 sft.
=211.79 m2
@ Tk.229.63 per m2 Tk. =48,596.59
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 7'-0" =1008.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 7'-0" =1372.00 cft
Base-F-3 1 x 14'-0" x 7'-0" x 7'-0" =686.00 cft
Base-F-4 4 x 15'-0"x 8'-0" x 7'-0" =3360.00 cft
Floor 1x 39'-8"x 37'-4" x 5'-0" =621.97 cft.
=7047.97 cft.
=199.57 m3
@ Tk.642.21 per m3 Tk. =1,28,165.84
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 39'-8"x 37'-4" x 0'-4" =488.69 cft.
=13.83 m3
@ Tk.6163.79 per m3 Tk. =85,245.21
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 368'-0"x 0'-5" =154.56 sft.
=14.36 m2
@ Tk. 585.39 per m3 Tk. =8,406.20
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" =191.52 cft
Base-F-2 :4x 7'-0"x 7'-0" x 1'-7" =309.68"
Base-F-3 :1 x 14'-0"x 7'-0" x 1'-9" =171.50"
Base-F-4 :3 x 15'-0"x 8'-0" x 1'-10" =659.88"
Footing C-1 :4 x 1'-3"x 1'-6" x 7'-0" =52.50"
Footing C-2 :4 x 1'-3"x 1'-7" x 7'-0" =55.30"
Footing C-3 :2 x 1'-3"x 1'-9"x 7'-0" =30.62 "
Footing C-4 :6 x 1'-3"x 1'-11" x 7'-0" =100.80 "
Vertical C-1 :4 x 1'-0"x 1'-3" x 10'-0" =50.00 "
Vertical C-2 :4 x 1'-0"x 1'-4" x 10'-0" =53.20"
Vertical C-3 :2 x 1'-0"x 1'-6" x 10'-0" =30.00"
Vertical C-4 :6 x 1'-0"x 1'-8" x 10'-0" =100.20"
Grade Beam :4 x 37'-4"x 1'-0"x 1'-4" =198.59 " (P.T.O)
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 405'-0"x 9'-6" =3847.50 sft.
Deduction Door and window:
D = 12 x 3'-0"x 6'-6" =234.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =436.50 sft
Net work =3411.00 sft.
=317.00 m2
@ Tk.622.14 per m2 Tk. =1,97,218.38
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3411.00 sft =6822.00 sft
Ceiling: 1 x 45'-0"x 44'-0" =1980.00 "
=8802.00 sft
=818.02 m2
@ Tk.167.01 per m2 Tk. =1,36,617.52
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =8802.00 sft
=818.02 m2
@ Tk.133.57 per m2 Tk. =1,09,262.93
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 12 x 17'-0"x 4 " x 4" =22.21 cft
W = 10 x 27'-0"x 4"x 4" =29.40"
=51.61 cft
=1.46 m3
Item No.13:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 12 x 2'-6"x 6'-6" =195.00 sft
W = 10 x 5'-0"x 4'-6" =225.00 "
=420.00 sft
=39.03 m2
@ Tk.6384.61 per m2 Tk. =2,49,191.32
Item No.14:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =60,000.00
Item No.15:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.17:
Supplying fitting and fixing of collapsible gate and necessary grills as per
Approved design etc. all complete of E/I.
L.S Tk. =90,000.00
Item No.18:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. =2, 00,000.00
Item No.19:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical Column C-1 :3 x 1'-0"x 1'-3" x 12'-0" =45.00cft.
Vertical Column C-2 :7 x 1'-0"x 1'-4" x 12'-0" =111.72 "
Vertical Column C-3 :2 x 1'-0"x 1'-4" x 12'-0" =31.92 "
Vertical Column C-1 :4 x 1'-0"x 1'-6" x 12'-0" =72.00 "
Tai-Beam :1 x 348'-0"x 0'-10"x 0'-10" =241.47 "
Lintel :1 x 405'-0"x 0'-10"x 0'-10" =85.05 "
Sun-sheet :4 x 6'-0"x 1'-6"x 4" =11.88 "
Stair :2x2 x 17'-2"x 6'-0"x 6" =205.92"
Step :2x2x1/2x6'-0"x 10"x6" =4.99"
Maharab Slab :1 x 7'-0"x 7'-0" x 5.5" =22.45 "
Roof Slab :1 x 42'-0"x 45'-0" x 5.5" =850.50 "
=1682.90 cft
=47.65 m3
@ Tk.9568.64 per m3 Tk. =4,55,945.69
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1682.90 x 1.75 x 490 =6545.79 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =4,90,803.33
Item No.03:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x160'-0"x 10"x 12'-0" =1599.36 cft.
=45.28 m3
@ Tk.4243.87 per m3 Tk. =1,92,162.43
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =6354.77 sft
=590.59 m2
@ Tk.133.57 per m2 Tk. =78,885.10
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 2 x 17'-0"x 4 " x 4" =3.70 cft
W = 4 x 27'-0"x 4"x 4" =11.76"
=15.46 cft
=0.44 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 2 x 4'-0"x 7'-0" =56.00 sft
W = 6 x 6'-0"x 5'-0" =180.00 "
=236.00 sft
=21.93 m2
@ Tk.6384.61 per m2 Tk. =1,40,014.49
Item No.08:
Contingency for un for Seen work L.S Tk.= 10,139.30
Total Tk. =15,00,000.00
Total Tk. (Fifteen Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Three Storied Residential Building of 1. MD. MOAZZEM HOSSAIN, S/O.
LATE SOLAIMAN HOSSAIN, M/O. MINA KHATUN,2. MST. AKTAR PARVIN, W/O. MD.
MOAZZEM HOSSAIN, M/O. LATE. SHARA of Present Land Location-Village-Dakkhin potuapara, P.O-
Natore, P.S-Natore, Dist.-Natore. Mouza-Natore, J.L.No:-SA-204, RS-151. Khation No:-RS-232, Pro-8832.
Plot No:-RS-4424. Quantity of Land Total=4.00 Decimals. The Estimate completes. The rate of L.G.E.D
2014-2015.
Plinth Area =1128.99 sft.
Ground Floor TotalEstimated Cost Tk. =32, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 5'-0"x 5'-0" x 8'-0" =800.00 cft
Base-F-2 4 x 5'-6"x 5'-6" x 8'-0" =968.00 cft
Base-F-3 2 x 6'-0"x 6'-0" x 8'-0" =576.00 cft
Base-F-4 2 x 13'-6"x 6'-6" x 8'-0" =1404..00 cft
=3748.00 cft.
=106.13 m3
@ Tk.74.39 per m3 Tk. =7,895.05
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 5'-0"x 5'-0" =100.00 sft.
Base-F-2 4 x 5'-6"x 5'-6" =121.00 sft.
Base-F-3 2 x 6'-0"x 6'-0" =72.00 sft.
Base-F-4 2 x 13'-6"x 6'-6" =175.50 sft.
Floor 1 x 32'-0"x 35'-2" =1125.12 sft.
=1593.62 sft.
=148.10 m2
@ Tk.229.63 per m2 Tk. =34,008.20
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 5'-0"x 5'-0" x 7'-0" =700.00 cft
Base-F-2 4 x 5'-6"x 5'-6" x 7'-0" =847.00 cft
Base-F-3 2 x 6'-0" x 6'-0" x 7'-0" =504.00 cft
Base-F-4 2 x 13'-6"x 6'-6" x 7'-0" =1228.50 cft
Floor 1x 32'-0"x 35'-2" x 6'-0" =6750.72 cft.
=10030.22 cft.
=248.02 m3
@ Tk.642.21 per m3 Tk. =1,59,280.82
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 32'-0"x 35'-2" x 0'-4" =371.28 cft.
=10.51 m3
@ Tk.6163.79 per m3 Tk. =64,781.43
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 368'-0"x 0'-5" =154.56 sft.
=14.36 m2
@ Tk. 585.39 per m3 Tk. =8,406.20
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 5'-0"x 5'-0" x 1'-2" =116.00 cft
Base-F-2 :4x 5'-6"x 5'-6" x 1'-4" =160.93"
Base-F-3 :2 x 6'-0"x 6'-0" x 1'-5" =102.24"
Base-F-4 :2 x 13'-6"x 6'-6" x 1'-5" =249.21"
Footing C-1 :4 x 1'-3"x 1'-3" x 7'-0" =43.75"
Footing C-2 :4 x 1'-3"x 1'-6" x 7'-0" =52.50"
Footing C-3 :2 x 1'-3"x 1'-7"x 7'-0" =27.65 "
Footing C-4 :4 x 1'-3"x 1'-7" x 7'-0" =55.30"
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :4 x 1'-0"x 1'-3" x 12'-0" =60.00"
Vertical C-3 :2 x 1'-0"x 1'-4" x 12'-0" =31.92"
Vertical C-4 :4 x 1'-0"x 1'-4" x 12'-0" =63.84"
Grade Beam :1 x 252'-6"x 1'-0"x 1'-3" =315.62 cft.
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :8 x 5'-0"x 1'-6"x 4" =19.80 "
Stair :2x2 x 16'-2"x 3'-6"x 6" =113.12"
Step :2x2x1/2x3'-6"x 10"x6" =2.91"
Fools Slab :2 x 11'-6"x 5'-8"x 4" =43.03 "
Roof Slab :1 x 32'-0"x 35'-2" x 5" =472.55"
=2217.62 cft =62.79m3
@ Tk.9568.64 per m3 Tk. =6,00,814.90
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2217.62 x 1.5 x 490 =7393.40 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,54,357.13
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x160'-0"x 10"x 3'-6" =466.48 cft.
=13.20 m3
@ Tk.4243.87 per m3 Tk. =56,019.08
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 405'-0"x 9'-6" =3847.50 sft.
Deduction Door and window:
D = 12 x 3'-0"x 6'-6" =234.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =436.50 sft
Net work =3411.00 sft.
=317.00 m2
@ Tk.622.14 per m2 Tk. =1,97,218.38
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3411.00 sft =6822.00 sft
Ceiling: 1 x 45'-0"x 44'-0" =1980.00 "
=8802.00 sft
=818.02 m2
@ Tk.167.01 per m2 Tk. =1,36,617.52
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =8802.00 sft
=818.02 m2
@ Tk.133.57 per m2 Tk. =1,09,262.93
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 12 x 17'-0"x 4 " x 4" =22.21 cft
W = 10 x 27'-0"x 4"x 4" =29.40 "
=51.61 cft
=1.46 m3
Item No.18:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
CURRICULUM VITAC
OF
SHANJIDA SHAHID
Call:01706729999.
1. Name : Shanjida Shahid
2. Father’s Name : Mr. Shahidul Islam
3. Mother’s Name : Mrs. Fahmida Akter
4. Present Address : Village:-Alaipur, P.O +P.S +Dist:-Natore.
5. Permanent Address :Village:-Dhokrakul, P.O:-Dhokrakul, P.S:-Puthia,
Dist:-Rajshahi.
