Professional Documents
Culture Documents
Wro Bogalech Mohamed g+4 Hotel Building
Wro Bogalech Mohamed g+4 Hotel Building
Wro Bogalech Mohamed g+4 Hotel Building
OCT, 2023
i
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Table of Contents
EXECUTIVE SUMMARY................................................................................................................................iii
1.0 INTRODUCTION.....................................................................................................................................1
2.0 PROJECT INFORMATION........................................................................................................................1
2.1 Project Description............................................................................................................................1
2.2 Site Location and Description............................................................................................................2
3.0 SUB-SURFACE CONDITIONS...................................................................................................................2
3.1 Typical Subsurface Profiles................................................................................................................2
3.2 Ground water....................................................................................................................................2
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION.....................................................................3
4.2 Earthwork..........................................................................................................................................3
4.2.1 Site Preparation..........................................................................................................................3
4.2.3 Grading and Drainage.................................................................................................................4
4.2.4 Construction Considerations.......................................................................................................4
4.3 Foundations.......................................................................................................................................5
4.3.1 Design Recommendations..........................................................................................................5
4.4 Seismic Considerations......................................................................................................................6
4.3.2 Construction Considerations.......................................................................................................7
5.0 GENERAL COMMENTS...........................................................................................................................8
5.1 Additional Recommendations...........................................................................................................8
APPENDIX A FIELD EXPLORATION..............................................................................................................10
Field Exploration Description.................................................................................................................13
Field Tests and Sampling Methods....................................................................................................13
Test Procedure...................................................................................................................................13
6.0 REFERENCES........................................................................................................................................19
7.0 ABBREVIATIONS...................................................................................................................................19
ii
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
EXECUTIVE SUMMARY
A geotechnical exploration has been performed for the Proposed NEW CREATION
INTERNATIONAL CHURCH G+4 OFFICE AND WORSHIP HALL BUILDING –
HAWASSA located at city:- hawassa, sub city:- taror, kebele:- hogane wacho, Ethiopia. Zedek
geotechnical scope of work included the advancement of Two (2) soil test borings to depths of
approximately 0.0 to 3.00 meter below existing site grades
.
Based upon geotechnical conditions encountered in the borings and our current understanding
of the proposed development the following geotechnical considerations were identified:
The test borings encountered existing uncontrolled fill and organic topsoil to depths
ranging from 0.0 to 1.0 meter. We recommend excavating the uncontrolled fill and topsoil from
within the building area and replacement with a controlled engineered fill.
Due to the high plasticity and relatively impermeable nature of the soils encountered
within our borings, water level data is limited. Based on sample moisture conditions, we
estimate the groundwater level to be between 20 and 60 meters below the existing ground
surface. We anticipate groundwater seepage in open excavations would be controlled
by sump pumping, if encountered.
Black grain, Black soil, & Gray Soil were observed in the upper portion of our borings. These soils
have the potential for volumetric changes due to changes in moisture conditions, and tend to
swell when wet and shrink when dry. Care should be taken to avoid moisture condition changes
during excavation. Open excavations where Black & Gray Soil are exposed should be protected
from open air and precipitation to minimize changes in moisture.
The natural soils encountered at the site are susceptible to disturbance from construction
traffic. Care should be taken to prevent disturbance of the natural soils.
Close monitoring of the construction operations discussed herein will be critical in achieving the design
subgrade support. We therefore recommend that Zedek be retained to monitor this portion of the
work.
This summary should be used in conjunction with the entire report for design purposes. It should be
recognized that details were not included or fully developed in this section, and the report must be read
in its entirety for a comprehensive understanding of the items contained herein. The section titled
GENERAL COMMENTS should be read for an understanding of the report limitation.
iii
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
1.0 INTRODUCTION
This report presents the results of our geotechnical engineering services performed for the Proposed NEW
CREATION INTERNATIONAL CHURCH,located at city:- hawassa, sub city:- tabor, kebele:- hogane
wacho Ethiopia. Our geotechnical engineering scope of work for this project included the advancement of
Two (2) soil test borings to depths ranging from approximately 0.0 to 3.00 meter below existing site
grades.
The purpose of these services is to provide information and geotechnical engineering recommendations
relative to the proposed building:
1
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
ITEM DESCRIPTION
Based on the results of the borings, subsurface conditions on the project site can be generalized
as follows:
Initially, uncontrolled fill and organic topsoil was encountered in our test borings. The uncontrolled
fill consisted of clayey sands and poorly-graded sands with silt. The topsoil was black & gray in color and
contained organic material. These soils were found to extend to depths ranging from 0.0 to 1.0 meter
below the existing grade.
Lean clays and fat clays were the predominant soils identified within our borings. These cohesive
soils were of various shades of olive-brown to grayish-brown in color. In boring B-1, stratum
consisting of grayish-brown silt was observed. Field consistencies for cohesive soils ranged from
very soft to stiff, and very loose for non-cohesive soils.
