Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
INSTRUMENT & CONTROL ITEMS 15 06-Dec-23 26-Dec-23
FIM-DA-IC-1000 Release of Free Issue Instrument and Control items by Company 15 06-Dec-23 26-Dec-23
VALVES 15 06-Dec-23 26-Dec-23
FIM-DA-VLV-1000 Release of Free issue valves by Company 15 06-Dec-23 26-Dec-23
PIPING/LINE PIPE 20 23-Oct-23 20-Nov-23
FIM-DA-PP/PL-1000 Release of Free issue Piping/line pipe items by Company 20 23-Oct-23 20-Nov-23
PIPING SPECIALITY ITEM 20 23-Oct-23 20-Nov-23
FIM-DA-PSI-1000 Release of Free issue Piping speciality items by Company 20 23-Oct-23 20-Nov-23
OTHER ASSOCIATED ITEMS 20 23-Oct-23 20-Nov-23
FIM-DA-OAS-1000 Release of Free issue Isolation joint by Company 20 23-Oct-23 20-Nov-23

OVERALL CONSTRUCTION 138 17-Aug-23 30-Jan-24

CONSTRUCTION 132 17-Aug-23 23-Jan-24


PERMANENT FACILITIES 132 17-Aug-23 23-Jan-24
DABBIYA 132 17-Aug-23 23-Jan-24
PRELIMINARY ACTIVITIES 93 17-Aug-23 07-Dec-23
CN-PA-1010 Mobilization of Manpower & Equipment 20 17-Aug-23 09-Sep-23
CN-PA-1000 Carried Out & Topo & Geo Survey 30 09-Sep-23 16-Oct-23
CN-PA-1020 Transportation & Coatin g of Pip eline in Subcontractor facility 30 31-Oct-23 07-Dec-23
SHOP ACTIVITIES 30 04-Dec-23 09-Jan-24
PRE-CASTING 29 04-Dec-23 08-Jan-24
CN-SA-1010 Precast for pipe support foundation 20 04-Dec-23 27-Dec-23
CN-SA-1020 Precast well Head Control Panel foundation 20 04-Dec-23 27-Dec-23
CN-SA-1030 Precast Solar Panel Foundation 20 05-Dec-23 28-Dec-23
CN-SA-1040 Precast Skid Structure Foundation 20 06-Dec-23 29-Dec-23
CN-SA-1050 Precast Portable generator foundation 20 06-Dec-23 29-Dec-23
CN-SA-1060 Precast Platform foundations 20 07-Dec-23 30-Dec-23
CN-SA-1070 Precast crash barrier foundations 20 08-Dec-23 02-Jan-24
CN-SA-1080 Precast fence , gate foundations 20 09-Dec-23 03-Jan-24
CN-SA-1090 Precast marker post foundation 20 11-Dec-23 04-Jan-24
CN-SA-1100 Precast CP Junction Box Foundation 20 11-Dec-23 04-Jan-24
CN-SA-1260 Precast Test post foundation 20 12-Dec-23 05-Jan-24
CN-SA-1280 Precast Earth Pit foundation 20 12-Dec-23 05-Jan-24
CN-SA-1270 Precast Drain Pit foundation 20 12-Dec-23 05-Jan-24
CN-SA-1290 Precast Earth Well foundation 20 13-Dec-23 06-Jan-24
CN-SA-1310 Precast Wind sock foundation 20 14-Dec-23 08-Jan-24
PRE-FABRICATION 30 04-Dec-23 09-Jan-24
STRUCTURE 25 04-Dec-23 03-Jan-24
CN-SA-PF-S-1000 Fabricate valve acces platforms 20 04-Dec-23 27-Dec-23
CN-SA-PF-S-1010 Farbricate cross over platform 20 06-Dec-23 29-Dec-23
CN-SA-PF-S-1031 Farbricate burnt pit,flange pit 20 06-Dec-23 29-Dec-23

