Professional Documents
Culture Documents
1414 Ps1 Ta1 NC PWD SPC Prm0 00001 Pape Soe Specifications 20230622 Rs02
1414 Ps1 Ta1 NC PWD SPC Prm0 00001 Pape Soe Specifications 20230622 Rs02
1414 Ps1 Ta1 NC PWD SPC Prm0 00001 Pape Soe Specifications 20230622 Rs02
RFP-2022-CCPC-416
Engineer of Record
Section No. Section Name Engineer of Record
00 10 00 General Instructions
00 11 00 Summary of Work Division 00 Specification
00 12 00 Mobilization and Demobilization Sections concerning
Procurement and
00 15 00 Temporary Facilities Contracting
00 17 00 Materials and Equipment Requirements are not
00 17 30 Project Specific Conditions sealed
DIVISION 03 CONCRETE
03 10 00 Concrete Forming Rev 0 Jun-2023
03 20 00 Concrete Reinforcing Rev 0 Jun-2023
Appendix A: SOE Elements that Contractor is Permitted to Change
DIVISION 05 STEELWORK
05 05 19 Post-Installed Anchors for Concrete Rev 0 Jun-2023
05 12 00 Structural Steel Rev 0 Jun-2023
DIVISION 22 PLUMBING
22 01 00 Mechanical Systems Rev 0 Jun-2023
DIVISION 26 ELECTRICAL
26 01 00 Electrical Systems Rev 0 Jun-2023
26 05 26 Primary Grounding Rev 0 Jun-2023
26 56 00 Temporary Street Lighting Rev 0 Jun-2023
DIVISION 31 EARTHWORK
31 05 17 Aggregates Rev 0 Jun-2023
31 09 13 Geotechnical Instrumentation and Monitoring Rev 0 Jun-2023
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 00 01 10
RFP-2022-CCPC-416 Table of Contents
June 2023 Page 3 of 3
DIVISION 33 UTILITIES
33 00 00 General Utilities Rev 0 Jun-2023
33 05 16 Maintenance Holes and Catch Basin Structures Rev 0 Jun-2023
33 42 11 Storm Utility Drainage Piping Rev 0 Jun-2023
33 44 51 CCTV Inspection of Pipeline Rev 0 Jun-2023
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 00 – Procurement and Contracting
Requirements
GENERAL
1.1 SCOPE
(a) This Section specifies the general instructions for the execution of the
Work.
PRODUCTS
EXECUTION
(b) Lay out Work in accordance with Section 01 71 23.16 and Drawings,
including providing benchmarks, control points, and replacing any
missing and/ or damaged control points and stakes.
(c) Verify all grades, lines, levels and dimensions indicated, and report
errors or inconsistencies to the Metrolinx Representative before
commencing Work or as soon as discovered.
(d) Contractor shall be responsible for the accuracy of the position, lines,
levels, dimensions, and alignment of all parts of the Work and for the
provision of all necessary instruments and labour therewith. Contractor
shall carefully preserve and protect all benchmarks, control points,
stakes, legal monuments, and other features used in setting out the
Work. If at any time during the progress of the Work, any error or
omissions are discovered on the position, lines levels, dimensions, and
alignment of any parts of the Work, the Contractor shall, at its own
expense, promptly rectify such errors to the satisfaction of the Metrolinx
Representative.
(e) The Metrolinx Representative may perform periodic checks of the
Contractor’s layout or measurement of the Work. Checking by the
Metrolinx Representative of any position, lines levels, dimensions and
alignment of any parts of the Work shall not in any way relieve the
Contractor of his responsibility of the correctness thereof.
(f) Carry out all measuring and surveying of the Work necessary to confirm
the quantities for payment of each item in Schedule 7 – Schedule of
Values, and any other subsequently appended quantities that arise due
to Changes to the Agreement.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 11 00
RFP-2022-CCPC-416 Summary of Work
June 2023 Page 1 of 7
GENERAL
1.1. SCOPE
(a) This Section, along with any references to certain elements of the Work
made hereunder, outlines the main tasks to be carried out by Contractor
to execute the Work required under the Agreement, and is not intended
to represent or imply the total scope requirements and details relevant to
the subject(s) referenced.
(b) The Contractor shall review and understand this Section in conjunction
with the Agreement, all of its Schedules, and all other documents listed
in Schedule 9 – Specifications and Drawings, in their entirety, to
ascertain the total scope requirements and activities required in the
delivery of the Work under this Agreement.
1.4. DEFINITIONS
(a) “ESB” – Emergency Services Building. Headhouse structure that
provides access to the tunnel from ground surface for emergency
services personnel. The ESB will contain ventilation fans and equipment
to provide ventilation and smoke extraction as part of the FLS design.
(b) “Ground Instrumentation” as defined in Schedule 9 – Specifications and
Drawings, Section 31 09 13 - Geotechnical Instrumentation and
Monitoring.
(c) “Instrumentation and Data Management System” (IDMS) means a web
accessible data management platform that provides access to all data in
a both graphical format and numerical format that allows for online
interpretation of that data.
(d) “Jet grouting” as defined in Schedule 9 – Specifications and Drawings,
Section 31 43 00 – Jet Grouting.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 11 00
RFP-2022-CCPC-416 Summary of Work
June 2023 Page 2 of 7
(e) “Pape Station” means the existing TTC subway station located between
Danforth Avenue, Gertrude Place and east of Pape Avenue.
(f) “Risk Management Plan” (RMP) means a document that defines how the
Project's risk management process will be executed and includes the
funds, tools and approaches that will be used to perform risk
identification, assessment, mitigation and monitoring activities.
(g) “Risk Register” means a tool used in the risk management of the Project
used to identify potential risks. The Risk Register serves as a repository
for all risks identified and includes additional information about each risk,
their rating, existing control measures and risk mitigation measures.
(h) “Sammon Avenue Headhouse” means the proposed headhouse
structure of the future Ontario Line Emergency Services Building (ESB)
adjacent to the intersection of Pape Avenue and Sammon Avenue, which
is to be constructed by others.
(i) “Slurry Walls” as defined in Schedule 9 – Specifications and Drawings,
Section 31 56 00 - Slurry Walls.
(j) “Support of Excavation” as defined in Schedule 9 – Specifications and
Drawings, Section 31 56 00 - Slurry Walls.
(k) “Temporary Bridge” as defined in Schedule 9 – Specifications and
Drawings, Section 01 53 13 – Temporary Bridges.
(l) “Tie Anchors” as defined in Schedule 9 – Specifications and Drawings,
Section 31 51 00 – Tiebacks and Tie Anchors.
(m) “Tiebacks” as defined in Schedule 9 – Specifications and Drawings,
Section 31 51 00 – Tiebacks and Tie Anchors
(n) “TTC Bus Loop” means the existing TTC bus loop that encompasses the
main TTC headhouse immediately to the north of the existing Pape
Station and immediately to the east of Pape Avenue.
PRODUCTS
EXECUTION
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 12 00
RFP-2022-CCPC-416 Mobilization and Demobilization
June 2023 Page 1 of 5
GENERAL
1.1 SCOPE
(a) This Section specifies the requirements for Mobilization and
Demobilization.
1.3 DEFINITIONS
(a) Mobilization and Demobilization: means the mobilization and
demobilization of the Contractor’s forces and equipment, supplies,
appurtenances and the like, manned and ready for completing the Work
required under the Agreement, and the subsequent demobilization and
removal from the Site of said equipment, materials appurtenances and
the like upon completion of the Work. Mobilization will not be considered
as work in fulfilling the Agreement requirements for commencement of
the Work.
PRODUCTS
EXECUTION
3.1 GENERAL:
(a) Contractor shall:
(i) Familiarize its staff and subcontractors with the Site, the location of
the Work and any limitations and constraints.
(ii) Before commencing Work, obtain all required access, road
occupancy and Contractor PLAA before entering onto land
impacted by the Work and ensure their validity throughout the
duration of Work.
(iii) Commence Mobilization after the Effective Date unless otherwise
required by the Agreement and directed by the Metrolinx
Representative.
(iv) Transport personnel, equipment, supplies and materials to the Site,
including Contractor’s offices, buildings, and other temporary
facilities.
(v) Obtain all required permits for transportation of the Contractor’s
Equipment.
(vi) Obtain all required permits for the Contractor’s and Project offices,
buildings, and other temporary facilities.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 12 00
RFP-2022-CCPC-416 Mobilization and Demobilization
June 2023 Page 4 of 5
(vii) Abide by all codes and regulations for use of existing infrastructure
adjacent to the Site, such as, but not limited to existing roads and
bridges. The Contractor will be held liable for any damages to
adjacent site infrastructure. The Contractor shall ensure that their
forces are in compliance with all bridge clearances, loading
requirements and access conditions.
(viii) Confirm and comply with all roadway, bridge loading and restricted
height clearances.
(ix) Ensure that equipment and materials are mobilized and
demobilized in accordance with all local, provincial, and federal
regulations and acts related to transportation and safety.
(x) Mobilize and demobilize equipment by means of access routes
shown on the Drawings or as indicated by the Metrolinx
Representative in accordance with Section 00 17 30.
(xi) Upon completion of the Work, restore all access areas to the same
condition as prior to the start of the Work, unless indicated
otherwise in Schedule 9 – Specifications and Drawings.
(xii) Conduct, complete and document trainings required to ensure all
of Contractor’s (and its Subcontractor’s) staff are qualified,
competent, knowledgeable and skilled enough to perform the Work
in accordance with the health, safety, environmental, quality,
schedule and technical requirements of the Agreement.
3.2 MOBILIZATION
(a) Mobilization is deemed to include the provision of the following:
(i) Contractor PLAAs required to commence Work.
(ii) Site Specific Safety Work Plan as outlined in Schedule 19 –
Construction Safety.
(iii) Submission of a ninety (90) calendar days Mobilization and
Commencement plan detailing the mobilization and Work activities
that Contractor plans to complete within the first ninety days, to be
reviewed and approved by Metrolinx or the Metrolinx
Representative.
(iv) Mobilization of adequate number of workers and staff to meet the
Schedule requirements.
(b) Mobilization includes assembly and delivery to the Site of plant,
equipment, materials and supplies, the clearing of and preparation of the
Contractor’s work area; the complete assembly, in working order, of all
equipment necessary to perform the required work; and all other
preparatory work required to allow for the commencement of the Work.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 12 00
RFP-2022-CCPC-416 Mobilization and Demobilization
June 2023 Page 5 of 5
3.3 DEMOBILIZATION
(a) Demobilization includes all activities associated with the safe and timely
removal from Site of personnel, equipment, supplies and materials not
used in the Agreement, including but not limited to the disassembly,
removal and transportation of the Contractor’s offices, buildings, and
other facilities including the Temporary Facilities.
(b) Demobilization includes submission and acceptance of final
documentation required to meet the requirements of the Agreement.
3.5 HANDOVER
(a) Prior to the completion of Demobilization, the Contractor shall be
required to clear the Site of all Construction materials and Handover the
Site and Work in accordance with Schedule 8 – Outline Commissioning
Schedule and Handover, to existing or better conditions, or as directed
by the Metrolinx Representative, acting reasonably.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 15 00
RFP-2022-CCPC-416 Temporary Facilities
June 2023 Page 1 of 6
GENERAL
1.1 SCOPE
(a) This Section addresses the temporary facilities and activities that will not
be incorporated into the final Work but are essential for the proper
execution and completion of the Agreement.
PRODUCTS
EXECUTION
3.1 GENERAL
(a) Design, supply, erect/install, disassemble, and demobilize whenever and
wherever necessary for the safe and timely completion of the Works, the
following temporary work facilities:
(i) Scaffolding;
(ii) Temporary access platforms;
(iii) Rigging equipment and machinery;
(iv) Lifts for employees and/or lifts for equipment/material; and
(v) Fixed and mobile cranes.
(b) Ensure that all temporary facilities provided by Contractor comply with
the environmental, health and safety requirements of the Agreement and
all applicable requirements of OHSA, Environmental Protection Act, or
any other applicable legislation.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 15 00
RFP-2022-CCPC-416 Temporary Facilities
June 2023 Page 2 of 6
3.2 ACCESS
(a) Use designated entrances for access and egress to various portions of
the Site, maintain such roads for duration of the Agreement Term and
make good damage resulting from Contractor’s use. Repair and restore
parts of the access roads and property broken or damaged by operations
performed under the Agreement
(b) Contractor parties shall check-in and check-out at the gate.
(i) Contractor Parties may be required to demonstrate proof of training
and qualifications to be on Metrolinx property.
(c) Build and maintain temporary roads where required and provide snow
removal during period of Work.
(d) Access roads shall remain in state of good repair, and a well-graded
condition.
3.7 PARKING
(a) Provide eight (8) parking spaces within the Pape Station Site near the
Site Offices for the exclusive use by Metrolinx and the Metrolinx
Representative. Provide one (1) parking space within the Sammon
Crossover Site laydown area near the Site Offices for the exclusive use
by the Metrolinx Representative. Contractor to confirm with the Metrolinx
Representative actual location of spaces. Contractor shall obtain off-site
parking for their own forces as needed. Metrolinx will not provide parking
for the Contractor, its Subcontractors, Suppliers and their forces.
3.9 SECURITY
(a) The Contractor shall be responsible for the security and protection of the
Site during the construction period including, but not limited to, any
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 15 00
RFP-2022-CCPC-416 Temporary Facilities
June 2023 Page 5 of 6
3.12 LIGHTING
(a) Provide temporary, portable lighting required to safely perform
Construction Work at night or in reduced visibility environments and in
accordance with the requirements of Schedule 10 – Environmental
Obligations.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 17 00
RFP-2022-CCPC-416 Material and Equipment
June 2023 Page 1 of 3
GENERAL
1.1 SCOPE
(a) This Section specifies the requirements for materials and equipment
required for the execution of the Work.
EXECUTION
2.1 GENERAL
(a) Provide new material and equipment of specified design and quality,
performing to published ratings and for which replacement parts are
readily available.
(b) Use products of one manufacturer for equipment or material of same
type or classification unless otherwise specified.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 00 17 30
RFP-2022-CCPC-416 Project Specific Conditions
June 2023 Page 1 of 6
GENERAL
1.1 SCOPE
(a) This Section covers project specific conditions as related to the
execution of the Work.
(b) Delivery and muck haulage hours for the Contractor to receive deliveries
or haul away material or spoils, are Monday to Friday, from 0900 to 1500
and Saturday 0800 to 1700.
(c) Work outside of the standard hours detailed in Article 1.11(a) of this
Section must comply with all requirements of the Agreement, Schedule
10 – Environmental Obligations and Schedule 11 – Communication and
Public Engagement Protocol, and must be approved by the Metrolinx
Representative prior to commencement of the planned Work.
1.16 HANDOVER
(a) The Contractor shall be required to clear the Site of all Construction
materials and Handover the Site and Work in accordance with Schedule
8 – Outline Commissioning Schedule and Handover, to existing or better
conditions, or as directed by the Metrolinx Representative, acting
reasonably.
SUPPLIERS
EXECUTION
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 01 – General Requirements
Part 1 GENERAL
1.1 SCOPE
(a) Work under this item shall consist of designing, fabricating, furnishing,
constructing, and maintaining the temporary bridges (vehicular and
pedestrian) of a clear span shown on the Drawings or as directed by the
Metrolinx Representative in accordance with these Specifications. The
bridge shall accommodate roadway and sidewalk criteria as shown on
the Drawings or as directed, including superstructure, substructure,
foundations, and all associated work.
