Standard for
Published by
National Electrical Contracto
Contractors
rs Association
NECA 407-2015
Standard for
An American
National Standard
Published by
National Electrical
Contractors Association
Revision History
NECA 407
NECA 07-2
-200
0066 or
orig
igin
inal
ally
ly publ
publiished
shed 04
04/2
/200
0022
NECA 407-2006 revised 12/ 2009
NECA 407-2014 revised 02/ 2015
NOTICE OF COPYRIGHT
This document is copyrighted by NECA
Reproduction of these documents either in hard copy or soft (including posting on the web) is prohibited
without copyright permission. For copyright permission to reproduce portions of this document, please
contact NECA Standards & Safety at (301) 657-3110 ext. 546, or send a fax to (301) 215-4500.
OR
Foreword
Foreword.........................
......................................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................v
.............v
1. Scope ........................
.....................................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
............... 1
1.1 Products and Applications
Applications Included ........................
........... .........................
.........................
.........................
........................
.........................
.........................
.........................
..................
..... 1
1.2 Products and Applications
Applications Excluded............................
Excluded................ ........................
.........................
.........................
.........................
.........................
.........................
.........................
.............. 1
1.3 Regulatory and Other Requirements .........................
............ .........................
.........................
.........................
.........................
.........................
........................
.........................
................
... 1
1.4 Mandatory Requirements, Permissive Requirements, Quality and Performance Recommendations,
Explanatory Material, and Informative
Informative Annexes .......................
........... .........................
.........................
.........................
.........................
.........................
......................
......... 1
2. Definitions .........................
......................................
..........................
..........................
.........................
.........................
..........................
..........................
..........................
...................
...... 3
5. Installation .........................
......................................
..........................
..........................
.........................
.........................
..........................
..........................
..........................
...................
...... 8
5.1
5.2 General ......................
.................................
Environmental .......................
Considerations ........................
.......................
.......................
.........................
............ .......................
......................... .......................
......................... ........................
......................... .......................
......................... .......................
.......................
.........................
...............................................
................
......................... ..... 88
.........................
.............
5.3 Installation of Cabinets .........................
............. .........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
.........................
.............. 8
5.4 Installation of Raceways and Cables ........................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
.................
..... 9
5.5 Installation of Panelboards .......................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
.....................
......... 9
5.6 Installation of Conductors ........................
............ .........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
...................
....... 10
5.7 Grounding and Bonding .........................
............. .........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
......................
......... 11
5.8 Accessories
Accessories ........................
...................................
.......................
.......................
.......................
.......................
.......................
........................
.......................
.......................
.......................
.......................
..................
...... 12
5.9 Panelboard Pre-Checks .........................
............. .........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
........................
........... 12
6. Cleaning, Testing,
Testing, and Commissioning ..........................
.......................................
..........................
..........................
..........................
.........................
............ 13
6.1 Cleaning
Cleaning.......................
..................................
.......................
........................
.......................
.......................
.......................
.......................
.......................
.......................
........................
.......................
.......................13
............13
6.2 Inspections .......................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
......................
......... 13
6.3 Acceptance Testing.........................
............. ........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
...................
....... 14
6.4 Installation of the Front Cover .......................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
.............. 14
6.5 Energizing Panelboards.........................
............. .........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
........................
........... 15
iii n
NECA 407 Standard for Installing and Maintaining Panelboards
7. Closeout.........................
......................................
..........................
..........................
..........................
.........................
.........................
..........................
..........................
.....................
........ 17
7.1 Test Data and Manuals ........................
........... .........................
........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
............... 17
7.2 Training ........................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
............... 17
7.3 Spare Parts and Special Tools .............
.........................
........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
............... 17
8. Inspections and Maintenance ......................
...................................
..........................
..........................
..........................
..........................
..........................
................
... 18
8.1 Frequency of Inspections and Maintenance........................ ........... .........................
.........................
.........................
.........................
.........................
.........................
................
... 18
8.2 Record Keeping .........................
............. .........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
.........................
........................
............ 18
8.3 Routine Inspections .........................
............ .........................
........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
..................
..... 18
8.4 Cleaning
Cleaning.......................
...................................
.......................
.......................
........................
.......................
.......................
.......................
.......................
.......................
.......................
........................
.......................19
...........19
8.5 Infrared
Infrared Scan.......................
..................................
.......................
........................
.......................
.......................
.......................
.......................
........................
.......................
.......................
.......................
...............
.... 19
8.6 Inspections .........................
............. .........................
.........................
........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
....................
....... 19
8.7 Terminations, Connections, and Lugs ......................... ............ .........................
........................
.........................
.........................
.........................
.........................
........................
............ 20
8.8 Conductors and Raceways ........................
............ ........................
.........................
.........................
.........................
.........................
.........................
.........................
.........................
....................
....... 20
8.9 Switches ........................
........... .........................
.........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
............... 20
8.10 Circuit Breakers .........................
............. .........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
.........................
........................
............ 21
8.11 Electrical Tests .........................
............. .........................
.........................
.........................
.........................
.........................
.........................
........................
.........................
.........................
.........................
............... 22
8.12 Re-energizing Panelboards .........................
............. .........................
.........................
........................
.........................
.........................
.........................
.........................
.........................
..................
..... 22
n iv
(This foreword is not a part of the standard)
Foreword
1. Scope
National Electrical Installation Standards™ (NEIS™) Suggestions for revisions and improvements to this
are designed to improve communication among standard are welcome. They should be addressed to:
specifiers, purchasers, and suppliers of electrical
construction services. They define a minimum NECA Codes and Standards
baseline of quality and workmanship for installing 3 Bethesda Metro Center, Suite 1100
electrical products and systems. NEIS™ are intended Bethesda, MD 20814
to be referenced in contract documents for electrical (301) 657-3110
construction projects. The following language is (301) 215-4500 fax
recommended: www.neca-neis.org
neis@necanet.org
Panelboards shall be installed and maintained in To purchase National Electrical Installation
accordance with NECA 407-2015, Standard for
Installing and Maintaining Panelboards (ANSI). Standards, contact the NECA Order Desk at (301)
215-4504 tel, (301) 215-4500 fax, or orderdesk@
Use of NEIS is voluntary, and the National Electrical necanet.org. NEIS can also be purchased in .pdf
Contractors Association assumes no obligation or download format from www.neca-neis.org/standards
liability to users of this publication. Existence of a
standard shall not preclude any member or non- Copyright © 2015, National Electrical Contractors
member of NECA from specifying or using alternate Association. All rights reserved. Unauthorized
construction methods permitted by applicable reproduction prohibited.
regulations.