Actual Level of Effort summary Issue For Approval


Page 31 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT
Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
CN-SA-PF-S-1020 Fabricate pipe supports 20 07-Dec-23 30-Dec-23
CN-SA-PF-S-1030 Farbricate crash barrier 20 07-Dec-23 30-Dec-23
CN-SA-PF-S-1100 Fabricate wind sock pole 20 07-Dec-23 30-Dec-23
CN-SA-PF-S-1050 Painting of cross over platform 20 08-Dec-23 02-Jan-24
CN-SA-PF-S-1040 Painting of valve access platforms 20 08-Dec-23 02-Jan-24
CN-SA-PF-S-1080 Paint burn pit, flange pit 20 09-Dec-23 03-Jan-24
CN-SA-PF-S-1060 Painting of pipe supports 20 09-Dec-23 03-Jan-24
CN-SA-PF-S-1070 Painting of crash barrier 20 09-Dec-23 03-Jan-24
CN-SA-PF-S-1110 Paint wind sock pole 20 09-Dec-23 03-Jan-24
PIPING 25 09-Dec-23 09-Jan-24
CN-SA-PF-P-1000 Fitup & welding 20 09-Dec-23 03-Jan-24
CN-SA-PF-P-1020 NDT 20 12-Dec-23 05-Jan-24
CN-SA-PF-P-1010 PWHT 20 14-Dec-23 08-Jan-24
CN-SA-PF-P-1030 Hydrotest & Painting of spool 20 15-Dec-23 09-Jan-24
SITE ACTIVITIES 39 07-Dec-23 23-Jan-24
FLOWLINE PHASE-I 32 07-Dec-23 15-Jan-24
CN-SSA-FL-1000 Right of Way 18 07-Dec-23 28-Dec-23
CN-SSA-FL-1010 Stringing 18 11-Dec-23 02-Jan-24
CN-SSA-FL-1020 Main Line (Fitup & Welding) 18 12-Dec-23 03-Jan-24
CN-SSA-FL-1030 Main Line NDT 18 13-Dec-23 04-Jan-24
CN-SSA-FL-1040 Main Line Field joint coating 18 14-Dec-23 05-Jan-24
CN-SSA-FL-1050 Trench excavation 18 15-Dec-23 06-Jan-24
CN-SSA-FL-1060 Pre Padding 18 16-Dec-23 08-Jan-24
CN-SSA-FL-1120 Manual Crossings 18 16-Dec-23 08-Jan-24
CN-SSA-FL-1123 HDD Crossings 18 16-Dec-23 08-Jan-24
CN-SSA-FL-1070 Pipe lowering 18 18-Dec-23 09-Jan-24
CN-SSA-FL-1122 Tie in / Crossing Welding 18 18-Dec-23 09-Jan-24
CN-SSA-FL-1121 Mechanical Crossings 18 18-Dec-23 09-Jan-24
CN-SSA-FL-1080 Post Padding 18 18-Dec-23 09-Jan-24
CN-SSA-FL-1130 CP (Bin Blazing) 18 22-Dec-23 13-Jan-24
CN-SSA-FL-1131 Back-filling 18 23-Dec-23 15-Jan-24
CN-SSA-FL-1132 Berm Construction 16 23-Dec-23 12-Jan-24
FLOWLINE PHASE-II 32 15-Dec-23 23-Jan-24
ISOLATION VALVE AREA WORKS 25 15-Dec-23 15-Jan-24
CN-RMS-1110 Excavation 7 15-Dec-23 23-Dec-23
CN-RMS-1120 Blinding 7 23-Dec-23 02-Jan-24
CN-RMS-1130 Wall Shutterin g 8 02-Jan-24 11-Jan-24
CN-RMS-1140 Wall Concrete 8 04-Jan-24 13-Jan-24
CN-RMS-1060 Welding 5 06-Jan-24 12-Jan-24
CN-RMS-1070 NDT 5 08-Jan-24 13-Jan-24

