Government
Procurement of Construction Brgy. Banhigan, Badian Cebu. Construction Materials Supplier 100% 1,224,372.00
Materials for nthe Sectional
Concereting of 0.270KM Acces
Road at Poruk 10 and Purok 8.
Construction of 2 Communal Brgy. Zaragosa, Badian Cebu. Construction Materials Supplier 100% 843,230.00
Toilets Within Baragay
Zaragosa.
Concreting of 0.118KM Access Brgy, Sohoton, Badian, Cebu Construction Materials Supplier 100% 601,590.00
road at Poruk 3 Tambis.
Procurement of Construction Brgy. Candiis Badian Cebu. Construction Materials Supplier 100% 545,311.00
Materials for the Concreting of
0.637KM Pathway at Sitio
Proper
Construction of school Building Municipality of Moalboal Construction Materials Supplier 100% 419,660.00
(CTU-Moalboal Campus)
Materials only
Procurement of Construction Brgy, Poblacion, Badian Cebu Construction Materials Supplier 100% 994,527.00
Materials for the Construction
of Day Care Center in Barangay
Poblacion
TOTAL AMOUNT 4,628,690.00