Work Method Statement Pranav
Work Method Statement Pranav
FOR
AIRBUS
PROJECT – AIRBUS
Drafting Mr. Rashid M Subhani (senior project engineer) Pranav Doors & Windows
Submitted on
Issue no.
Revision no. Nil
Revision date Nil
Submitted to
Submitted by
INSTALLATION OF GOODS
HANDOVER
e. All survey reports will be submitted before commencing work execution at site.
f. Fabrication size will be released according to the site Survey& size openings.
The system design will be done as per the parameter stated in the Technical
specification and details mentioned in the drawings.
The Design Systems will meet standards and will comply with building regulations
and local building / safety regulations.
4.0 PROCURREMENT:
4.2 GLASS:
i). Glass will be procured as per approved make and shade from the approved
supplier only
Mentioned in System drawings.
ii). Glass Manufacturer certificates will be provided to the client.
iii) MIR (Material inspection report) will be generated at the time of receipt of goods.
4.3 HARDWARES AND ACCESSORIES:
i) All hardware’s and all accessories will be procured as per approved make /shade.
ii) Ordering of hardware’s item prior to client approval..
4.4 FINISHED GOODS:
i).Powder corted finish material will be processed from approved vendor after joint
decision between PDW & GMR .
ii). Powder corting shade /layer thickness will be checked as per our Quality ITP for
Quality Control.
iii). MIR (Material inspection report) will be generated at the time of receipt of goods.
iv). GMR can visit our processor for Audit to cross check the Quality processes
5.0 IN HOUSE -FABRICATION PROCESS:
i). Fabrication process will be carried in our factory itself at Dera Basi Plant.
ii). After Quality check and approvals of Aluminum goods, it will be issued to
production
department as per the production plan.
iii). Production will plan their activities according to the priorities required at site.
5.1 CUTTING PROCESS:
i) As per approved shop drawings, Profile length will be cut down to get desired size.
ii). Double header cutting machine will be used to cut these lengths.
iii. After cutting profile, the operator will ensure Correct Cutting finish, Correct Degree
/Angularity.
iv). After checking of section, Size /length will be mentioned with permanent marker
on
non-visible area.
5.2 MACHINNING PROCESS: Milling, Drilling, Notching Process:
i). As per approved Shop drawings profiles will be processes for notching/Milling
/Drilling as per the requirement to make system.
ii). After checking of Material process Quality it will be moved to Assembly
department for assembling.
5.3 ASSEMBLY - PROCESS:
i). Assembly department will receive the profiles in required sizes to make the
system.
ii). Assembly shop department operator will read the desired drawings to assemble
the parts.
iii). Angularity and correct 90 degree fitment will be checked before final assembling.
iv). All accessories will be installed with ref. to approved GMR drawings.
v). Final check will be done by production supervisor to ensure Final Quality of the
product.
vi) Quality Supervisor will check the fabricated material as per ITP checkpoints to
ensure to provide Quality product .
SUPPLY AND LOGISTICS:
6.1 Scope:
Supply and logistics department will help the production and installation work in a
smoother way,it also deals with priorities required by project team to ensure to the
fulfilment of the material as per the customer requirement.
6.2 Methodology:
i). All frames, shutters will be packed well with use of packing tapes and papers to
ensure no damages to the finished Goods during transportation of goods to site from
factory.
ii.) Set of frames will be stacked in such a way in vehicle that no movement is there
during movement, and no impact of material on each other to avoid any physical
transportation damages.
iii). All test certificates and reports will be provided to Client Site Quality team for all
types of material supplied or installed at site.
7.0 SAMPLE AND SAMPLE BOARD SUBMISSION AND APPROVAL:
Client will review and approve the system as per approved shop drawings and
site openings.
After client Final comments and approval – Pranav Doors & Windows will start
its procurement, fabrication & installation in full flash.
Submitted by :