National Electrical Installation Standards, NEIS, and
the NEIS logo are registered trademarks of the National
This publication is intended to comply with the
Electrical Contractors Association. National Electrical
National Electrical Code® (NEC). Because they are
quality standards, NEIS may in some instances Code and NEC Association,
Fire Protection are registeredQuincy,
trademarks
MA. of the National
go beyond the minimum safety requirements of
the NEC. It is the responsibility of users of this
publication to comply with state and local electrical
codes and Federal and state OSHA safety regulations
as well as follow manufacturers’ installation
instructions when installing electrical products and
systems.
v n
<This page intentionally left blank>
1. Scope
1.1 Products and Applications Included performed under the supervision of a qualified
person. All work shall be performed in accordance
This standard describes installation and maintenance
with NFPA 70E, Standard for Electrical Safety in the
procedures for panelboards, and special procedures
Workplace.
used after adverse operating conditions such as a
short-circuit, ground-fault, or immersion in water. General requirements for installing electrical
products and systems are described in NECA 1,
This standard applies to panelboards rated 600 Volts
Standard for Good Workmanship in Electrical
(AC and DC) or less, with main disconnects or
Construction (ANSI). Other NEIS provide additional
lugs, and with feeder or branch circuit overcurrent
guidance for installing particular types of electrical
devices.
products and systems. A complete list of NEIS is
This publication applies to single panelboards and provided in Annex A.
multi-section panelboards that are installed in the
field and used for distributing power for commercial, 1.4 Mandatory Requirements, Permissive
institutional, and industrial loads in nonhazardous Requirements, Quality and Performance
locations both indoors and outdoors. Recommendations, Explanatory Material,
and Informative Annexes
1.2 Products and Applications Excluded Mandatory Requirements. Mandatory
This publication does not apply to panelboards that requirements in manufacturer’s instructions, or
are factory-installed as part of a Listed enclosure or of Codes or other mandatory Standards that may
assembly, live-front panelboards, or panelboards or not be adopted into law, are those that identify
employing cast enclosures for hazardous or special actions that are specifically required or prohibited
1 n
NECA 407 Standard for Installing and Maintaining Panelboards
n 2
2. Scope
1. Definitions
Branch Circuit, Multiwire A branch circuit that power circuits; designed to be placed in a cabinet,
consists of two or more ungrounded conductors cutout box, or enclosure placed in or against a wall
that have a voltage between them, and a grounded or partition and accessible only from the front.
conductor that has equal voltage between it and each
ungrounded conductor of the circuit and that is Surface-Mounted Panelboard A panelboard
connected to the neutral or grounded conductor of that is installed on the surface of a wall, partition, or
the system similar construction, such that the cabinet is exposed
on the mounting surface.
Flush-Mounted Panelboard A panelboard that
is installed recessed into a wall, partition, or similar
construction, such that the front of the cabinet is
flush with the mounting surface.
3 n
3. Scope
1. Safety Procedures
Before performing cleaning, inspections, testing, Do not enter equipment enclosures when components
maintenance, or repairs, electrically isolate are energized. Do not remove access covers, doors,
conductors and equipment in accordance with or panels when equipment is energized. Do not
established written procedures. All work and actions expose conductors, connections, or terminations
must conform to the requirements of NFPA 70E, when components are energized. Using established
Standard for Electrical Safety in the Workplace. safety procedures, guard energized conductors and
equipment in close proximity to work.
The process of de-energizing conductors and
equipment is considered “live” work and can result
in an arc flash due to equipment failure. When
3.2 Safe Work Practices
de-energizing conductors and equipment, follow Perform preliminary inspections and tests prior to
safety procedures for working on or near live circuits. beginning work to determine existing conditions.
Failure to observe these precautions may result in Check existing conditions against available record
severe personal injury or death. documents.
Do not work on energized conductors or equipment. Use insulated hand tools when working on or
Electrically isolate conductors and equipment around energized equipment. Use only properly
in accordance with established procedures and rated tools for the energy present. Maintain tool
manufacturer’s instructions. inventories to ensure that all tools are accounted for
prior to energizing equipment.
Use care in opening and closing doors to energized
equipment. Conductors and terminations may be Ensure that egress from the work area is
exposed and within the reach of openings. unobstructed, and that fire extinguishers approved
for use in electrical fires are readily available.
n 4
Standard for Installing and Maintaining Panelboards NECA 407
Do not make any modifications to the equipment or Apply lockout/tagout devices in accordance with
attempt to operate with interlocks or safety barriers a formal, written policy and in accordance with
removed. Engage lock-bars for compartment doors NFPA 70E-2012, Standard for Electrical Safety in the
so equipped to prevent doors from accidentally Workplace. Padlock and red tag all source switching
closing. devices in the open position. Remove locks and
tags only after work is complete and tested, and
3.3 Personal Protective Equipment (PPE) all personnel are clear of the area. Protect against
accidental energization of automatic or remotely
Use appropriate Personal Protective Equipment controlled equipment by identifying, opening,
(PPE) and established safety procedures when locking, and tagging starting devices. Open and lock
working on or near energized electrical equipment or tag all load isolation devices to ensure that there
or equipment that has not been de-energized, tested, are no loads connected to the equipment.
grounded, locked out of operation, and red tagged in
accordance with NFPA 70E. Use Listed personal protective grounds that are
sufficient for the available short circuit current of the
Wear appropriate PPE in accordance with the system. Connect personal protective grounds to the
incident energy levels of the equipment. line terminals of the main circuit breaker or main
lugs, to the neutral terminal bus bar, if so equipped,
Wear 100 percent natural fiber clothing or flame
resistant apparel. Do not wear conductive articles and to the grounding terminals of the equipment.
