task_code status_code wbs_id

Activity ID Activity Status WBS Code


EC2430 Not Started EC00620
EC1080 Completed EC00620
EC1010 Completed EC00620
EC2440 Not Started EC00620.1
EC1650 Not Started EC00620.1.3
EC1580 Not Started EC00620.1.3
EC1660 Not Started EC00620.1.3
EC1690 Not Started EC00620.1.3
EC1840 Not Started EC00620.1.3
EC1900 Not Started EC00620.1.3
EC1980 Not Started EC00620.1.3
EC2110 Not Started EC00620.1.3
EC1360 Not Started EC00620.1.3
EC2140 Not Started EC00620.1.3
EC1990 Not Started EC00620.1.3
EC1410 Not Started EC00620.1.3
EC1470 Not Started EC00620.1.3
EC1500 Not Started EC00620.1.3
EC1520 Not Started EC00620.1.3
EC1490 Not Started EC00620.1.3
EC1510 Not Started EC00620.1.3
EC1570 Not Started EC00620.1.3
EC2370 Not Started EC00620.1.4
EC1820 Not Started EC00620.1.4
EC2240 Not Started EC00620.1.4
EC1550 Not Started EC00620.1.4
EC1630 Not Started EC00620.1.4
EC1670 Not Started EC00620.1.4
EC1700 Not Started EC00620.1.4
EC1790 Not Started EC00620.1.4
EC1850 Not Started EC00620.1.4
EC1910 Not Started EC00620.1.4
EC1950 Not Started EC00620.1.4
EC2080 Not Started EC00620.1.5
EC2270 Not Started EC00620.1.5
EC1090 Completed EC00620.1.1
EC1140 Completed EC00620.1.1
EC1170 Completed EC00620.1.1
EC1190 Completed EC00620.1.1
EC1210 Completed EC00620.1.1
EC1240 In Progress EC00620.1.1
EC1250 Not Started EC00620.1.1
EC1300 Not Started EC00620.1.1
EC1310 Not Started EC00620.1.1
EC1340 Not Started EC00620.1.1
EC1350 Not Started EC00620.1.1
EC1390 Not Started EC00620.1.2
EC1400 Not Started EC00620.1.2
EC1540 Not Started EC00620.1.2
EC1780 Not Started EC00620.1.2
EC1530 Not Started EC00620.1.2
EC1420 Not Started EC00620.5
EC1430 Not Started EC00620.5
EC1810 Not Started EC00620.5
EC2090 Not Started EC00620.5
EC2280 Not Started EC00620.5
EC2310 Not Started EC00620.5
EC2400 Not Started EC00620.5
EC2380 Not Started EC00620.5
EC2390 Not Started EC00620.5
EC2420 Not Started EC00620.2
EC1640 Not Started EC00620.2.1
EC1150 Completed EC00620.2.1
EC1220 Completed EC00620.2.1
EC1230 Completed EC00620.2.1
EC1260 Completed EC00620.2.1
EC1290 In Progress EC00620.2.1
EC1320 Not Started EC00620.2.1
EC1330 Not Started EC00620.2.1
EC1380 Not Started EC00620.2.1
EC1480 Not Started EC00620.2.1
EC1620 Not Started EC00620.2.1
EC1710 Not Started EC00620.2.2
EC1720 Not Started EC00620.2.2
EC1860 Not Started EC00620.2.2
EC1870 Not Started EC00620.2.2
EC2020 Not Started EC00620.2.2
EC1730 Not Started EC00620.2.3
EC1800 Not Started EC00620.2.3
EC1880 Not Started EC00620.2.3
EC1920 Not Started EC00620.2.3
EC1830 Not Started EC00620.2.3
EC1890 Not Started EC00620.2.3
EC1930 Not Started EC00620.2.3
EC1960 Not Started EC00620.2.3
EC1940 Not Started EC00620.2.3
EC1970 Not Started EC00620.2.3
EC2050 Not Started EC00620.2.3
EC2130 Not Started EC00620.2.3
EC2160 Not Started EC00620.2.3
EC2220 Not Started EC00620.2.3
EC2300 Not Started EC00620.2.3
EC1740 Not Started EC00620.2.3
EC2320 Not Started EC00620.2.3
EC2230 Not Started EC00620.2.3
EC2150 Not Started EC00620.2.4
EC2170 Not Started EC00620.2.4
EC2200 Not Started EC00620.2.4
EC2210 Not Started EC00620.2.4
EC2410 Not Started EC00620.2.4
EC2040 Not Started EC00620.2.4
EC2070 Not Started EC00620.2.4
EC2120 Not Started EC00620.2.4
EC2000 Not Started EC00620.2.4
EC2030 Not Started EC00620.2.4