6. Home District : Rajshahi.
7. Date of Birth : 22-08-1995.
8. Marital Status : Unmarried.
9. Religion : Muslim.
10. Nationality : Bangladeshi (By Birth)
11. Contact No : 01706729999.
12. Educational Qualification:S.S.C-GPA-4.94, Group-Science, Rajshahi Board-2011.
13.Educational Qualification:H.S.C-GPA-4.00,Group-Science, Rajshahi Board-2013
Signature
………………………
(Shanjida Shahid)
Date:……………….
“DETAILS ESTIMATE”
Details Estimated for the Three Storied Residential Building of 1. MD. ABDUL BAREK, F/O. LATE
ABDUL AZIZ MUNSHI, M/O. LILY BEGUM,2. MST. NAZMA BEGUM, W/O. MD. ABDUL BAREK,
of Present Land Location-Village-Debottor, P.O-Debottor, P.S-Atghorea, Dist.-Pabna. Mouza-Debottor,
J.L.No:-RS-59, Khation No:-SA-39, RS-93,Pro-326. Plot No:-SA-79, RS-99. Quantity of Land Total=4.50
Decimals Or=0.045ACR. The Estimate completes. The rate of L.G.E.D 2014-2015.
Plinth Area =1206.53sft.
Ground Floor TotalEstimated Cost Tk. =34, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 8'-0" =1152.00 cft
Base-F-2 5 x 7'-0"x 7'-0" x 8'-0" =1960.00 cft
Base-F-3 1 x 8'-0"x 8'-0" x 8'-0" =512.00 cft
Base-F-4 2 x 15'-6"x 8'-6" x 8'-0" =2108.00 cft
=5732.00 cft.
=162.31 m3
@ Tk.74.39 per m3 Tk. =12,074.24
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" =144.00 sft.
Base-F-2 5 x 7'-0"x 7'-0" =245.00 sft.
Base-F-3 1 x 8'-0"x 8'-0" =64.00 sft.
Base-F-4 2 x 15'-6"x 8'-6" =263.50 sft.
Floor 1 x 49'-7"x 24'-0" =1189.68 sft.
=1906.18 sft.
=177.15 m2
@ Tk.229.63 per m2 Tk. =40,678.95
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 7'-0" =1008.00 cft
Base-F-2 5 x 7'-0"x 7'-0" x 7'-0" =1715.00 cft
Base-F-3 1 x 8'-0" x 8'-0" x 7'-0" =448.00 cft
Base-F-4 2 x 15'-6"x 8'-6" x 7'-0" =1844.50 cft
Floor 1x 49'-7"x 24'-0" x 4'-0" =4759.68 cft.
=9775.18 cft.
=276.79 m3
@ Tk.642.21 per m3 Tk. =1,77,757.30
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 49'-7"x 24'-0" x 0'-4" =1189.92 cft.
=33.69 m3
@ Tk.6163.79 per m3 Tk. =2,07,658.08
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 368'-0"x 0'-5" =154.56 sft.
=14.36 m2
@ Tk. 585.39 per m3 Tk. =8,406.20
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" =191.52 cft
Base-F-2 :5x 7'-0"x 7'-0" x 1'-6" =367.50"
Base-F-3 :1 x 8'-0"x 8'-0" x 1'-8" =106.88"
Base-F-4 :2 x 15'-6"x 8'-6" x 1'-10" =482.99"
Footing C-1 :4 x 1'-3"x 1'-3" x 7'-0" =43.75"
Footing C-2 :5 x 1'-3"x 1'-6" x 7'-0" =65.62"
Footing C-3 :1 x 1'-6"x 1'-9"x 7'-0" =18.37 "
Footing C-4 :4 x 1'-3"x 1'-9" x 7'-0" =61.25"
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :5 x 1'-0"x 1'-3" x 12'-0" =75.00"
Vertical C-3 :1 x 1'-3"x 1'-6" x 12'-0" =22.50"
Vertical C-4 :4 x 1'-0"x 1'-6" x 12'-0" =72.00"
Grade Beam :1 x 252'-6"x 0'-10"x 1'-6" =315.49 "
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-10"x 3'-6"x 6" =103.83"
Step :2x2x1/2x3'-6"x 10"x6" =2.91"
Fools Slab :4 x 3'-11"x 4'-0"x 4" =20.69 "
Roof Slab :1 x 49'-7"x 24'-0" x 5" =499.76"
=2754.63 cft =78.00m3
@ Tk.9568.64 per m3 Tk. =7,46,353.92
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2754.63 x 1.2 x 490 =7347.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,50,878.06
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x145'-0"x 10"x 2'-6" =301.96 cft.
=8.55 m3
@ Tk.4243.87 per m3 Tk. =36,285.08
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 305'-0"x 9'-6" =2897.50 sft.
Deduction Door and window:
D = 16 x 3'-0"x 6'-6" =312.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =514.5 sft
Net work =2383.00 sft.
=221.46 m2
@ Tk.622.14 per m2 Tk. =1,37,779.12
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3050.00 sft =6100.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7599.96 sft
=706.31 m2
@ Tk.167.01 per m2 Tk. =1,17,960.83
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =7599.96 sft
=706.31 m2
@ Tk.133.57 per m2 Tk. =94,341.82
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 16 x 17'-0"x 4 " x 4" =29.62 cft
W = 9 x 27'-0"x 4"x 4" =26.46"
=56.08 cft
=1.58 m3
Item No.18:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
“DETAILS ESTIMATE”
Details Estimated for the Three Storied Residential Building of 1. MD. ABDUL BAREK, F/O. LATE
ABDUL AZIZ MUNSHI, M/O. LILY BEGUM,2. MST. NAZMA BEGUM, W/O. MD. ABDUL BAREK,
of Present Land Location-Village-Debottor, P.O-Debottor, P.S-Atghorea, Dist.-Pabna. Mouza-Debottor,
J.L.No:-RS-59, Khation No:-SA-39, RS-93, Pro-326. Plot No:-SA-79, RS-99. Quantity of Land Total=4.50
Decimals Or=0.045ACR. The Estimate completes. The rate of L.G.E.D 2014-2015.
Plinth Area =1206.53 sft.
Second Floor TotalEstimated Cost Tk. =21, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :5 x 1'-0"x 1'-3" x 12'-0" =75.00 "
Vertical C-3 :1 x 1'-3"x 1'-6" x 12'-0" =22.50 "
Vertical C-4 :4 x 1'-0"x 1'-6" x 12'-0" =72.00 "
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-10"x 3'-6"x 6" =103.83 "
Step :2x2x1/2x3'-6"x 10"x6" =2.91 "
Fools Slab :4 x 3'-11"x 4'-0"x 4" =20.69 "
Roof Slab :1 x 49'-7"x 24'-0" x 5" =499.76 "
=1101.26 cft
=31.18m3
@ Tk.9568.64 per m3 Tk. =2,98,350.19
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
1101.26 x 1.5 x 490 =3671.53 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,75,291.31
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 305'-0"x 9'-6" =2897.50 sft.
Deduction Door and window:
D = 16 x 3'-0"x 6'-6" =312.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =514.5 sft
Net work =2383.00 sft.
=221.46 m2
@ Tk.622.14 per m2 Tk. =1,37,779.12
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3050.00 sft =6100.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7599.96 sft
=706.31 m2
@ Tk.167.01 per m2 Tk. =1,17,960.83
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =7599.96 sft
=706.31 m2
@ Tk.133.57 per m2 Tk. =94,341.82
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 16 x 17'-0"x 4 " x 4" =29.62 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=56.08 cft
=1.58 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 16 x 2'-6"x 6'-6" =260.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
=462.50 sft
=42.98 m2
@ Tk.6384.61 per m2 Tk. =2,74,410.53
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =60,000.00
Item No.09:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
Item No.12:
Contingency for un for Seen work L.S Tk.= 42,941.14
Total Tk. =21,00,000.00
Total Tk. (Twenty One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Three Storied Residential Building of 1. MD. ABDUL BAREK, F/O. LATE
ABDUL AZIZ MUNSHI, M/O. LILY BEGUM,2. MST. NAZMA BEGUM, W/O. MD. ABDUL BAREK,
of Present Land Location-Village-Debottor, P.O-Debottor, P.S-Atghorea, Dist.-Pabna. Mouza-Debottor,
J.L.No:-RS-59, Khation No:-SA-39, RS-93, Pro-326. Plot No:-SA-79, RS-99. Quantity of Land Total=4.50
Decimals Or=0.045ACR. The Estimate completes. The rate of L.G.E.D 2014-2015.
SUMMARY
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of MD. ABDUL MALEK, S/O- MD. LUTFAR
RAHMAN PRAMANIK, M/O-MST KHAIRUN NAHAR,of Present Land Location-Village-Mohis danga
vatopara, P.O-Mohis danga , P.S-Boraigram, Dist.-Natore. Mouza:-Boraigram, J.L.No:-RS-44, Khation
No:-CS-308,564A) Plot No:-RS-719. Quantity of Land Total=16.00 Decimals Or=0.16ACR. The Estimate
completes. The rate of L.G.E.D 2014-2015.
Plinth Area =1480.88sft.
Ground Floor TotalEstimated Cost Tk. =35, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 8'-0" =1152.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 8'-0" =1568.00 cft
Base-F-3 2 x 14'-0"x 7'-0" x 8'-0" =1568.00 cft
Base-F-4 2 x 15'-0"x 8'-0" x 8'-0" =1920.00 cft
=6208.00 cft.
=175.78 m3
@ Tk.74.39 per m3 Tk. =13,076.27
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" =144.00 sft.
Base-F-2 4 x 7'-0"x 7'-0" =196.00 sft.
Base-F-3 2 x 14'-0"x 7'-0" =196.00 sft.
Base-F-4 2 x 15'-0"x 8'-0" =240.50 sft.
Floor 1 x 39'-8"x 37'-4" =1480.00 sft.
=2256.88 sft.
=209.75 m2
@ Tk.229.63 per m2 Tk. =48,164.89
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 7'-0" =1008.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 7'-0" =1372.00 cft
Base-F-3 2 x 14'-0" x 7'-0" x 7'-0" =1372.00 cft
Base-F-4 2 x 15'-0"x 8'-0" x 7'-0" =1680.00 cft
Floor 1x 39'-8"x 37'-4" x 4'-0" =5923.52 cft.
=11355.52 cft.
=321.54 m3
@ Tk.642.21 per m3 Tk. =2,06,496.20
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 39'-8"x 37'-4" x 0'-4" =488.69 cft.
=13.83 m3
@ Tk.6163.79 per m3 Tk. =85,245.21
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 350'-0"x 0'-5" =147.00 sft.
