Professional Documents
Culture Documents
Download
Download
Download
SAND2002-0751
Unlimited Release
Printed March, 2002
Prepared by
Sandia National Laboratories
Albuquerque, New Mexico 87185 and Livermore, California 94550
Sandia is a multiprogram laboratory operated by Sandia Corporation,
a Lockheed Martin Company, for the United States Department of
Energy under Contract DE-AC04-94AL85000.
Printed in the United States of America. This report has been reproduced directly
from the best available copy.
Telephone: (865)576-8401
Facsimile: (865)576-5728
E-Mail: reports@adonis.osti.gov
Online ordering: http://www.doe.gov/bridge
Telephone: (800)553-6847
Facsimile: (703)605-6900
E-Mail: orders@ntis.fedworld.gov
Online order: http://www.ntis.gov/ordering.htm
Boulder City Battery Energy Storage
Feasibility Study
ABSTRACT:
Sandia National Laboratories and Black & Veatch, Inc., conducted a system feasibility study to examine
options for placing at Boulder City, Nevada an advanced energy storage system that can store off-peak,
hydroelectric generated electricity for use during on-peak times. It evaluated the feasibility and economic
impact of an energy storage demonstration project currently under consideration for the Municipal Utility
Power Company for the City of Boulder City. The study included evaluations of a proposed site and
appropriate advanced battery technologies, pre-conceptual design, artist’s conceptions, seasonal electricity
load profiles, cost estimates for the battery storage system plus site development and operating costs, and
an economic evaluation of the site’s payback potential. The study concluded that the Boulder City site is a
viable candidate for a Demonstration Unit of an advanced Battery Energy Storage System (BESS) utilizing
either Sodium Sulfur, Vanadium Redox, or Zinc Bromine and Regenesys® technologies and that it would
provide a net value to the City of Boulder.
Appendices
Figure 1-1 Sample Peak Shaving Operation for June 30, 1999....................................... 1-2
Figure 1-2 Stand-alone BESS. ...................................................................................... 1-11
Figure 2-1 Boulder City Load Profiles for Several Peak Days....................................... 2-2
Figure 2-2 Load Duration Curves ................................................................................... 2-3
Figure 2-3 Monthly Peak Loads ..................................................................................... 2-5
Figure 2-4 Sample Peak Shaving Operation for June 30, 1999....................................... 2-7
Figure 3-1 6MW/48MWh Sodium Sulfur Battery (Ohito substation,
Tokyo Electric Power Co.). ............................................................................ 3-3
Figure 3-2 Sample Zinc Bromine Site Layout................................................................ 3-6
Figure 3-3 Sample Vanadium Redox Maintenance Schedule. ....................................... 3-8
Figure 4-1 Hemenway Substation during construction, aerial view............................... 4-2
Figure 4-2 Hemenway Substation, Panoramic View...................................................... 4-3
Figure 4-3 Site Footprint................................................................................................. 4-4
Figure 4-4 Computer Rendering From South: Self-Enclosed BESS .............................. 4-5
Figure 4-5 Computer Rendering From South: BESS Enclosed in Building................... 4-6
Figure 4-6 Computer Rendering From West: Self-Enclosed BESS ............................... 4-7
Figure 4-7 Computer Rendering From West: BESS Enclosed in Building.................... 4-8
Figure 4-8 Electrical One line Diagram.......................................................................... 4-9
Figure 4-9 Visitor’s Center Layout............................................................................... 4-12
50000
45000
40000
35000
Battery Discharging
30000
kW
25000
20000
15000
Battery Charging
10000
5000
0
0 4 8 12 16 20 24
Hour
Orignial Adjusted
Figure 1-1 Sample Peak Shaving Operation for June 30, 1999.