EC2330 Not Started EC00620.2.5
EC1020 Completed EC00620.6
EC1030 Completed EC00620.6
EC1180 In Progress EC00620.6
EC1280 Not Started EC00620.6
EC1590 Not Started EC00620.6
EC1680 Not Started EC00620.6
EC2190 Not Started EC00620.6
EC2060 Not Started EC00620.6
EC2180 Not Started EC00620.6
EC2340 Not Started EC00620.7
EC1610 Not Started EC00620.7
EC1000 Completed EC00620.7
EC2260 Not Started EC00620.7
EC2250 Not Started EC00620.7
EC1270 Not Started EC00620.7
EC1130 Completed EC00620.7
EC1200 In Progress EC00620.7
EC1100 Completed EC00620.7
EC1110 Completed EC00620.7
EC1440 Not Started EC00620.7
EC1040 Completed EC00620.7
EC1750 Not Started EC00620.7
EC1050 Completed EC00620.7
EC2290 Not Started EC00620.7
EC1600 Not Started EC00620.8
EC2360 Not Started EC00620.8
task_name start_date
Activity Name (*)Start
Substantial Completion - All TCO
Curbing 11/2/2010 7:00
Building Pad Delivered by Owner 11/1/2010 7:00
Complete Building 1
Install Backing & Cauld Windows Floor 4 11/15/2011 13:48
Stucco Bands 11/15/2011 9:36
Stucco Grey 11/29/2011 15:24
Stucco Finish Coat 12/28/2011 8:00
Caulk 2/1/2012 8:00
Stucco Band Trim 2/14/2012 13:48
Paint Exterior 3/8/2012 13:48
Demobilize Scaffolding 3/26/2012 12:48
Mobilize Scaffolding 8/8/2011 14:24
Shell Complete
Install Railings 3/8/2012 13:48
Install Exterior Windows and Sliding Glass Doors Floor 1 8/24/2011 14:24
Install Exterior Windows and Sliding Glass Doors Floor 2 9/15/2011 7:00
Install Exterior Windows and Sliding Glass Doors Floor 3 10/5/2011 8:36
Install Exterior Windows and Sliding Glass Doors Floor 4 10/21/2011 7:00
Install Backing & Cauld Windows Floor1 9/16/2011 7:00
Install Backing & Cauld Windows Floor 2 10/6/2011 8:36
Install Backing & Cauld Windows Floor 3 10/24/2011 7:00
Final Inspections and Punchlist 11/13/2012 13:48
Building 2 Elevators Complete 12/2/2011 11:12
Tenant Finishes for Clubhouse Areas 7/3/2012 7:00
Unit Finishes Building North - Floor 1 9/28/2011 14:24
Unit Finishes Building South - Floor 1 10/5/2011 14:24
Unit Finishes Building North - Floor 2 10/12/2011 14:24
Unit Finishes Building South - Floor 2 10/19/2011 14:24
Unit Finishes Building North - Floor 3 10/26/2011 14:24
Unit Finishes Building South - Floor 3 11/2/2011 14:24
Unit Finishes Building North - Floor 4 11/9/2011 15:24
Unit Finishes Building South - Floor 4 11/16/2011 15:24
Pool & Deck 3/28/2012 12:48
Pergola and Amenities 9/19/2012 8:36
Building Pad Including UG Utils 11/2/2010 8:00
First Floor Masonry Structure 1/6/2011 11:00
Second Floor Slab & Collar Beam 1/25/2011 11:00
Second Floor Masonry Structure 3/2/2011 8:00
Third Floor Slab & Collar Beam 3/15/2011 8:00
Third Floor Masonry Structure 4/20/2011 7:00
Fourth Floor Slab & Collar Beam 5/6/2011 7:00
Fourth Floor Masonry Structure 6/10/2011 7:00
Roof Slab 6/28/2011 7:00
Stair and Elevator Masonry Structure 8/2/2011 7:00
Roof Slab/Collar Beam 8/8/2011 14:24
Place Roof Trusses and Sheathing 8/24/2011 14:24
Place Mechanical Equipment Supports 8/24/2011 14:24
Felt and Tile Roofing 9/28/2011 14:24
Roof Complete
Built-Up Asphalt Roofing 9/28/2011 14:24
Start Garage 6/23/2011 13:00
Shop Drawings, Review & Approval 6/23/2011 13:00
Fab & Delivery 10/5/2011 13:00
Erect Precast Structure 1/18/2012 14:00
Fire Protection and Lighting 6/1/2012 13:00