=13.66 m2
@ Tk. 585.39 per m3 Tk. =7,996.42
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" =191.52 cft
Base-F-2 :4x 7'-0"x 7'-0" x 1'-7" =309.68"
Base-F-3 :2 x 14'-0"x 7'-0" x 1'-9" =343.00"
Base-F-4 :2 x 15'-0"x 8'-0" x 1'-10" =439.92 "
Footing C-1 :4 x 1'-3"x 1'-6" x 7'-0" =52.50"
Footing C-2 :4 x 1'-3"x 1'-7" x 7'-0" =55.30"
Footing C-3 :2 x 1'-3"x 1'-9"x 7'-0" =30.62 "
Footing C-4 :6 x 1'-3"x 1'-11" x 7'-0" =100.80"
Vertical C-1 :4 x 1'-0"x 1'-0" x 10'-0" =50.00 "
Vertical C-2 :4 x 1'-0"x 1'-4" x 10'-0" =53.20 "
Vertical C-3 :2 x 1'-0"x 1'-6" x 10'-0" =30.00"
Vertical C-4 :6 x 1'-0"x 1'-8" x 10'-0" =100.20 "
Grade Beam :1 x 315'-0"x 0'-10"x 1'-3" =327.99"
Tai-Beam :1 x 315'-0"x 0'-10"x 0'-10" =218.57 "
Lintel :1 x 350'-0"x 0'-5"x 0'-6" =73.50 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-11"x 4'-0"x 6" =59.68"
Step :2x2x1/2x4'-0"x 10"x6" =16.66"
Fools Slab :2 x 8'-10"x 4'-10"x 4" =28.17 "
Fools Slab :1 x 11'-10"x 8'-10"x 4" =34.49 "
Roof Slab :1 x 42'-8"x 40'-4" x 5" =722.77"
=3255.89 cft
=92.19m3
@ Tk.9568.64 per m3 Tk. =8,82,132.92
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
3255.89 x 1.2 x 490 =8683.95 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =6,51,122.57
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x160'-0"x 10"x 3'-0" =399.84 cft.
=11.32 m3
@ Tk.4243.87 per m3 Tk. =48,040.60
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7198.96 sft
=669.04 m2
@ Tk.167.01 per m2 Tk. =1,11,736.37
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =7198.96 sft
=669.04 m2
@ Tk.133.57 per m2 Tk. =89,363.67
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 14 x 17'-0"x 4 " x 4" =25.92 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=52.38 cft
=1.48 m3
Item No.18:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1171.16 x 1.5 x 490 =3904.57 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,92,764.65
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7198.96 sft
=669.04 m2
@ Tk.167.01 per m2 Tk. =1,11,736.37
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =7198.96 sft
=669.04 m2
@ Tk.133.57 per m2 Tk. =89,363.67
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 14 x 17'-0"x 4 " x 4" =25.92 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=52.38 cft
=1.48 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 14 x 2'-6"x 6'-6" =227.50 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
=430.00 sft
=39.96 m2
@ Tk.6384.61 per m2 Tk. =2,55,129.01
Item No.08:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =60,000.00
Item No.09:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of MD. ABDUL MALEK,
S/O- MD. LUTFAR RAHMAN PRAMANIK, M/O-MST KHAIRUN NAHAR,of Present
Land Location-Village-Mohis danga vatopara, P.O-Mohis danga, P.S-Boraigram, Dist.-
Natore. Mouza: -Boraigram, J.L.No:-RS-44, Khation No:-CS-308,564A) Plot No:-RS-719.
Quantity of Land Total=16.00 Decimals or=0.16ACR. The Estimate completes. The rate of
L.G.E.D 2014-2015.
SUMMARY
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of RANENDRA NARAYAN DAS, S/O-
KHITENDRA NATH DASH, Senior officer Agroni Bank Ltd. Natore Branch, natore. of Present Land
Location-Borohorispur, Natore. Mouza:-Borohorispur, J.L.No:-RS-224, Khation No:-SA-624, RS-434,
PRO-2580. PlotNo:-RS-852. Quantity of Land Total=6.50 Decimals Or=0.065 ACR. The Estimate
completes. The rate of L.G.E.D 2014-2015.
Plinth Area =1650.00sft.
Frist Floor Total Repairing Estimated Cost Tk. =10, 00,000.00
Item No. 01:
Sand cement plaster, 12 mm thick with Portland and cement and sand
(minimum FM 1.5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall: 2 x 220'-0"x 10'-0" =4400.00sft.
=408.92 m2
@ Tk.167.01 per m2 Tk. =68,293.72
Item No.02:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-01
Total =4400.00 sft
=108.92 m2
@ Tk.133.57 per m2 Tk. =54,619.44
Item No.03:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 15 x 17'-0"x 4 " x 4" =27.76 cft
W = 12 x 27'-0"x 4"x 4" =35.28"
=63.04 cft
=1.78 m3
Item No.04:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 15 x 2'-6"x 6'-6" =243.75 sft
W = 12 x 5'-0"x 4'-6" =270.00 "
=513.75 sft
=47.75 m2
@ Tk.6384.61 per m2 Tk. =3,04,865.12
Item No.05:
Distemper Work at Door, Window's and necessary grills and etc. all
complete.
L.S Tk. =60,000.00
Item No.06:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of 1)MD. MOTALEB HOSSAIN, S/O-NUR
HOSSAIN, M/O-SOBURZAN BEGUM,2)MST. MONOWARA KHATUN, W/O-MD. MOTALEB
HOSSAIN, M/O-JOBALA BEGUM,of Present Land Location-Village-Kandivatua, P.O+P.S+Dist.-Natore.
Mouza:-Vita, J.L.No:-RS-144, Khation No:-Hal-377,PRO-611. Plot No:-RS-5552. Quantity of Land
Total=3.92 Decimals OR=0.0392 ACR. The Estimate completes. The rate of L.G.E.D 2015-2016.
Plinth Area =1016.42sft.
Ground Floor TotalEstimated Cost Tk. =21, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 5 x 6'-0"x 6'-0" x 8'-0" =1440.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 8'-0" =1568.00 cft
Base-F-3 2 x 15'-0"x 8'-0" x 8'-0" =1920.00 cft
=4928.00 cft.
=139.54 m3
@ Tk.74.39 per m3 Tk. =10,380.38
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 5 x 6'-0"x 6'-0" =180.00 sft.
Base-F-2 4 x 7'-0"x 7'-0" =196.00 sft.
Base-F-3 2 x 15'-0"x 8'-0" =240.00 sft.
Floor 1 x 46'-10"x 22'-3" =1042.03 sft.
=1658.03 sft.
=154.09 m2
@ Tk.229.63 per m2 Tk. =35,383.68
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 5 x 6'-0"x 6'-0" x 6'-0" =1080.00 cft
Base-F-2 4 x 7'-0"x 7'-0" x 6'-0" =1176.00 cft
Base-F-3 2 x 15'-0" x 8'-0" x 6'-0" =1440.00 cft
Floor 1x 46'-10"x 22'-3" x 2'-0" =2084.06 cft.
=5780.06 cft.=163.67 m3
@ Tk.642.21 per m3 Tk. =1,05,110.51
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 46'-10"x 22'-3" x 0'-4" =343.87 cft.
=9.73 m3
@ Tk.6163.79 per m3 Tk. =59,973.67
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 350'-0"x 0'-5" =147.00 sft.
=13.66 m2
@ Tk. 585.39 per m3 Tk. =7,996.42
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :5 x 6'-0"x 6'-0" x 1'-4" =239.40 cft
Base-F-2 :4x 7'-0"x 7'-0" x 1'-7" =309.68 "
Base-F-3 :2 x 15'-0"x 8'-0" x 1'-9" =420.00"
Footing C-1 :5 x 1'-3"x 1'-3" x 7'-0" =54.68"
Footing C-2 :4 x 1'-3"x 1'-6" x 7'-0" =52.50"
Footing C-3 :4 x 1'-3"x 1'-7"x 7'-0" =55.30 "
Vertical C-1 :5 x 1'-0"x 1'-0" x 10'-0" =50.00 "
Vertical C-2 :4 x 1'-0"x 1'-3" x 10'-0" =50.00 "
Vertical C-3 :4 x 1'-0"x 1'-4" x 10'-0" =53.20 "
Grade Beam :1 x 248'-0"x 0'-10"x 1'-3" =258.23"
Tai-Beam :1 x 248'-0"x 0'-10"x 0'-10" =172.08 "
Lintel :1 x 350'-0"x 0'-5"x 0'-6" =73.50 "
Sun-sheet :10 x 5'-0"x 1'-6"x 4" =24.75 "
Stair :2x2 x 14'-11"x 4'-0"x 6" =59.68 "
Step :2x2x1/2x4'-0"x 10"x6" =16.66 "
Fools Slab :2 x 6'-6"x 7'-0"x 4" =30.03 "
Roof Slab :1 x 46'-10"x 22'-3" x 5" =437.65"
=2357.34 cft
=66.75m3
@ Tk.9568.64 per m3 Tk. =6,38,706.72
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2357.34 x 1.2 x 490 =6287.38 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =4,71,427.75
Item No.08:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 46'-10"x 22'-3" =1042.03 "
=6741.03 sft
=626.48 m2
@ Tk.167.01 per m2 Tk. =1,04,628.42
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =6741.03 sft
=626.48 m2
@ Tk.133.57 per m2 Tk. =83,678.93
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 13 x 17'-0"x 4 " x 4" =24.06 cft
W = 12 x 27'-0"x 4"x 4" =35.28"
=59.34 cft
=1.68 m3
Item No.12:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 13 x 2'-6"x 6'-6" =211.25 sft
W = 12 x 5'-0"x 4'-6" =270.00 "
=481.25 sft
=44.72 m2
@ Tk.6384.61 per m2 Tk. =2,85,519.75
Item No.13:
Contingency for un for Seen work L.S Tk.= 4,853.25
Total Tk. =21,00,000.00
Total Tk. (Twenty One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of 1)MD. MOTALEB HOSSAIN, S/O-NUR
HOSSAIN, M/O-SOBURZAN BEGUM,2)MST. MONOWARA KHATUN, W/O-MD. MOTALEB
HOSSAIN, M/O-JOBALA BEGUM,of Present Land Location-Village-Kandivatua, P.O+P.S+Dist.-Natore.
Mouza:-Vita, J.L.No:-RS-144, Khation No:-Hal-377,PRO-611. Plot No:-RS-5552. Quantity of Land
Total=3.92 Decimals OR=0.0392 ACR. The Estimate completes. The rate of L.G.E.D 2015-2016.
Plinth Area =1016.42 sft.
First Floor TotalEstimated Cost Tk. =12, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :5 x 1'-0"x 1'-0" x 10'-0" =50.00 "
Vertical C-2 :4 x 1'-0"x 1'-3" x 10'-0" =50.00 "
Vertical C-3 :4 x 1'-0"x 1'-4" x 10'-0" =53.20 "
Tai-Beam :1 x 248'-0"x 0'-10"x 0'-10" =172.08 "
Lintel :1 x 350'-0"x 0'-5"x 0'-6" =73.50 "
Sun-sheet :10 x 5'-0"x 1'-6"x 4" =24.75 "
Stair :2x2 x 14'-11"x 4'-0"x 6" =59.68 "
Step :2x2x1/2x4'-0"x 10"x6" =16.66 "
Fools Slab :2 x 6'-6"x 7'-0"x 4" =30.03 "
Roof Slab :1 x 46'-10"x 22'-3" x 5" =437.65 "
=967.55 cft
=27.39m3
@ Tk.9568.64 per m3 Tk. =2,62,085.04
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
967.55 x 1.0 x 490 =2150.50 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =1,61,244.49
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 46'-10"x 22'-3" =1042.03 "
=6741.03 sft
=626.48 m2
@ Tk.167.01 per m2 Tk. =1,04,628.42
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =6741.03 sft
=626.48 m2
@ Tk.133.57 per m2 Tk. =83,678.93
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 13 x 17'-0"x 4 " x 4" =24.06 cft
W = 12 x 27'-0"x 4"x 4" =35.28 "
=59.34 cft
=1.68 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 13 x 2'-6"x 6'-6" =211.25 sft
W = 12 x 5'-0"x 4'-6" =270.00 "
=481.25 sft
=44.72 m2
@ Tk.6384.61 per m2 Tk. =2,85,519.75
Item No.08:
Contingency for un for Seen work L.S Tk.= 10,502.83
Total Tk. =12,00,000.00
Total Tk. (Twelve Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of 1)MD. MOTALEB HOSSAIN, S/O-NUR
HOSSAIN, M/O-SOBURZAN BEGUM,2)MST. MONOWARA KHATUN, W/O-MD. MOTALEB
HOSSAIN, M/O-JOBALA BEGUM,of Present Land Location-Village-Kandivatua, P.O+P.S+Dist.-Natore.