Provide warning signs at all primary disconnects
such as watches, rings, or necklaces.
indicating that the terminals are grounded. Do
not remove the personal protective grounds until
3.4 De-Energizing Electrical Equipment ready to test or energize conductors and equipment.
Follow all manufacturer’s instructions and Ground all possible sources of induced voltage and
recommendations for electrically isolating equipment stored electric energy, such as conductors in close
and components. Render equipment electrically safe. proximity to energized parts and capacitors.
Follow lock-out/tag-out procedures. Disconnect all
Carefully inspect the work area and remove any tools
sources of power before opening any enclosures or
and objects left inside before energizing conductors
compartments. Verify that source circuit breakers
and equipment. Install all devices, panels, doors, and
and switches are open.
covers before energizing.
5 n
4.
1. Receiving,
Scope Inspecting, Handling
and Storage
n 6
Standard for Installing and Maintaining Panelboards NECA 407
7 n
5.
1. Installation
Scope
installation. temperatures
explosive above
fumes, 40°C
dust, (104°F),
vapors, corrosive
dripping or
or standing
Verify that supply overcurrent device(s) for water, abnormal vibration, mechanical shock, high
panelboards and the panelboard feeders have a rating humidity, or unusual operating conditions, unless
not greater than that of the panelboard and the the panelboard is designed and identified by the
panelboard feeder. manufacturer for such conditions.
Ensure that panelboard withstand ratings and circuit Do not install panelboards in locations where the
breaker interrupting ratings exceed the available conditions would damage the equipment.
fault current from the system as indicated by the
short-circuit and coordination study provided
by the owner, if available. Verify that series-rated
5.3 Installation of Cabinets
panelboards meet the manufacturer’s Listing for Locate cabinets so that they are readily accessible and
series-rating. Check that panelboards are tested and not exposed to physical damage.
marked with testing combinations of the line-side Install cabinets level and plumb. Mount the cabinet
overcurrent device and load-side circuit breaker(s) as
required by NEC Article 240 for series-rated devices. securely to the mounting surface using manufacturer
recommended methods, supports, and fasteners.
Coordinate panelboard locations to ensure that the
required minimum working space clearances are Provide suitable guards or temporary covers on the
maintained in accordance with NEC Article 110. cabinet after installation and prior to the permanent
Ensure that the working space permits at least a panelboard cover being installed to protect the
90-degree opening of equipment doors or hinged cabinet from foreign substances such as paint,
panels. Provide sufficient access to permit removing plaster, and acoustic spray.
doors, covers, and panels for routine inspection,
Close unused openings in panelboard enclosures
maintenance, and testing.
using identified closures or other approved means
Ensure that illumination is provided for panelboard that provide protection substantially equivalent to
working spaces in accordance with NEC Article 110. the wall of the enclosure as necessary to return the
enclosure to the environmental rating required by
the application.
n 8
Standard for Installing and Maintaining Panelboards NECA 407
In damp or wet locations, locate surface-mounted Ensure that feeder conductors between sections are
cabinets to prevent moisture or water from entering sized not less than the panelboard bus ampacity, or
and accumulating within the cabinet. Provide a not less than separate main overcurrent protective
minimum of 6 mm (1/4 in.) airspace between the devices, where installed.
cabinet and the wall or other supporting surface.
Ensure adequate gutter space is available for wiring
Install weatherproof cabinets in wet locations. between sections.
Allow a minimum of 1 m (3 ft) clearance between Install raceways in a manner that will prevent water
the ceiling and the cabinet unless an adequate that is accumulating in the raceways from entering
fireproof shield, such as a fireproof ceiling, is and accumulating in cabinets.
provided.
Use properly sized and spaced knockouts to match
Mount surface-mounted panelboard cabinets located feeder and branch-circuit raceway and cable layouts.
outdoors so that there is at least 6 mm (1/4 in.) of
air space between the cabinet and the wall or other Use proper Listed fittings to attach cables and
supporting surface. Keep in mind that mounting raceways to the cabinet.
standoffs are typically stamped into the cabinet.
Support raceways, cables, cable trays, and busways
5.3.2 Supporting Panelboards attached to cabinets independently from the cabinets
themselves.
Provide temporary cabinet supports for anchoring
flush-mounted panelboards during wall construction. Provide raceway and cable fittings Listed for wet
Supply structural floor supports to support the locations for raceways and cables that enter the top
of panelboards in wet locations.
panelboard if required due to the wall construction
or the panelboard weight and design.
5.5 Installation of Panelboards
Support cabinets independently of raceways. Clean the cabinet of all foreign materials remaining
after installation prior to installing the panelboard
Provide seismic restraints where required by the in the cabinet. Contact the panelboard manufacturer
building code, the approved plans, or the project before using products with hydrocarbon spray
specifications. propellants, or hydrocarbon based sprays or
5.3.3 Multi-Section Panelboards compounds to clean, dry, or lubricate panelboard
components during installation or maintenance, as
Ensure that all sections of multi-section panelboards these products will cause the degradation of certain
have identical main bus and terminal ratings unless plastics.
separate main overcurrent devices are provided.
9 n
NECA 407 Standard for Installing and Maintaining Panelboards
Verify that the cabinet is Listed for the installation of 5.6 Installation of Conductors
the specific panelboard.
Identify conductors originating within each
Protect panelboard parts from contamination during panelboard. The means of identifying ungrounded
installation. conductors are permitted to be by separate color
coding, marking tape, tagging, or other approved
Verify that component placement in the panelboard means. Document the means of identifying
is in accordance with contract documents. If there conductors in a manner that is readily available or is
is a discrepancy, contact the project manager and permanently posted at each panelboard.
the engineer of record to determine the appropriate
course of action. Perform insulation resistance testing of panelboards
prior to terminating conductors (see Section 10.1).