Finishes, Barrier Cables & Striping 8/15/2012 13:00
Complete Garage
Punchlist Garage 11/27/2012 14:00
Complete Garage 1
Complete Building 2
Roof Slab/Collar Beam 8/29/2011 7:12
Building Slab Incl. UG Utils 11/30/2010 8:00
First Floor Masonry Structure 2/7/2011 8:00
Second Floor Slab & Collar Beam 3/24/2011 8:00
Second Floor Masonry Structure 3/28/2011 11:00
Third Floor Slab & Collar Beam 4/8/2011 13:00
Third Floor Masonry Structure 5/12/2011 13:00
Fourth Floor Slab & Collar Beam 5/31/2011 13:00
Fourth Floor Masonry Structure 7/5/2011 13:00
Roof Slab 7/21/2011 13:00
Stair and Elevator Masonry Structure 8/22/2011 8:48
Place Roof Trusses and Sheathing 10/3/2011 7:12
Place Mechanical Equipment Supports 10/3/2011 7:12
Built-Up Asphalt Roofing 11/4/2011 7:12
Felt and Tile Roofing 11/4/2011 7:12
Roof Complete
Install Exterior Windows and Sliding Glass Doors Floor 1 10/3/2011 7:12
Install Exterior Windows and Sliding Glass Doors Floor 2 10/28/2011 7:12
Install Exterior Windows and Sliding Glass Doors Floor 3 11/21/2011 14:00
Install Exterior Windows and Sliding Glass Doors Floor 4 12/15/2011 9:48
Install Backing & Cauld Windows Floor1 10/31/2011 7:12
Install Backing & Cauld Windows Floor 2 11/22/2011 14:00
Install Backing & Cauld Windows Floor 3 12/16/2011 9:48
Install Backing & Cauld Windows Floor 4 1/16/2012 9:48
Stucco Bands 1/18/2012 9:48
Stucco Grey 2/3/2012 9:48
Stucco Finish Coat 3/8/2012 9:48
Caulk 4/11/2012 8:48
Stucco Band Trim 4/27/2012 8:48
Paint Exterior 6/8/2012 8:48
Demobilize Scaffolding 8/16/2012 8:48
Mobilize Scaffolding 10/3/2011 7:12
Shell Complete
Install Railings 6/8/2012 8:48
Unit Finishes Building North - Floor 3 2/1/2012 14:00
Unit Finishes Building South - Floor 3 2/8/2012 14:00
Unit Finishes Building North - Floor 4 2/15/2012 14:00
Unit Finishes Building South - Floor 4 2/22/2012 14:00
Final Inspections and Punchlist 11/27/2012 8:12
Building 1 Elevators Complete 1/11/2012 14:00
Unit Finishes Building North - Floor 2 1/18/2012 14:00
Unit Finishes Building South - Floor 2 1/25/2012 14:00
Unit Finishes Building North - Floor 1 1/4/2012 14:00
Unit Finishes Building South - Floor 1 1/11/2012 14:00
Courtyard Walks and Amenities 9/4/2012 8:48
Design Building Addition 11/1/2010 7:00
Shop Drawings, Review and Approval 11/1/2010 8:00
Fab & Delivery 2/22/2011 8:00
Erect Precast Structure 5/31/2011 9:30
Fire Protection and Lighting 10/14/2011 9:30
Finishes and Striping 12/29/2011 10:30
Complete Garage
Punch List Garage 4/26/2012 9:30
Complete Garage 2
Curbs & Paving 9/4/2012 8:48
Curbs & Paving 10/14/2011 9:30
Curbing 11/1/2010 8:00
Entry Feature/Sign Wall 6/1/2012 13:00
Fountain/Water Feature 5/25/2012 13:00
Finish Paving, Striping and Signs 6/2/2011 9:11
Walkways 11/15/2010 8:00
Roadway Pavers 2/23/2011 8:00
Storm Drainage Site Work 11/2/2010 8:00
Site Electrical Work & Temp Power 11/2/2010 8:00
Electric to Building 2 Power Vault 8/24/2011 14:24
Electric to Building 4 Power Vault 11/1/2010 8:00
Electric to Building 1 Power Vault 10/3/2011 7:12
Electric to Building 3 Power Vault 11/1/2010 8:00
Curbs & Paving 6/1/2012 13:00
Site Cleanup 5/24/2011 7:00
Landscape & Irrigation 11/20/2012 13:48
end_date resource_list delete_record_flag
(*)Finish (*)Resources Delete This Row
1/8/2014 13:48