Mouza:-Vita, J.L.No:-RS-144, Khation No:-Hal-377,PRO-611. Plot No:-RS-5552. Quantity of Land
Total=3.92 Decimals OR=0.0392 ACR. The Estimate completes. The rate of L.G.E.D 2015-2016.
SUMMARY
“DETAILS ESTIMATE”
Details Estimated for the Five Storied Residential Building of MD.HAFIZUR RAHMAN, S/O-LATE MD.
CHOIYEN UDDIN of Present Land Location-Village-Nurpur Malonchi, P.O+P.S:-Bagatipara Dist.-Natore.
Mouza:-Kazla, J.L.No:-RS-144, Khation No:-SA-38,RS:-268,PRO-3209. Plot No:-SA-320,RS-1810.
Quantity of Land Total=4.95 Decimals OR=0.0495 Acre. The Estimate completes. The rate of L.G.E.D
2015-2016.
Plinth Area =133.84 sqm.
Boundary Wall & Main Gate Cost Tk. =5,00,000.00
Item No.01:
The structure consists of Brick & R.C.C boundary wall (10"x10") R.C.C
piller, 5", 10", & 5" thick 1st class brick work by (1:4) sand cement mortar
in/c. both side sand cement finishing. in/c colour work etc. all complete as
per direction of the E-I-C.
Total=187.00 rft.
@ Tk.12,50.00 per rft. Tk. =2,33,750.00
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base- 1x187'-0"x 1'-6" =280.50 sft.
=26.06 m2
@ Tk.229.63 per m2 Tk. =5,987.17
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base- 1 x 187'-0"x 1'-6" x 1'-0" =280.50 cft
Floor 1x 40'-9"x 53'-1" x 2'-0" =4326.02 cft.
=4606.52 cft.
=130.44 m3
@ Tk.642.21 per m3 Tk. =83,769.87
Item No.04:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 187'-0"x 0'-5" =78.54 sft.
=7.29 m2
@ Tk. 585.39 per m3 Tk. =4,272.99
Item No.05:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x187'-0"x 10"x 10'-0" =129.75 cft.
=3.67 m3
@ Tk.4243.87 per m3 Tk. =15,575.00
Item No.06:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 187'-0"x 7'-6" =1402.50 sft.
=130.34 m3
@ Tk.622.14 per m2 Tk. =81,089.72
Item No. 07:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1402.50 sft =2805.00 sft
=260.68 m2
@ Tk.167.01 per m2 Tk. =43,536.16
Item No.08:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-07
Total =2805.00 sft
=260.68 m2
@ Tk.133.57 per m2 Tk. =34,819.02
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 13 x 17'-0"x 4 " x 4" =24.06 cft
W = 12 x 27'-0"x 4"x 4" =35.28 "
=59.34 cft
=1.68 m3
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical :12 x 1'-0"x 1'-4" x 10'-0" =159.60 sft.
Tai-Beam :1 x 240'-0"x 0'-10"x 0'-10" =166.53 "
Lintel :1 x 280'-0"x 0'-5"x 0'-6" =58.8 "
Sun-sheet :8 x 5'-0"x 1'-6"x 4" =19.8 "
Stair :2x2 x 16'-5"x 0'-10"x 6" =27.35 "
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Fools Slab :1 x 6'-0"x 8'-0"x 4" =15.84 "
Roof Slab :1 x1011.44 sft. x 5" =424.8 "
=876.05 cft
=24.80 m3
“DETAILS ESTIMATE”
Details Estimated for the B.B.B Nesco Ltd. Natore office Main gate, Boundary wall, Re-construction and
replesment etc. work for extention of RHD. The Estimate completes. The rate of P.D.B -2014.
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
2 x 5'-0"x 5'-0" x 4'-0" =200.00 cft
2 x 4'-6"x 4'-6" x 4'-0" =162.00 cft
=362.00 cft
=10.25 m3
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Road(Gate) 1x 18'-0"x 15'-0" x 0'-3" =67.5 cft.
=1.91 m3
@ Tk.6163.79 per m3 Tk. =11,772.83
Item No.05:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base :1 x 5'-0"x 5'-0" x 1'-0" =25.00 cft
Base :1x 4'-6"x 4'-6" x 1'-0" =20.25 "
Footing :2 x 1'-3"x 1'-3" x 4'-0" =12.50"
Vertical :2 x 1'-0"x 1'-0" x 10'-0" =20.00"
Grade Beam :2 x 10'-0"x 0'-10"x 0'-10" =13.87"
Floor :1 x 18'-0"x 15'-0"x 5" =113.40 "
=205.02 cft
=5.80m3
@ Tk.9568.64 per m3 Tk. =55,498.11
Item No.06:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
205.02 x 1.2 x 490 =546.82 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =41,000.56
Item No.07:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 2x 18'-0"x 10'-0" =360.00 sft.
=33.45 m2
@ Tk.622.14 per m2 Tk. =20,810.58
Item No.12:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 13 x 2'-6"x 6'-6" =211.25 sft
W = 12 x 5'-0"x 4'-6" =270.00 "
=481.25 sft
=44.72 m2
@ Tk.6384.61 per m2 Tk. =2,85,519.75
Item No.13:
Contingency for un for Seen work L.S Tk.= 4,853.25
Total Tk. =21,00,000.00
Total Tk. (Twenty One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of 1.SAMIMA CHAUDHURY, W/O- MD.
MAHMUDUL HAQUE CHAUDHURY, 2.RUMANA CHOWDHURY, W/O-S.M. ARIFUR
RAHAMAN, 3.SHOHANA CHOWDHURY, W/O-B.M. SAMIUL ISLAM, of Present Land Location-
Village-Mirpara, P.O+ P.S+ Dist.-Natore. Mouza:-Borgacha, J.L.No:-RS-146, Khation No:-RS-715. PRO-
6563. Plot No:-RS-4176, 4177. Quantity of Land Total (3.00+7.00)=10.00 Decimals Or=0.10ACR. The
Estimate completes. The rate of L.G.E.D 2019-2020.
Plinth Area =161.46 m2.
Second and Thard Floor incomplete work Estimated Cost Tk. =25, 00,000.00
Item No. 01:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2538.00 sft =5076.00 sft
Ceiling: 1 x 44'-7"x 42'-6" =1894.65 "
=6970.65 sft
=647.82 m2
@ Tk.167.01 per m2 Tk. =1,08,717.15
Item No.02:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-01
Total =6970.65 sft
=647.82 m2
@ Tk.133.57 per m2 Tk. =86,529.32
Item No.03:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D =2 x14 x 17'-0"x 4 " x 4" =51.83 cft
W =2x 10 x 27'-0"x 4"x 4" =58.80 "
=110.63 cft
=3.13 m3
Item No.08:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.(Two Floo)
L.S Tk. =4, 60,000.00
Item No.09:
Contingency for un for Seen work L.S Tk.= 76,822.83
Total Tk. =25,00,000.00
Total Tk. (Twenty Five Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the four storied Residential building of MOST. SHANAZ BEGUM, W/O-
MD.SAIFUL ISLAM of Present Location-Village-Borohorishpur, P.O+ P.S+ Dist.-Natore. Mouza-
Borohorishpur, J.L.No:-RS-224. Khation No:-RS-302.PRO-2297. Plot No:-SA-167.RS-256. Quantity of
Land Total =5.00 Decimals. The Estimate completes. The rate of L.G.E.D 2018-2019.
Plinth Area =868.89 sft.
Ground Floor TotalEstimated Cost Tk. =17, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base- 12 x 6'-6"x 6'-6" x 8'-0" = 4056.00 cft
= 114.85 m3
@ Tk.74.39 per m3 Tk. =8,543.70
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base- 12 x 6'-6"x 6'-6" = 507.00 sft.
Floor 1 x 33'-0"x 26'-4" = 868.89 sft.
= 1375.89 sft.
= 127.87 m2
@ Tk.229.63 per m2 Tk. =29,362.79
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base- 12 x 6'-0"x 6'-0" x 7'-0" = 3024.00 cft
Floor 1x 33'-0"x 26'-4" x 7'-0" = 6082.23 cft.
= 9106.23 cft.
= 257.85 m3
@ Tk.642.21 per m3 Tk. =1,65,598.52
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 33'-0"x 26'-4" x 0'-4" = 286.73 cft.
= 8.11 m3
@ Tk.6163.79 per m3 Tk. =50,045.76
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 265'-0"x 0'-5" = 111.30 sft.
= 10.34 m2
@ Tk. 585.39 per m3 Tk. =6,052.90
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base- :12 x 6'-6"x 6'-6" x 1'-3" = 633.75 cft
Footing :12x 1'-3"x 1'-3" x 7'-0" = 131.25"
Vertical :12x 1'-0"x 1'-0" x 10'-0" = 120.00 "
Grade Beam :1 x 205'-0"x 0'-10"x 1'-3" = 213.45 "
Tai-Beam :1 x 205'-0"x 0'-10"x 0'-10" = 142.24 "
Lintel :1 x 250'-0"x 0'-5"x 0'-6" = 52.50 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" = 17.32 "
Stair :2x2 x 14'-11"x 4'-0"x 6" = 119.36 "
Step :12x2x1/2x4'-0"x 10"x6" = 59.97"
Fools Slab :2 x 8'-6"x 5'-0"x 4" = 28.05 "
Roof Slab :1 x 35'-0"x 30'-0" x 5" = 441.00"
= 1958.89 cft
= 55.46 m3
@ Tk.9568.64 per m3 Tk. = 5,30,676.77
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
1958.89 x 1.10 x 490 = 4790.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =3,59,154.20
Item No.08:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 245'-0"x 9'-6" = 2327.50 sft.
Deduction Door and window:
D = 7 x 3'-0"x 5'-6" = 136.50 sft
W = 7 x 5'-0"x 4'-6" = 141.75 "
(-) = 278.25 sft
Net work = 2049.25 sft.