The lowest cost resources are those provided by the Western Area Power
Administration (WAPA) and the Salt Lake City Area Integrated Projects (SLCA/IP),
which comes through the Colorado River Commission (CRC). This results in the
Schedule A and B WAPA allocations being dispatched first, followed by the SLCA/IP
(CRC) capacity. Beyond the City’s hydroelectric allocations, purchases are made
through the City’s Amendment 1 purchases from Nevada Power Company (NPC) and
through Schedule D purchases. Purchases from non-utility capacity owned by Reliant are
also possible, if scheduled a year in advance.
The ability of Boulder City to receive its full hydroelectric allocation is dependent
on water flow resources, including yearly rainfall and snowfall. These hydroelectric
resources were sufficient to meet the City’s full load for seven months in 1999 and for
Table 1-3
Site Layout and Footprint
Sodium Sulfur Vanadium Redox Zinc Bromine
Structure Outdoor rated Building enclosure. Building enclosure.
battery enclosures
and PCS enclosures.
Footprint About 5,000 ft2 12,000 to 17,000 ft2 5,000 to 7,000 ft2
Table 1-4
Life and Performance
Sodium Sulfur Vanadium Redox Zinc Bromine
Life 15 years 7 to 15 years 10 to 20 years
Efficiency
72 percent 70 to 80 percent 65 to 70 percent
(AC to AC)
O&M Cost $32.5k per year $50k per year $30-150k per year
EPC Cost $12 Million $10.9 to $11 Million $5.8 to 8 Million
Engineering shown in this table is for the electrical interconnect, Visitor’s Center,
and parking lot only. BESS engineering is considered to be part of the EPC estimate.
Contingency for the battery systems is also considered to be part of the EPC estimates
and is assumed to be five percent for all the technologies.
We project the operations and maintenance costs to be approximately $35,000
annually. The O&M cost does not include the cost of visitor center attendants.
1.6 Conclusions
The following conclusions can be drawn from the feasibility study of a Boulder
City BESS Demonstration Unit using advanced battery system technologies.
45000
40000
35000
30000
25000
June 30, 1999
20000
January 28, 1999
15000
April 19, 1999
10000
October 1, 1999
5000
0 3 6 9 12 15 18 21 24
Hour
Figure 2-1 Boulder City Load Profiles for Several Peak Days
70000
60000
50000
40000
30000
2010
20000
1999
10000
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
Hours
60000
50000
40000
kW
30000
20000
10000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2000 2010
50000
45000
40000
35000
Battery Discharging
30000
kW
25000
20000
15000
Battery Charging
10000
5000
0
0 4 8 12 16 20 24
Hour
Orignial Adjusted
Figure 2-4: Sample Peak Shaving Operation for June 30, 1999
35
30
Busbar Energy Cost
25
$/kWh
20
15
10
0
0 50 100 150 200 250 300 350 400
Cycles/year
Figure 2-5: Busbar Energy Cost for Mature BESS (20-year life)
Table 3-1
Vendor Response Summary
Developer Technology Headquarters US Representative
The vendor for Regensys® technology, Innogy Technology Ventures Ltd. (Ditcot,
Oxfordshire, UK), was invited to participate in the evaluation. However, Innogy
indicated that the project (2.5 kW, 10 MWh) was under their minimum plant size.
Innogy’s focus is on much larger plants, such as their two 120 MWh plants under
construction in the United Kingdom and at Columbus Air Force Base in Mississippi.
Therefore, Innogy’s technology was not considered for this project.
Developers were informed that they will not be bound to their estimated project
costs or technical characteristics for the project solicitation. However, their responses
would assist the Project Team in understanding the technology attributes, costs, and
approaches that might be taken in the demonstration.
None of the technologies has reached full commercial status, complete with
certifications from Underwriters Laboratories (UL). One of the zinc-bromine developers
indicated that UL certification would be completed for the battery component in time for
this project; however, we believe this might be optimistic. It is likely that only the power
electronics, controls, and other BOS components will have UL certification. Note that
UL certification is not a requirement for this utility-hosted project.