1/8/2014 13:48
11/30/2011 9:36 Thermal Protection Subcontractor
11/29/2011 15:24 Thermal Protection Subcontractor
12/27/2011 17:00 Thermal Protection Subcontractor
1/31/2012 17:00 Thermal Protection Subcontractor
2/14/2012 13:48 Thermal Protection Subcontractor
3/1/2012 13:48 Thermal Protection Subcontractor
3/26/2012 12:48 Painter
4/11/2012 13:48 Thermal Protection Subcontractor
8/24/2011 15:24 Thermal Protection Subcontractor
4/27/2012 13:48
4/27/2012 12:48 Thermal Protection Subcontractor
9/22/2011 8:00 Thermal Protection Subcontractor
10/12/2011 9:36 Thermal Protection Subcontractor
10/28/2011 8:00 Thermal Protection Subcontractor
11/21/2011 14:48 Thermal Protection Subcontractor
9/29/2011 13:48 Thermal Protection Subcontractor
10/19/2011 15:24 Thermal Protection Subcontractor
11/2/2011 9:36 Thermal Protection Subcontractor
1/3/2013 9:36 Finishes & Fit-out Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties
3/12/2012 16:00 Conveying Subcontractor, Electrician
1/3/2013 10:36 Finishes & Fit-out Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties
7/6/2012 13:48 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor a
7/18/2012 8:00 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor a
7/25/2012 8:00 FF&E Specialties, Painter, Drywall Subcontractor, Finishes & Fit-out Subcontractor, Rough Carpenter,
8/1/2012 8:00 Finish Carpenter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E S
8/8/2012 8:00 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor a
8/15/2012 8:00 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor a
8/24/2012 10:12 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor a
8/31/2012 10:12 Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor,
10/17/2012 9:36 Pool Installation Subcontractor, Pool Installation Subcontractor
11/29/2012 14:48 Pool Installation Subcontractor, Pool Installation Subcontractor
1/7/2011 8:00 Concrete Foundation Subcontractor
1/26/2011 11:00 Laborer-Construction
2/25/2011 11:00 Laborer-Construction
3/18/2011 8:00 Laborer-Construction
4/21/2011 8:00 Laborer-Construction
5/6/2011 9:00 Laborer-Construction
6/10/2011 8:00 Laborer-Construction, Laborer-Construction
6/28/2011 8:00 Laborer-Construction, Laborer-Construction
8/2/2011 8:00 Laborer-Construction, Laborer-Construction
8/8/2011 15:24 Laborer-Construction, Laborer-Construction
8/24/2011 15:24 Laborer-Construction, Laborer-Construction
9/28/2011 15:24 Roofing Subcontractor, Specialty Metal Fabricator Subcontractor, Roofing Subcontractor, Specialty M
9/28/2011 15:24 Roofing Subcontractor, Roofing Subcontractor
12/2/2011 13:12 Roofing Subcontractor, Roofing Subcontractor
12/2/2011 11:12
11/15/2011 13:12 Roofing Subcontractor, Roofing Subcontractor