= 190.45 m2
@ Tk.622.14 per m2 Tk. =1,18,486.56
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 1 x 245'-0"x 10'-0" = 2450.00 sft
Ceiling: 1 x 38'-0"x 29'-0" = 1102.00 "
= 3552.00 sft
= 330.11 m2
@ Tk.167.01 per m2 Tk. =55,131.67
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total = 3552.00 sft
= 330.11 m2
@ Tk.133.57 per m2 Tk. = 44,092.79
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 7 x 17'-0"x 4 " x 4" = 12.95 cft
W = 7 x 27'-0"x 4"x 4" = 20.58 "
= 33.53 cft
= 0.95 m3
@ Tk.75943.71 per m3 Tk. = 72,146.50
Item No.12:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 7 x 3'-4"x 6'-6" = 151.51 sft
W = 7 x 5'-0"x 4'-6" = 157.50 "
= 309.01 sft
= 28.71 m2
@ Tk.6384.61 per m2 Tk. = 1,83,302.15
Item No.13:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. = 50,000.00
Item No.14:
Contingency for un for Seen work L.S Tk.= 27,405.69
Total Tk =17,00,000.00
Total Tk. (Seventeen Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the four storied Residential building of MOST. SHANAZ BEGUM, W/O-
MD.SAIFUL ISLAM of Present Location-Village-Borohorishpur, P.O+ P.S+ Dist.-Natore. Mouza-
Borohorishpur, J.L.No:-RS-224. Khation No:-RS-302.PRO-2297. Plot No:-SA-167.RS-256. Quantity of
Land Total =5.00 Decimals. The Estimate completes. The rate of L.G.E.D 2018-2019.
Plinth Area =868.89 sft.
First Floor TotalEstimated Cost Tk. =10, 50,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical :12x 1'-0"x 1'-0" x 10'-0" = 120.00 "
Grade Beam :1 x 205'-0"x 0'-10"x 1'-3" = 213.45 "
Tai-Beam :1 x 205'-0"x 0'-10"x 0'-10" = 142.24 "
Lintel :1 x 250'-0"x 0'-5"x 0'-6" = 52.50 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" = 17.32 "
Stair :2x2 x 14'-11"x 4'-0"x 6" = 119.36 "
Step :12x2x1/2x4'-0"x 10"x6" = 59.97"
Fools Slab :2 x 8'-6"x 5'-0"x 4" = 28.05 "
Roof Slab :1 x 35'-0"x 30'-0" x 5" = 441.00"
= 1193.89 cft
= 33.80 m3
@ Tk.9568.64 per m3 Tk. = 3,23,420.03
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1193.89 x 1.00 x 490 = 2660.00kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =1,99,446.80
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 245'-0"x 9'-6" = 2327.50 sft.
Deduction Door and window:
D = 7 x 3'-0"x 5'-6" = 136.50 sft
W = 7 x 5'-0"x 4'-6" = 141.75 "
(-) = 278.25 sft
Net work = 2049.25 sft.
= 190.45 m2
@ Tk.622.14 per m2 Tk. =1,18,486.56
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 1 x 245'-0"x 10'-0" = 2450.00 sft
Ceiling: 1 x 38'-0"x 29'-0" = 1102.00 "
= 3552.00 sft
= 330.11 m2
@ Tk.167.01 per m2 Tk. =55,131.67
Item No.05:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 7 x 17'-0"x 4 " x 4" = 12.95 cft
W = 7 x 27'-0"x 4"x 4" = 20.58 "
= 33.53 cft
= 0.95 m3
SUMMARY
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 45'-4"x 37'-3" x 0'-4" =557.21 cft.
=15.77 m3
@ Tk.6163.79 per m3 Tk. =97,202.96
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 350'-0"x 0'-5" =147.00 sft.
=13.66 m2
@ Tk. 585.39 per m3 Tk. =7,996.42
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" =191.52 cft
Base-F-2 :6x 7'-0"x 7'-0" x 1'-7" =464.52"
Base-F-3 :2 x 14'-0"x 7'-0" x 1'-9" =343.00"
Base-F-4 :2 x 16'-0"x 8'-0" x 1'-10" =469.24"
Footing C-1 :4 x 1'-3"x 1'-6" x 7'-0" =52.50"
Footing C-2 :6 x 1'-3"x 1'-7" x 7'-0" =82.95"
Footing C-3 :2 x 1'-3"x 1'-9"x 7'-0" =30.62 "
Footing C-4 :6 x 1'-3"x 1'-11" x 7'-0" =100.80"
Vertical C-1 :4 x 1'-0"x 1'-0" x 10'-0" =40.00 "
Vertical C-2 :6 x 1'-0"x 1'-4" x 10'-0" =79.80"
Vertical C-3 :2 x 1'-0"x 1'-6" x 10'-0" =30.00"
Vertical C-4 :6 x 1'-0"x 1'-8" x 10'-0" =100.20"
Grade Beam :1 x 325'-0"x 0'-10"x 1'-3" =338.40"
Tai-Beam :1 x 325'-0"x 0'-10"x 0'-10" =225.51"
Lintel :1 x 350'-0"x 0'-5"x 0'-6" =73.50"
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-11"x 4'-0"x 6" =59.68"
Step :2x2x1/2x4'-0"x 10"x6" =16.66"
Fools Slab :1 x 7'-0"x 13'-4"x 4" =30.79 "
Fools Slab :1 x 8'-6"x 4'-0"x 4" =11.22"
Roof Slab :1 x 48'-6"x 40'-4" x 6" =978.00"
=3736.23 cft
=105.78m3
@ Tk.9568.64 per m3 Tk. =10,12,170.73
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
3736.23 x 1.5 x 490 = 12456.35kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =9,33,977.12
Item No.08:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7198.96 sft
=669.04 m2
@ Tk.167.01 per m2 Tk. =1,11,736.37
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total =7198.96 sft
=669.04 m2
@ Tk.133.57 per m2 Tk. =89,363.67
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 14 x 17'-0"x 4 " x 4" =25.92 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=52.38 cft
=1.48 m3
“DETAILS ESTIMATE”
Details Estimated for the Three Storied Residential Building of MD. MAHAFUZUR RAHMAN, S/O-
MD. ABDUR RAHMAN PORAMANIK, M/O-MST. SAMIA BEGUM of Present Land Location-Village-
Kathalbaria, P.O-Lakhipur, P. S+Dist.-Natore. Mouza: - Kathalbaria, J.L. No: -SA-346, RS-122. Khation
No: -Sabak-318. SA-320. RS-370. PRO-1331. Plot No: -SA-1566. RS-2099. Quantity of Land Total=5.00
Decimals Or=0.05 ACR. The Estimate completes. The rate of L.G.E.D 2018-2019.
Plinth Area =1649.13 sft.
First Floor Estimated Cost Tk. =28, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 10'-0" =40.00 "
Vertical C-2 :6 x 1'-0"x 1'-4" x 10'-0" =79.80"
Vertical C-3 :2 x 1'-0"x 1'-6" x 10'-0" =30.00"
Vertical C-4 :6 x 1'-0"x 1'-8" x 10'-0" =100.20"
Tai-Beam :1 x 325'-0"x 0'-10"x 0'-10" =225.51"
Lintel :1 x 350'-0"x 0'-5"x 0'-6" =73.50"
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-11"x 4'-0"x 6" =59.68"
Step :2x2x1/2x4'-0"x 10"x6" =16.66"
Fools Slab :1 x 7'-0"x 13'-4"x 4" =30.79 "
Fools Slab :1 x 8'-6"x 4'-0"x 4" =11.22"
Roof Slab :1 x 48'-6"x 40'-4" x 6" =978.00"
=1662.67 cft
=47.08m3
@ Tk.9568.64 per m3 Tk. =4,50,491.57
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1662.67 x 1.5 x 490 = 5543.23kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =4,15,631.38
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 350'-0"x 9'-6" =3325.00 sft.
Deduction Door and window:
D = 14 x 3'-0"x 6'-6" =273.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =475.50 sft
Network =2849.50 sft.
=264.82 m2
@ Tk.622.14 per m2 Tk. =1,64,755.11
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2849.50 sft =5699.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7198.96 sft
=669.04 m2
@ Tk.167.01 per m2 Tk. =1,11,736.37
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =7198.96 sft
=669.04 m2
@ Tk.133.57 per m2 Tk. =89,363.67
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 14 x 17'-0"x 4 " x 4" =25.92 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=52.38 cft
=1.48 m3
SUMMARY
Item No.03:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 48'-8"x 32'-3" x 0'-4" =517.86 cft.
=14.66 m3
@ Tk.6163.79 per m3 Tk. =90,361.16
Item No.04:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 350'-0"x 0'-5" =147.00 sft.
=13.66 m2
@ Tk. 585.39 per m3 Tk. =7,996.42
Item No.05:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(used FM 1.80) and 20mm downgraded Stone chips as per design in base,
bed beam, raft foundation, grade beam including cost of reinforcement &
its fabrication etc. all complete as per direction of the E/I.
Pile :28 x 50'-8"x 1'-0" x 1'-0" =1418.48 cft
Base- :16 x 6'-0"x 6'-0" x 2'-6" =1440.00 "
Footing :16 x 1'-6"x 2'-0" x 7'-0" =336.00 "
Vertical :16 x 1'-3"x 1'-8" x 11'-0" =365.20 "
Grade Beam :1 x 325'-0"x 1'-0"x 1'-4" =432.25"
Tai-Beam :1 x 325'-0"x 1'-0"x 1'-0" =325.00"
Lift :1 x 19'-4"x 0'-10"x 10" =13.41 "
Stair :1x2 x 20'-0"x 4'-0"x 6" =80.00"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Roof Slab :1 x 48'-8"x 32'-3" x 6" =784.64"
=5198.31 cft
=147.19m3
@ Tk.9568.64 per m3 Tk. =14,08,408.12
Item No.06:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: cranking looking bending binding with 22 BAG
wire etc. all complete supported on mortar blocks (1:3) with cement &
sand metal chairs & hangers as per drawing & direction etc. complete as
per direction of the E/I.
Quantity taken Item No-05
5198.31 x 1.90 x 490 = 21952.40kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =16,45,990.95
Item No.07:
250mm thick brick work in approved bonds in superstructure walls in
ground flood 1st with cement mortar 1:6 with portland cement and sand
(used FM 1.50) including racking out joints curing etc. complete as per
design including supply carrying & cost of all materials
1 x162'-0"x 10"x 6'-0" =809.67 cft.
=22.92 m3
@ Tk.4243.87 per m3 Tk. =97,269.50
Item No.08:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. =70,000.00
Item No.09:
Required size of Septic tank 18'-0" long 6'-0" breadth, 7'-0" Height in/c
250mm thick brick wall both sides and cement plaster R.C.C Top man
hole cover etc. all complete of the E/I.
Item No.10:
Required size of soak well 6'-0" & 20'-0" height in/c 250mm thick
Jeffery brick work in/c R.C.C Top in/c all finishing etc. all complete of
the E/I.
1 Nos @ Tk.90, 000.0 Tk. =90,000.00
Item No.11:
Contingency for un for Seen work L.S Tk.= 69,409.90
Total Tk. =39,00,000.00
Total Tk. (Thirty-Nine Lac’s) only.
FIRST FLOOR
Plinth Area =146.07m2
=1571.71 sft.