Install the panelboard. Align and tighten the
panelboard in the cabinet per manufacturer Install conductors for panelboards equipped
instructions. with ground-fault protection in accordance with
manufacturer recommendations.
Adjust the panelboard so that the dead-front shield
flange is 5mm (3/16 in.) or less from the front of Verify that terminals, connectors, and lugs are
surface-mounted cabinets, or from the surrounding compatible with conductor types, sizing, and
wall surfaces for flush-mounted cabinets. temperature ratings, considering over-sized
conductors to compensate for ambient temperature,
5.5.1 Circuit Breakers and Fuses voltage drop, and harmonic load currents.
curre nts.
Ensure that circuit breakers and/or fuses are of the Ensure that all conductors installed in parallel are the
proper type, voltage class, and rating. same length, insulation type, material type, and wire
size, and that all conductors are terminated in the
Ensure that circuit breakers and/or fuses conform to same manner for each individual phase.
the engineering coordination study provided by the
owner, if required. Distribute and arrange conductors in the wiring
gutters of cabinets. Train conductors neatly in
Ensure that each molded-case circuit breaker groups, bundle, and wrap with wire ties after load
voltage rating is appropriate for
fo r the voltage and balancing (See Section 6.6). Keep in mind that
configuration of the system. Do not install a three- bundling conductors may impact conductor ratings.
phase disconnect or overcurrent device to the bus of
any panelboard that has less than three phase buses. Provide sufficient conductor lengths to reach
Do not install Delta circuit breakers in panelboards. the terminals and to avoid placing strain on the
terminals. Maintain the largest practical bending
Install an additional fastener on plug-in type radius of conductors.
overcurrent devices that are backfed and used to
terminate field-installed ungrounded supply conductors Strip conductor insulation carefully. Do not nick or
in accordance with the manufacturer’s instructions. ring conductors. For aluminum conductors, clean
all oxide from the stripped portion of the conductor,
Compare the placement of circuit breakers in the apply an anti-oxide inhibitor formulated to not
panelboard with the appropriate panel schedule on damage thermoplastic insulation or supports, or as
the approved plans. Notify the project manager and specified by the panelboard manufacturer, and insert
the engineer of record in writing of any discrepancies immediately into the terminal.
in the circuit breaker arrangement.
Connect conductors to terminals using suitable
Install fuses after all conductors are installed and hardware such as listed lugs, bolts, flat washers,
terminated. locking washers, and nuts. Do not install more
n 10
Standard for Installing and Maintaining Panelboards NECA 407
than one conductor in any termination, unless the Provide instruction and warning labels identifying
termination is marked as suitable for more than one phasing and voltages on the panelboard. See Section
conductor. 6.2.1.
11 n
NECA 407 Standard for Installing and Maintaining Panelboards
Bond all non-current carrying metallic parts of Set adjustable time current trip devices to the settings
specified in the engineering coordination study
service equipment in accordance with applicable
supplied by the owner, if required.
codes and manufacturer recommendations.
Ensure that all dead-front shields and panelboard
Install a main bonding jumper per NEC
barriers are properly aligned and tightened.
requirements and manufacturer installation
instructions. Protect the panelboard from on-going construction
Install a grounding electrode conductor per NEC activities until the panelboard is cleaned, tested, and
commissioned in accordance with Section 6.
requirements.
5.8 Accessories
Install any field-installed panelboard accessories
and components in accordance with manufacturer’s
instructions.
n 12
6. Scope
1. Cleaning, Testing, and
Commissioning
drawings and contract documents. Confirm that panelboards are properly labeled,
including voltage, interrupting ratings, and system
Verify that fuse and/or circuit breaker sizes and
configuration, as applicable. Verify that panelboards
types correspond to approved drawings and the
and enclosures are labeled as suitable for the
coordination study provided by the owner, if installation location.
applicable, as well as to the circuit breaker’s address
for microprocessor-communication packages. Confirm that the method used to identify conductors
originating within each panelboard is documented in
Check all bolts, connections, and terminations
a manner that is readily available or is permanently
for tightness using a calibrated torque wrench or posted at each panelboard. The means of identifying
screwdriver. Refer to the manufacturer’s instructions
ungrounded conductors are permitted to be by
and markings for proper torque values. Keep in mind
separate color coding, marking tape, tagging, or
that the repeated tightening of loose connections
other approved means.
will extrude aluminum conductors and may cause
adverse operating conditions. Inspect aluminum For four-wire, delta-connected systems, provide
conductors for extrusion and rework terminations, if instruction and warning labels identifying
required. phasing and voltages on panelboards. Legibly and
13 n
NECA 407 Standard for Installing and Maintaining Panelboards
permanently field mark panelboards with: “Caution: Verify correct ratings. Adjust settings of circuit
_____ Phase Has ______ Volts to Ground.” breakers in accordance with the coordination study
supplied by owner, if applicable.
For ungrounded AC systems, legibly and
permanently field mark panelboards with: “Caution:
Ungrounded System Operating – _____ Volts 6.3 Acceptance Testing
Between Conductors.” Do not proceed with tests until deficiencies identified
in Section 6.2 are corrected. Ensure panelboard is
For high-impedance grounded neutral AC systems, de-energized and electrically isolated. Follow the
legibly and permanently field mark the panelboard safety procedures in Section 3.
with: “Caution: High Impedance-Grounded Neutral
AC System Operating – _____ Volts Between Test panelboards in accordance with manufacturer
Conductors” and “May Operate – _____ Volts recommendations. Record and maintain test results
to Ground for Indefinite Periods Under Fault for future comparisons.
Conditions.”