Actual Level of Effort summary Issue For Approval


Page 32 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT
Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
CN-RMS-1080 Touch up painting 5 09-Jan-24 15-Jan-24
CN-RMS-1090 Install specialty items 5 09-Jan-24 15-Jan-24
CN-RMS-1100 Install flanges 5 09-Jan-24 15-Jan-24
BURN-PIT 23 15-Dec-23 11-Jan-24
CN-BP-1000 Cutting, Excavation, Leveling and Backfilling 7 15-Dec-23 23-Dec-23
CN-BP-1010 Gatch Works 7 23-Dec-23 02-Jan-24
CN-BP-1020 Fitup & welding 5 26-Dec-23 02-Jan-24
CN-BP-1030 NDT (RT) 3 28-Dec-23 02-Jan-24
CN-BP-1040 Installation of Burn Pit Concrete Trench 3 02-Jan-24 05-Jan-24
CN-BP-1050 Cast in-situ of Burn Pit Stair 3 05-Jan-24 09-Jan-24
CN-BP-1060 Installation of Handrail 2 09-Jan-24 11-Jan-24
CN-BP-1070 Installation of Protection Slabs 2 09-Jan-24 11-Jan-24
CN-BP-1080 Protective barrier around burn pit 2 09-Jan-24 11-Jan-24
FLOW LINE HYDROTESTING 4 15-Jan-24 19-Jan-24
CN-PRE-HYT-1000 Cleaning 1 15-Jan-24 16-Jan-24
CN-PRE-HYT-1010 Gauging 1 16-Jan-24 16-Jan-24
CN-PRE-HYT-1020 Header Fixing 1 16-Jan-24 16-Jan-24
CN-PRE-HYT-1030 Water Fill ing + Temperature Stabilization 1 16-Jan-24 17-Jan-24
CN-PRE-HYT-1040 Pressurization + Strength Test 1 16-Jan-24 17-Jan-24
CN-PRE-HYT-1050 Leak Test + De-pressurization 1 16-Jan-24 17-Jan-24
CN-PRE-HYT-1060 Dewatering + Header Cutting 1 17-Jan-24 18-Jan-24
CN-PRE-HYT-1070 Swabbing 1 17-Jan-24 18-Jan-24
CN-PRE-HYT-1080 Drying of flow line to required dew point 1 18-Jan-24 19-Jan-24
CN-PRE-HYT-1090 Nitrogent purging of flow line 1 18-Jan-24 19-Jan-24
TIE IN ACTIVITIES 4 18-Jan-24 23-Jan-24
CN-RMS-1000 Manual Excavation & Precast Support Installation 2 18-Jan-24 20-Jan-24
CN-RMS-1010 Fitup & Welding 2 18-Jan-24 20-Jan-24
CN-RMS-1020 NDT & hydrotest 2 20-Jan-24 23-Jan-24
CN-RMS-1040 Golden Jts Welding 1 20-Jan-24 22-Jan-24
CN-RMS-1050 Golden Jts NDT (RT) & Paint Touch up 1 22-Jan-24 23-Jan-24
WELL HEAD 29 15-Dec-23 18-Jan-24
CIVIL WORKS 28 15-Dec-23 18-Jan-24
CN-SSA-WH-CV-1000 Site Grading 5 15-Dec-23 21-Dec-23
CN-SSA-WH-CV-1010 Mechanical excavation for foundations 7 15-Dec-23 23-Dec-23
CN-SSA-WH-CV-1020 Manual excavation for platform foundations 8 16-Dec-23 26-Dec-23
CN-SSA-WH-CV-1030 Installation of Gates 6 26-Dec-23 03-Jan-24
CN-SSA-WH-CV-1040 Fence Mesh 7 29-Dec-23 08-Jan-24
CN-SSA-WH-CV-1050 Back-filling 6 03-Jan-24 10-Jan-24
INSTALLATION OF PRECAST FOUNDATION
FO 27 15-Dec-23 16-Jan-24
CN-SSA-WH-IF-1000 Pipe Support foundation 6 15-Dec-23 21-Dec-23