First Floor Total Cost Tk. =11, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(used FM 1.80) and 20mm downgraded Stone chips as per design in base,
bed beam, raft foundation, grade beam including cost of reinforcement &
its fabrication etc. all complete as per direction of the E/I.
Vertical :16 x 1'-3"x 1'-8" x 11'-0" =365.20 "
Tai-Beam :1 x 325'-0"x 1'-0"x 1'-0" =325.00"
Lift :1 x 19'-4"x 0'-10"x 10" =13.41 "
Stair :1x2 x 20'-0"x 4'-0"x 6" =80.00"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Roof Slab :1 x 48'-8"x 32'-3" x 6" =784.64"
=1571.58 cft
=44.50m3
@ Tk.9568.64 per m3 Tk. =4,25,804.48
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: cranking looking bending binding with 22 BAG
wire etc. all complete supported on mortar blocks (1:3) with cement &
sand metal chairs & hangers as per drawing & direction etc. complete as
per direction of the E/I.
Quantity taken Item No-01
1571.58 x 2.00 x 490 = 6986.06kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,23,814.77
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (used FM 1.50) including racking out joints curing etc.
complete as per design including supply carrying & cost of all materials
and labor etc. all complete as per direction of the E/I.
Wall- 1x 150'-0"x 3'-6" =525.00 sft.
=48.79 m2
@ Tk.622.14 per m2 Tk. =30,354.21
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(used FM 1.5) in proportion 1:4 finished, booth with neat cement finish on
plinth walls, floors or wherever directed including preparing the surfaces,
rounding of corners and junctions, curing including cost of all materials
and their carrying etc. complete as per specifications and direction o f the
E/I.
Ceiling: 1 x 56'-6"x 43'-6" =2457.75 sft
=228.41 m2
@ Tk.167.01 per m2 Tk. =38,146.75
Item No.05:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. =60,000.00
Item No.06:
Contingency for un for Seen work L.S Tk.= 21,879.79
Total Tk. =11,00,000.00
Total Tk. (Eleven Lac’s) only.
SECOND FLOOR
Plinth Area =146.07m2
=1571.71 sft.
Second Floor Total Cost Tk. =11, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(used FM 1.80) and 20mm downgraded Stone chips as per design in base,
bed beam, raft foundation, grade beam including cost of reinforcement &
its fabrication etc. all complete as per direction of the E/I.
Vertical :16 x 1'-3"x 1'-8" x 11'-0" =365.20 "
Tai-Beam :1 x 325'-0"x 1'-0"x 1'-0" =325.00"
Lift :1 x 19'-4"x 0'-10"x 10" =13.41 "
Stair :1x2 x 20'-0"x 4'-0"x 6" =80.00"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Roof Slab :1 x 48'-8"x 32'-3" x 6" =784.64"
=1571.58 cft
=44.50m3
@ Tk.9568.64 per m3 Tk. =4,25,804.48
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: cranking looking bending binding with 22 BAG
wire etc. all complete supported on mortar blocks (1:3) with cement &
sand metal chairs & hangers as per drawing & direction etc. complete as
per direction of the E/I.
Quantity taken Item No-01
1571.58 x 2.00 x 490 = 6986.06kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,23,814.77
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (used FM 1.50) including racking out joints curing etc.
complete as per design including supply carrying & cost of all materials
and labor etc. all complete as per direction of the E/I.
Wall- 1x 150'-0"x 3'-6" =525.00 sft.
=48.79 m2
@ Tk.622.14 per m2 Tk. =30,354.21
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(used FM 1.5) in proportion 1:4 finished, booth with neat cement finish on
plinth walls, floors or wherever directed including preparing the surfaces,
rounding of corners and junctions, curing including cost of all materials
and their carrying etc. complete as per specifications and direction o f the
E/I.
Ceiling: 1 x 56'-6"x 43'-6" =2457.75 sft
=228.41 m2
@ Tk.167.01 per m2 Tk. =38,146.75
Item No.05:
Supplying fitting and fixing of Sanitary, Water Supply, and Electrification
other’s work etc. all complete of the E/I.
L.S Tk. =60,000.00
Item No.06:
Contingency for un for Seen work L.S Tk.= 21,879.79
Total Tk. =11,00,000.00
Total Tk. (Eleven Lac’s) only.
Total Cost:( 39,00,000.00) + (11,00,000.00) + (11,00,000.00)
In Total=61,00,000.00
In Total Tk. (Sixty-One Lac’s) only.
DETAILS ESTIMATE
Details Estimated for the Construction of SREE SREE KALI MONDIR of Present Land Location-Village-
Kanaikhali, P.O+P. S+Dist.-Natore. Mouza:-Natore, J.L. No:-SA-204, RS-151. Khation No:-SA-1812. Plot
No:-SA-2646. Quantity of Land Total=4.00 Decimals Or=0.04 ACR. The Estimate completes. The rate of
L.G.E.D 2018-2019.
Plinth Area =571.99 sft.
Ground Floor TotalEstimated Cost Tk. =15, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 6 x 8'-0"x 6'-0" x 7'-0" =2016.00 cft
=57.08 m3
@ Tk.74.39 per m3 Tk. =4246.18
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 6 x 8'-"x 6'-0" =288.00 sft.
=26.76 m2
@ Tk.229.63 per m2 Tk. =6,144.89
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 6 x 8'-0"x 6'-0" x 6'-0" =1728.00 cft
=48.93 m3
@ Tk.642.21 per m3 Tk. =31,423.33
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 24'-0"x 23'-10" x 0'-4" =188.75 cft.
=5.34 m3
@ Tk.6163.79 per m3 Tk. =32,914.63
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 95'-0"x 0'-5" =39.90 sft.
=3.70 m2
@ Tk. 585.39 per m3 Tk. =2,165.94
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :6x 8'-0"x 6'-0" x 1'-6" =432.00 cft
Footing C-1 :6 x 1'-3"x 1'-3" x 7'-0" =65.62 "
Footing C-2 :6 x 1'-6"x 1'-6" x 7'-0" =94.50 "
Vertical C-1 :6 x 1'-0"x 1'-0" x 30'-0" =180.00 "
Vertical C-2 :6 x 1'-3"x 1'-3" x 30'-0" =281.25 "
Grade Beam :1 x 190'-0"x 1'-0"x 1'-3" =237.50 "
Tai-Beam :1 x 215'-0"x 1'-0"x 1'-1" =232.20 "
Lintel :1 x 95'-0"x 0'-5"x 0'-10" =33.23 "
Round slab :1 x 80'-0"x 0'-0" x 5" =33.60 "
Roof Slab :1 x 29'-0"x 28'-6" x 5" =347.13"
=1937.03 cft
=54.85 m3
@ Tk.9568.64 per m3 Tk. =5,24,839.90
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
1937.03 x 1.5 x 490 = 6457.93kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =4,84,215.59
Item No.08:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 95'-0"x 14'-6" =1377.50 sft.
=128.02 m2
@ Tk.622.14 per m2 Tk. =79,646.36
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 1377.50 sft =2755.00 sft
Ceiling: 1 x 29'-0"x 28'-6" =826.50 "
=3581.50 sft
=332.85 m2
@ Tk.167.01 per m2 Tk. =55,589.27
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total =3581.50 sft
=332.85 m2
@ Tk.133.57 per m2 Tk. =44,458.77
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 2 x 17'-0"x 4 " x 4" =3.70 cft
W = 2 x 27'-0"x 4"x 4" =5.88 "
=9.58 cft
=0.27 m3
Details Estimated for the Construction of Four storied Commercial & Residential building of
MD. HAZIZUR RAHMAN S/0-Late Choiyen uddin of Present Land Location-Village-Nurpur malonchi,
P.O+P.S:-Bagatipara. Dist.-Natore. Mouza:-Kazla, J.L. No:-RS-144. Khation No:-SA-38. RS-268. PRO-
3209. Plot No:-SA-320. RS-1810. Quantity of Land Total=4.95 Decimals Or=0.0495 ACR. The Estimate
completes. The rate of L.G.E.D 2018-2019.
(Ground floor, first floor and Second floor Rest work Estimated cost)
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of SUKANTO KURMI, S/O-MR. SHANKOR
KURMI @ SHREE SHANKOR ROY, M/O-SUMITRA KURMI of Present Land Location-Village-
Lenguria, P.O-Natore, P. S+Dist.-Natore. Mouza: -Lengra, J.L. No:-RS-74. Khation No:-RS-293. PRO-
1361. Plot No:-RS-344. Quantity of Land Total=3.00 Decimals Or=0.03 ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =832.00 sft.
Ground Floor TotalEstimated Cost Tk. =28, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 2 x 6'-0"x 6'-0" x 8'-0" =576.00 cft
Base-F-2 3x 6'-6"x 6'-6" x 8'-0" =1014.00 cft
Base-F-3 5 x 10'-6"x 6'-6" x 8'-0" =2730.00 cft
=4320.00 cft.
=122.32 m3
@ Tk.74.39 per m3 Tk. =9,099.38
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 2 x 6'-0"x 6'-0" =72.00 sft.
Base-F-2 3 x 6'-6"x 6'-6" =126.75 sft.
Base-F-3 5 x 10'-6"x 6'-6" =341.25 sft.
Floor 1 x 16'-0"x 52'-0" =832.00 sft.
=1372.00 sft.
=127.50 m2
@ Tk.229.63 per m2 Tk. =29,277.82
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 2 x 6'-0"x 6'-0" x 7'-0" =504.00 cft
Base-F-2 3x 6'-6"x 6'-6" x 7'-0" =887.25 cft
Base-F-3 5 x 10'-6" x 6'-6" x 7'-0" =2388.75 cft
Floor 1x 16'-0"x 52'-0" x 6'-0" =4992.00 cft.
=8772.00 cft.
=248.39 m3
@ Tk.642.21 per m3 Tk. =1,59,518.54
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 16'-0"x 52'-0" x 0'-4" =274.56 cft.
=7.77 m3
@ Tk.6163.79 per m3 Tk. =47,892.64
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 170'-0"x 0'-5" =113.40 sft.
=10.54 m2
@ Tk. 585.39 per m3 Tk. =6,152.44
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :2 x 6'-0"x 6'-0" x 1'-4" =95.76 cft
Base-F-2 :3x 6'-6"x 6'-6" x 1'-6" =190.12"
Base-F-3 :5 x 10'-6"x 6'-6" x 1'-7" =539.17"
Footing C-1 :2 x 1'-3"x 1'-5" x 7'-0" =24.85"
Footing C-2 :3 x 1'-3"x 1'-6" x 7'-0" =39.37"
Footing C-3 :10 x 1'-3"x 1'-7"x 7'-0" =138.25 "
Vertical C-1 :2 x 1'-0"x 1'-2" x 10'-0" =23.20 "
Vertical C-2 :3 x 1'-0"x 1'-3" x 10'-0" =37.50"
Vertical C-3 :10 x 1'-0"x 1'-4" x 10'-0" =133.00"
Grade Beam :1 x 236'-0"x 0'-10"x 1'-3" =245.73"
Tai-Beam :1 x 236'-0"x 0'-10"x 0'-10" =163.75"
Lintel :1 x 270'-0"x 0'-5"x 0'-6" =56.70"
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 16'-2"x 2'-6"x 6" =80.80"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Fools Slab :1 x 10'-6"x 4'-10"x 4" =16.74 "
Roof Slab :1 x 19'-0"x 55'-0" x 5" =438.90"
=2244.49 cft
=63.55m3
@ Tk.9568.64 per m3 Tk. =6,08,087.07
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2244.49 x 1.7 x 490 =8480.72kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =6,35,884.38
Item No.08:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 270'-0"x 9'-6" =2565.00 sft.