Perform insulation resistance testing (see Section
Confirm that panelboards are field or factory marked 10.1).
to warn qualified persons of potential electric
arc flash hazards. Verify that markings meet the Perform ground resistance testing (see Section 10.2).
requirements of NEC Article 110. Markings must be
Perform circuit breaker testing (see Section 10.3).
located so as to be clearly visible to qualified persons
before examination, adjustment, servicing, or Measure the contact resistance across each
maintenance of the equipment. NOTE: ANSI Z535.4- switchblade and fuseholder of switches. The contact
2011, Product Safety Signs and Labels, provides resistance values should not exceed the high levels of
guidelines for the design of safety ssigns
igns and labels for the normal range as indicated by the manufacturer’s
application to products. published data. Investigate values that deviate from
adjacent poles or similar switches by more than 50
6.2.2 Switches
percent of the lowest value.
Operate switches to insure smooth operation. Verify
Correct deficiencies identified by inspections and
appropriate lubrication on moving parts and sliding
surfaces. Visually check blade alignment, blade tests, and retest panelboards.
penetration, traveland
Check indicating stops, and mechanical
control operation.
devices for proper Provide written reports of tests and observations.
Make notes describing defective materials and
operation. Check that phase barriers are in place, if unsatisfactory test results. Include details of repairs,
applicable. replacements, adjustments, and corrective actions
taken. Provide copies of reports to the general
Inspect each fuse holder to determine whether it seems
contractor, project manager, and engineer of record.
to be adequately supporting the fuse and that the
fuseholder is securely attached to the mounting base.
6.4 Installation of the Front Cover
Verify proper labeling.
Ensure that all personal protective grounding cables
6.2.3 Circuit Breakers and devices are removed from inside panelboards
prior to installing the cover.
Operate circuit breakers to insure smooth operation.
Provide manufacturer’s filler plates for unused
Inspect circuit breaker for correct mounting. Check panelboard spaces. The closure methods must
factory bus connections. Inspect circuit breakers for provide protection substantially equivalent to the
cracks or other defects. wall of the enclosure.
n 14
Standard for Installing and Maintaining Panelboards NECA 407
Install the front cover. Ensure that no conductors are Energize lighting circuits, contactors, motors, and
pinched between the cabinet and cover, and that all heaters after all overcurrent devices have been closed.
enclosure parts are properly aligned and tightened.
Align the front cover squarely with building lines, Inspect the panelboard for mechanical rattles or
and tighten. excessive humming. Investigate hardware that has
not been tightened or metal parts that are improperly
6.4.1 Restore Finishes assembled as possible sources of extraneous noise.
Inspect exposed finishes. Remove burrs, dirt and Measure phase-to-phase, phase-to-neutral, phase-to-
construction debris, and repair damaged finishes ground and neutral-to-ground voltages after loading
including chips, scratches, and abrasions to match the panelboards to verify proper operation and
original finish. Apply suitable paint or other proper neutral-to-ground bonding.
corrosion-resistant materials where finishes are
damaged. Inspect all indicating and control devices for correct
operation.
6.5 Energizing Panelboards Perform an infrared scan of the panelboard under
Consult the panelboard manufacturer for any load (see Section 10.4).
abnormal operating conditions encountered. Qualified
personnel should be present when the equipment 6.6 Balancing Loads
is energized for the first time. If short-circuit
Measure and record steady state load currents at
conditions caused by damage or poor installation
the panelboard feeder under normal operating
practices have not been detected in the procedure
specified above, serious personal injury and property conditions as advised by the owner.
damage can occur when the equipment is energized. Rearrange circuits within the panelboards to balance
the load between the phases to within 20 percent of
Ensure that all affected persons are notified prior to
each other. Maintain proper phasing for multi-wire
energizing panelboards.
branch circuits.
Ensure that all personal protective grounds are
Perform circuit changes outside of the normal
removed, and the front access cover is installed and
tightened prior to energizing panelboards. occupancy/working schedule of the facility. Make
special arrangements with the owner to avoid
Ensure that there is no load on the panelboard and disrupting critical 24-hour services such as facsimile
that all load isolation devices are open and locked or machines, on-line data processing, and computing,
tagged. transmitting, and receiving equipment.
Energize the panelboard. Measure and record the Recheck loads under normal operating conditions
phase-to-phase and phase-to-neutral voltages. after making circuit changes. Measure and record
feeder load readings. Rebalance and recheck as
6.5.1 Energize equipment supplied from the required to balance loads.
panelboard
Mark each panelboard to indicate the device or
Energize equipment supplied from the panelboard equipment where the power to the panelboard
starting at the source end of the panelboard and originates.
working toward the load. Remove locks and tags and
close load isolation devices to verify proper phase Provide a typed panelboard circuit directory. Clearly
rotation, with regard to the utilization equipment identify the specific purpose or use of every circuit.
supplied from the panelboard. Close main, feeder, Identify spare or unused overcurrent devices. Revise
and branch circuit devices in sequence. the directory to reflect circuit changes required to
15 n
NECA 407 Standard for Installing and Maintaining Panelboards
n 16
7. Scope
1. Closeout
7.1 Test Data and Manuals installation, operation, and maintenance manuals as
references. Notify the owner or general contractor a
Update contract documents with the final system
minimum of seven days in advance of training.
configuration and parameters.
Submit test results and data from all factory and 7.3 Spare Parts and Special Tools
field testing of panelboards including a record of any
Deliver spare parts and special tools to the owner
actions taken to correct deficiencies.
or general contractor in accordance with contract
Deliver as-built documents, test data, and panelboard documents.
manufacturer’s standard installation, operation,
and maintenance manuals to the owner or general In the absence of contractual requirements,
deliver the panelboard manufacturer’s minimum
contractor in accordance with contract documents.
recommended spare parts and special tools.
In the absence of contractual requirements, deliver a
Have the owner or general contractor sign for
minimum of one set of all documents to the owner
delivered items.
or general contractor.
7.2 Training
Provide training for the owner’s maintenance
personnel, if required by contract documents.