(b) The work to construct, maintain, remove, and restore the approaches to
the temporary vehicular and pedestrian bridges is not included under this
item and shall be paid for separately under the applicable roadway items.
Part 2 PRODUCTS
2.1 MATERIALS
(a) The Contractor may use timber, steel, concrete or any other material or
combination of materials that are in sound condition, capable of safely
carrying the specified loads, and meet the approval of the Metrolinx
Representative. Materials for the temporary bridge shall confirm to the
applicable sections of Ontario Provincial Standard Specification (OPSS)
and in accordance with the following OPSS references:
(i) Concrete: OPSS 904.
(ii) Structural Steel: OPSS 906.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 53 13
RFP-2022-CCPC-416 Temporary Bridges
June 2023 Page 8 of 10
joints, if included, shall be installed flush with the top of the wearing
surface to provide continuous surface.
(i) Barriers – Vehicular concrete traffic barriers Type TL3 shall be provided
in accordance with the Ministry of Transportation Ontario standards.
(j) Railings – Handrails shall be provided on the pedestrian bridges
according to CSA S6-19 for handrails and combined rails.
(k) Substructures – The abutments and foundations shall be designed to
support the superstructure and retain the approaches. The temporary
bridge abutments and foundations may be located on top of the existing
support of excavation slurry walls.
(l) Footings – The Contractor shall be allowed the use of the slurry wall
panels or spread footings only as foundations for the temporary bridge.
For the design of the substructures and foundations, refer to the
geotechnical information in the Pape Station Support of Excavation
Geotechnical Data Reports. The design of the substructure foundations
shall be based on the provided geotechnical report and existing borings
or based upon additional borings done at this site by the Contractor at
his own expense for the purpose of the temporary bridge design.
Assumptions and methods used to determine the soil's capacity to
support the footing loads are to be developed by the design Engineer
based on the information given in the Geotechnical Data Reports.
(m) Anticipated footing settlement based on the allowable soil bearing
values.
(n) The bridge footing system shall adequately consider the bearing capacity
of the support structure including the slurry wall panels and the soil
bearing capacity of the applicable geological unit for any element of the
bridge that is founded in soil.
(o) Show method of draining water from the structure to prevent water from
entering the shaft excavation.
Part 3 PRODUCTS
3.3 MAINTENANCE
(a) For the duration of the Project, all temporary bridge components shall be
inspected, and have any deficiencies corrected, to ensure its structural
integrity, safety and performance are not compromised.
(b) Prior to opening the temporary bridge to traffic, the Contractor’s Bridge
Engineer shall perform an initial inspection of the bridge. After opening
the temporary bridge to traffic, the Contractor’s Bridge Engineer shall
perform routine inspections of the bridge at 3-month intervals. The initial
and subsequent inspections shall be performed and documented by
qualified personnel in accordance with MTO "Bridge Inspection Manual".
END OF SECTION
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 55 26
RFP-2022-CCPC-416 Traffic Control
June 2023 Page 1 of 18
GENERAL
1.1 SCOPE
(a) This specification covers the requirements for temporary traffic
management, including partial and full road closures, sidewalk closures,
Site driveways and bus stop relocations.
(d) Coordinate with TPA any required removal or relocation of bike share
stations owned by TPA.
(e) Coordinate with TPA any closure of on-street parking spaces and
parking spaces in parking lots operated by TPA.
(f) Notify the Ontario Trucking Associations of any directional full closures of
roadways or vehicular turning movement restrictions 2 weeks prior to
implementation.
(g) For residences that cannot be accessed by the City of Toronto Solid
Waste Collection vehicles coordinate residential waste removal with City
of Toronto Solid Waste Management Services.
(i) Prepare the traffic analysis for the TIA with the Synchro software
package in conformance with best practices and applicable
guidelines and policies of the City of Toronto, including Guidelines
for Using Synchro 11 (including SimTraffic 11).
(ii) Analyze weekday AM and PM traffic peak periods in the TIA, and
other time periods as required by the City of Toronto, for
intersections impacted by the Work, including intersections along
haul routes.
(iii) Update the TIA whenever changes to construction staging or work
zone layout results in changes to the public impacts of the Work.
(iv) Use turning movement counts for the TIA that are less than 2 years
old, except where the City of Toronto accepts use of older turning
movement counts and it can be shown that the older turning
movement counts are still representative.
(v) When updating the TIA consider all construction projects and
future modifications of roadway and intersection configurations that
impact the intersections included in the traffic analysis.
(l) Prepare and submit for review by Metrolinx Representative and approval
by the City of Toronto traffic control Drawings for Work impacting
travelled ways, bicycle facilities, multi-use paths and sidewalks, for which
the Specifications and Drawings do not provide traffic control Drawings,
and include the following information:
(i) Modification to existing road configuration, road structures, and
appurtenances.
(ii) The location, anticipated duration, and nature of each lane closure,
detour, and lane shift.
(iii) Road conditions prior to implementation shown in background
(greyed out), including street lighting, road configurations, roadside
barriers, and the locations of other existing street furniture or
features such as trees, fire hydrants, catch-basins, and other
furniture or features that will aid in the City’s understanding of the
traffic control drawings.
(iv) Work Zones, including ingress/egress points.
(v) Traffic control and protection devices (signage, PVMS, barriers,
traffic control persons, police control, TC-54s, etc.).
(vi) Traffic movements, pedestrian, and bicycle routes including
alternate routes where applicable.
(vii) Identification of all transit routes impacted by lane closures.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 55 26
RFP-2022-CCPC-416 Traffic Control
June 2023 Page 8 of 18
PRODUCTS
2.1 MATERIALS
(a) Intentionally blank.
2.2 EQUIPMENT
(a) Use only traffic control devices, including pavement markings, for which
there are active OPSS, OPSD, MTOD, City of Toronto Construction or
Material Specifications, City of Toronto Standard Drawings, or that are
authorized under the Highway Traffic Act or the Ontario Regulations
thereto.
(b) Energy attenuation with inertial module system (OPSD 923.302,
November 2006, revision 1) may be used.
EXECUTION
3.1 COMPLIANCE
(a) Comply with requirements of Acts, Regulations and By-Laws in force for
regulation of traffic or use of roadways upon or over which it is necessary
to carry out Work or haul Materials or Equipment.
(b) Do not implement Work impacting public roadways, bicycle facilities,
multi-use paths or sidewalks without review by Metrolinx Representative
and any required City of Toronto permits.
(c) Comply with requirements of City of Toronto Accessibility Design
Guidelines, Construction Specification for Maintenance of Traffic and
Multi-use Trail Design Guidelines.
(d) Comply as much as appropriate in urban conditions with Ontario Traffic
Manual Book 7, the TAC Geometric Design Guide for Canadian Roads,
MTO Roadside Design Manual and the City of Toronto Construction
Specification for Maintenance of Traffic.
(e) Implement traffic control with traffic control persons in compliance with
O.Reg. 213/91, section 69, and the Ontario Traffic Manual Book 7.
(f) Ensure that all Construction Activities comply with the TTMP and any
subsequent amendments or updates as agreed to by the Metrolinx
Representative, City of Toronto, and the TTC.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 55 26
RFP-2022-CCPC-416 Traffic Control
June 2023 Page 10 of 18
(g) Be advised that closures of traffic lanes, bike lanes, sidewalks and
parking spaces located within City of Toronto rights-of-way that have a
duration of more than 12 months require approval of the City of Toronto
Council.
(b) Maintain and leave in place all existing traffic signs, information,
wayfinding and pedestrian wayfinding signs, and pavement markings
except where the Specifications and Drawings indicate removal.
(c) Promptly remove temporary traffic control devices when no longer
required upon completion of the Work, but hand over the following at
Contract completion to Metrolinx in accordance with the requirements of
Schedule 8 – Handover.
(i) Temporary traffic decks and associated barriers and traffic signage
on Gertrude Place and Danforth Avenue.
(ii) TCDs relating to the closure of Lipton Avenue and the closed TPA
parking lot.
(iii) Maintain temporary modifications of traffic signage installed on the
traffic signal at the intersection of Pape Avenue and Lipton
Avenue.
(iv) Curb modification and removal of flexible delineator posts at the
intersection of Eaton Avenue and Danforth Avenue.
(v) Signage modification relating to parking space closures on
Danforth Avenue, Eaton Avenue, Pape Avenue and Sammon
Avenue.
(vi) Closures and realignment of traffic lanes, temporary concrete
barriers and temporary sidewalk on Pape Avenue just south of
Sammon Avenue.
(vii) Sidewalk closure on Sammon Avenue.
(d) Provide and maintain signs, flashing warning lights and other devices
required to indicate construction activities or other temporary and
unusual conditions resulting from Work which requires road user
response.
(e) Use TC-64 signs and portable variable message signs for advance
notification and warning devices as required by the City of Toronto.
(f) Operate, maintain and modify traffic signals that are handed over by the
City of Toronto pursuant to the Metrolinx/Third Party Traffic Control
and/or Traffic Management Device Handover Terms and Conditions, if
any.
(g) Retain an Electrical Maintenance Contractor that is pre-approved by the
City of Toronto for all activities required for operating, maintaining and
modifying traffic signals, as required.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 55 26
RFP-2022-CCPC-416 Traffic Control
June 2023 Page 14 of 18
(h) Close on-street parking spaces only as required for the Work and as
follows:
(i) On Lipton Avenue.
(ii) On the north side of Sammon Avenue Pape Avenue and a point 30
metres further east (3 spaces).
(iii) On Pape Avenue where lane closures are implemented.
(iv) On the north and south sides of Danforth Avenue between
Langford Avenue and Pape Avenue.
(v) On Eaton Ave between Danforth Ave and a point 10 metres further
north.
(i) Provide replacement parking for any residential permit parking spaces
that are closed on Gertrude Place, Muriel Avenue or Eaton Ave by
renting parking spaces in the Green-P parking lot 90, located at 17 Eaton
Avenue.
(j) Implement the storm sewer Work, jet grouting and SOE installation on
Gertrude Place as follows:
(i) Maintain 1 traffic lane on Gertrude Place and Muriel Avenue.
(ii) Close on-street parking spaces on Gertrude Place and Muriel
Avenue only as required for the Work.
(k) Implement jet grouting and SOE installation on Danforth Avenue as
follows:
(i) Provide one westbound and one eastbound traffic lane with
minimum width of 4.0 metres adjacent to the Site.
(ii) Close bike lanes only as required for the Work, and paint sharrow
pavement markings when the bike lanes are closed.
(iii) Shorten westbound left-turn and right-turn lanes at the intersection
of Pape Avenue and Danforth Avenue when required for the Work.
(iv) Close the westbound left-turn lane and prohibit the westbound left-
turning movement at the intersection of Pape Avenue and Danforth
Avenue when required for the Work.
(l) Modify the curb at the intersection of Eaton Avenue and Danforth
Avenue only as shown in the Drawings, and adjust the sidewalk as
required to be AODA compliant.
(m) Install temporary road decks on Danforth Avenue and Gertrude Place to
cover open excavations within the City’s right-of-way.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 55 26
RFP-2022-CCPC-416 Traffic Control
June 2023 Page 16 of 18
(i) Do not use the intersection of Lipton Avenue and Pape Avenue to enter
the Site.
(j) Manage all construction vehicle movements on Lipton Avenue, within the
Pape Station bus loop and at the walkway between the East Headhouse
and Eaton Avenue with traffic control persons.
(k) Do not permit construction vehicles to reverse within the Pape Station
bus loop or the travelled way.
(l) Install and maintain pavement markings on Lipton Ave to delineate the
space that is for exclusive use of TTC buses.
(k) Ensure that temporary bus stops comply with TTC’s Design Manual DM-
0412-02.
(l) Provide an access route to the Pape Station East Headhouse in
compliance with O.Reg. 332/12, and particularly section 3.2.5.
END OF SECTION
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 56 33
RFP-2022-CCPC-416 Temporary Barriers and Enclosures
June 2023 Page 1 of 6
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for temporary barriers and
enclosures, including energy attenuators, hoarding, dust tight screens,
and barricades.
PRODUCTS
2.1 MATERIALS
(a) Intentionally blank.
2.2 EQUIPMENT
(a) Use only traffic control devices, for which there are active OPSS, OPSD,
MTOD, City of Toronto Construction and Material Specifications, or City
of Toronto Standard Drawings, or that are authorized under the Highway
Traffic Act or the Ontario Regulations thereto.
EXECUTION
3.1 GENERAL
(a) All work to be conducted in accordance with City and Ontario Provincial
permits and approvals.
(b) Obtain approvals from the City for traffic control programs.
3.3 HOARDINGS
(a) Erect hoarding using practices that comply with O.Reg. 213/91 and
Section 4.2 of Metrolinx Stations Services Standard MX-STS-STD-001
“Temporary Construction and Customer Experience Requirements for
GO Facilities”.
(b) Erect hoarding using construction grade lumber framing and exterior
grade fir plywood conforming to CSA O121. Contractor to determine size
and spacing of posts and supports to ensure hoarding will remain intact
throughout the duration of construction.
(c) Apply plywood panels vertically with seams flush and butt jointed.
(d) Leave in place all hoardings at completion unless otherwise directed by
the Metrolinx Representative.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 56 33
RFP-2022-CCPC-416 Temporary Barriers and Enclosures
June 2023 Page 4 of 6
3.6 ENCLOSURES
(a) Provide secure, rigid guard rails, fencing, and barricades around deep
excavations, open shafts, open stair wells, open edges of floors and
roofs, and where indicated in the Agreement, Specifications and
Drawings in compliance with O.Reg. 213/91, or as required to ensure
worker safety.
(b) Provide as required by governing authorities and as indicated in the
Agreement, Specifications and Drawings.
(c) Provide temporary construction barriers and energy attenuators as
shown in the Specifications and Drawings and where required to ensure
public and worker safety.
END OF SECTION
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 71 23.16
RFP-2022-CCPC-416 Construction Surveying
June 2023 Page 1 of 8
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements and criteria for control survey,
land surveys, and mapping necessary for the construction of the Works.
(i) Surveyor:
A. Provides supervision for all surveying activities.
B. An Ontario Land Surveyor (OLS) or Professional Engineer
(P.Eng.), to supervise all surveys for construction of the
Works. The OLS or P.Eng. shall have at least 10 years of
professional experience as an OLS or P.Eng. with at least five
years’ experience in a similar role on projects of similar scale
and complexity and be familiar with coordinate transformations
between the various Geodetic Coordinate Systems as
described in Section 3.2
PRODUCTS
EXECUTION
3.1 GENERAL
(a) Contractor shall:
(i) Submit its surveys, mapping, and construction works using the
OL2020 Geodetic Coordinate System set out in Section 3.2(a)(i).
(ii) Provide all required survey reports and submittals to the Metrolinx
Representative duly signed and sealed by the OLS or the P.Eng.
(iii) Review and validate the applied scale factor and geodetic
coordinates of all drawings, plans of survey, and coordinate and
elevation listings provided by Metrolinx in PDF, CADD, and other
formats, prior to acceptance.
(iv) Provide drawings in a ground chainage and dimension system as
per Metrolinx standards.