10/5/2011 14:00 Concrete Foundation Subcontractor, Project Managers, Concrete Foundation Subcontractor, Project M
1/18/2012 15:00 Concrete Foundation Subcontractor, Project Managers, Concrete Foundation Subcontractor, Project M
6/1/2012 13:00 Concrete Foundation Subcontractor, Project Managers
9/13/2012 14:00 Concrete Foundation Subcontractor, Fire Suppression Subcontractor, Electrician, Project Managers, C
11/27/2012 15:00 Concrete Foundation Subcontractor, Project Managers, Concrete Foundation Subcontractor, Project M
12/18/2012 8:12
12/18/2012 8:12 Concrete Foundation Subcontractor, Project Managers
12/18/2012 8:12
3/11/2013 8:12
10/3/2011 8:12 Laborer-Construction, Laborer-Construction
2/9/2011 8:00 Concrete Foundation Subcontractor, Project Managers
2/25/2011 17:00 Laborer-Construction
4/29/2011 8:00 Laborer-Construction
4/11/2011 11:00 Laborer-Construction
5/12/2011 14:00 Laborer-Construction
5/31/2011 14:00 Laborer-Construction, Laborer-Construction
7/5/2011 14:00 Laborer-Construction, Laborer-Construction
7/21/2011 14:00 Laborer-Construction, Laborer-Construction
8/22/2011 9:48 Laborer-Construction, Laborer-Construction
8/29/2011 8:12 Laborer-Construction, Laborer-Construction
11/4/2011 8:12 Roofing Subcontractor, Specialty Metal Fabricator Subcontractor, Roofing Subcontractor, Specialty M
11/4/2011 8:12 Roofing Subcontractor, Roofing Subcontractor
12/22/2011 15:00 Roofing Subcontractor, Roofing Subcontractor
1/11/2012 15:00 Roofing Subcontractor, Roofing Subcontractor
1/11/2012 14:00
11/4/2011 8:12 Thermal Protection Subcontractor, Glass & Glazing Subcontractor, Thermal Protection Subcontractor
11/29/2011 15:00 Thermal Protection Subcontractor, Glass & Glazing Subcontractor, Thermal Protection Subcontractor
12/22/2011 9:48 Thermal Protection Subcontractor, Glass & Glazing Subcontractor
1/20/2012 9:48 Thermal Protection Subcontractor, Glass & Glazing Subcontractor
11/16/2011 9:12 Thermal Protection Subcontractor, Thermal Protection Subcontractor
12/7/2011 9:48 Thermal Protection Subcontractor
1/5/2012 9:48 Thermal Protection Subcontractor
2/1/2012 9:48 Thermal Protection Subcontractor
2/3/2012 9:48 Thermal Protection Subcontractor
3/8/2012 9:48 Thermal Protection Subcontractor
4/11/2012 8:48 Thermal Protection Subcontractor
4/27/2012 9:48 Thermal Protection Subcontractor, Thermal Protection Subcontractor
6/1/2012 9:48 Thermal Protection Subcontractor, Thermal Protection Subcontractor
8/16/2012 9:48 Thermal Protection Subcontractor, Thermal Protection Subcontractor
9/4/2012 9:48 Thermal Protection Subcontractor, Thermal Protection Subcontractor
10/19/2011 8:12 Thermal Protection Subcontractor, Thermal Protection Subcontractor
9/4/2012 9:48
7/31/2012 9:48 Thermal Protection Subcontractor, Thermal Protection Subcontractor
11/7/2012 11:24 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
11/14/2012 11:24 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
11/19/2012 8:12 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
11/27/2012 8:12 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
3/11/2013 7:12 Finishes & Fit-out Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HV
4/18/2012 8:48 Conveying Subcontractor, Electrician
10/24/2012 10:24 HVAC, Electrician, Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Sub
10/31/2012 10:24 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
10/17/2012 8:48 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
10/24/2012 8:48 Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Drywal
1/14/2013 13:24 Landscaping Subcontractor, Landscaping Subcontractor