Discuss routine maintenance, operating procedures,
and cleaning using the manufacturer’s standard
17 n
8. Scope
1. Inspections and Maintenance
This section describes recommended procedures for the Update testing and maintenance records to reflect
inspection, maintenance, and testing of panelboards. The the dates of inspections, testing, and maintenance,
installer is only responsible for these tasks if required or along with a summary of the work performed.
referenced by contract documents. Otherwise, these
inspection and maintenance recommendations are Review testing and maintenance records annually to
provided as guidance for the owner. identify performance trends and changes in electrical
characteristics over time.
Cleaning, inspection, maintenance, and testing
should only be performed by qualified personnel 8.3 Routine Inspections
on panelboards to which power has been turned-
off, disconnected, and electrically isolated, unless Inspect areas and spaces around panelboards for
required for testing, so that no accidental contact any accumulation of dirt or dust. Remove any
can be made with energized parts. Follow the safety accumulations of dirt or dust. Remove trash,
procedures in Section 3. Follow all manufacturer’s combustible material, and other debris from areas
warnings and instructions. around panelboards.
n 18
Standard for Installing and Maintaining Panelboards NECA 407
Measure and record panelboard voltage and load 8.5 Infrared Scan
currents, if possible, noting the date and time of day
After cleaning panelboards and components in
the measurements were made. Provide comments
accordance with Section 8.4, energize the panelboard
regarding known variations in loading, such as load
and perform an infrared scan (see Section 10.4).
additions or equipment maintenance outages.
Maintain adequate ventilation during cleaning. Check all bolts, nuts, washers, and pins for tightness.
Tighten loose hardware or use manufacturer’s
replacement parts as required.
Visually inspect panelboards for evidence of
discoloration, abnormal dust accumulation, metal Inspect cabinets for signs of rust, corrosion, or
shards, or any other indication of overheating, wear, deteriorating paint. Inspect cabinets for evidence
or other abnormal conditions prior to cleaning. of localized heat damage to the paint. Investigate
sources of heat. Repair painted surfaces.
Plan the times of cleaning, inspections, testing, and
maintenance to minimize outages. Check that covers are in place and fastened. Plug
any unused knockouts. The closure methods must
Clean the cabinet with a brush, vacuum cleaner, or
provide protection substantially equivalent to the
clean, dry, lint-free rags to remove any accumulation
wall of the enclosure.
of dust, dirt, or other foreign matter. Do not use
liquids, solvents or detergents when cleaning
panelboards or components. Inspect the panelboard
Seal off any for evidence
cracks or openings whichofhave
moisture.
allowed
moisture to enter the cabinet. Look for any recent
Avoid blowing dust into panelboards. Do not use a
changes in sprinklers or other plumbing that might
blower or compressed air.
expose indoor panelboards to a source of liquids.
Clean supports, terminals, and other major Eliminate sources of water, moisture, or liquids, or
insulating surfaces with clean, dry, lint-free rags or provide adequate barriers to protect panelboards
soft-bristled brushes. from sources of water, moisture, or liquids. Inspect
and replace any components or devices that show
Thoroughly clean fusible switches inside and outside. evidence of damage from moisture.
Clean the contact areas of fuses and fuse holders.
Clean the insulating area of fuses. Inspect panelboards and internal components for
evidence of overheating, arc spatter, sooty deposits,
Remove dust, soot, grease, moisture, and foreign and tracking. Investigate and correct sources of
material from the surface of circuit breakers. arcing or overheating. Consult the panelboard
manufacturer for recommendations.
19 n
NECA 407 Standard for Installing and Maintaining Panelboards
Verify that fuse and/or circuit breaker sizes and types 8.8 Conductors and Raceways
correspond to record drawings and coordination
Inspect supply conductors and terminations for
study supplied by the owner, if available, as well as
overheating, discoloration, and oxidation. Investigate
to the circuit breaker’s address for microprocessor
and correct any deficiencies.
communication packages, if equipped. Record
settings of adjustable circuit breakers and compare Ensure that conductors are protected within their
with engineering coordination study supplied by ampacity.
owner, if available. Notify the owner of discrepancies
between actual circuit breaker settings and the Visually check panelboard, cables, and raceways for
coordination study. proper bonding and grounding. Correct improper
bonding and grounding.
Confirm correct operation and sequencing of
electrical and mechanical interlock systems, if so Inspect conductors for discoloration, arcing, pitting,
equipped. Attempt closure on locked-open devices. melting, and flaking of insulation and/or metal
Attempt to open locked-closed devices. parts. Repair or replace damaged components in
accordance with manufacturer recommendations.
8.7 Terminations, Connections, and Lugs
Inspect for frayed or broken wires. Replace or repair
Inspect all terminations,
for tightness connections,
using a calibrated torque and lugsor
wrench conductors as necessary.
screwdriver. Refer to manufacturer’s instructions and Check set screws in all raceway connectors for
markings for proper torque values. Be careful not to tightness and for stripped threads. Replace or repair
overtighten or strip threads. Keep in mind that the connectors as necessary using manufacturer’s
repeated tightening of loose connections will extrude replacement parts.
aluminum conductors and may cause adverse
Inspect raceways for moisture. Seal raceways and
operating conditions. Inspect aluminum conductors
provide a means to drain moisture away from
for extrusion and rework terminations, if required.
panelboards.
Inspect terminations, connections, and lugs for
alignment, physical damage, burns, corrosion, 8.9 Switches
discoloration, flaking, heat damage, arcing, pitting,
Operate each switch several times to ensure that all
melting, deterioration, carbonization, cracks, chips,
breaks, partial discharge, or moisture. Investigate and mechanisms are free and in proper working order.
eliminate sources of any damage. Check switches for damaged or broken parts, free
movement, corrosion, dirt, and excessive wear.