Actual Level of Effort summary Issue For Approval


Page 33 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT
Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
CN-SSA-WH-IF-1010 Solar Panel foundation 6 21-Dec-23 28-Dec-23
CN-SSA-WH-IF-1030 Passive Cooling Shelter 4 28-Dec-23 03-Jan-24
CN-SSA-WH-IF-1120 Fence Foundation 6 30-Dec-23 08-Jan-24
CN-SSA-WH-IF-1130 Well Head Gate 1 Foundation 6 30-Dec-23 08-Jan-24
CN-SSA-WH-IF-1060 WHCP foundation 3 30-Dec-23 04-Jan-24
CN-SSA-WH-IF-1110 Removable Protective Barrier foundation (WH Area) 3 30-Dec-23 05-Jan-24
CN-SSA-WH-IF-1080 Telecom tower foundation 3 02-Jan-24 05-Jan-24
CN-SSA-WH-IF-1090 WH acess platform foundation 3 04-Jan-24 08-Jan-24
CN-SSA-WH-IF-1100 Cross over platform Type-1 foundation 3 04-Jan-24 09-Jan-24
CN-SSA-WH-IF-1140 Well Head Gate 2 Foundation 2 09-Jan-24 11-Jan-24
CN-SSA-WH-IF-1150 Control Area Gate 1 Foundation 2 09-Jan-24 11-Jan-24
CN-SSA-WH-IF-1160 Control Area Gate 2 Foundation 2 09-Jan-24 11-Jan-24
CN-SSA-WH-IF-1170 Emergency Gate 1 Foundation 2 11-Jan-24 12-Jan-24
CN-SSA-WH-IF-1180 Corner Post Foundation 2 12-Jan-24 16-Jan-24
CN-SSA-WH-IF-1190 E&I foundation 3 12-Jan-24 16-Jan-24
CN-SSA-WH-IF-1200 Cable Route Marker foundation 3 12-Jan-24 16-Jan-24
CN-SSA-WH-IF-1210 Drain Pit foundation 2 12-Jan-24 15-Jan-24
CN-SSA-WH-IF-1220 Wind sock foundation 1 12-Jan-24 13-Jan-24
INSTALLATION OF STRUCTURAL
STRUCTURA SUPPORT 19 21-Dec-23 13-Jan-24
CN-SSA-WH-ISS-1000 Pipe Support 7 21-Dec-23 29-Dec-23
CN-SSA-WH-ISS-1010 E&I Supports 4 23-Dec-23 28-Dec-23
CN-SSA-WH-ISS-1020 Cross over platform Type-1 2 04-Jan-24 06-Jan-24
CN-SSA-WH-ISS-1030 Cross over platform Type-2 2 10-Jan-24 12-Jan-24
CN-SSA-WH-ISS-1040 WH Access platform 2 11-Jan-24 13-Jan-24
INSTALLATION OF PIPING & EQUIPMENTS
EQ 17 28-Dec-23 18-Jan-24
CN-IN-EQ-1000 Solar panel 2 28-Dec-23 30-Dec-23
CN-IN-EQ-1060 Spool Installation 4 03-Jan-24 08-Jan-24
CN-IN-EQ-1020 Passive cooling shelter & stair 2 05-Jan-24 08-Jan-24
CN-IN-EQ-1070 Fitup & welding 4 05-Jan-24 10-Jan-24
CN-IN-EQ-1010 PWHT 4 06-Jan-24 11-Jan-24
CN-IN-EQ-1040 Telecom Tower 3 06-Jan-24 10-Jan-24
CN-IN-EQ-1080 NDT 4 08-Jan-24 12-Jan-24
CN-IN-EQ-1090 Torqueing & Tensioning of Piping Sectio ns 4 09-Jan-24 13-Jan-24
CN-IN-EQ-1050 Wind Sock 2 12-Jan-24 15-Jan-24
CN-IN-EQ-1100 Hydrotest 4 13-Jan-24 18-Jan-24
CN-IN-EQ-1110 Golden Jts Welding 4 13-Jan-24 18-Jan-24
CN-IN-EQ-1120 Golden Jts NDT (RT) & Paint Touch Up 4 13-Jan-24 18-Jan-24
CN-IN-EQ-1130 Final Box-up & Torqueing of Piping Sections 4 13-Jan-24 18-Jan-24
E&I WORKS 29 15-Dec-23 18-Jan-24
CN-WH-EI-1070 Trench for Inst. cable laying 2 15-Dec-23 18-Dec-23