Specific conditions encountered at each boring location are indicated on the individual boring logs.
Stratification boundaries on the boring logs represent the approximate location of changes in soil
types; in-situ, the transition between materials may be gradual.
2
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Groundwater level fluctuations occur due to seasonal variations in the amount of rainfall, runoff and
other factors not evident at the time the borings were performed. In addition, perched water can
develop over low permeability soil or rock strata. Therefore, groundwater levels during construction or
at other times in the life of the structure may be higher or lower than the levels indicated on the boring
logs. The possibility of groundwater level fluctuations should be considered when developing the design
and construction plans for the project.
4.2 Earthwork
The following presents recommendations for site preparation, excavation, subgrade preparation
and placement of engineered fills on the project. The recommendations presented for design
and construction of earth supported elements including foundations, slabs and pavements are
contingent upon following the recommendations outlined in this section.
Earthwork on the project should be observed and evaluated by Zedek. The evaluation of
earthwork should include observation and testing of engineered fill, subgrade preparation,
foundation bearing soils, and other geotechnical conditions exposed during the construction of
the project.
3
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
The soils encountered in the borings will be sensitive to disturbance from construction activity.
Construction activity should be monitored, and should be curtailed if the construction activity is causing
sub-grade disturbance. A Zedek representative can help with monitoring and developing
recommendations to aid in limiting subgrade disturbance.
4
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Surface water should not be allowed to pond on the site and soak into the
soil during
construction. Construction staging should provide drainage of surface water and precipitation away from
the building and pavement areas. Any water that collects over or adjacent to construction areas should be
promptly removed, along with any softened or disturbed soils. Surface water control in the form of
sloping surfaces, drainage ditches and trenches, and sump pits and pumps will be important to avoid
ponding and associated delays due to precipitation and seepage.
All excavations should be sloped or braced as required by OSHA regulations to provide stability and safe
working conditions. Temporary excavations will probably be required during grading operations. The
grading contractor, by his contract, is usually responsible for designing and constructing stable,
temporary excavations and should shore, slope or bench the sides of the excavations as required to
maintain stability of both the excavation sides and bottom. All excavations should comply with
applicable local, state and federal safety regulations, including the current Occupational Health and
Safety Administration (OSHA) Excavation and Trench Safety Standards.
Construction site safety is the sole responsibility of the contractor who controls the means, methods
and sequencing of construction operations. Under no circumstances shall the information provided
herein be interpreted to mean that Zedek is assuming any responsibility for construction site safety or
the contractor's activities; such responsibility shall neither be implied nor inferred.
4.3 Foundations
In our opinion, the proposed building can be supported by an Combined footing foundation system
bearing on natural, undisturbed inorganic soils or engineered fill after removal of the existing fill and
topsoil. Design recommendations for Deep foundations for the proposed structure is presented in the
following paragraphs.
5
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
The methods of assessing the likely earthquake intensity and frequency for any given site
are complex, requiring reasonable judgment and collection of geological and seismic data.
Due to such a complexity, for the project site under consideration, the recommendation
is to rely on the Ethiopian Building Code provisions and the seismic risk map of Ethiopia.
The current Ethiopian Building Code Standard for Earthquake is prepared with
provision of Peak Ground Acceleration ratio (PGA) with a return period of 475 years.
Accordingly, five distinct seismic regions are identified with different ranges of PGA values
as shown in the legend of the figure below. Note that the ratio of the PGA to the
gravitational acceleration, g, corresponds to α0 (the bedrock acceleration ratio). When
this is considered WERABIE falls under high seismic zone (zone 4) with bedrock
acceleration ratio of 0.15g.
6
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
If unsuitable bearing soils are encountered in footing excavations, the excavations should be extended
deeper to suitable soils and the footings could bear directly on these soils at the lower level or on lean
concrete backfill placed in the excavations. The footings could also bear on properly compacted backfill
extending down to the suitable soils. Over excavation for compacted backfill placement below footings
should extend laterally beyond all edges of the footings at least 20 centimeter per foot of over excavation
depth below footing base elevation. The over excavation should then be backfilled up to the footing base
elevation with well-graded granular material placed in lifts of 20 centimeter or less in loose thickness and
compacted to at least 95 percent of the material's maximum standard Proctor dry density (ASTM D-698).
The over excavation and backfill procedure are described in the figure below.
7
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
8
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Provide about 1.3m wide water tight apron around structure with appropriate take away ditch
system. The apron must have adequate slope to facilitate rain water flow in to the take away
ditch easily. Any crack opening of the apron through aging should be sealed with concrete to
avoid rain water percolation into the foundation.
Remove at least 0.8m thick soil below the apron and replace with well compacted and well
graded select material.
Grading work and watering is not recommended close to the building since this activity will
facilitate water infiltration into the foundation soil below the granular fill material Locate water
and drainage lines so that if drainage occurs water will not be readily accessible to foundation
soil thereby creating damage Septic tank should be constructed from water tight structures.