A. All CADD drawings referencing the Ontario Line Geodetic
Coordinate System the dimensions and Alignment chainages
shall be illustrated as ground measurements. Ground
measurements shall be derived from grid measurements by
applying the project scale factor where:
(1) Ground distance = grid distance / project scale factor, or
(2) Grid distance = ground distance x project scale factor.
(3) The project scale factor for the OL2020 GCS is 0.999886.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 01 71 23.16
RFP-2022-CCPC-416 Construction Surveying
June 2023 Page 4 of 8
include standard iron bars, iron bars, iron tubes, round iron bars, and cut
crosses. Contractor shall submit an inventory plan illustrating the position
of the monuments referenced to OL2020 GCS coordinates, and a
Boundary Monuments Inventory Report indicating the survey boundary
markers, condition, and types.
(b) Within 3 months of completion of construction and restoration work,
Contractor shall engage a licensed OLS to replace all legal survey
monuments shown on the inventory plan that have been destroyed or
disturbed and submit a Final Boundary Monuments Inventory Report to
the Metrolinx Representative.
(c) In the areas where design and construction activities take place within 1
m of a property limit, Contractor shall engage a licensed OLS to stake
out the property limit in the field and prepare field notes and sketches to
document the fieldwork.
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 03 – Concrete
GENERAL
1.1 SCOPE
(a) This Specification covers the design and construction requirements for
formwork, falsework, and temporary supports used in the construction of
concrete structures.
(b) Concrete forming will be required for construction of the concrete guide
walls and for construction of the cap beam on top of the slurry wall end
walls.
(c) Concrete forming will also be required for other concrete structures,
including, but not limited to:
(i) The SOE base slab at the transition between narrow and wide
sections.
(ii) To create sumps as provisions in the SOE base slab to
accommodate the permanent sumps of the future station structure.
(iii) For construction joints as required for the SOE base slab.
1.2 RELATED REQUIREMENTS
(a) Section 02 42 00 – Removal and Salvage of Construction Materials
(b) Section 03 20 00 – Concrete Reinforcement
(c) Section 03 21 21.11 – Glass Fibre-Reinforced Polymer Reinforcement
Bars
(d) Section 03 30 00 – Cast-in-Place Concrete
(e) Section 31 23 00 – Excavation and Fill
(f) Section 31 56 00 – Slurry Walls
PRODUCTS
2.1 DESIGN REQUIREMENTS
(a) Formwork Design:
(i) Formwork design shall be according to CAN/CSA S269.3.
(b) Falsework Design:
(i) Falsework design shall be according to CSA S269.1 and as
specified herein.
(ii) The wood design shall be according to CSA/CAN3-086.
(iii) The structural steel design shall be according to CSA S6.
(iv) Deflection of falsework beams supporting walls and roof slabs shall
be limited to L/270, where L is the span. The loading for deflection
shall be the weight of concrete and formwork.
(v) When deflection of a beam is 10 mm or more, provisions shall be
made to compensate for deflection. When a provision is made to
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 10 00
RFP-2022-CCPC-416 Concrete Forming
June 2023 Page 8 of 12
2.2 MATERIALS
(a) General:
(i) Forms and falsework shall be constructed of wood, metal, or
concrete.
(b) Wood:
(i) Wood shall be according to CSA/CAN3-O86.
(c) Plywood:
(i) Plywood for formwork shall be 7 ply, 17 mm minimum thickness
exterior grade Douglas Fir Plywood according to CSA O121.
(ii) For exposed surfaces, the finish side shall be medium density
overlay plywood.
(d) Metal:
(i) Structural steel shall be according to CAN/CSA G40.20/G40.21
and be of the grade shown on the Shop Drawings.
(ii) Aluminum shall be according to CSA-S157 and be of the alloy and
temper shown on the Shop Drawings.
(iii) Used metal shall be in good condition with all previous fabrication,
adversely affection the required strength corrected.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 10 00
RFP-2022-CCPC-416 Concrete Forming
June 2023 Page 9 of 12
(e) Accessories:
(i) All accessories used shall comply with the details shown on the
Shop Drawings or with the recommendations of the manufacturer
of the specified accessory.
(ii) Hardware left in place, either exposed or embedded in concrete
within 20 mm of its surface, shall be hot dip galvanized.
(iii) Tie rods that are to remain in the walls shall be cut back 50 mm
from the face of the wall. Grout exposed form tie holes on all
exposed surfaces of the concrete. Cavities shall be filled with
cement mortar and the surface left sound, smooth, even and
uniform in colour. The maximum diameter of plastic cones for form
ties shall be 30 mm.
(iv) Hot dip galvanizing shall be according to ASTM 123.
(f) Granular A Fill:
(i) Granular A fill shall be in accordance with Specification Section 31
23 00 – Excavation and Fill, and OPSS 1010.
EXECUTION
3.1 FORMWORK
(a) General:
(i) Forms shall be smooth; clean; free from warps, splits, holes, and
bulges; and constructed and maintained to be mortar tight.
(b) Exposed Surfaces:
(i) Forms for exposed surfaces shall be new, except that forms may
be re-used for exposed surfaces providing their condition is such
as to produce a surface equal to one that would be attained using
new materials.
(ii) Where possible, plywood used on exposed surfaces shall be in full
sheets shall be so arranged that the face grain is perpendicular to
the studs or joists.
(c) Studs, Joists, and Decking:
(i) Studs and joists shall be spaced not more than 400 mm on
centres.
(ii) Edges of abutting sheets shall be nailed to the same stud or joist
with 50 mm nails at not more than 200 mm centers.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 10 00
RFP-2022-CCPC-416 Concrete Forming
June 2023 Page 10 of 12
(iii) When prefabricated form panels are used, adjacent panels shall be
placed such that the joints are maintains flush.
(d) Form Release Oil:
(i) Non-staining form release oil shall be applied to the faces of forms
against which concrete is to be placed.
(ii) The form release oil shall be applied before placing reinforcement.
(e) Ties:
(i) When internal form ties are used, concrete cover to any metal left
upon removal of the forms shall be 60 mm minimum.
(f) Exposed Corners:
(i) All exposed corners on concrete work and shall be chamfered.
(ii) The chamfer shall have a vertical and horizontal dimension of 20
mm.
3.2 FALSEWORK
(a) General:
(i) Sound adjustable falsework shall be built such that the structure
remains true to line and grade after anticipated settlement.
(ii) Mudsills shall not be placed until the contractor has a set of
falsework Shop Drawings on site.
(b) Foundation Work:
(i) The falsework structure shall be supported on mudsills or structure
footings.
(ii) A leveling pad consisting of a minimum of 100 mm of compacted
granular fill, Type A, or of cast-in-place concrete shall be placed
under mudsills to provide a level surface.
(iii) Reduction of the bearing capacity of existing ground or compacted
fill, due to water or ice, shall be prevented by suitable drainage or
protection.
(c) Wooden Shoring:
(i) All wooden posts shall be solid, not built up.
(ii) Where splicing is necessary, the posts shall be cut square and the
two pieces shall be in full contact over the splice.
(iii) Scabbing shall be provided on all four faces of a post to be splices.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 10 00
RFP-2022-CCPC-416 Concrete Forming
June 2023 Page 11 of 12
(iv) Each post shall be braced in two directions both above and below
the splice immediately adjacent to the scabbing.
(v) Splices on adjacent posts shall be staggered.
(vi) Splicing of round posts shall not be permitted.
(vii) Bracing material shall be at least 38 x 89 mm lumber except for
cross bracing for side forms where 19 x 138 mm lumber may be
used.
(viii) Bracing shall be nailed to each post with at least 100 mm nails for
38 x 89 mm lumber and two 75 mm nails for 19 x 139 mm lumber.
(ix) Splicing of bracing shall not be permitted.
(x) Wedges used for purposes of falsework adjustment or to facilitate
removal shall be hardwood.
(d) Metal Shoring:
(i) Erection of metal frame shoring shall be according to CSA S269.1.
(ii) The maximum extension of jacks shall not exceed the lesser of the
manufacturer’s recommendations or 600 mm.
(iii) Shims used for leveling mudsills shall be fir plywood or solid
lumber.
(iv) Wedges used to provide full bearing in U-heads shall be hardwood.
3.3 TEMPORARY SUPPORTS
(a) The construction of temporary supports shall be as specified in the Shop
Drawings.
3.4 REMOVAL OF FORMWORK, FALSEWORK, AND TEMPORARY SUPPORTS
(a) All formwork and falsework shall be removed.
(b) The method and sequence of removal of the formwork and falsework
shall be such that it permits the concrete to take up the stresses
gradually.
(c) Formwork shall not be removed until the concrete has attained a
minimum strength as follows:
(i) At 50% of the concrete design strength for walls, columns, sides of
beams and other vertical surfaces.
(ii) At 75% of the concrete design strength for horizontal surfaces of
beams and slabs and for overhangs extending more than 0.6 m.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 10 00
RFP-2022-CCPC-416 Concrete Forming
June 2023 Page 12 of 12
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 20 00
RFP-2022-CCPC-416 Concrete Reinforcing
June 2023 Page 1 of 10
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for the reinforcing steelwork
of cast-in-place concrete structures for the support of excavation (SOE).
This includes reinforcement for the slurry wall panels, including guide
walls and cap beams, and for the base slab.
(b) For details of SOE elements of the Contract and the elements that can
be adjusted by the Contractor versus what cannot be changed and must
remain as indicated in the Drawings and Specifications, refer to
Appendix A – SOE Elements that Contractor is Permitted to Change, of
this Specification Section.
PRODUCTS
2.1 MATERIALS
(a) Steel Reinforcement:
(i) Steel reinforcement shall be according to OPSS 1440 except yield
strengths shall be as specified in the Specifications and Drawings.
(ii) Standard reinforcing steel shall be Grade 400.
(b) Mechanical Connectors:
(i) Mechanical connectors may be the form saver type, the filled
sleeve type, the swaged sleeve couple type, the threaded couple
type, the hot rolled thread bar coupler type, or the forger bar
coupler type.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 20 00
RFP-2022-CCPC-416 Concrete Reinforcing
June 2023 Page 7 of 10
EXECUTION
3.1 GENERAL
(a) All steel reinforcement and accessories shall be kept clean of all mud,
oil, and other deleterious materials and stored clear of ground contact.
(b) All reinforcement shall be placed as shown in the Drawings and
according to the tolerances shown in the Drawings. Tolerances include
fabrication tolerances.
(e) Cutting:
(i) The cutting of reinforcing bars, and splice bars by oxyacetylene
torch may be carried out only when permitted in writing by the
Metrolinx Representative.
(f) Bending:
(i) Field bending of reinforcing bars shall not be permitted.
(g) Welding:
(i) Welding, including tack welding, shall not be permitted.
(h) Splicing:
(i) Splices for reinforcing steel shall be made as specified in the
approved Shop Drawings.
(ii) Development lengths and lap splices shall be in accordance with
CSA A23.3-19.
(iii) Electrical continuity of reinforcement bars shall be accomplished
through mechanical ties. Use minimum 2 tie wires per every 400m
spacing minimum.
(iv) For hoisted reinforcement cages, use lap splice couplers consisting
of drop forged U-bolt and saddle type wire rope clips, or approved
equal, certified and tested for rebar used.
(i) Mechanical Connections:
(i) General:
A. Mechanical connections shall only be permitted as specified in
the Drawings, or as reviewed by the Metrolinx Representative
and detailed in the Shop Drawings.
B. The form saver type of mechanical connector shall only be
used at construction joints.
C. The mechanical connections shall be qualified by tests made
on sample splices according to the Job Control Tests clause of
this Specification Section.
D. All procedures and equipment for mechanical connections
shall be according to the manufacturer’s recommendations.
E. Ends of reinforcing bars to be joined shall be cut nominally
square.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 20 00
RFP-2022-CCPC-416 Concrete Reinforcing
June 2023 Page 10 of 10
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Sections: 03 20 00 Concrete Reinforcing; 03 30 00 Cast-in-Place Concrete
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A1: SOE Elements that Contractor is Permitted to Change : for Specification Section 03 20 00 – Concrete Reinforcing and 03 30 00 – Cast-in-Place Concrete
(Table A1 is specifically for the SOE base slab)
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(see Note 2) ‘(B)’ applies to both of the sites
SOE base slab thickness Yes No Yes (B) Must support permanent structure (permanent structure NIC)
(P) Must support infill concrete in Wide Section (infill concrete NIC)
(B) Must support Slurry Wall compressive forcing acting axially into SOE base slab
(P) Must support TBM passage through shafts (TBM works NIC)
(P) Must support TBM break-in and break-out forces through End Walls (transferred to
base slab from TBM thrust frame). (TBM works NIC)
SOE base slab reinforcement design Yes Yes Yes, with As above
and detailing (provided as a (for shop conditions
base design) drawings and
detailing)
SOE base slab connection to Slurry Yes Yes Yes, with As above
Wall (or to an alternative support (provided as a (for shop conditions
element below base slab) base design) drawings and
detailing)
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 21 21.11
RFP-2022-CCPC-416 Glass Fibre-Reinforced Polymer Reinforcement Bars
June 2023 Page 1 of 10
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for the fabrication, handling,
placement, and quality control of the Glass Fibre-Reinforced Polymer
(GFRP) reinforcement bars.
(b) GFRP reinforcement bars will be used in the Pape Station SOE slurry
walls for panels within the end walls and head walls.
(vi) Head Wall: The section of slurry wall running parallel and
alongside the existing TTC structure and its previous SOE system.
(vii) Reinforcing Steel Bars: Uncoated deformed steel bars made of
carbon steel as defined in CSA G30.18, used for the reinforcement
of concrete.
(viii) Soft-eye: A discrete section of shaft wall designed to be excavated
through at the start of a tunnel drive from the shaft or for the
breakthrough of a tunnel drive into the shaft.
(ix) Steel Reinforcement: All types of steel reinforcement for concrete
including steel bars.
(x) Swaged: To apply circumferential pressure to a sleeve surrounding
a bar to deform the sleeve sufficiently to achieve bearing between
the deformed sleeve and the deformations on the bar.
(xi) Ultimate Tensile Strength: The breaking load of the material per
unit area established by tensile testing.
(xii) Yield Strength: The stress at which the material exhibits a specified
deviation of proportionality of stress and strain.
(iv) When bar marks are shown on the Shop Drawings, they shall be
used in the schedule.
(v) A copy of the signed and sealed GFRP reinforcement schedule
shall be kept at the site before and during fixing of the GFRP
reinforcement.
(d) Procedures for installing, splicing and securing reinforcing cages in the
excavation including details on how to prevent GFRP reinforcement from
floating or moving from its designed location during cage installation and
concreting.
(e) Provide Quality Control Sheet using an approved form for each
placement location.
(f) Manufacturer’s Product Data:
(i) Chemical and physical properties.
(ii) Certificates of compliance.
(iii) Test reports.
(iv) Delivery, storage, and handling instructions.
PRODUCTS
2.1 MATERIALS
(a) GFRP bars shall be V-ROD bars manufactured by Pultrall Inc. GFRP
bars shall be V-ROD 60 for straight bars and V-ROD Bent Bars 50 for
the straight portion of bent bars, or approved equal.
(b) All GFRP reinforcement shall meet or exceed the materials properties
provided in CSA S807:19.