Actual Level of Effort summary Issue For Approval


Page 34 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT
Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
CN-WH-EI-1080 Instrument and F&G cable laying 2 15-Dec-23 18-Dec-23
CN-WH-EI-1090 Install Wellhead control panel 2 15-Dec-23 18-Dec-23
CN-WH-EI-1035 Trench for Electrical cable laying 4 15-Dec-23 20-Dec-23
CN-WH-EI-1010 Earthing Cable Laying 2 15-Dec-23 16-Dec-23
CN-WH-EI-1000 Deep Earthwell drilling 3 15-Dec-23 19-Dec-23
CN-WH-EI-1170 Glanding 2 18-Dec-23 21-Dec-23
CN-WH-EI-1180 Termination 2 19-Dec-23 21-Dec-23
CN-WH-EI-1050 Install power cables 2 20-Dec-23 23-Dec-23
CN-WH-EI-1020 Cadweld earthing works 4 28-Dec-23 03-Jan-24
CN-WH-EI-1100 Installation of JBs 2 11-Jan-24 13-Jan-24
CN-WH-EI-1110 Installation of Tubes 3 12-Jan-24 16-Jan-24
CN-WH-EI-1120 Installation of field instruments and F&G devices 2 15-Jan-24 17-Jan-24
CN-WH-EI-1130 Installation of ESD Push button 2 15-Jan-24 17-Jan-24
CN-WH-EI-1160 F&G Detector Tag Installation 2 17-Jan-24 18-Jan-24
WELLHEAD-VENDOR MOB- DEMOB
DEMO 4 17-Jan-24 23-Jan-24
SOLAR PANEL 2 18-Jan-24 19-Jan-24
CN-PRE-SP-1000 Solar panel: Loop checking & loading 2 18-Jan-24 19-Jan-24
CN-PRE-SP-1010 Solar panel: Completion of SAT 2 18-Jan-24 19-Jan-24
PLC PANEL 2 18-Jan-24 20-Jan-24
CN-PRE-PLC-1000 PLC: Loop Checking of interconnecting cables & Functional checking of CI & WHC 2 18-Jan-24 20-Jan-24
TELECOM TOWER 2 18-Jan-24 19-Jan-24
CN-PRE-CI-1000 Pole Energenization 2 18-Jan-24 19-Jan-24
CN-PRE-CI-1010 Loop Checking 2 18-Jan-24 19-Jan-24
CN-PRE-CI-1020 Cause and effect LCP Checking 2 18-Jan-24 19-Jan-24
WELL HEAD CONTROL PANEL 2 17-Jan-24 20-Jan-24
CN-PRE-WHCP-1010 WHCP: Flushing /Accumulator charging 2 17-Jan-24 19-Jan-24
CN-PRE-WHCP-1020 WHCP: Power up & Pressure testing 1 17-Jan-24 18-Jan-24
CN-PRE-WHCP-1000 WHCP: Nitrogen purging 2 18-Jan-24 20-Jan-24
CN-PRE-WHCP-1030 WHCP: Interconnection check and functional of LCP 1 18-Jan-24 19-Jan-24
FIELD INSTRUMENT 4 18-Jan-24 23-Jan-24
CN-PRE-FI-1010 Continuity & meggering of electrical cables 2 18-Jan-24 20-Jan-24
CN-PRE-FI-1000 Loop checking of instrument cables 2 19-Jan-24 23-Jan-24
MECHANICAL COMPLETION 4 23-Jan-24 26-Jan-24
PERMANENT FACILITY 4 23-Jan-24 26-Jan-24
MECHANICAL COMPLETION DABBIYA
DABBI 4 23-Jan-24 26-Jan-24
MC-DA-1000 ITR A sign off 1 23-Jan-24 24-Jan-24
MC-DA-1010 Walkdown completion 1 24-Jan-24 24-Jan-24
MC-DA-1020 PUnch A close out 1 24-Jan-24 25-Jan-24
MC-DA-1030 MC dossier issued 1 25-Jan-24 26-Jan-24
MC-DA-1040 MC dossier approved 1 25-Jan-24 26-Jan-24
PRECOMMISSIONING & RFC 3 26-Jan-24 30-Jan-24

Actual Level of Effort summary Issue For Approval


Page 35 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT
Agreement # 4700017420 - P90297 - ASR GAS WELL TIE-INS (2023-2028) DY320

Activity ID Activity Name Original Duration Start Finish 2023 2024


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb ar
PERMANENT FACILITIES 3 26-Jan-24 30-Jan-24
PRECOMMISIONING & RFC DABBIYA
DABBIY 3 26-Jan-24 30-Jan-24
RFC-900 ITR B sign off 1 26-Jan-24 27-Jan-24
RFC-1010 Walkdown completion 1 26-Jan-24 27-Jan-24
RFC-1020 Punch B close out 1 26-Jan-24 27-Jan-24
RFC-1030 RFC dossier issued 1 27-Jan-24 29-Jan-24
RFC-1040 RFC dossier approved 1 29-Jan-24 30-Jan-24

PAC,FINAL DOCUMENTATION
DOCUMENTATIO & HANDOVER 1 30-Jan-24 31-Jan-24

DABBIYA 1 30-Jan-24 31-Jan-24


PAC & FINAL DOCUMENTATION 1 30-Jan-24 31-Jan-24
PAC-DA-2000 PAC & Final Documentation 1 30-Jan-24 31-Jan-24

Actual Level of Effort summary Issue For Approval


Page 36 of 36
Date Revision Checked Approved
Actual Work
03-Oct-23 Schedule Rev.A MT
Remaining Work
10-Oct-23 Schedule Rev.B MT
Critical Remaining Work
31-Oct-23 Schedule Rev.C MT
Milestone 06-Nov-23 Schedule Rev.1 MT

You might also like