Deduction Door and window:
D = 8 x 3'-0"x 6'-6" =156.00 sft
W = 8 x 4'-0"x 4'-6" =144.00 "
(-) =300.00 sft
Network =2265.00 sft.
=210.50 m2
@ Tk.622.14 per m2 Tk. =1,30,960.47
Item No. 09:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2265.00 sft =4530.00 sft
Ceiling: 1 x 19'-0"x 55'-0" =1045.00 "
=5575.00 sft
=518.12 m2
@ Tk.167.01 per m2 Tk. =86,531.22
Item No.10:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total =5575.00 sft
=518.12 m2
@ Tk.133.57 per m2 Tk. =69,205.28
Item No.11:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 8 x 17'-0"x 4 " x 4" =14.81 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=41.27 cft
=1.16 m3
Item No.12:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 8 x 2'-6"x 6'-6" =130.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
=332.50 sft
=30.90 m2
@ Tk.6384.61 per m2 Tk. =1,97,284.44
Item No.13:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of SUKANTO KURMI, S/O-MR. SHANKOR
KURMI @ SHREE SHANKOR ROY, M/O-SUMITRA KURMI of Present Land Location-Village-
Lenguria, P.O-Natore, P. S+Dist.-Natore. Mouza: -Lengra, J.L. No:-RS-74. Khation No:-RS-293. PRO-
1361. Plot No:-RS-344. Quantity of Land Total=3.00 Decimals Or=0.03 ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =832.00 sft.
First Floor TotalEstimated Cost Tk. =17, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :2 x 1'-0"x 1'-2" x 10'-0" =23.20 "
Vertical C-2 :3 x 1'-0"x 1'-3" x 10'-0" =37.50"
Vertical C-3 :10 x 1'-0"x 1'-4" x 10'-0" =133.00"
Tai-Beam :1 x 236'-0"x 0'-10"x 0'-10" =163.75"
Lintel :1 x 270'-0"x 0'-5"x 0'-6" =56.70"
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 16'-2"x 2'-6"x 6" =80.80"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Fools Slab :1 x 10'-6"x 4'-10"x 4" =16.74 "
Roof Slab :1 x 19'-0"x 55'-0" x 5" =438.90"
=971.24 cft
=27.50 m3
@ Tk.9568.64 per m3 Tk. =2,63,137.60
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
971.24 x 1.7 x 490 =3669.79 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,75,160.85
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 270'-0"x 9'-6" =2565.00 sft.
Deduction Door and window:
D = 8 x 3'-0"x 6'-6" =156.00 sft
W = 8 x 4'-0"x 4'-6" =144.00 "
(-) =300.00 sft
Network =2265.00 sft.
=210.50 m2
@ Tk.622.14 per m2 Tk. =1,30,960.47
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2265.00 sft =4530.00 sft
Ceiling: 1 x 19'-0"x 55'-0" =1045.00 "
=5575.00 sft
=518.12 m2
@ Tk.167.01 per m2 Tk. =86,531.22
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total =5575.00 sft
=518.12 m2
@ Tk.133.57 per m2 Tk. =69,205.28
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 8 x 17'-0"x 4 " x 4" =14.81 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=41.27 cft
=1.16 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 8 x 2'-6"x 6'-6" =130.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
=332.50 sft
=30.90 m2
@ Tk.6384.61 per m2 Tk. =1,97,284.44
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of SUKANTO KURMI, S/O-MR. SHANKOR
KURMI @ SHREE SHANKOR ROY, M/O-SUMITRA KURMI of Present Land Location-Village-
Lenguria, P.O-Natore, P. S+Dist.-Natore. Mouza: -Lengra, J.L. No:-RS-74. Khation No:-RS-293. PRO-
1361. Plot No:-RS-344. Quantity of Land Total=3.00 Decimals Or=0.03 ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =832.00 sft.
Third Floor TotalEstimated Cost Tk. =18, 50,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, coarse sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :2 x 1'-0"x 1'-2" x 10'-0" =23.20 "
Vertical C-2 :3 x 1'-0"x 1'-3" x 10'-0" =37.50"
Vertical C-3 :10 x 1'-0"x 1'-4" x 10'-0" =133.00"
Tai-Beam :1 x 236'-0"x 0'-10"x 0'-10" =163.75"
Lintel :1 x 270'-0"x 0'-5"x 0'-6" =56.70"
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 16'-2"x 2'-6"x 6" =80.80"
Step :2x2x1/2x4'-0"x 10"x6" =3.33"
Fools Slab :1 x 10'-6"x 4'-10"x 4" =16.74 "
Roof Slab :1 x 19'-0"x 55'-0" x 5" =438.90"
=971.24 cft
=27.50 m3
@ Tk.9568.64 per m3 Tk. =2,63,137.60
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
971.24 x 1.7 x 490 =3669.79 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,75,160.85
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 270'-0"x 9'-6" =2565.00 sft.
Deduction Door and window:
D = 8 x 3'-0"x 6'-6" =156.00 sft
W = 8 x 4'-0"x 4'-6" =144.00 "
(-) =300.00 sft
Network =2265.00 sft.
=210.50 m2
@ Tk.622.14 per m2 Tk. =1,30,960.47
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 2265.00 sft =4530.00 sft
Ceiling: 1 x 19'-0"x 55'-0" =1045.00 "
=5575.00 sft
=518.12 m2
@ Tk.167.01 per m2 Tk. =86,531.22
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-09
Total =5575.00 sft
=518.12 m2
@ Tk.133.57 per m2 Tk. =69,205.28
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 8 x 17'-0"x 4 " x 4" =14.81 cft
W = 9 x 27'-0"x 4"x 4" =26.46 "
=41.27 cft
=1.16 m3
Item No.07:
Manufacturing and supplying of Door's and Window's Panel Shutter in/c
best quality local timbers in/c fitting fixing etc. all complete as per
direction of the E/I.
D = 8 x 2'-6"x 6'-6" =130.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
=332.50 sft
=30.90 m2
@ Tk.6384.61 per m2 Tk. =1,97,284.44
Item No.08:
Supplying and fitting fixing floor Tiles work (Homogenous tiles) as per
approved Choice in/c carrying and finishing etc. all complete of E/I.
SUMMARY
In total Tk.=81,00,000.00
VALUATION CERTIFICATE
(Title in questions may be discussed with legal adviser)
This is to certify that the and Residential Land of 1. MD. ASHRAFUL ISLAM, S/O-MD. SHAFIKUL
ISLAM. 2. MST. MARZINA KHATUN, W/O- MD. ASHRAFUL ISLAM. of present location-Kanaikhali,
P.S+P.O+Dist.:- Natore and assessed the present market value (per-haps) below as:-
LAND LOCATION
The land is situated by the South side of Dhaka to Rajshahi road attached Natore pourashava road near at
kanaikhali stadium. The place is heart of the city town. The land is very suitable place for Residence and
Business.
Plinth Area:
Ground floor Total = 2507.77 sft
@ Tk. 2260.00 Per sft Tk. =56,67,560.20
1st floor Total = 2507.77 sft
@ Tk. 1130.00 Per sft Tk. =28,33,780.10
2nd floor Total = 2507.77 sft
@ Tk. 1130.00 Per sft Tk. =28,33,780.10
3rd floor Total = 2507.77 sft
@ Tk. 1130.00 Per sft Tk. =28,33,780.10
4th floor Total = 2507.77 sft
@ Tk. 1130.00 Per sft Tk. =28,33,780.10
Total Tk.=2,26,02,680.60
Say=2,26,02,680.00
Total Tk. (Two Crore Twenty-six Lac’s Two Thousand Six Hundred Eighty taka) only.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of MISS. KHADIZA KHANAM DINK, W/O.
MD. ABUL KASHEM SHEK, M/O-LATE BEGUM SAKINA, of Present Land Location-Village-
Burervag, P. O+P.S-Naldanga, Dist.Natore. Mouza- Burervag, J.L. No: -RS-35, Khation No: -RS-146, Pro-
349. Plot No: -RS-96. Quantity of Land Total=4.00 Decimals Or=0.040ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =1189.56 sft.
Ground Floor TotalEstimated Cost Tk. =34, 00,000.00
Item No.01:
Earthwork in excavation of canals, ponds, drains, foundation reaches etc
by excavating earth, filling baskets, carrying throwing to desired place &
distance in all type of soils, except work & gravels slushy & organic soil,
leveling dressing etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 8'-0" =1152.00 cft
Base-F-2 5 x 7'-0"x 7'-0" x 8'-0" =1960.00 cft
Base-F-3 1 x 8'-0"x 8'-0" x 8'-0" =512.00 cft
Base-F-4 2 x 15'-6"x 8'-6" x 8'-0" =2108.00 cft
=5732.00 cft.
=162.31 m3
@ Tk.74.39 per m3 Tk. =12,074.24
Item No.02:
Single layer brick flat soling in foundation or anywhere with 1 st class or
picked jhama bricks true to level including filling the gaps with sand
(minimum FM 0.80) @ 0.012m3 of sand per m2 over 75mm thick sand
(minimum FM 0.80) cushion etc. all complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" =144.00 sft.
Base-F-2 5 x 7'-0"x 7'-0" =245.00 sft.
Base-F-3 1 x 8'-0"x 8'-0" =64.00 sft.
Base-F-4 2 x 15'-6"x 8'-6" =263.50 sft.
Floor 1 x 49'-7"x 24'-0" =1189.68 sft.
=1906.18 sft.
=177.15 m2
@ Tk.229.63 per m2 Tk. =40,678.95
Item No.03:
Sand (minimum FM 1.80) filling in foundation trenches and plinth
including supplying placing in layers of 225mm thickness, watering if
necessary and compacting by drop hammer (durum’s) etc. all complete
including supply carrying and cost of all materials and lab our etc. all
complete as per direction of the E/I.
Base-F-1 4 x 6'-0"x 6'-0" x 7'-0" =1008.00 cft
Base-F-2 5 x 7'-0"x 7'-0" x 7'-0" =1715.00 cft
Base-F-3 1 x 8'-0" x 8'-0" x 7'-0" =448.00 cft
Base-F-4 2 x 15'-6"x 8'-6" x 7'-0" =1844.50 cft
Floor 1x 49'-7"x 24'-0" x 4'-0" =4759.68 cft.
=9775.18 cft.
=276.79 m3
@ Tk.642.21 per m3 Tk. =1,77,757.30
Item No.04:
Mass concrete by (1:3:6) sand cement mortar Proportion by approved
strength in/c carrying etc. all complete as per direction of the E/I.
Floor 1x 49'-7"x 24'-0" x 0'-4" =1189.92 cft.
