concn ZAMUL OFFSHORE SERVICES COMPANY
OFFSHORE HOOK UP, UPGRADE MODIFICATION, SCADA INSTALLATION
AND COMISSIONING SUPPORT
(CONTRACT : 6600044802)
TOOL BOX TALK
Location: QMS OMAR Date: 13-JAN-2022
Start Time:06:30 AM ‘TB Log No :TBQM-OMAR-COAT-114
Meeting Duration:30 Minutes Number of Attendees: 4
sussed:
* COATING REPAIR REQUIREMENTS AS PER SAES-H-004.
To,
PARTICIPANTS
Zasnil Emp. Aramco 157 Name of Avtendes | Posion | Signacare
# IQAMA
1 lagtq |wezees |c-Pactar” | wen roreman
2 | suecon | 22ast03575 | pain Miah Pea Gn ~
‘APPLICATOR
3 | suecon |puyyes245| sempre —_| musta
QC Inspector : QC Supervisor
Name: UMER SAEED KHAN Name FRANCIS BINUYA
Discipline: COATIYG Disciaine: (COATING
Signature: Signatures >
a ide * [2 -STANH EZ.
tn
Pagel¢ COATING REPAIR REQUIREMENTS AS PER SAES-H-004.
Cover all coated areas near to the defective area before commence
repair or patching up. Use heavy duty textile or fabric adhesive tape
AS PER SAES-H-004 Para 9.5.1.
For areas less than 0.1 m?, grind to a rough metal surface using at
least an 80 grit disc sander. Alternatively, spot blast or power tool
cleaning to bare steel. Feather edge of coating at least 25 mm beyond
bare metal AS PER SAES-H-004 Para 9.5.2.
For areas greater than 0.1 m?, blast clean to obtain the metal surface
pretreatment originally specified. Feather edge of coating at least 25
mm beyond bare metal AS PER SAES-H-004 Para 9.5.3.
Dust and debris shall be removed from the substrate prior to coating
application AS PER SAES-H-004 Para 9.5.5.
Apply coating by brush for areas less than 0.1 m? and by spray for
areas greater than 0.1 m? to the original specification except that the
first coat of a multi-coat system shall be thinned as recommended in
the product data sheet (SAES-H-002V/SAES-H-101V) AS PER
SAES-H-004 Para 9.5.5.
‘TBT Log No: TBQM- OMAR-COAT-114 Page 2