(c) Straight bar geometric and strength properties shall be as shown in the
table below (based on Pultrall V-ROD 60):
Bar size Effective Nominal Area Minimum
designation Diameter (CSA S807 Guaranteed
Table 1) Tensile
(V-ROD 60 or
Strength
approved equal)
mm2 mm2 MPa
#2 (6M) 6.9 32 1100
#3 (10M) 10.3 71 1100
#4 (12M) 13.6 129 1100
#5 (15M) 17.2 199 1100
#6 (20M) 20.4 284 1100
#7 (22M) 23.6 387 1100
#8 (25M) 27.0 510 1100
#9 (30M) 30.4 645 1000
#10 (32M) 33.7 819 1000
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 21 21.11
RFP-2022-CCPC-416 Glass Fibre-Reinforced Polymer Reinforcement Bars
June 2023 Page 7 of 10
(d) Bent bar geometric and strength properties shall be as shown in the
table below (based on Pultrall V-ROD Bent Bars 50):
Bar size Effective Nominal Minimum Guaranteed
designation Diameter Cross- Tensile Strength
Section
(V-ROD Bent Straight Bent
Area
Bars 50 or Portion Portion
approved
mm mm2 MPa MPa
equal)
#3 (10M) 10.3 71 1022 460
#4 (12M) 13.6 127 1019 459
#5 (15M) 17.2 198 1001 450
#6 (20M) 20.4 285 1028 463
#7 (22M) 23.6 388 1005 452
#8 (25M) 27.0 507 992 446
(e) GFRP bars shall be imprinted with bar identification including fiber type,
size, grade, modulus of elasticity and batch number.
(f) The largest GFRP bar that shall be used in the slurry wall reinforcing
cage at the soft eye location in the slurry wall end walls shall be 32 mm
diameter.
(g) All GFRP reinforcement shall have a minimum tensile modulus of
elasticity of 60 GPa for straight bars and 50 GPa for the straight portion
of bent bars.
EXECUTION
3.1 GENERAL
(a) Deliver, store, and handle GFRP bars in compliance with manufacturer’s
instructions.
(b) All GFRP reinforcement and accessories shall be kept clean of all mud,
oil, and other deleterious materials and stored clear of ground contact.
(c) Store GFRP bars under cover to avoid direct sunlight and chemical
substances.
(d) All reinforcement shall be placed as shown in the Drawings and
according to the tolerances shown in Specification Section 31 56 00 –
Slurry Walls. Tolerances include fabrication tolerances.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 21 21.11
RFP-2022-CCPC-416 Glass Fibre-Reinforced Polymer Reinforcement Bars
June 2023 Page 8 of 10
(e) The concrete cover and placing accuracy tolerances shall be the same
as for steel reinforcing as required in the Drawings and Specifications.
Refer to Specification Section 03 20 00 – Concrete Reinforcing.
(f) Due to the flexibility of GFRP reinforcing bars, use a spreader bar when
hoisting bundles of GFRP bars.
(d) Bending:
(i) Bending of GFRP bars shall be carried out only during the
fabrication process and must be carried out before the full curing of
the bars. Strictly no field bending / alteration shall be permitted.
(e) Splicing:
(i) Mechanical couplers shall not be used; only lapped splices and lap
splice couplers shall be used.
(ii) For hoisted reinforcement cages, use lap splice couplers consisting
of drop forged U-bolt and saddle type wire rope clips, or approved
equal, certified and tested for rebar used.
(iii) Lapped splice and embedment lengths for GFRP reinforcing bars
shall be in accordance with the greater of the manufacturer’s
requirements, ACI 440.1R or CSA S806-12 (R2021).
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 1 of 28
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for the construction of cast-in-
place concrete structures for the support of excavation (SOE) including
slurry wall guide walls, cap beams for top of the slurry wall end walls, the
mud slab at the bottom of the shaft excavation and the SOE base slab.
(b) Concreting of the slurry wall panels shall follow the requirement for
placement of concrete by tremie method in this Specification Section.
(c) For details of SOE elements of the Contract and the elements that can
be adjusted by the Contractor versus what cannot be changed and must
remain as indicated in the Drawings and Specifications, refer to
Appendix A – SOE Elements that Contractor is Permitted to Change, of
this Specification Section.
PRODUCTS
2.1 MATERIALS
(a) Tremie Concrete:
(i) Material supply shall be as per the requirements for Other
Concrete contained in this Specification Section.
(b) Concrete (Other Concrete, not placed by Tremie Method):
(i) Concrete shall be according to Metrolinx General Guidelines,
OPSS 1350, and CSA 23.1.
(ii) All structural concrete shall meet the requirements of CSA A23.1
Class F-1.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 9 of 28
(g) Burlap:
(i) The burlap shall be according to AASHTO M182, Class 4, and
shall be free from substances that are deleterious to concrete.
(ii) The burlap shall have no tears or holes.
(h) Water:
(i) Water used for curing and fog misting of concrete, including pre-
soaking of burlap, and for making bonding agents and mortar and
mixing proprietary patching materials shall be according to OPSS
1302.
(i) Moisture Vapour Barrier:
(i) The material shall be a white opaque polyethylene film according
to ASTM C 171, at least 100 μm thick.
(j) Curing Compound:
(i) Curing compound. A liquid membrane-forming curing compound,
that is in accordance with ASTM C309, Type 1 for concrete not
exposed to sunlight, and Type 1-D with white fugitive dye for
concrete exposed to sunlight, Class A or B as appropriate for the
use or location.
(k) Insulation Material:
(i) Insulation material shall be mineral wool, glass fibre, plastic foam
or other suitable material, having an R value not less than 0.02 m2
C/W per 1 mm thickness.
(ii) Straw insulation shall not be used.
(iii) Loose or absorbent insulation material shall not be used unless it is
completely contained within waterproof wrapping.
(l) Waterstops:
(i) Waterstops used for the slurry wall panels shall be in accordance
with OPSS 1204. Refer to Specification Section 07 10 00 –
Waterproofing System, for the waterstop product and requirements
for the waterstops to be installed between adjacent slurry wall
panels using panel stop ends.
(m) Joint Filler:
(i) Joint Filler shall be according to OPSS 1308.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 11 of 28
2.2 EQUIPMENT
(a) General:
(i) Equipment made of aluminum material shall not come in contact
with the plastic concrete.
(b) Tremie Equipment:
(i) The tremie pipe shall consist of a tube, having a diameter of not
less than 250 mm, constructed with sections having flange
couplings fitted with gaskets. The discharge end shall have a
proper seal so that water will not enter the tube at any time.
(ii) The discharge ends at each end of the tremie pipe shall be
fabricated to allow for the full opening of the discharge ends by
slightly raising the pipe.
(c) Concrete Pump:
(i) The concrete pump shall be such design, size, and condition to
ensure a continuous and adequate supply of concrete without
segregation and without adversely affecting other properties of
concrete.
(d) Consolidating Equipment:
(i) Internal vibrators shall be of the high frequency type with 8,000
minimum to 12,000 maximum vibrations per minute when
immersed in concrete.
(ii) External vibrators shall have a minimum frequency of 3,600
vibrations per minute.
(e) Mixer for Bonding Agents:
(i) The mixer for the bonding agent shall be a stationary mixer, power
driven, and capable of uniformly mixing the materials.
(f) Hand Finishing Tools:
(i) Floats shall be made of magnesium or wood.
(ii) Magnesium bull floats shall be commercially made.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 12 of 28
EXECUTION
(b) General:
(i) All concrete surfaces against which new concrete is to be placed,
including formed and sawcut surfaces, shall be clean, laitance free,
and free from loose or unsound fragments, coatings, and any other
foreign substances. The surface shall be sufficiently rough to
ensure that a full bond is developed with the new concrete.
(ii) The concrete surface shall be uniformly roughened to a surface
profile of 5 ± 2 mm by means of wet abrasive blast cleaning to
ASTM D4259. Mechanical methods such as scabbling, chipping, or
bush hammering to expose the aggregates shall be hydroblasted
to remove all loose or bruised concrete from the surface.
(iii) Roughening is not required for new concrete substrate with a
roughened finish imparted at the time of placement meeting the
profile requirement but will require a hydroblast to provide a clean
laitance free surface.
(c) Cleaning:
(i) All concrete and structural steel surfaces against which new
concrete is to be placed shall be cleaned by power washing no
more than 24-hours prior to placing concrete.
(d) Pre-Wetting:
(i) Except for concrete placed by tremie method, all hard concrete
surfaces to receive fresh concrete shall be in a “saturated surface
dry condition” by the following:
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 15 of 28
(ii) Each layer of concrete shall be vibrated. Vibrators shall extend into
the previous layer to produce a homogenous mixture at the layer
interface.
(iii) Vibration shall not be used to make the concrete flow or to spread
the concrete more than 1.5 m from the point of deposit.
(d) Finishing of Formed Surfaces:
(i) All Classes of Form Finish:
A. All concrete finishing work shall conform to the requirements of
CAN/CSA- A23.1 / A23.2 except as specified herein.
B. All ties, bolts, nails, and other metal specifically required for
construction purposes shall be removed or cut back to a depth
of 50 mm from the surfaces of the concrete and the resulting
holes filled.
C. No dry ties shall be permitted; form tie rods shall remain
embedded and terminate not less than 50 mm from the formed
face of the concrete. Removable embedded fasteners on the
ends of the rods shall be such as to leave holes of a regular
shape for reaming and filling.
D. All ties, bolts, nails and other metal specifically required for
construction purposes shall be removed or cut back to a depth
of 50 mm from the surfaces of the concrete and the resulting
holes filled. Removable embedded fasteners on the ends of
the rods shall be such as to leave holes of a regular shape for
reaming and filling.
(ii) Class 1 Finish:
A. Formwork shall be mortar tight. Panel marks and texture are of
no importance.
B. Honeycombs and voids over 500 mm2 in area shall be filled.
(iii) Class 2 Finish:
A. Formwork shall be mortar tight and shall render a true surface.
Fins 3 mm wide (maximum) shall be allowed at the panel
joints; however, sheathing joints must be mortar tight.
Irregularities of 3 mm in height with areas of 50 mm x 75 mm
shall be allowed to a maximum of four such areas per 3 m2 of
formwork. Patches of dissimilar material will not be permitted.
Horizontal and vertical joints shall be aligned.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 18 of 28
C. Air flow in the space between the moisture vapour barrier and
the burlap shall be prevented.
D. Water shall not be allowed to drip, flow, or puddle on the
concrete surface when placing the burlap or at any time prior
to the concrete has achieved final set.
(iii) Curing with Moisture Vapour Barrier:
A. Air flow in the space between the moisture vapour barrier and
the concrete surface shall be prevented.
B. The moisture vapour barrier strips shall overlap 150 mm and
shall be held in place at the edges and laps to prevent
displacement without marring the surface of the concrete.
(iv) Curing with Curing Compound:
A. Immediately prior to application, the curing compound shall be
agitated by mechanical means to provide a homogeneous
mixture and shall be applied to completely cover the surface of
the concrete.
B. A second application of curing compound shall be applied
within 30 to 60 minutes after the first application.
C. Each application shall be such that the membrane formed is
uniform in thickness and colour and free of breaks and
pinholes.
D. The rate of each application shall not be less than the rate
specified by the manufacturer of the compound.
(v) Curing Compound Sampling:
A. Curing compounds shall be sampled at the site from the spray
nozzle during application.
B. Samples shall be taken at a frequency of one sample per
Contract or one sample per 1,000 linear metres, whichever
provides the greater number of samples.
(vi) Curing Formed Surfaces:
A. Formed surfaces shall require no additional curing where the
formwork is left in place for the minimum specified curing
period.
B. Where the formwork is removed prior to the curing period is
completed, formed surfaces shall be cured with burlap and
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 22 of 28
water according to the Curing with Burlap and Water clause for
the remainder of the minimum curing period.
(h) Control of Temperature and Temperature Difference:
(i) General:
A. During the curing period, the concrete temperature shall not
fall below 10°C or exceed 70°C.
B. The temperature difference between the centre of the concrete
component at a location where the concrete is expected to
reach the highest temperature and the surface shall not
exceed 20°C, for:
(1) Large concrete components where the smallest
dimension is 1 m.
(2) Any concrete subject to cold weather.
(ii) Monitoring:
A. The Contractor shall monitor, record, and submit records for
the concrete and ambient air temperature:
(1) Large concrete components where the smallest
dimension is 1 m.
(2) Any concrete subject to cold weather.
B. The Contractor shall supply and install thermocouple wires
and associated instrumentation with a combined accuracy of
± 1.5°C capable of recording and displaying temperature.
C. The instrumentation shall include data loggers capable of
recording at hourly intervals or less and shall allow direct
reading of temperature.
D. The thermocouples for concrete temperature measurement
shall be installed as shown in Table 2 prior to placing concrete.
E. Thermocouples for monitoring ambient air temperature shall
be installed in the shade close to the surface of the concrete at
a minimum frequency of one thermocouple per stage.
F. Recording of concrete temperatures shall begin at the start of
placement.
G. The temperature shall be recorded automatically at intervals
no greater than one hour until the end of the monitoring period.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 03 30 00
RFP-2022-CCPC-416 Cast-In-Place Concrete
June 2023 Page 23 of 28
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Sections: 03 20 00 Concrete Reinforcing; 03 30 00 Cast-in-Place Concrete
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A1: SOE Elements that Contractor is Permitted to Change : for Specification Section 03 20 00 – Concrete Reinforcing and 03 30 00 – Cast-in-Place Concrete
(Table A1 is specifically for the SOE base slab)
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(see Note 2) ‘(B)’ applies to both of the sites
SOE base slab thickness Yes No Yes (B) Must support permanent structure (permanent structure NIC)
(P) Must support infill concrete in Wide Section (infill concrete NIC)
(B) Must support Slurry Wall compressive forcing acting axially into SOE base slab
(P) Must support TBM passage through shafts (TBM works NIC)
(P) Must support TBM break-in and break-out forces through End Walls (transferred to
base slab from TBM thrust frame). (TBM works NIC)
SOE base slab reinforcement design Yes Yes Yes, with As above
and detailing (provided as a (for shop conditions
base design) drawings and
detailing)
SOE base slab connection to Slurry Yes Yes Yes, with As above
Wall (or to an alternative support (provided as a (for shop conditions
element below base slab) base design) drawings and
detailing)
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 03 37 13
RFP-2022-CCPC-416 Shotcrete
June 2023 Page 1 of 13
Part 1 GENERAL
1.1 SCOPE
(a) The Work described in this Specification includes shotcrete required for
use in repairs of any temporary concrete. The shotcrete described in this
Specification Section is intended for any substandard, damaged or
leaking slurry wall concrete, as defined in Section 31 56 00 – Slurry
Walls.
Part 2 PRODUCTS
2.1 MATERIALS
(a) Shotcrete: Either pre-bagged pre-mixed material suitable for use in the
Site-batched Wet-mix process, or Ready-mix material for use in the
Ready-mix Wet-mix process, conforming to the requirements of ACI
506.2, except as supplemented or amended by this Specification.
(b) Manufacturers: Microsil Shotcrete by King Packaged Materials
Company, Redkrete Deep Patch by Concrete Chemicals, or Jiffy Silica
Fume Enhanced Shotcrete by Jiffy Concrete Products.