A summary of the technologies, as characterized by readiness, is provided in
Table 3-2. While sodium sulfur is clearly at a more advanced stage in field experience
and production capabilities, all three technologies appear to be sufficiently developed to
be included in the Boulder City project.
(Existing
Substation)
Control Room
& SCADA
Staging Area
12 kV/480V
Stepup Transform er
PCS &
DC Switchgear
Battery
String 110 feet
Chiller
64 feet
Figure 3-2: Sample Zinc Bromine Site Layout.
power conversion losses of four percent (also incurred twice), the non-battery energy
losses would be about 11.5 percent. A BESS system with 80 percent AC/AC efficiency
must have a battery round-trip energy efficiency of 90 percent, which is unlikely. Table
3-4 reflects reported life and performance data.
Table 3-5
O&M and Capital Costs
Sodium Sulfur Vanadium Redox Zinc Bromine
Operators on-site None None None
Required Remote monitoring. Quarterly or annual Remote monitoring,
maintenance Three-year maintenance. annual inspections.
inspections include Periodic parts Specific
retorquing terminals, replacement (pumps maintenance items
collecting/analyzing and fans every 5 to still to be
OCV data, sensor 10 years). developed.
calibration, system
testing.
O&M Cost $32.5k per year $50k per year $30-150k per year
Table 3-7 contains the developer estimates. The costs for the 2.5 MW, 10 MWh
Boulder City Project are within a reasonably close range, from a low of $8M (zinc
bromine) to a high of $12M (sodium sulfur). The long-term costs vary by a factor of
almost three.
3.7 Conclusions
Of the original four technologies considered for the Boulder City Project, three
appear to meet the basic requirements: sodium sulfur, vanadium redox, and zinc
bromine. The Regenesys® technology is intended for larger systems and would not be
considered for a 2.5MW/10 MWh installation.
All three technologies appear to have adequate field experience, although they
differ significantly on the depth of experience. Sodium sulfur has a number of multi-
megawatt grid-connected projects in Japan, and is by far the most experienced and has
the highest production capacity.
All of the technologies can meet the footprint and height restrictions without
difficulty. However, sodium sulfur and zinc bromine have a distinct advantage in
footprint.
Lifetimes will be in the 10-15 year time frame, and AC to AC round-trip
efficiencies are expected to be in the low 70 percent range.
All of the technologies are capable of unattended operation, and the maintenance
costs will be in the range of $30,000 to $150,000 per year, with four of the five responses
in the $30,000 to $50,000 per year range. The specific maintenance requirements are still
under development for some of the flow technologies.
Capital costs for the Boulder City project range from a low of about $5.8M (zinc
bromine) to a high of about $12M (sodium sulfur). The sodium sulfur estimate and the
lowest zinc bromine estimate indicate similar low long term capital cost targets of around
$30M for a 100 MWh system ($300/kWh).
Table 4-6
BESS Demonstration Unit Capital Costs
( Thousands of Year 2001 US$)
Sodium Sulfur Vanadium Redox Zinc Bromine
EPC Battery 12,000 11,000 5,800 to 8,000
System Cost
Electrical Upgrade 65 65 65
Visitor’s Center 275 275 275
Parking Lot 121 121 121
Engineering 300 300 300
Construction 150 150 150
Management
Contingency 632 612 323 to 432
Total 13,543 12,523 7,034 to 9,343
We estimated the net benefits of the project for Boulder City as a net present
worth of the difference between the City’s project benefits and costs. Project costs
comprise the City’s allocation of capital-related costs, the cost to operate and maintain
the facility, and the cost to recharge the batteries during off-peak periods. Project
benefits comprise the reduced purchases of energy and capacity that are attributable to
the battery storage project. Specific credit for ancillary services has not been included
because, at present, costs to the city for ancillary services are embedded in the energy and
capacity payments.