Follow manufacturer instructions for cleaning,
Verify proper blade penetration, travel stops, and
repairing, and replacing damaged parts. Plated
mechanical operation.
parts may become dark over a period of time due
to oxidation. Do not remove this discoloration, as Inspect contact surfaces, blades, and jaws for
it will reduce the thickness of the plating. Consult discoloration, overheating, pitting, arcing, and
the manufacturer for recommendations regarding corona. Clean and dress readily accessible copper
discoloration of parts. electrical contacts, blades, and jaws in accordance
with manufacturer recommendations. Many
Rework overheated connections. Replace damaged
contact surfaces, such as arcing contacts, are silver
components. Tighten connections to proper torque
tungsten or other types of materials that must
levels using a calibrated torque wrench or screwdriver
after replacement. Refer to manufacturer’s instructions never be dressed. When contacts of these materials
require maintenance, they must be replaced. If
and markings for proper torque values.
contact clips have lost their tension, replace clips
n 20
Standard for Installing and Maintaining Panelboards NECA 407
or replace the switch. Contact the manufacturer Look for evidence of overheating of cartridge fuses.
for recommendations when repairing or replacing Replace fuses having discolored or weakened casings.
burned contacts. Investigate and correct the cause of the overheating.
Inspect arc chutes and phase insulating barriers. Inspect ferruled or knife blades of cartridge fuses
Repair or replace as required. for corrosion or oxidation. Clean and polish contact
surfaces. Clean surfaces with a non-corrosive
Lubricate operating mechanism and sliding contact cleaning agent. Plated parts may become dark
surfaces, if required, according to manufacturers’ over a period of time due to oxidation. Do not
instructions. If no instructions are given on remove this discoloration, as it will reduce the
the devices, sliding copper contacts, operating thickness of the plating. Consult the manufacturer
mechanisms, and interlocks may be lubricated with for recommendations regarding parts that show
clean, light grease. Wipe off excess lubrication to deterioration.
avoid contamination.
Measure fuse resistance. Investigate fuse-resistance
Tighten fuseholder connections in accordance values that deviate from each other by more than
with manufacturer recommendations. Inspect 15 percent. Replace defective fuses. Re-tighten plug
each fuse holder to determine whether it seems fuses.
to be adequately supporting the fuse and that the
fuseholder is securely attached to the mounting base.
Inspect fuse clips for discoloration, overheating,
8.10 Circuit Breakers
corrosion, or physical damage. Replace weak or Operate circuit breakers several times in order to
burned clips. Install new fuse clips and suitable exercise the mechanism and contacts, and to ensure
clamps. Use manufacturer’s replacement parts. smooth operation. Do not oil or grease parts of
molded case circuit breakers.
Measure the contact resistance across each
switchblade and fuseholder. The contact resistance Visually check circuit breakers for evidence of
values should not exceed the high levels of the overheating and thermal damage. Investigate and
normal range as indicated by the manufacturer’s eliminate sources of overheating.
published data. Investigate values that deviate from
adjacent poles or similar switches by more than 50 Check circuit breakers for visual defects, chipping,
percent of the lowest value. cracks, breaks, burns, and deterioration. Replace
Look for fuses that have been bridged with wire, Check circuit breaker terminals and connections
metal strips, disks, or appear to have been forced or for tightness using calibrated torque wrench or
hammered into place. Replace with correct fuses and screwdriver. Refer to manufacturer’s instructions and
consult the manufacturer for recommendations for markings for proper torque values. Keep in mind
21 n
NECA 407 Standard for Installing and Maintaining Panelboards
n 22
9. Inspection
1. Scope and Re-Energization
After Adverse Operating Conditions
9.1 Inspection and Testing Following a Perform electrical testing as specified in Section 6.3,
Short-Circuit or Ground-Fault including primary current injection testing of circuit
breakers. Compare insulation resistance test results
Consult the manufacturer for recommendations with previous test results and with the original
before performing any testing or maintenance factory test data corrected for temperature variations
following a short-circuit or ground-fault. using the manufacturer’s recommended multipliers.
Panelboards that are rebuilt or modified in the Correct deficiencies or replace components in
field may require evaluation by a qualified safety accordance with manufacturer recommendations.
certification organization to validate that the
equipment continues to meet the requirements of the Re-energize the panelboard in accordance with
applicable product safety standard. Section 8.12.
Identify and remove the cause of the short-circuit or
ground-fault. 9.2 Panelboards Soaked By or Submersed
Under Water
Clean, inspect, test, and maintain the panelboard in
Panelboards or components of panelboards
accordance with Section 8.
that are subject to exposure to water should be
Inspect the overcurrent protective device(s) that evaluated using the guidelines outlined in the
operated for possible arc-damage to the contacts, NEMA publication, “Evaluating Water-Damaged
arc chutes and/or insulation. Do not open sealed Electrical Equipment,” and the UL publication,
devices. Replace any sealed units that are suspected “Considerations for Flood Immersed Products.”
of sustaining damage. Consult the manufacturer for Consult the manufacturer and the local inspection
recommendations. authority before cleaning up or restoring water
damaged panelboards
that are rebuilt or components.
or modified in the field Panelboards
may
Check for arcing paths or strike points to ground
and from phase-to-phase. Eliminate sources of arcing require evaluation by a qualified safety certification
and clean carbon paths on insulating surfaces in organization to validate that the equipment
accordance with manufacturer recommendations. continues to meet the requirements of the applicable
product safety standard.
Inspect the panelboard for physical damage in
structural components, bussing, and conductors. De-energize and lockout panelboards in accordance
Check for mechanical distortion, thermal damage, Section 3.
metal deposits, or products of combustion. Consult
the manufacturer for recommendations. Clean and dry all parts of the panelboard carefully
using clean, dry cloths. Dry panelboards using
Examine all devices and bus supports for cracks external heaters. Do not exceed 82°C (180°F) when
or breakage. Consult the manufacturer for drying panelboards using heaters.
recommendations. Inspect individual devices for the possible entrance
of water, dirt or foreign matter.
23 n
NECA 407 Standard for Installing and Maintaining Panelboards
breakers.