(c) Portland Cement: CSA-A5, Type 10 except for total alkali content when
determined as mixed sulfates of sodium, potassium, and sodium oxide
shall not exceed 0.6 of 1 per cent.
(d) Silica Fume: CSA A3001, Type SF. Maximum 10 percent by weight of
Portland Cement.
(e) Aggregates:
(i) Clean, hard, natural, with sharp particles, free from organic matter,
and containing not more than 5 per cent by weight of deleterious
substances. Do not use aggregates that are known, or have the
potential, to produce deleterious expansion in the concrete as a
result of cement- aggregate reactions, when used in proposed
shotcrete mixes. Aggregates shall be normal density.
(ii) Coarse aggregate: Material conforming to grading requirement for
CSA A23.1, Table 11, Group I, nominal aggregate size 10 mm to
2.5 mm.
(iii) Fine Aggregate (Coarse Sand): Natural sand conforming to CSA
A23.1, Table 10, Grading FAl.
(iv) Moisture content 5 per cent maximum.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 03 37 13
RFP-2022-CCPC-416 Shotcrete
June 2023 Page 8 of 13
Note: 1. US mesh sizes shown do not correspond exactly to the standard Canadian
metric sieve sizes shown. They are approximate equivalents given for
information only.
2. Gradations to be based on standard Canadian metric sieve sizes.
(f) Water:
(i) Clean and potable containing less than 5 ppm of chlorides, free
from oil, acid, alkali, organic matter, and other deleterious
substances.
(g) Admixtures:
(i) General: Admixtures shall be compatible with each other and with
other shotcrete materials. Calcium chloride, thiocyanate, or
admixtures containing more than 0.05 per cent chloride ions, shall
not be permitted. Use of admixtures shall be done in strict
accordance with the manufacturer's printed instructions.
(ii) Accelerating Admixture: Contractor shall follow requirements of
ASTM C494/C494M, Type C for the Wet- mix process.
(iii) Water-Reducers: Contractor shall follow requirements of ASTM
C1141.
(iv) Air-Entraining: Contractor shall follow requirements of ASTM
C1141.
(v) Superplasticizing (High-Range Water-Reducing) Admixture:
Contractor shall follow requirements of ASTM C1141.
(h) Accessories:
(i) Curing Compound: ASTM C309; Type 2 white pigmented.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 03 37 13
RFP-2022-CCPC-416 Shotcrete
June 2023 Page 9 of 13
(i) Fibers:
(i) Fibers shall not be used.
2.3 EQUIPMENT
(a) Conform to requirements of ACI 506R.
(b) Pre-moistening equipment: Self-cleaning equipment that can thoroughly
moistening shotcrete material and discharging mixed material without
carry-over from one batch to the next. Hydromix, or double water ring,
equipment will not be considered as pre-dampening equipment.
(c) Mixing equipment: Self-cleaning mixer that can thoroughly mixing sand
and cementing materials.
(d) Pumps shall be positive displacement pumps equipped with hydraulic or
mechanically powered pistons, with compressed air added at the
discharge nozzle.
(e) Delivery equipment: Equipment that can discharge a continuous smooth
stream of uniformly mixed sand and cementing materials free from
slugs through the hose to nozzle at required velocity.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 03 37 13
RFP-2022-CCPC-416 Shotcrete
June 2023 Page 10 of 13
Part 3 EXECUTION
3.1 GENERAL
(a) Dry mix method and wet mix method are acceptable shotcrete
application methods for the Work.
(b) Wet Mix Process:
(i) Pressure for water supply pump shall be minimum 0.10 MPa
higher at discharge nozzle than air pressure at material hose
entrance.
(ii) Weight measuring equipment requirements and tolerances shall
be in accordance with ASTM C94/C94M. Do not measure by
volume.
(iii) Proportion cementing materials, aggregates, and admixtures
where applicable to produce shotcrete material meeting specified
performance requirements.
(iv) Mix ratio of moist sand and cement, by weight, shall be a
maximum of 2.6 for site batching.
(v) Total volumetric air content shall be 7 percent plus or minus 1
percent before placement as determined by ASTM Cl73/Cl73M or
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 03 37 13
RFP-2022-CCPC-416 Shotcrete
June 2023 Page 11 of 13
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 05 – Steel Work
GENERAL
1.1 SCOPE
(a) This Specification provides requirements for post installed anchors for
concrete used to install the strut support brackets to the slurry wall.
PRODUCTS
2.1 MATERIALS
(a) Steel Threaded Anchor Rods, Nuts, and Washers:
(i) Threaded anchor rod shall be in accordance with Specification
Section 03 20 00 – Concrete Reinforcing and shall comprise
threaded steel rods or reinforcing dowels. The threaded steel
anchor rods shall conform to CSA G40.20/ G40.21 or ASTM
F1554.
(ii) High strength nuts, and hardened washers shall be suitable for use
with the types of anchor rods being specified and shall be in
accordance with ASTM A153.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 05 05 19
RFP-2022-CCPC-416 Post Installed Anchors for Concrete
June 2023 Page 6 of 8
EXECUTION
3.2 INSTALLATION
(a) Post-Installed Threaded Anchor Rods:
(i) All anchors shall be installed in conformance with manufacturer's
instructions. Do not exceed manufacturer’s recommended
installation torque.
(ii) Locate / avoid existing steel reinforcing prior to anchor installation
using rebar location or drilling methods. The methods of locating
reinforcing and installing post-installed threaded anchor rods shall
ensure the slurry wall reinforcing steel is not damaged.
(iii) Holes drilled in the slurry wall concrete for the adhesive anchor
installation shall be located as shown on the Contractor’s approved
shop drawings. The drilled holes shall not conflict with the existing
reinforcement and shall provide the minimum cover. If reinforcing is
encountered during the drilling operation, the holes shall be
relocated and the uncompleted holes shall be filled with epoxy
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 05 05 19
RFP-2022-CCPC-416 Post Installed Anchors for Concrete
June 2023 Page 7 of 8
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 05 12 00
RFP-2022-CCPC-416 Structural Steel
June 2023 Page 1 of 10
GENERAL
1.1 SCOPE
(a) This Specification provides requirements for structural steel used for the
SOE support members including, but not limited to, walers, pipe struts,
other steel struts, strut support brackets, waler brackets, waler jog
connections, stiffener plates, tieback bearing plates and trumpets, tie
anchor plates, slurry wall embedded sleeves and plates and any other
steel members, plates or brackets associated with the steel member
assembly or other steel components of the SOE system.
PRODUCTS
2.1 MATERIALS
(a) Steel:
(i) Structural steel shall be new and of the grade and category
specified in the Specifications and Drawings. Structural steel shall
be according to CAN/CSA G40.20/G40.21, Grade 350W for rolled
shapes, Grade 350W for plate, and Grade 300 for miscellaneous
steel work.
(ii) Substitution of other material for size and grade is not permitted
unless reviewed by the Metrolinx Representative.
(iii) The steel shall be identified as specified in the Control of Material
clause.
(b) Bolts, Nuts, and Washers:
(i) Bolts shall be according to ASTM F3125M grade A325M, unless
otherwise noted. Bolt strength and assembly shall be in
accordance with CSA S16.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 05 12 00
RFP-2022-CCPC-416 Structural Steel
June 2023 Page 8 of 10
(ii) Nuts, and hardened washers shall be suitable for use with the
types of bolts being specified and shall be according to ASTM
F3125M.
(iii) The nuts, bolts and washers shall be supplied and shipped
together as an assembly from the same manufacturer.
(iv) Bolts nuts, and washers used with steel specified in the
Agreement, Specifications and Drawings shall be Type 1.
(c) Electrodes:
(i) Welding electrodes, electrode and flux or electrode and gas
combinations shall be low hydrogen (level H16 or less) and shall
be according to CSA W47.1, CSA W48, and Section 12 of CSA
W59.
(ii) Weld metal used with corrosion resistant steels shall have similar
corrosion resistance and colour to the base metal and shall be
according to CSA W59.
(d) Hot dip galvanizing: galvanize steel where indicated, to ASTM A123,
minimum zinc coating of 600g/m2.
EXECUTION
3.2 ERECTION
(a) General:
(i) Additional permanent material may be provided to ensure that the
member capacities are not exceeded during erection, if permitted
by the Metrolinx Representative.
(ii) The additional material shall be shown in the erection diagram.
(iii) The Metrolinx Representative shall be notified in writing of the
starting erection date at least 14 Calendar Days prior to the
commencement of field operations.
(iv) Repairs to erected material shall only be permitted after the
Metrolinx Representative has reviewed the repair procedure.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 05 12 00
RFP-2022-CCPC-416 Structural Steel
June 2023 Page 9 of 10
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 07 – Thermal and Moisture Protection
GENERAL
1.1 SCOPE
(a) This Specification includes furnishing and installing a Waterstop (also
called Waterbar) within the concrete slurry wall panels across the
construction joint, for the entire vertical length of each panel, with the
exception of the bottom 2 m within the slurry wall socket length.
(b) Waterstop shall also be installed across any construction joints in the
SOE base slab.
(c) Waterstops shall be installed using steel stop end elements during slurry
wall construction in accordance with Specification Section 31 56 00.
(d) The Waterstops installed across the slurry wall panel joints and installed
across the construction joints of the SOE base slab are the only
waterproofing system component required under this Agreement and as
such, this Specification Section only covers this product.
PRODUCTS
2.1 GENERAL
(a) Provide Waterstop material that are free from damage and defects.
EXECUTION
3.1 PREPARATION
(a) Installer shall inspect Stop end groove prior to installing Waterstop.
(b) Installer shall inspect Waterstop for damage and defects:
(i) If damage or defects are observed, cut out defective portion a
minimum of 250 mm from the edge of the damage or defect and
discard. Perform an approved welded splice to join Waterstop.
(ii) If multiple damage or defects are observed in a single roll requiring
multiple portions to be cut out, welded splices to join good portions
of Waterstop may not be more closely spaced than 10 m,
otherwise entire roll is to be discarded.
3.2 INSTALLATION
(a) Waterstop for Stops Ends:
(i) A suitable area to install Waterstop in the Stop ends and perform
splice welds in the Waterstop shall be provided:
A. Area shall be clean, free of debris and waste materials and
have sufficient space.
B. Area shall be covered where welded splices are performed.
C. Ambient temperature and material temperature for performing
welded splices shall be in accordance with the manufacturer’s
recommendations or requirements.
(ii) Installation of Waterstop in Stop end shall be performed by the
Installer and shall follow the recommendations and requirements of
the Stop end fabricator and the Waterstop manufacturer.
(iii) Waterstop in Stop end shall terminate 2 m above the bottom of the
Stop end to ensure proper concrete encapsulation around the
bottom of the Waterstop.
(iv) Welded splices for Waterstop shall follow the requirements of the
manufacturer and be performed only by the Installer.
(v) Splices in Waterstops shall be separated by at least 0.5 m from a
tie back penetration in the slurry wall.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 07 10 00
RFP-2022-CCPC-416 Waterproofing System
June 2023 Page 6 of 6
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 22 – Plumbing
GENERAL
1.1 SCOPE
(a) The Mechanical Specifications and Drawings specify complete systems,
including all labour and material required.
(b) This work shall include all labour, materials, tools, equipment,
transportation, etc., necessary for the removal of the complete systems
of plumbing, heating, ventilating, air conditioning, thermal insulation and
temperature control.
(c) The intent of these specifications is to provide complete demolition of the
existing building and while no attempt has been made to detail or list
each individual part required, it is the intent of these specifications to
include all parts and the furnishing of all labour reasonably implied by
these documents and which are required to deliver to the Owners, the
systems complete, and ready for operation.
1.2 RELATED REQUIREMENTS
(a) Intentionally blank.
1.3 MEASUREMENT AND PAYMENT PROCEDURES
(a) Work related to this Section is considered incidental to the Work and will
be measured and paid as part of the Items B.1.1 through B.1.7.
1.4 REFERENCE STANDARDS
(a) Standards for this Division of the work, for materials and workmanship
shall conform to the latest edition of the Canadian Standards
Association, the Ontario Building Code and Ontario Plumbing Code, all
other applicable Codes, and local codes, which govern the work required
for completion of this project.
(b) Ensure that the watermain disconnect meets the City of Toronto
requirements, including but not limited to the following specs:
(i) TS 510 Construction Specification for Removal.
(ii) TS 7.40 Watermain and Water Service Tracer Wire.
(iii) TS 441 Construction Specification for Watermain Installation in
Open Cut.
(iv) TS 7.30 Procedure for Disinfecting Watermains.
(v) TS 7.70 Watermain Replacement and Connection Procedure
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 22 01 00
RFP-2022-CCPC-416 Mechanical Systems
June 2023 Page 2 of 3
(c) Before commencing work, check and verify all sizes, locations, materials,
elevations, levels, and dimensions to ensure proper and correct
installation. Verify existing and municipal services.
PRODUCTS
2.1 EXAMINATION OF DRAWINGS AND SPECIFICATIONS
(a) Before commencing work, this Contractor shall examine all drawings and
specifications relative to this work. No allowance will be made for failure
to make such examination and to take into account all aspects which
may govern the execution and completion of the work.
2.2 SUBDIVISION OF WORK
(a) The work specified in the following sections of the specifications has
generally been divided into Trade Sections for the purpose of ready
reference.
(b) The division of the work among subcontractors and suppliers is solely
the responsibility of the Contractor and the Metrolinx Representative
assumes no responsibility to act as an arbiter to establish subcontractor
limits between any sections or divisions of the work.
2.3 EXISTING BUILDING SITE
(a) Examine site and local conditions and verify the dimensions.. Before
commencing work, examine the work of other Sections and report at
once any defect or interference affecting the work, its completion or
warranty. No allowance will be made later for any expense incurred
through failure to make these examinations or to report any such
discrepancies in writing.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 22 01 00
RFP-2022-CCPC-416 Mechanical Systems
June 2023 Page 3 of 3
EXECUTION
3.1 GENERAL.
(a) The work shall include, but shall not necessarily be limited to the
following:
(i) General Mechanical demolition work as noted on drawings.
(ii) Demolition of all building grilles, registers, diffusers, ductwork and
all related accessories.
(iii) Demolition of all Mechanical equipment within the demolished
building complete with all related Electronic Controls.
(iv) Demolition of building Sprinkler System. Cut and cap existing water
main pipe near property line and remove water service and
disconnect at mainline in the street.
(v) Demolition of building Domestic water piping. Cut and cap existing
water main pipe near property line and remove water service and
disconnect at mainline in the street.
(vi) Demolition of building drainage piping. Cut and cap existing drain
mains near property line and remove sanitary service and
disconnect at mainline in the street.
(vii) Hazardous material (Ozone depleting substances) removal from
Air-
(viii) conditioning units, and other non-fixed small refrigeration
equipment that may contain refrigerants.
(ix) Demolition of building Storm drainage piping. Existing catch basins
external to building shall remain where indicated on contract
drawings. Site storm lines beneath building may be altered to
connect to existing catch basins. Redundant Storm lines not
connecting to Catch basins to be removed and capped to main line
in the street. Cut and cap existing redundant Storm drain mains
near property line and remove Storm service and disconnect at
mainline in the street where required by the City of Toronto Water
Department.
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 26 – Electrical
Part 1 GENERAL
1.1 SCOPE
(a) The Electrical Specifications and Drawings specify complete systems.