=33.69 m3
@ Tk.6163.79 per m3 Tk. =2,07,658.08
Item No.05:
25mm thick Damp proof course (D.P.C) work at plinth level by (1:2:4) casting in/c carrying etc. all
complete of E/I.
Wall- 1 x 368'-0"x 0'-5" =154.56 sft.
=14.36 m2
@ Tk. 585.39 per m3 Tk. =8,406.20
Item No.06:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Base-F-1 :4 x 6'-0"x 6'-0" x 1'-4" =191.52 cft
Base-F-2 :5x 7'-0"x 7'-0" x 1'-6" =367.50"
Base-F-3 :1 x 8'-0"x 8'-0" x 1'-8" =106.88"
Base-F-4 :2 x 15'-6"x 8'-6" x 1'-10" =482.99"
Footing C-1 :4 x 1'-3"x 1'-3" x 7'-0" =43.75"
Footing C-2 :5 x 1'-3"x 1'-6" x 7'-0" =65.62"
Footing C-3 :1 x 1'-6"x 1'-9"x 7'-0" =18.37 "
Footing C-4 :4 x 1'-3"x 1'-9" x 7'-0" =61.25"
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :5 x 1'-0"x 1'-3" x 12'-0" =75.00"
Vertical C-3 :1 x 1'-3"x 1'-6" x 12'-0" =22.50"
Vertical C-4 :4 x 1'-0"x 1'-6" x 12'-0" =72.00"
Grade Beam :1 x 252'-6"x 0'-10"x 1'-6" =315.49 "
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-10"x 3'-6"x 6" =103.83"
Step :2x2x1/2x3'-6"x 10"x6" =2.91"
Fools Slab :4 x 3'-11"x 4'-0"x 4" =20.69 "
Roof Slab :1 x 49'-7"x 24'-0" x 5" =499.76"
=2754.63 cft =78.00m3
@ Tk.9568.64 per m3 Tk. =7,46,353.92
Item No.07:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-06
2754.63 x 1.2 x 490 =7347.00 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =5,50,878.06
Item No.08:
250mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:6 with portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials
1 x145'-0"x 10"x 2'-6" =301.96 cft.
=8.55 m3
@ Tk.4243.87 per m3 Tk. =36,285.08
Item No.09:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 305'-0"x 9'-6" =2897.50 sft.
Deduction Door and window:
D = 16 x 3'-0"x 6'-6" =312.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =514.5 sft
Net work =2383.00 sft.
=221.46 m2
@ Tk.622.14 per m2 Tk. =1,37,779.12
Item No. 10:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3050.00 sft =6100.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7599.96 sft
=706.31 m2
@ Tk.167.01 per m2 Tk. =1,17,960.83
Item No.11:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-10
Total =7599.96 sft
=706.31 m2
@ Tk.133.57 per m2 Tk. =94,341.82
Item No.12:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 16 x 17'-0"x 4 " x 4" =29.62 cft
W = 9 x 27'-0"x 4"x 4" =26.46"
=56.08 cft
=1.58 m3
Item No.18:
Required size of Septic tank 10'-0" long 5'-0" breadth, 6'-0" Height
in/c 250mm thick brick wall both sides and cement plaster R.C.C Top
man hole cover etc. all complete of the E/I.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of MISS. KHADIZA KHANAM DINK, W/O.
MD. ABUL KASHEM SHEK, M/O-LATE BEGUM SAKINA, of Present Land Location-Village-
Burervag, P. O+P.S-Naldanga, Dist.Natore. Mouza- Burervag, J.L. No: -RS-35, Khation No: -RS-146, Pro-
349. Plot No: -RS-96. Quantity of Land Total=4.00 Decimals Or=0.040ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =1189.56 sft.
First Floor TotalEstimated Cost Tk. =21, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :5 x 1'-0"x 1'-3" x 12'-0" =75.00"
Vertical C-3 :1 x 1'-3"x 1'-6" x 12'-0" =22.50"
Vertical C-4 :4 x 1'-0"x 1'-6" x 12'-0" =72.00"
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-10"x 3'-6"x 6" =103.83"
Step :2x2x1/2x3'-6"x 10"x6" =2.91"
Fools Slab :4 x 3'-11"x 4'-0"x 4" =20.69 "
Roof Slab :1 x 49'-7"x 24'-0" x 5" =499.76"
=1101.26 cft
=31.18 m3
@ Tk.9568.64 per m3 Tk. =2,98,350.19
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1101.26 x 1.5 x 490 =3671.53 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,75,291.31
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 305'-0"x 9'-6" =2897.50 sft.
Deduction Door and window:
D = 16 x 3'-0"x 6'-6" =312.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =514.5 sft
Net work =2383.00 sft.=221.46m2
@ Tk.622.14 per m2 Tk. =1,37,779.12
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3050.00 sft =6100.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7599.96 sft
=706.31 m2
@ Tk.167.01 per m2 Tk. =1,17,960.83
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =7599.96 sft
=706.31 m2
@ Tk.133.57 per m2 Tk. =94,341.82
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 16 x 17'-0"x 4 " x 4" =29.62 cft
W = 9 x 27'-0"x 4"x 4" =26.46"
=56.08 cft
=1.58 m3
Item No.12:
Contingency for un for Seen work L.S Tk.= 52,941.14
Total Tk. =21,00,000.00
Total Tk. (Twenty-One Lac’s) only.
“DETAILS ESTIMATE”
Details Estimated for the Four Storied Residential Building of MISS. KHADIZA KHANAM DINK, W/O.
MD. ABUL KASHEM SHEK, M/O-LATE BEGUM SAKINA, of Present Land Location-Village-
Burervag, P. O+P.S-Naldanga, Dist.Natore. Mouza- Burervag, J.L. No: -RS-35, Khation No: -RS-146, Pro-
349. Plot No: -RS-96. Quantity of Land Total=4.00 Decimals Or=0.040ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
Plinth Area =1189.56 sft.
Third Floor TotalEstimated Cost Tk. =22, 00,000.00
Item No.01:
Reinforcement cement concrete (1:2:4) with Portland cement, course sand
(minimum FM 1.80) and 20mm downgraded Stone chips as per design in
base, bed beam, raft foundation, grade beam or anywhere in below plinth
level including cost of reinforcement & its fabrication etc. all complete as
per direction of the E/I.
Vertical C-1 :4 x 1'-0"x 1'-0" x 12'-0" =48.00 "
Vertical C-2 :5 x 1'-0"x 1'-3" x 12'-0" =75.00"
Vertical C-3 :1 x 1'-3"x 1'-6" x 12'-0" =22.50"
Vertical C-4 :4 x 1'-0"x 1'-6" x 12'-0" =72.00"
Tai-Beam :1 x 252'-6"x 0'-10"x 0'-10" =175.20 "
Lintel :1 x 305'-0"x 0'-5"x 0'-6" =64.05 "
Sun-sheet :7 x 5'-0"x 1'-6"x 4" =17.32 "
Stair :2x2 x 14'-10"x 3'-6"x 6" =103.83"
Step :2x2x1/2x3'-6"x 10"x6" =2.91"
Fools Slab :4 x 3'-11"x 4'-0"x 4" =20.69 "
Roof Slab :1 x 49'-7"x 24'-0" x 5" =499.76"
=1101.26 cft
=31.18 m3
@ Tk.9568.64 per m3 Tk. =2,98,350.19
Item No.02:
Supplying & fabrication of deformed MS Rod (Deformed Bar Sixty
grade) reinforcement of required sizes and length as per drawing including
straightening removing: use if any cranking looking bending binding with
22 BAG wire etc. all complete supported on mortar blocks (1:3) with
cement & sand metal chairs & hangers as per drawing & direction etc.
complete as per direction of the E/I.
Quantity taken Item No-01
1101.26 x 1.5 x 490 =3671.53 kg
2.2046 x 100
@ Tk.74.98 per kg Tk. =2,75,291.31
Item No.03:
125mm thick brick work in approved bonds in superstructure walls or
anywhere in ground flood 1st with cement mortar 1:4 with Portland
cement and sand (minimum FM 1.50) including racking out joints
curing etc. complete as per design including supply carrying & cost of
all materials and labor etc. all complete as per direction of the E/I.
Wall- 1x 305'-0"x 9'-6" =2897.50 sft.
Deduction Door and window:
D = 16 x 3'-0"x 6'-6" =312.00 sft
W = 9 x 5'-0"x 4'-6" =202.50 "
(-) =514.5 sft
Net work =2383.00 sft.=221.46m2
@ Tk.622.14 per m2 Tk. =1,37,779.12
Item No. 04:
Sand cement plaster, 12mm thick with Portland and cement and sand
(minimum FM 1'5) in proportion 1:4 finished, booth with neat cement
finish on plinth walls, floors or wherever directed including preparing the
surfaces, rounding of corners and junctions, curing including cost of all
materials and their carrying etc. complete as per specifications and
direction of the E/I.
Wall : 2x 3050.00 sft =6100.00 sft
Ceiling: 1 x 53'-7"x 28'-0" =1499.96 "
=7599.96 sft
=706.31 m2
@ Tk.167.01 per m2 Tk. =1,17,960.83
Item No.05:
Distemper work at wall and ceiling two coat over a coat as per approved
color in/c carrying etc. all complete of the E/I.
Quantity Item No-04
Total =7599.96 sft
=706.31 m2
@ Tk.133.57 per m2 Tk. =94,341.82
Item No.06:
Manufacturing and supplying of Door's and Window's Frame in/c best
quality local timbers in/c fitting fixing etc. all complete as per direction of
the E/I.
D = 16 x 17'-0"x 4 " x 4" =29.62 cft
W = 9 x 27'-0"x 4"x 4" =26.46"
=56.08 cft
=1.58 m3
Item No.12:
Contingency for un for Seen work L.S Tk.= 62,941.14
Total Tk. =22,00,000.00
Total Tk. (Twenty-Two Lac’s) only.
DETAILS ESTIMATED COST
Details Estimated for the Four Storied Residential Building of MISS. KHADIZA KHANAM DINK, W/O.
MD. ABUL KASHEM SHEK, M/O-LATE BEGUM SAKINA, of Present Land Location-Village-
Burervag, P. O+P.S-Naldanga, Dist.Natore. Mouza- Burervag, J.L. No: -RS-35, Khation No: -RS-146, Pro-
349. Plot No: -RS-96. Quantity of Land Total=4.00 Decimals Or=0.040ACR. The Estimate completes. The
rate of L.G.E.D 2018-2019.
SUMMARY
In Total Tk.=98,50,000.00
This is to certify that the and Residential Land of 1. MISS. KHADIZA KHANAM DINK, W/O. Late
ABUL KASHEM SHEK, M/O-LATE BEGUM SAKINA, 2. A. K. M. KHURSHID ALOM S/O- LATE
ABUL KASHEM SHEK of present location- Village-Burervag, P. O+P.S-Naldanga, Dist.Natore and
assessed the present market value (per-haps) below as: -
LAND LOCATION
The land is situated by the West side of Natore to Naldanga road attached Naldanga pourashava road near at
Naldanga Upzila more. The place is heart of the city town. The land is very suitable place for Residence and
Business.