Perform insulation-resistance testing of the
panelboard (see Section 10.1).
n 24
10.Scope
1. Testing Procedures
Consult panelboard manufacturer’s published data Perform long-time delay time-current characteristic
for acceptable test results. If published data is not tests by passing 300 percent rated primary current
available, investigate any values which deviate from through each pole separately unless series testing is
previous test results under similar conditions by required to defeat ground fault functions.
more than 50 percent of the lowest value. Investigate
any results less than 1 megohm with the overcurrent Determine the short-time pickup and delay.
protective devices in the open position for possible
tracking on insulation or insulation breakdown. Determine the ground-fault pickup and time delay.
25 n
NECA 407 Standard for Installing and Maintaining Panelboards
Determine the instantaneous pickup current using record of all infrared scan results to track electrical
run-up or pulse method. Instantaneous pickup characteristics of panelboards over time.
values of molded-case circuit breakers should be
within manufacturer’s published tolerances. Consult the panelboard manufacturer for repair
or replacement recommendations if infrared scan
The trip characteristic of breakers should fall results indicate overheating of components.
within the manufacturer’s published time-current
characteristic tolerance band, including adjustment De-energize the panelboard. Observe the safety
factors. Replace circuit breakers exceeding the procedures in Section 3. Test the panelboard to
specified trip time at 300 percent of pickup. confirm that it is de-energized. Install all accessible
covers, panels, and doors. Re-energize the
Verify the correct operation of any auxiliary features panelboard and loads in accordance with Section
such as trip and pickup indicators, zone interlocking, 8.12.
electrical close and trip operation, trip-free, and anti-
pump functions.
Provide supplemental
during infrared scan tobarriers
preventand safety precautions
accidental contact
with exposed energized components. Follow the
safety procedures in Section 3.
n 26
(This annex is not part of the standard)
Annex
1. A: Reference Standards
Scope
This publication, when used in conjunction with the National Electrical Code and panelboard manufacturers’
literature, provides sufficient information to install and maintain panelboards operating at 600 Volts or less.
The following publications may also provide useful information:
NEMA PB 1.1-2007, General Instructions for Proper Handling, Installation, Operation, and Maintenance of
Panelboards Rated 600 Volts or Less (ANSI)
27 n
NECA 407 Standard for Installing and Maintaining Panelboards
(303)
(303) 697-8441
697-8431 tel
fax
www.netaworld.org
NECA/NEMA 105-2007, Standard for Installing Metal Cable Tray Systems (ANSI)
NECA 111-2003, Standard for Installing Nonmetallic Raceways (RNC, ENT, LFNC) (ANSI)
NECA/NACMA 120-2012, Standard for Installing Armored Cable (AC) and Metal-Clad Cable (MC) (ANSI)
NECA 121-2007, Standard for Installing Nonmetallic-Sheathed Cable (Type NM-B) and Underground Feeder
and Branch-Circuit Cable (Type UF) (ANSI)
NECA 130-2010, Standard for Installing and Maintaining Wiring Devices (ANSI)
NECA 169-2010, Standard for Installing and Maintaining Arc-Fault Circuit Interrupters (AFCIs) and Ground-
Fault Circuit Interrupters (GFCIs) (ANSI)
NECA 200-2010, Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
(ANSI)
NECA 202-2013, Standard for Installing and Maintaining Industrial Heat Tracing Systems (ANSI)
n 28
Standard for Installing and Maintaining Panelboards NECA 407
NECA 230-2010, Standard for Selecting, Installing, and Maintaining Electric Motors and Motor Controllers
(ANSI)
NECA/FOA 301-2009, Standard for Installing and Testing Fiber Optic Cables (ANSI)
NECA 303-2005, Standard for Installing Closed-Circuit Television (CCTV) Systems (ANSI)
NECA 305-2010, Standard for Fire Alarm System Job Practices (ANSI)
NECA 331-2009, Standard for Building and Service Entrance Grounding and Bonding
NECA 400-2007, Standard for Installing and Maintaining Switchboards (ANSI)
NECA 402-2014, Standard for Installing and Maintaining Motor Control Centers (ANSI)
NECA/EGSA 404-2014, Standard for Installing Generator Sets (ANSI)
NECA 406-2014, Standard for Installing Residential Generator Sets (ANSI)
NECA 407-2015, Standard for Installing and Maintaining Panelboards (ANSI)
NECA 408-2009, Standard for Installing and Maintaining Busways (ANSI)
NECA 409-2009, Standard for Installing and Maintaining Dry-Type Transformers (ANSI)
NECA 410-2013, Standard for Installing and Maintaining Liquid-Filled Transformers (ANSI)
NECA 411-2014, Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS) (ANSI)
NECA 412-2012, Standard for Installing and Maintaining Photovoltaic (PV) Power Systems (ANSI)
NECA 413-2012, Standard for Installing and Maintaining Electric Vehicle Supply Equipment (ANSI)
NECA 420-2014, Standard for Fuse Applications (ANSI)
NECA 430-2006, Standard for Installing Medium-Voltage Metal-Clad Switchgear (ANSI)
NECA/IESNA 500-2006, Standard for Installing Indoor Commercial Lighting Systems (ANSI)
NECA/IESNA 501-2006, Standard for Installing Exterior Lighting Systems (ANSI)
NECA/IESNA 502-2006, Standard for Installing Industrial Lighting Systems (ANSI)
NECA 503-2005, Standard for Installing Fiber Optic Lighting Systems
NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling (ANSI)
NECA/NCSCB 600-2014, Standard for Installing and Maintaining Medium-Voltage Cable (ANSI)
NECA/NEMA 605-2005, Recommended Practice for Installing Underground Nonmetallic Utility Duct (ANSI)
NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installation
Methods for Commercial Buildings (ANSI)
NECA 700-2010, Standard for Installing Overcurrent Protection to Achieve Selective Coordination (ANSI)
NECA 701-2013, Standard for Energy Management, Demand Response and Energy Solutions (ANSI)
29 n
<This page intentionally left blank>
National Electrical Contractors Association
3 Bethesda Metro Center
Center,, Suite 1100
Bethesda, MD 20785
301-657-3110 • 301-214-4500 fax
www.necanet.org