Include all labour and material required.
(b) Contractor’s scope of services shall include, but not be limited to, the
decommissioning, removal and disposal of existing high voltage
transformers, high and low voltage equipment, removal and disposal of
lighting systems and sub-systems, disconnect and removal of all
electrical equipment including power systems, heating and cooling
systems, fire alarm systems and all sub- systems inside and outside of
buildings, removal and disposal of conduits and wiring associated with
existing buildings to be demolished; disconnection and removal of all
communication wiring and equipment as well as all wiring, conduits and
equipment related to mechanical equipment.
(c) Include for disposal of all electrical materials including disposal of
regulated substances (hazardous materials, Polychlorinated Biphenyl
(PCB), ballasts, PCB oil).
(d) All potential hazardous materials shall be identified, removed and
disposed of prior to building demolition in accordance with Ontario
Regulation 362 and as specified in other Sections.
Part 2 PRODUCTS
Part 3 EXECUTION
3.1 ELECTRICAL
(a) Prior to building demolition de-energize main electrical service to the
building.
(b) Coordinate with local utility.
(c) Prior to building demolition de-energize telephone service to the building.
(d) Coordinate with Bell Canada and/or any other communications Utility
supplier.
END OF SECTION
OL North Civil Works Schedule 9 – Specification and Drawings
Pape Segment Support of Excavation Section 26 05 26
RFP-2022-CCPC-416 Primary Grounding
June 2023 Page 1 of 16
GENERAL
1.1 SCOPE
(a) This specification describes the requirements for the procurement,
installation, and testing of an interconnected primary and auxiliary
ground electrodes system of Pape Station SOE and Sammon Crossover
SOE. This primary grounding systems shall be connected to the auxiliary
ground electrodes of Pape Station and Sammon Crossover permanent
structures and building for the purposes of equipment grounding, safety
grounding, neutral grounding, and mitigating the stray current induced
corrosion of underground metal structures, including the reinforcing
rebars. This grounding system works as an isolated primary ground
electrodes system for Pape Station Support of Excavation (SOE) and
Sammon Crossover SOE as well. These are considered buried-
underground or concrete encased (imbedded-in-concrete) grounding
systems.
(j) Qualifications:
(i) Contractor’s Design Engineer as referred to in this specification
shall be a licensed Professional Engineer in the province of
Ontario.
(ii) Contractors are responsible for ensuring that work is performed by
staff that are qualified and adequately trained in using the
necessary tools, equipment, materials, and machinery required for
grounding installation.
(iii) Grounding system testing shall be performed by Level III, or higher
level, Electrical Testing Technicians in accordance with
ANSI/NETA ETT standard.
(k) Test Reports:
(i) Provide certified test reports of integrity test and measured ground
resistance according to latest edition of industry accepted
standards IEEE 81-2012.
PRODUCTS
2.1 MATERIALS
(a) Driven electrodes (or Ground Rods): Ground rod dimensions and
material shall be, 19 mm diameter, 3 m long, and copper clad steel.
Ground rods are to be CSA C22.2 No. 41 certified.
OL North Civil Works Schedule 9 – Specification and Drawings
Pape Segment Support of Excavation Section 26 05 26
RFP-2022-CCPC-416 Primary Grounding
June 2023 Page 8 of 16
2.2 EQUIPMENT
(a) It is the Contractor’s responsibility for defining all the required equipment,
tools, and machinery that may be required to complete the installation.
The following is a non-exhaustive list of equipment that is required – and
shall be expanded upon by the Contractor as required:
(i) Exothermic welding equipment and necessary accessories.
(ii) Irreversible compression connector crimping tools and necessary
accessories.
(iii) Cable reel stands and handling equipment for installing copper
conductors.
(iv) Ground resistance test equipment.
(v) Continuity test equipment.
OL North Civil Works Schedule 9 – Specification and Drawings
Pape Segment Support of Excavation Section 26 05 26
RFP-2022-CCPC-416 Primary Grounding
June 2023 Page 12 of 16
EXECUTION
3.1 INSTALLATION
(a) Equipotential planes shall be established by tightly connecting all
longitudinal and transverse rebars together and bonding them to a #4/0
bare copper conductor, 7 strand, class A, at 6 m intervals. The means of
bonding to rebars shall be by listed compressive/pressure connectors of
brass, copper, copper alloy, or an equally substantial approved means.
Equipotential planes shall be bonded together and to the primary
grounding system.
(b) Install continuous grounding system including, electrodes, conductors
and connectors as indicated to requirements of local authority having
jurisdiction.
(c) Install irreversible connectors and exothermic welds in accordance with
manufacturer's instructions.
(d) Protect exposed grounding conductors and connectors during and after
construction.
(e) Design provisions which require conductor or connector to be prepared
for future installation are required to be protected from dust and moisture
(i.e., covered and sealed with 20 mil puncture resistant material).
(f) All buried or concrete encased connections to electrodes (ground rod)
and flat structure steel to use Exothermic welding process which is in
accordance with IEEE 837.
(g) All buried or concrete encased connections to rebar or copper conductor
to use exothermic welding process or irreversible compression
connectors which is in accordance with IEEE 837.
(h) Connections to bonding plates mounted on concrete surfaces of base
slab and SOE panels to be completed using a tin plated two - hole heavy
duty terminal that is connected to a copper conductor via irreversible
compression connection. Use stainless steel hardware to bolt the
terminal to the bonding plate which is torqued to specifications suitable
for the bolt size. In order for the bonding plate to be IEEE 837 certified, it
must be connected with a heavy duty two-hole terminal which is also
IEEE 837 certified.
(i) Use tinned copper conductors for applications where buried ground
conductors are nearby steel structures belonging to others.
(j) Use insulated copper ground cable for applications where ground
conductors are installed nearby buried pipes.
OL North Civil Works Schedule 9 – Specification and Drawings
Pape Segment Support of Excavation Section 26 05 26
RFP-2022-CCPC-416 Primary Grounding
June 2023 Page 13 of 16
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 26 56 00
RFP-2022-CCPC-416 Temporary Street Lighting
June 2023 Page 1 of 6
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for design, supply,
installation, operation and maintenance of new temporary street lighting,
and the operation and maintenance of Street Lighting Assets on
municipal Right of Way.
PRODUCTS
2.1 MATERIALS
(a) All Materials and Labour shall be based on Toronto Hydro approved civil
and electrical standards.
(b) Use only Toronto Hydro-approved materials and obtain all such materials
only from a Toronto Hydro approved supplier.
(c) Obtain inspection and validation that delivered materials are all Toronto
Hydro-approved materials obtained from Toronto Hydro-approved
suppliers.
(d) Obtain inspection and validation of field-installed materials.
EXECUTION
3.1 GENERAL
(a) Execute a Coordination Agreement and a Street Lighting Service and
Work Agreement with THES prior to performing any Work on Street
Lighting Assets.
(b) Execute a Statement of Area of Transfer with THES prior to, and for the
full term for performing the Work covered under this section (the
“Statement of Area of Transfer”). Prior to executing the Statement of
Area of Transfer, coordinate with THES and jointly undertake any
inspections, testing or assessment of all Street Lighting Assets as
required to determine the condition, state of repair and any defects in the
Street Lighting Assets (the “Baseline Inspection”). The Baseline
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 26 56 00
RFP-2022-CCPC-416 Temporary Street Lighting
June 2023 Page 5 of 6
(i) Provide a 24-hour call centre service which can receive and process
calls from THES, the City and the public with respect to the performance
of any of the foregoing services.
(j) For each failure to meet any of the Service Response Standards,
conduct a root cause analysis of such failure and provide such analysis
together with a remedial plan to prevent the recurrence of such failure to
THES within 30 Calendar Days of the end of the month in which such
failure occurred.
(k) After completion of the Work in the Area of Transfer and all Street
Lighting Assets have been cleaned and re-lamped, provide to THES a
Statement of Area of Transfer Return form (the “Statement of Area of
Transfer Return”) no fewer than 30 Working Days in advance of the
proposed date of termination of a Statement of Area of Transfer. The
Statement of Area of Transfer shall not be terminated without consent of
THES.
(l) Upon issuing the Statement of Area of Transfer Return form, permit
THES to undertake any inspections, testing or assessment of all Street
Lighting Assets in the Area of Transfer, that THES deems necessary, in
its sole discretion; and provide THES all data, records (including
invoices), operational records, log books, charts, maps, plans, drawings,
lists of materials, supplies and equipment, contracts and supporting
documentation maintained by the Contractor with respect to the Street
Lighting Assets in the Area of Transfer.
(m) In accordance with Schedule 8 – Outline Commissioning Program and
Handover, Handover all Street Lighting Assets in good working order to
THES after the final inspection, approval and acceptance of the Street
Lighting Assets and execution of the Statement of Area of Transfer
Return by THES.
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 31 – Earthwork
GENERAL
1.1 SCOPE
(a) This Specification describes the Contractor requirements for the supply,
storage and use of granular A as backfill material.
1.9 SAMPLES
(a) The Contractor shall inform the Metrolinx Representative, at least four
weeks prior to commencing production, of the proposed source of
aggregates, and shall provide access for sampling.
(b) The Contractor shall submit the source information of materials to be
incorporated into the Work or stockpiled for Metrolinx Representative
review.
(c) If, in the opinion of the Metrolinx Representative, materials from the
proposed source do not meet, or cannot reasonably be processed to
meet, specified requirements, the Contractor shall locate an alternative
source or demonstrate that the material from the source in question can
be processed to meet specified requirements.
(d) Should a change of materials source be proposed during the Work, the
Contractor shall advise the Metrolinx Representative a minimum of 20
Working Days in advance of the proposed change and shall provide
access to allow sampling and testing.
(e) The Contractor is advised that review of a material at source does not
ensure future acceptance if it is subsequently found to lack uniformity, or
if it fails to conform to specified requirements.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 05 17
RFP-2022-CCPC-416 Aggregates
June 2023 Page 3 of 5
PRODUCTS
2.1 MATERIALS
(a) Granular A material (19mm max) as per OPSS.MUNI 1010.
(b) The Contractor shall ensure the aggregate quality meets all of the listed
requirements: sound, hard, durable material free from soft, thin,
elongated or laminated particles, organic material, clay lumps or
minerals, or other substances that would act in deleterious manner for
use intended.
(c) The Contractor shall ensure flat and elongated particles of coarse
aggregate are in accordance with ASTM D4791.
EXECUTION
3.1 PREPARATION
(a) Processing requirements:
(i) The Contractor shall ensure aggregates are processed uniformly
using methods that prevent contamination, segregation and
degradation.
(ii) The Contractor shall ensure aggregates are blended, if required, to
obtain gradation requirements, percentage of crushed particles, or
particle shapes, as specified. The Contractor shall use methods
and Equipment satisfactory to the Metrolinx Representative.
(iii) The Contractor shall wash aggregates, if required to meet the
Specification requirements.
(iv) The Contractor shall, when operating in stratified deposits, use
excavation Equipment and methods that produce uniform,
homogeneous aggregate.
3.2 HANDLING
(a) The Contractor shall handle and transport aggregates to avoid
segregation, contamination and degradation.
3.3 STOCKPILING
(a) The Contractor shall stockpile aggregates on Site only within designated
staging areas. The Contractor shall not stockpile on completed pavement
surfaces.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 05 17
RFP-2022-CCPC-416 Aggregates
June 2023 Page 4 of 5
(b) The Contractor shall establish stockpiling Sites to be level, well drained,
and of adequate bearing capacity and stability to support stockpiled
materials and handling equipment.
(c) The Contractor shall, except where stockpiled on acceptably stabilized
areas, provide compacted sand base not less than 300 mm in depth to
prevent contamination of aggregate. The Contractor shall stockpile
aggregates on the ground but shall not incorporate the bottom 300 mm
of pile into the Work.
(d) The Contractor shall separate different aggregates by structurally
adequate, full depth bulkheads, or stockpile far enough apart to prevent
intermixing.
(e) The Contractor shall not use intermixed or contaminated materials. The
Contractor shall remove and dispose of materials rejected by the
Metrolinx Representative within 2 Working Days of rejection.
(f) The Contractor shall stockpile materials in uniform layers of thickness as
follows:
(i) Maximum 1.5 metres for coarse aggregate and base course
materials.
(ii) Maximum 1.5 metres for fine aggregate and sub-base materials.
(iii) Maximum 1.5 metres for other materials.
(g) The Contractor shall uniformly spot-dump aggregates delivered to
stockpile in trucks and shall build up stockpile as specified.
(h) The Contractor shall not cone piles or spill material over edges of piles.
(i) The Contractor shall not use conveying stackers.
(j) The Contractor shall, during winter operations, prevent ice and snow
from becoming mixed into stockpile or in material being removed from
stockpile.
3.4 CLEANING
(a) The Contractor shall leave aggregate stockpile Site in a tidy, well drained
condition, free from standing surface water.
(b) The Contractor shall leave any unused aggregates in neat compact
stockpiles to the satisfaction of the Metrolinx Representative.
3.5 PLACING
(a) Place on a clean surface, properly shaped and compacted and free from
snow or ice.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 05 17
RFP-2022-CCPC-416 Aggregates
June 2023 Page 5 of 5
3.6 COMPACTING
(a) Compact each layer to minimum 100% Standard Proctor Maximum Dry
Density to ASTM D698.
(b) Add water as required to maintain material at or near optimum moisture
content while compacting.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 1 of 23
GENERAL
1.1 SCOPE
(a) This Specification describes the requirements for geotechnical
instrumentation and monitoring during excavation and construction of the
Works.
(b) The Contractor shall engage an Instrumentation Specialist Contractor
who shall supply, install, take control of preinstalled instrumentation,
commission the IDMS, host data, baseline, monitor, report monitoring
results, protect, maintain, and handover of geotechnical and structural
instrumentation to the Contract 2 Contractor, unless decommissioned
under this Contract. Following the baseline monitoring period, the
Contractor shall routinely monitor the instrumentation and disseminate
the monitoring data in accordance with the frequency of monitoring set
out in this Specification Section.
(b) Payment:
(i) Payment for Geotechnical Instrumentation installation and
monitoring shall be included under:
A. Item C.1.4– ‘Geotechnical Instrumentation - GIMP, Installation
& Monitoring’ (Pape Station SOE).
B. Item D.1.4– ‘Geotechnical Instrumentation - GIMP, Installation
& Monitoring’ Sammon SOE).
(ii) Each Item shall include, but not be limited to, the following:
A. The preparation and submission of submittal documentation
detailed in Clause 1.7 of this Section.
B. Instrumentation installation and monitoring within and outside
the Site.
C. Monitoring of instrumentation within Existing TTC
Infrastructure.
D. Monitoring of building monitoring points.
E. Integration of monitoring data into the IDMS.
F. Replacement of damaged instrumentation.
G. Handover of the Work in accordance with Schedule 8 –
Outline Commissioning program and Handover.
(iii) Each item excludes:
A. The installation and baseline monitoring for instrumentation
installed by others as detailed in Schedule 16 - Other
Contractors
B. The installation and monitoring of OSTs (wall targets). This
Work is considered incidental to other Works and costs shall
be included within the appropriate Agreement item to which
they pertain most closely.
(iv) Payment for each lump sum item shall be as follows:
A. 20% upon acceptance of the Contractor’s Instrumentation and
Monitoring Plan.