9
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
APPENDIX A
FIELD
EXPLORATION
10
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Exhibit A-1
11
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Exhibit A-2
12
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Test Procedure
Operation of the DCP requires three persons; one person to hold the apparatus vertical and
one person operating the hammer and the other to record the depth of penetration. The
following steps are followed:
1. The operator holds the device vertical by the handle on the top shaft and "sealing" the
cone tip by dropping the hammer until the widest part of the cone is just below the testing
surface. A second person records the height at the bottom of the anvil in reference to the
ground, this is recorded as initial penetration as "blow zero".
2. The operator lifts the hammer from the anvil to the handle, and then releases the
hammer. The second person records the new height at the bottom of the anvil.
3. Step 2 is repeated until the desired depth of testing is reached or the full length of the lower
rod is buried. The rod is 1m high and since there is unavailability of extension rod the test is
done by excavating the soil every 1m.the soil is less confined near the surface and during
excavation the upper soil is disturbed so that the DCP is able to penetrate further per drop thus
making the initial drops unreliable hence the first two reading are taken as seating blows.
13
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
The test is done up to 4m based on the soil condition. At that time, a specially adapted jack is
used to extract the device. If the tip is disposable (i.e., not fastened to the lower shaft and left
in the soil after test is complete), hitting the hammer lightly on the handle is acceptable.
An automatic SPT hammer was used to advance the polyethylene bags sampler in the borings
performed at this site. A greater efficiency is typically achieved with the automatic hammer
compared to the conventional safety hammer operated with a cathead and rope. Published
correlations between the SPT values and soil properties are based on the lower efficiency
cathead and rope method. This higher efficiency affects the standard penetration resistance
blow count (N) value by increasing the penetration per hammer blow over what would be
obtained using the cathead and rope method. The effect of the automatic hammer's efficiency
has been considered in the interpretation and analysis of the subsurface information for this
report.
The samples were tagged for identification, sealed to reduce moisture loss, and taken to our
laboratory for further examination, testing, and classification. Information provided on the boring
logs attached to this report includes soil descriptions, consistency evaluations, boring depths,
sampling intervals, and groundwater conditions.
14
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
15
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
𝑎
( 𝐹2
) 𝐾𝑑, for B > F4................................(4-2)
𝐵
Where
- B = Width of foundation
- D = Depth of foundation
- qa = Allowable bearing pressure for settlement limited to 25 mm.
- Kd
= 1 + 0.33 < 1.33
𝐷
- F1= 0.05
- F2 = 0.08
- F3 = 0.3
- F4 = 1.2
The following average allowable bearing pressures are calculated for different foundation widths at a
depth of 3.00m below the ground level for settlement limited to 25mm. Footing width is a significant
parameter since a large foundation width will affect the soil to a greater depth and strains integrated over
a greater depth will produce a larger settlement. Bearing capacity values calculated in table 4-2 are based
on the minimum expected SPT N value obtained from the average value TP-01 and 02 (i.e. SPT N Value
of 21.8)
16
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Depth
SPT N Wtd.
TP of N
Value Average
count
0.00 2
0.01 4
0.01 9
0.16 10
1 0.35 6 23.0
0.39 32
0.53 13
0.67 16
0.67 45
0.04 1
0.11 4
0.14 5
0.28 5
2 0.47 11 11.6
0.55 13
0.59 13
0.63 12
0.75 16
17
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
Width, Design
TP S B Depth(m) N F1 F2 F3 Kd Qall
1 25 1 3.5 11.6 0.05 0.08 0.3 1.33 308.99
1 25 1.5 3.5 11.6 0.05 0.08 0.3 1.33 278.09
1 25 2 3.5 11.6 0.05 0.08 0.3 1.33 255.40
1 25 2.5 3.5 11.6 0.05 0.08 0.3 1.33 242.25
1 25 3 3.5 11.6 0.05 0.08 0.3 1.33 233.67
1 25 3.5 3.5 11.6 0.05 0.08 0.3 1.33 227.64
Proposed foundation
S.N Type of Building Type of Allowable (Recommended) Depth Below
Foundation Bearing Capacity ( kPa ) Ground Level
(Meter)
Remark
Foundation rests on 3.00m Thick well compacted granular fill material. The compaction shall be carried
out every 0.2m thickness of selected soil.
One Boreholes of depth 3.00m were manually dug, in-situ tests conducted, disturbed and undisturbed
samples collected. By taking into consideration the type of the buildings, spacing of the columns, total
column load and the subsurface conditions, Combined footing has been proposed. The Allowable Bearing
Capacity and Foundation depth is summarized here under.
18
PREPARED BY AWOKE DESALEGN
ZEDEK GEOTECHNICAL SOIL INVESTIGATION LABORATORY & &
ENVIROMENTAL PROTECTION CONSULTING PLC
6.0 REFERENCES
7.0 ABBREVIATIONS
19
PREPARED BY AWOKE DESALEGN