The lowest cost resources are those provided by the Western Area Power
Administration (WAPA) and the Salt Lake City Area Integrated Projects (SLCA/IP),
which comes through the Colorado River Commission (CRC). This results in the
Schedule A and B WAPA allocations being dispatched first, followed by the SLCA/IP
(CRC) capacity. Beyond the City’s hydroelectric allocations, purchases are made
through the City’s Amendment 1 purchases from Nevada Power Company (NPC), with
the requirement that the capacity must be reserved a month in advance and through
Schedule D purchases. Purchases from Reliant are also possible, if scheduled a year in
advance.
Project Background
Please provide responses to the following questions via email by Wednesday, June 27 (California time).
Only include information that is of a non-proprietary nature that can be included in public reports.
Technology
Technical Papers and Photos. Provide, in electronic form, general materials describing your technology,
such as technical papers. Include some high-resolution photographs, if available.
Experience. Provide a list of recent relevant projects, including descriptions and ratings. In particular,
include information about systems that have been fielded on a commercial basis. What is the largest
system built to date?
Production Capabilities. What is your current production capacity of the battery technology
(MWh/year)? What was the actual production in 2000 (MWh)?
Safety. Describe any hazardous (such as corrosive or highly flammable) chemicals found in your system
and the methods used to ensure safety. Describe any safety practices that you recommend, other than
electrical safety. Also, describe the method used to contain electrolyte internal and external to the DC
battery.
Power curve. Provide current and voltage specifications for the underlying DC battery module or cell,
including voltage window and average discharge voltage. Provide a curve showing energy output (kWh)
versus continuous (non-pulse) power output (kW).
Site Layout. Given the Boulder City height restriction of 25 feet, describe conceptually how the system
would be configured, e.g., how would standard modules be configured in outdoor structures. Give rough
dimensions of major components. Estimate total footprint of the system (length x width), including the
battery, cooling system, power conversion system, switchgear, step up transformer, and all other balance-
of-system equipment. Do NOT include access roads, parking, or visitors information display in your
estimate. If there are any siting characteristics that we would want to know, such as standard containers
that you would likely use, describe these. It is not necessary to provide drawings.
Configuration. Describe the basic electrical layout of the system that you would likely use for the
demonstration system, such as how you would aggregate DC modules, inverter ratings, etc. It is not
necessary to provide drawings.
UL Listing. Describe the components of the system that would not be UL listed. Provide other relevant
certification information.
Life. What would be the approximate life of the system, assuming that it were cycled to discharge 10
MWh of energy, 100 days per year? Are there are certain components (such as reactor stacks) that could be
replaced at end-of-life without replacing the entire system? If so, what would be the life of these
components and the approximate percentage of total AC system cost?
Efficiency. What is the round-trip efficiency, including AC transformer and power conversion losses, of
the system? Assume constant power discharge of 2 MW and constant power charge of 1 MW.
Load Following. The preferred operating strategy would be to dynamically vary the output over the
duration of the 4-6 hour peak period, such that power imports to Boulder City would not exceed a preset
threshold value. The maximum output would be at the peak hour, and would be limited by the 2.5 MW
O&M. Considering the whole AC system, is it necessary to have an operator on-site on a full-time or part-
time basis? What maintenance and inspection activities are required on a monthly basis? Annual basis?
Other schedule? What procedures and parts replacements would be required to ensure warranty
compliance? Would you provide a service contract to perform this maintenance? Whether provided by
you or performed by the owner, what would be an approximate cost to the utility for this service?
Demonstration Project Capital Costs. Provide an estimate of the total capital cost of the demonstration
project. This estimate is not a quote and is not binding in any way. The estimate should assume that the
manufacturer does not provide any cost sharing.
Assume that over the next few years you were to install another 50 MWh of utility BESS systems. After
that time, using the same assumptions as above, what would be the approximate cost of a scaled up 25
MW, 100 MWh system (in 2001 dollars)?
What do you believe is your long-term projected cost of a 25 MW, 100 MWh system (in 2001dollars)?