B. 30% upon the installation of all Geotechnical Instrumentation
and commissioning of the IDMS and including web based
access.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 3 of 23
PRODUCTS
2.1 MATERIALS
(a) Cement-bentonite grout backfill mix for all instrumentation installations:
as per recommended instrument manufacturers’ recommendation or
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 8 of 23
2.2 EQUIPMENT
(a) General:
(i) Provide all instruments and accompanying equipment and
accessories, as specified herein. Metrolinx will retain all products
obtained for this Project.
(ii) Where instrument model numbers are given in this Section,
interpret them to represent models selected on the basis of factory
specifications.
(iii) Only use signal cables for instruments provided by the
manufacturer of the associated instrument and suitable for the
expected environment.
(iv) Store all instrumentation and related materials in a secured area
on site, within temperature and humidity limits recommended by
manufacturers, and protected from damage, dirt, dust, or other
foreign materials.
(v) All instrumentation locations are indicated in the Drawings.
(b) Inclinometers (In-Place Inclinometer System and Manual Probe
Inclinometer System):
(i) In-Place Inclinometer System:
A. Slope Indicator Co. (Division of Durham Geo), Serial HD In-
Place Inclinometer bi-axial sensor system, model 57804722,
or approved equal. Sensor wheels to suit 70 mm outer
diameter casing, sensor wheel model 57805342.
B. Gauge length: 1,000 mm.
C. Range: ±10 degrees from vertical.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 9 of 23
EXECUTION
3.1 GENERAL
(a) Geotechnical conditions to be anticipated are presented in the
Agreement: Geotechnical Baseline Report (GBR) and the Geotechnical
Data Reports (GDRs).
(b) Engage an Instrumentation Engineer in accordance with Cl. 1.8 (a) of
this Specification Section.
(c) Characterize and dispose of all waste generated by the Work in
accordance with Specification Section 02 42 00 – Removal and Salvage
of Construction Materials, and Specification Section 31 20 01 – Muck
and Excavated Materials Disposal.
(d) Incorporate the Ontario Line Control network (OL2020) into the
Geotechnical and Instrumentation monitoring program.
(e) Incorporate the Deep Bench Marks that will be provided by Metrolinx into
the Geotechnical and Instrumentation monitoring program and other
applications where stable vertical benchmarks are required.
(f) Allow sufficient time for all instrumentation installation, baseline readings,
and associated work in the construction schedule.
(g) Inform Metrolinx Representative with a 36 hr minimum advanced notice
to allow the Metrolinx Representative to observe installation of any
instrumentation.
(h) Install all instrumentation complete and functional. Replace
instrumentation that does not meet specified requirements at own
expense.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 15 of 23
3.4 PROTECTION
(a) Execute the Work in such a manner that impacts to instrumentation are
avoided.
(b) Preventative – appropriate physical protections should:
(i) Be installed in a manner that does not hamper the function of the
instruments and allow for regular maintenance and communication
access.
(ii) Protect from typical construction activities and disturbances in the
area.
3.5 MAINTENANCE
(a) Maintain all instrumentation in accordance with the manufacturer’s
recommended procedures and schedules.
(b) Replace installations if they are damaged, malfunctioning or if they
become inaccessible based on direction from Metrolinx Representative.
(c) Replacements shall be done at a maximum of one (1) week after
notification. Critical Instruments as directed by the Metrolinx
Representative shall be replaced within 2 Business Days or as approved
by Metrolinx Representative.
(d) Report all damaged or non-functional instrumentation to the Metrolinx
Representative immediately upon discovery, prior to attempted recovery
or restoration.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 21 of 23
3.6 MONITORING
(a) General:
(i) Following the baseline period, the Contractor, under the guidance
of the Instrumentation Specialist and the Metrolinx Representative,
will monitor each instrument at the frequency specified herein.
During suspension of construction activities, frequencies may be
reduced as agreed upon with the Metrolinx Representative.
(ii) The Contractor or shall in no way impeded regular or emergency
access to all instrumentation, so as to not delay the monitoring
unnecessarily.
(iii) The Instrumentation Engineer shall provide instrumentation data to
the Metrolinx Representative within 24 hours of obtaining the data.
(iv) When instruments detect abrupt changes, as determined by the
Instrumentation Engineer, in measured values that exceed the
response criteria, or other notable conditions, the Contractor will
take additional readings as Directed by the Metrolinx
Representative.
(b) Response Levels:
(i) Response Criteria are listed on the Contract Drawings,
(ii) When instrumentation data exceed the Response Criteria,
implement the procedures specified herein.
(c) Exceeding Trigger Levels of Instrument:
(i) Upon Contractor notifying the Metrolinx Representative of an
exceedance the Metrolinx Representative will verify measurements
and notify the Contractor immediately of the verified results.
(ii) The Metrolinx Representative will inform the Contractor of any
increase in the frequency of future monitoring of that instrument
and adjacent instruments.
(iii) The Contractor shall undertake the increased monitoring until such
time as the Metrolinx Representative instructs otherwise.
(iv) Implement procedures as specified in the Corrective Action Plan to
limit further movements.
(v) Regular weekly meetings shall be coordinated by the Contractor
until regular unmodified monitoring resumes or otherwise
instructed by the Metrolinx Representative.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 22 of 23
3.9 DECOMMISSIONING
(a) Should it be requested by Metrolinx Representative decommission all
borehole instruments in accordance with provincial regulatory
requirements. Do not decommission instruments without written approval
from the Metrolinx Representative.
(b) The only anticipated instrumentation to be decommissioned is that which
is no longer serviceable due to damage or conflicted location.
(c) Restore the ground surface to match the surrounding ground surface.
(d) Handle and dispose of all waste, groundwater, and soil generated during
decommissioning in accordance with regulatory requirements, with the
Construction Agreement, Schedule 10 – Environmental Obligations,
Specification Section 02 42 00 – Removal and Salvage of Construction
Materials, and Specification Section 31 20 01 – Muck and Excavated
Materials Disposal.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 09 13
RFP-2022-CCPC-416 Geotechnical Instrumentation and Monitoring
June 2023 Page 23 of 23
END OF SECTION
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 11 00
RFP-2022-CCPC-416 Tree Clearing and Grubbing
June 2023 Page 1 of 9
Part 1 GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for clearing that consists of
clearing and grubbing trees, brush, bushes, and other vegetation.
(b) The Contractor’s Work includes:
(i) Tree clearing, tree pruning and tree protection in accordance with
the Arborist Report, Drawings Specifications and Agreement.
(ii) Chemical vegetation control measures.
(c) Work locations - Work shall be performed as identified in the Arborist
Report, Contract Drawings, Specifications and Agreement.
(i) Area A – Pape Station Area:
A. Area between properties at Gertrude Place, Eaton Ave and
Lipton Ave.
(i) Tree wound paint: once liter can with manufacturer’s label.
(ii) Herbicide: one litre can with manufacture’s label.
Part 2 PRODUCTS
2.1 MATERIALS
(a) Tree wound paint: bituminous based paint of standard manufacture
specially formulated for tree wounds.
(b) Herbicide: Conteva Garlon XRT by Corteva or approved equal.
(c) Silt Sock: 300mm SiltSoxx by Filtrexx or approved equal.
Part 3 CONSTRUCTION
(i) The Contractor shall comply with The Noise Bylaw (Chapter 591,
City of Toronto Municipal Code) that permits operation of
construction equipment ONLY during Monday to Friday 7:00 a.m.
to 7:00 p.m., Saturdays 9:00 a.m. to 7:00 p.m., and no construction
noise on Sundays and statutory holidays (amending bylaw 505-
2006).
(ii) The Contractor is responsible to keep site clean, tidy, and clear of
all debris to the satisfaction of the Metrolinx Representative.
(iii) The Contractor to advise when works have been completed so that
locations can be inspected.
(iv) Construction and other operations at the site must be properly
fenced off at all times and signed to prevent entry of or injury to,
the public. Legislated safety equipment must be worn at all times
by the workers on site.
(v) Copies of any Ministry of Labour Inspection reports or orders and
Joint Health and Safety Committee minutes must be available on
site.
(vi) Construction and other materials must only be stored in areas
approved by the Metrolinx Representative. No materials are to be
stored on City right of way, laneways, walkways, planted areas or
within the drip line circumference of a tree. When storing materials
in the vicinity of trees, the requirements of Toronto Specifications
of Construction near Trees must be adhered to.
(vii) All trees located on or close to a construction site or within any
Tree-Protection Zones must be protected from damage in
accordance with Toronto Specifications for Construction Near
Trees and any other tree protection measure as deemed
appropriate by the Parks, Forestry and Recreation (PFR) Division.
(viii) Roads and walkways must be kept clear of debris, excavation and
construction materials. The Contractor must clean roads and
walkways as often as necessary to ensure they are clear.
3.2 PROTECTION
(a) The Contractor shall prevent damage to trees, landscaping, benchmarks,
existing buildings, existing pavement, utility lines and site appurtenances
which are to remain as detailed in the Agreement.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 11 00
RFP-2022-CCPC-416 Tree Clearing and Grubbing
June 2023 Page 7 of 9
(b) The Contractor must protect trees and plants on Site and adjacent
properties, where indicated, adhering to local by-laws, and as shown in
the Arborist Report.
(c) The Contractor shall install tree protection fencing prior performing the
Work.
(d) The Contractor shall ensure that all tree clearing and pruning is
completed under the direct supervision of the Contractor’s Certified
Arborist.
(e) Contractor shall notify the contract permitting authorities if any trees not
designated for removal are damaged as a result of Contractor’s or
Subcontractor’s activities. Contractor shall comply with the permitting
authorities’ requirements for tree repair and shall retain the services of a
Certified Arborist to repair trees identified to be retained that are
damaged as a result of Contractor’s or Subcontractors’ activities at no
additional cost to the Owner.
(f) If damaged tree is irreparable, Contractor shall be responsible for
removal and replacement of the tree and/or payment of compensation
and fees as required by the permitting agencies at no additional cost to
the Owner.
(g) Remove all protective fencing upon completion of Work.
(h) The Contractor shall be responsible for providing the appropriate utility
crossing protection measures as per utility companies' crossing
requirements and in accordance with the terms and conditions outlined in
the crossing agreement/permit.
(i) The Contractor shall repair any damaged items to the approval of the
Metrolinx Representative.
3.3 PREPARATION
(a) The Contractor shall notify Metrolinx eight weeks in advance to
coordinate and schedule the Work.
(b) The Contractor shall inspect the Site and verify items designated to
remain or be protected.
(c) The Contractor shall locate and protect utility lines. The Contractor shall
preserve in operating condition active Utilities traversing the Site.
(d) The Contractor shall notify Utility authorities before starting the work.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 11 00
RFP-2022-CCPC-416 Tree Clearing and Grubbing
June 2023 Page 8 of 9
3.5 ACCESS
(a) Tree clearing crews shall be required to access the Places of the Work
via existing public access points. Contractor shall be responsible for
Street Occupancy Permit if any lane closure and temporary laydown
areas are required from public right-of-way.
3.10 RESTORATION
(a) Any fence removed or damaged during the work shall be restored with
the same type of fence that existed prior to construction.
(b) Any areas of tree removal voids shall be backfilled with granular A or
similar approved material as approved by the Metrolinx Representative.
3.11 CLEANING
(a) Perform cleaning in accordance with the Agreement.
(b) Maintain Work in tidy condition, free from accumulation of waste
products and debris.
(c) Do not clean equipment where the wash-water can enter the stormwater
sewers.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 14 13
RFP-2022-CCPC-416 Soil Stripping and Stockpiling
June 2023 Page 1 of 4
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for stripping and stockpiling
topsoil.
PRODUCTS
EXECUTION
(d) The area to be stripped does not include areas within the Overall Site
Boundary as shown in the Agreement that will be temporarily occupied
by the Contractor for jet grouting works.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 20 01
RFP-2022-CCPC-416 Muck and Excavated Materials Disposal
June 2023 Page 1 of 5
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for handling, transporting,
and disposal of all muck and excavated materials from the bulk
excavation of the Pape Station Main Box and Sammon Crossover
headhouse, the tieback drilling, any material during demolitions and
utility relocations, and any material from the slurry wall construction
carried out within or for the support of excavation systems for Pape
Station Main Box and Sammon Crossover headhouse.
(iii) Environmental Protection Act, R.S.O. 1990, c.E.19 & R.R.O. 1990,
Regulation 347: General - Waste Management.
(c) OSOR Section 1370 – Environmental Control.
(d) Canadian and Provincial Statutes:
(i) Environmental Protection Act, R.S.O. 1990, c.E.19 & R.R.O. 1990,
Regulation 347: General - Waste Management.
PRODUCTS
2.1 EQUIPMENT
(a) Vehicles used for hauling and disposing of excavated material and muck
shall be properly muffled to minimize noise. Vehicles shall not impose
loads that will damage existing utilities and structures. Vehicles shall
include covers and liners to prevent infiltration, spills, leaks or release of
liquids.
(b) If a conveyor system is to be used, it shall be designed to operate safely
and quietly while withstanding all operating and wind loads. The systems
shall be designed to minimize spillage and control dust and noise. The
Contractor shall guard all idlers, pulleys, and drives that are accessible
unless specific safety procedures are established for work around
unguarded components.
(c) Street sweeping and dust control equipment will be required. The
Contractor shall be responsible to maintain the cleanliness of
surrounding roadways to the satisfaction of the City.
EXECUTION
3.1 GENERAL
(a) Conduct all operations to minimize the impact of noise in accordance
with the Agreement. Equipment shall be equipped with noise
suppressors such as silencers or mufflers.
(b) The temporary stockpile shall be of a manageable size; configured with
stable slopes and shall be designed to protect excavated materials from
precipitation, runoff, and erosion.
(c) Stockpiles shall not impede or interfere with natural site drainage.
(d) Temporary stockpile area shall be designed to prevent materials from
entering drains, utilities and manholes.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 20 01
RFP-2022-CCPC-416 Muck and Excavated Materials Disposal
June 2023 Page 5 of 5
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 22 13
RFP-2022-CCPC-416 Grading
June 2023 Page 1 of 7
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for grading, including earth
excavation and the management of excavated materials.
PRODUCTS
2.1 EQUIPMENT
(a) The type of earth moving equipment used shall be suited to the material
to be excavated, moved, placed and compacted, the degree of
compaction required, and space available.
(b) Street sweeping and dust control equipment will be required. The
Contractor shall be responsible to maintain the cleanliness of
surrounding roadways to the satisfaction of the city.
EXECUTION
3.1 GENERAL
(a) Removal of Ice, Snow, and Frozen Ground:
(i) The Contractor shall remove and dispose of all ice, snow, and
frozen material from all surfaces prior to placing fill and from all
materials being used for backfill or any other construction
purposes.
(b) Removal of Disturbed Material:
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 22 13
RFP-2022-CCPC-416 Grading
June 2023 Page 5 of 7
(i) The Contractor shall remove and dispose of all disturbed material
from all surfaces prior to placing fill in accordance with
Specification Section 02 42 00 – Removal and Salvage of
Construction Materials, Specification Section 02 41 13 – Site
Demolition, Specification Section 02 42 16 – Structure Demolition,
and Specification Section 31 20 01 – Muck and Excavated
Materials Disposal.
