Professional Documents
Culture Documents
URVISHA - MOM - 44 - 28.11.2023 - SM Nirman
URVISHA - MOM - 44 - 28.11.2023 - SM Nirman
ACTIONS TO ACTUAL
SL. SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
NO. Schedule Date (R0): IN DAYS (Status Date: 27-11-2023)
BY : DATE
A Safety
Block-D Block C / 2 Nos of sump dewatering not done. Deck slab
If larva found in any place of SMN working area
A.0 Dengue Care & SMN deshuttering material not removed from basement at Block
50,000/- will be charged instatntly.
Block-E C.
Deck slab and basement housekipping satisfactary. But It’s a
Block-D House kipping work SMN 8/4/2023 8/11/2023 8/24/2023 continuous process request to keep it Up and maintaind
properly.
B Quality
C Progress Status Blok Wise
Block-C
Micro schedule submitted.
C.3 Deck Slab SMN 4/30/2023 9/10/2023 10/9/2023 -215 Completed
Status:
Column casting work is in progress.
Column casting status: 34/41.
C.4 1st Floor Slab Civil Activity SMN 6/5/2023 10/29/2023 11/24/2023 Ramp-01 Ready to casting.
Ramp:-02 Shuttering work started.
Slab shuttring work not started.
Page 1 of 3
ACTIONS TO ACTUAL
SL. SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
NO. Schedule Date (R0): IN DAYS (Status Date: 27-11-2023)
BY : DATE
Block-D
Block-E
Club
Ambuja requested to complete deck slab before If Club deck slab not completed with in 30-11-2023 LD will
Puja and requested to submitted catch up plan. be applicable.
SMN shall given engineer on or before 28-08- Raft Casting100% Done.
2023. Balance Raft Casting Date:- 05-11-2023.
Retatining Wall Complition up to 2.4 M Height: 10-11-23.
Status: 42 M completed outoff 88 M.
Due to shortage of shuttering material (weller) retaining wall
and column casting work delay.
C.8 Pile Cap and Raft SMN SMN 4/3/2023 02.05.2023 31.05.2023 30-06.2023 11/23/2023 -242 Retaining Tie rod cutting work delay due to unavailibity of
welder.
Page 2 of 3
ACTIONS TO ACTUAL
SL. SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
NO. Schedule Date (R0): IN DAYS (Status Date: 27-11-2023)
BY : DATE
Builder
1 Hoist/Material
Hoist.
Outside scaffolding
4 material and
building wrapping
Page 3 of 3