2/10/2011 8:00 Concrete Foundation Subcontractor, Project Managers


5/31/2011 10:30 Concrete Foundation Subcontractor, Project Managers
10/14/2011 10:30 Concrete Foundation Subcontractor, Project Managers, Concrete Foundation Subcontractor, Project M
1/27/2012 11:30 Concrete Foundation Subcontractor, Fire Suppression Subcontractor, Electrician, Project Managers, C
4/26/2012 9:30 Concrete Foundation Subcontractor, Project Managers
7/5/2012 10:30
7/5/2012 10:30 Concrete Foundation Subcontractor, Project Managers, Concrete Foundation Subcontractor, Project M
7/5/2012 10:30
12/26/2012 13:24 Paving & Roadways Subcontractor, Paving & Roadways Subcontractor
1/9/2012 8:18 Paving & Roadways Subcontractor, Paving & Roadways Subcontractor
2/15/2011 8:00 Paving & Roadways Subcontractor
10/26/2012 15:36 FF&E Specialties, FF&E Specialties
11/7/2012 16:36 Pool Installation Subcontractor, Pool Installation Subcontractor
8/10/2011 10:11 Paving & Roadways Subcontractor, Paving & Roadways Subcontractor
2/16/2011 9:36 Landscaping Subcontractor
6/2/2011 10:11 Landscaping Subcontractor
2/15/2011 8:00 Utilities Subcontractor
11/17/2010 17:00 Electrician
1/5/2012 9:00 Electrician, Electrician
2/11/2011 8:00 Electrician
1/11/2012 15:00 Electrician, Electrician
12/6/2010 8:00 Electrician
9/13/2012 14:00 Paving & Roadways Subcontractor, Paving & Roadways Subcontractor
8/2/2011 8:00 Landscaping Subcontractor, Landscaping Subcontractor
1/8/2014 13:48 Landscaping Subcontractor, Project Managers
ber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor

ber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor


enter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor
enter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor
-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC
er, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor, Finishes & Fit-out Subcontractor, Rough Carpenter
enter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor
enter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor, Finish
enter, Millwork Subcontractor, Floor and Carpet Layer, Plumber, Electrician, HVAC, FF&E Specialties, Painter, Drywall Subcontractor
alties, Painter, Drywall Subcontractor, Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Carpenter, Millwork Subcontractor
or, Roofing Subcontractor, Specialty Metal Fabricator Subcontractor

te Foundation Subcontractor, Project Managers


te Foundation Subcontractor, Project Managers

ractor, Electrician, Project Managers, Concrete Foundation Subcontractor, Fire Suppression Subcontractor, Electrician, Project Managers
te Foundation Subcontractor, Project Managers

or, Roofing Subcontractor, Specialty Metal Fabricator Subcontractor

tor, Thermal Protection Subcontractor, Glass & Glazing Subcontractor


tor, Thermal Protection Subcontractor, Glass & Glazing Subcontractor
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
and Carpet Layer, Painter, Plumber, HVAC, Electrician

penter, Finish Carpenter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician
enter, Millwork Subcontractor, Drywall Subcontractor, Floor and Carpet Layer, Painter, Plumber, HVAC, Electrician

te Foundation Subcontractor, Project Managers


ractor, Electrician, Project Managers, Concrete Foundation Subcontractor, Fire Suppression Subcontractor, Electrician, Project Managers

te Foundation Subcontractor, Project Managers


nter, Drywall Subcontractor
nter, Drywall Subcontractor
Plumber, Electrician, HVAC
ontractor, Rough Carpenter
nter, Drywall Subcontractor
nter, Drywall Subcontractor, Finishes & Fit-out Subcontractor, Rough Carpenter, Finish Car
nter, Drywall Subcontractor
er, Millwork Subcontractor
r, Electrician, Project Managers
r, Electrician, Project Managers