A Gantt chart is a visual project schedule that shows tasks, durations, and dependencies for a software project. It offers a clear overview of progress and helps coordinate activities. The document provides an example Gantt chart for a 90-day restaurant management system project, outlining tasks like requirement gathering, analysis, design, coding, testing, deployment, and documentation with estimated durations and dependencies.
A Gantt chart is a visual project schedule that shows tasks, durations, and dependencies for a software project. It offers a clear overview of progress and helps coordinate activities. The document provides an example Gantt chart for a 90-day restaurant management system project, outlining tasks like requirement gathering, analysis, design, coding, testing, deployment, and documentation with estimated durations and dependencies.
A Gantt chart is a visual project schedule that shows tasks, durations, and dependencies for a software project. It offers a clear overview of progress and helps coordinate activities. The document provides an example Gantt chart for a 90-day restaurant management system project, outlining tasks like requirement gathering, analysis, design, coding, testing, deployment, and documentation with estimated durations and dependencies.
AIM : To prepare time Line Chart/ Gantt Chart/ PERT Chart for selected software project.
THEORY :
A Gantt chart is a visual representation of a project schedule in software engineering, providing a
timeline view of various tasks, their durations, and dependencies. It is a widely used project management tool that offers a clear, intuitive overview of project progress and helps teams coordinate and track their activities effectively.
Gantt Chart
● Requirement gathering will take 10 days.
● Analysis will take 8 days. ● Designing of the system will take 30 days as it is a critical stage. ● Coding will take 52 days and needs to be done carefully. ● Testing of the system being developed is important to deliver a quality software and will take 10 days at least. ● Deployment will take 10 days. ● Documentation will be done throughout the the development of the software and hence takes 80 days. ● The total time required to develop the Restaurant Management System is 90 days.