(c) Compaction:
(i) Subsequent to completion of stripping and any required
excavation, any exposed soils which contain excessive organics
and other compressible, weak, and deleterious materials should be
excavated, removed, and replaced with engineered fill approved by
the Metrolinx Representative compatible with subgrade conditions.
(ii) Earth and granular materials shall be compacted according to
OPSS.MUNI 501 if the thickness of fill placed is greater than 0.6 m
over an area of 100 m2.
(iii) For compaction purposes, reclaimed asphalt pavement (RAP) or
reclaimed concrete material (RCM) or both shall be treated as
earth or rock when such material is respectively included in the fill.
(iv) Compaction load above TTC station shall not exceed the 9.6
kN/m2.
(d) Tolerances:
(i) Vertical tolerances for the elevation of the site as specified on the
Drawings after any required excavation or backfill:
A. + 50 mm.
B. - 50 mm.
3.2 DRAINAGE
(a) Provide effective drainage during all stages of the work.
(b) In stripping operations where there is excavation below subgrade and
when provision for surface drainage is impractical, backfill materials shall
be placed as soon as possible following excavation.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 00
RFP-2022-CCPC-416 Excavation and Fill
June 2023 Page 1 of 11
GENERAL
1.1 SCOPE
(a) This Specification covers requirements for excavation, backfill and
compaction for site formation, structures, trenches, drainage, lean
concrete backfill, and the footprint of demolished structures / properties.
(iv) Engineered Fill: Fill that is sourced, sorted and placed according to
a specification.
(v) Excess Material: Excess soil materials resulting from construction
related activities on site, may include impacted soils defined as
Waste, or Reusable Fill that can be used on site.
(vi) Granular Fill: Granular material that consists of a reasonably clean
sand or gravel (as per OPSS.PROV 1010), free from excessive silt,
clay, or clay balls.
(vii) Imported Fill: Fill imported to be used on site which meets the
standards for designated land use type, as specified in Table 1 for
contaminants contained within the soil, groundwater and sediment,
intended for use under Part XV.1 of the Environmental Protection
Act, published by the Ministry of the Environment, Conservation
and Parks (MECP). It is to be free of organics, topsoil, and
deleterious material such as Construction Rubble.
(viii) Lean Concrete Backfill: Mix of aggregate, cementing material and
water, with or without chemical admixtures, that reaches 8.0 MPa
minimum compressive strength at 28 days.
(ix) Native or Reusable Fill: In accordance with Ontario Regulation
153, soil excavated from the site which meets standards for
designated land use type, as specified in Tables 2 and 3 for
contaminants contained within the soil and groundwater, intended
for use under Part XV.1 of the Environmental Protection Act,
published by the MECP, and other environmental regulations.
(x) No-fines Concrete or Pervious Concrete: A concrete that is
designed with high porosity and allows water to pass though. No-
fines concrete typically consists of cement, fly ash, water and
coarse aggregate. It is commonly used in concrete pavement to
reduce surface runoff and allow the recharging of ground water.
The high porosity is achieved by a network of interconnected voids
since it has little or no fines and contains just enough cement paste
to cover the surface of coarse aggregates while maintaining the
interconnectivity of voids.
(xi) Rock: Natural beds or massive fragments, of the hard, stable,
cemented part of the earth’s crust, igneous, metamorphic, or
sedimentary in origin, and includes large boulders having a volume
of 1 cubic meter or greater.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 00
RFP-2022-CCPC-416 Excavation and Fill
June 2023 Page 4 of 11
(iii) Area of which the fill will be placed, in square meters, and volume
of material to be placed, in cubic meters (per area, if areas are
separated).
(iv) If required, confirmation by calculation that placed fill material does
not adversely affect existing structures or facilities due to the
additional loading.
(v) Type of engineered fill material to be placed with details of
geotechnical and, if required, chemical properties in accordance
with this Specification Section.
(vi) Details of proposed field compaction and testing requirements, in
accordance with this Specification Section.
(vii) Details of the source of the material proposed to be used.
(viii) Details of staging, handling and protection of the stockpiled
material on site.
(ix) Details of protection of the placed material on site.
(x) Details of dust and noise mitigation measures to be used.
(b) If lean concrete backfill is to be used on site, , submit details of the mix
design. Design requirements are given in TS 1350 Amendment to
OPSS.MUNI 1350 – Material Specifications for Concrete – Materials and
Production.
(c) Provide Metrolinx Representative certification that materials in lean
concrete backfill do not include contaminants to groundwater quality.
(d) For any material used as engineered fill, whether material is Reusable
Fill or Imported Fill, submit geotechnical laboratory test results with
grading curves and physical testing results.
(e) For Imported Fill, submit analytical chemical analysis of representative fill
samples.
(f) Prior to commencing the Work, submit an Existing Conditions
Assessment report in accordance with Specification Section 02 22 00 –
Existing Conditions Assessment, for property and structures that may be
affected by the Work. The assessment shall include adjacent properties,
buildings, structures and utilities where applicable.
(b) Native / reusable fill and imported fill materials shall be reviewed and
accepted by the Metrolinx Representative.
(c) All excavation works may be inspected by the Metrolinx Representative.
PRODUCTS
2.1 MATERIALS
(a) Granular Fill:
(i) Granular material shall conform to OPSS.PROV 1010 and as
specified on the Drawings. Granular material shall be not lumpy or
frozen, and shall be free from slag, cinders, ashes, rubbish, or
other material that is objectionable or deleterious. Granular
material shall be free of boulders or flat rocks larger than 100 mm
in diameter and shall be sufficiently free of silt or clay that it cannot
be compacted into a ball by hand.
(b) Native / Reusable Fill:
(i) Material shall be free from frozen lumps, cinders, ashes, refuse,
organic matter, boulders encountered with size as defined in the
Geotechnical Baseline Report (GBR), and other deleterious
material.
(c) Lean Concrete Backfill:
(i) Cement Type: Normal Portland GU, Portland Limestone GUL.
(ii) Minimum 28-day cylinder compressive strength: 8.0 MPa.
(iii) Maximum nominal size of coarse aggregate: 25 mm.
(iv) Minimum slump at point of discharge: 150 mm.
(v) Minimum density: 1900 kg/m3.
(vi) Maximum cement content: 90 kg/m3.
(vii) Class of exposure: N/A.
(viii) Chemical admixtures: as needed to modify performance properties
of strength, flow, set and permeability.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 00
RFP-2022-CCPC-416 Excavation and Fill
June 2023 Page 7 of 11
(ix) Water: fresh, clean, potable and free from oils, salts and impurities.
Water content shall facilitate a fluid workable mix without segregation.
(x) Sustainable Concrete with at least 20% by mass of Portland cement
substituted with Supplementary Cementitious Materials (SCM) such as
ground granulated blast furnace slag, fly ash and/or silica fume.
(xi) Flowable mix which does not need mobile equipment for placement.
(xii) Lean concrete backfill shall be unshrinkable with no subsidence.
(xiii) Lean concrete backfill shall conform to TS 13.10 “Construction
Specification for Unshrinkable Fill” except as defined herein.
(d) No-fines Concrete or Pervious Concrete:
(i) Aggregate Size Range: 10 mm to 20 mm.
(ii) Aggregate / cement ratio: 6:1.
(iii) Water / cement ratio: 0.30 to 0.40.
(iv) Density range: Between and 1600 kg/m3 2200 kg/m3.
(v) Target Strength Range: 1.5 MPa to 5 MPa.
2.2 EQUIPMENT
(a) Compaction equipment shall be according to OPSS.PROV 501.
(b) Lean concrete mixing equipment capable of proportioning aggregate,
cement and water shall conform with City of Toronto TS 1350. Lean
concrete backfill shall be transported to site by ready-mix trucks. Lean
concrete backfill shall be placed into the excavation using ready-mix
truck chutes or by pumping.
(c) Provide equipment conforming to manufacturer’s recommendations for
the lean concrete mix including additives and cementing materials.
(d) Street sweeping and dust control equipment will be required. The
Contractor shall be responsible to maintain the cleanliness of
surrounding roadways to the satisfaction of the City.
EXECUTION
3.1 REMOVALS
(a) Removals shall be according to Section 02 42 00 – Removal and
Salvage of Construction Materials.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 00
RFP-2022-CCPC-416 Excavation and Fill
June 2023 Page 8 of 11
3.4 EXCAVATION
(a) For excavation within the support of excavation for the shafts at Pape
Station and Sammon Crossover Headhouse, refer to Specification
Section 31 23 16 – Shaft Excavation.
(b) Any other excavation work that may be required under this Contract is
expected to be limited to the following:
(i) Any required utility work or utility diversion work.
(ii) Removal of any unsuitable material in the subgrade and
replacement with a suitable engineered fill prior to placing a
concrete structure.
(c) Remove organics and compressible, weak and deleterious materials to
expose competent stable dry subgrade for structure foundations. The
sub-excavated material must be replaced by approved engineered fill.
(j) Lean concrete backfill below 2.0 MPa compressive strength shall be
removed and replaced at no extra cost to Metrolinx.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 1 of 13
GENERAL
1.1 SCOPE
(a) This Specification covers:
(i) The requirements for bulk excavation within the support of
excavation system.
(ii) The requirements to ensure that the excavation is carried out
evenly, such that the existing TTC structure is not subjected to
adverse loading caused by an unbalanced excavation.
(iii) The requirements for ensuring excavation does not advance
further than the elevation that other SOE support elements are
required to be installed, including strutting and tiebacks.
(iv) Requirements for excavating at the bottom of the excavation and
preparing the subgrade for the SOE base slab construction.
(v) Requirements for scaling adhered soil materials from the surface of
the slurry wall panels during bulk excavation.
(b) Payment:
(i) Payment will be made for the following items according to
measurement of the completed work:
A. Item C.2.10 – ‘Mass Excavation – Soil’ (Pape Station North
SOE).
B. Item C.3.10 – ‘Mass Excavation – Soil’ (Pape Station South
SOE).
C. Item D.2.7 – ‘Mass Excavation – Soil’ (Sammon Ave SOE).
(ii) Each Item shall include the excavation, handling, transport and
disposal of excavated materials.
(d) Muck and Excavated Materials: All materials and spoils generated during
bulk excavation from within the support of excavation system.
(e) Narrow Section: The section of shaft closest to the End Wall that is used
to receive or launch the TBM.
(f) Slurry Wall: Reinforced concrete slurry wall panel constructed below
ground using the slurry method of trench stabilization. Slurry walls are
structural walls.
(g) Support of Excavation (SOE): A temporary earth retaining system
intended to control the ground to facilitate a safe and efficient space for
construction.
(h) Strut: A brace or supporting member which resists thrusts in the direction
of its own length. May be diagonal or horizontal.
(i) Steel strand: A bundle of wires making a strand that forms one of several
strands that, in turn, makes up a tieback (or strand anchor).
(j) Tieback (also Strand Anchor and Tendon): An anchor consisting of
bundles of steel wire strands that are prestressed to support, and limit
the lateral movements, of an earth retaining structure. Tiebacks may be
anchored into rock, or into a suitable soil unit, at one end and anchored
to the earth retaining structure at the other. Tiebacks are typically
installed at a medium angle of inclination.
(k) Tie Anchor: Similar to a tieback but installed horizontally between two
earth retaining headwalls. Tie anchors are prestressed to limit movement
and deflection of the two walls they tie together.
(l) Unbalanced Excavation: An uneven load created when excavation takes
place on one side of a structure.
(m) USCS: Unified Soil Classification System. The Unified Soil Classification
System is a method to characterize and classify soils. The USCS system
was introduced by Casagrande and was adopted by the Corps of
Engineers. The USCS system is a globally recognized system to
characterize fine grained to coarse grained soils and organic materials.
(n) Waler: A horizontal beam used to brace or support vertical secant piles.
(o) Wide Section: The section of shaft closest to the Head Wall that is used
to perform and accommodate the underpinning works for tunnelling
beneath the existing TTC structure.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 4 of 13
(xii) Procedure for support in place utilities in the footprint of the support
of excavation.
(xiii) Plan for site illumination.
(e) Prior to any bulk excavation, submit for review by the Metrolinx
Representative an Excavation Contingency Plan for Compromised Slurry
Wall Integrity. The plan should include the following:
(i) Measures to determine and mitigate defective slurry wall panels
including zones where there is an open connection to the retained
soil behind the slurry wall, zones of defective concrete, and zones
of soil and / or water inundation.
(f) Prior to any bulk excavation, submit for review by the Metrolinx
Representative a Contingency Plan for Compromised Strut and Waler
Integrity. The plan shall include the following:
(i) Procedure for protecting struts and walers from damage due to
excavation and lifting activities, and remedial work plan in case of
damage to struts or walers including method of removing the
damaged element, installing a new element, monitoring localized
deformations, and providing measures to locally restrain the slurry
wall.
(g) Prior to any bulk excavation, submit for review by the Metrolinx
Representative a Crane and Lifting Equipment Package. This shall
include:
(i) Details of crane(s) to be used including clamshell buckets, muck
boxes and all other attachments. Specification data sheets shall be
provided for all crane equipment.
(ii) Copy of crane permit.
(iii) Design of crane pad, signed-and-sealed by a Professional
Engineer licensed in the province of Ontario.
(iv) Impact Assessment Report to show that the crane load has no
adverse impact on adjacent structures including the existing TTC
structures and the support of excavation.
(v) Crane procedures for mucking including safety procedures for
working around a crane, and support personnel for crane
operations including Rigger-in-Charge, Rigger and Walker, and
other personnel involves in the safe operation of cranes.
(vi) Details for offload, erection and inspection procedures of the crane.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 8 of 13
(vii) Procedures for powering down and lowering the boom ahead of
inclement weather or lightning storms, and for inspection and start-
up procedures upon resuming work.
(viii) Procedures for lowering heavy equipment safely and without
physical contact with installed bracing.
(ix) Critical lift procedures.
(h) Submit weekly Bulk Excavation Progress Reports that include:
(i) Excavation status for the North Shaft and South Shaft and the
Wide Section and Narrow Section within each shaft.
(ii) Status of bulk excavation complete and work remaining, with
weekly updated schedule information for the bulk excavation
estimate to complete.
(iii) Status of the entrapped groundwater drawdown status with respect
to the lowest excavation level.
(iv) Details of any contaminated or hazardous ground encountered.
(v) Details of boulders encountered with size as defined in the
Geotechnical Baseline Report (GBR).
(vi) Any other unexpected conditions.
(vii) Equipment utilization and equipment downtime summary.
(ii) Crane Rigger-in-Charge shall have not less than five (5) years of
recent experience working on projects of similar type, size, and
complexity.
(iii) Crane Rigger shall have not less than three (3) years of recent
experience working on projects of similar type, size, and
complexity.
(iv) Crane Walker shall have not less than three (3) years of recent
experience working on projects of similar type, size, and
complexity.
PRODUCTS
2.1 EQUIPMENT
(a) Equipment and vehicles used for excavation, hauling and disposing of
excavated material and muck shall be properly muffled to minimize
noise. Vehicles shall not impose loads that will damage existing utilities
and structures. Vehicles shall include covers to prevent infiltration, spills,
leaks or release of liquids.
(b) Crane equipment, and boom and jib configurations, shall be included in
the Crane and Lifting Equipment Package, with specification data sheets
provided for all equipment. Cranes to be used on site shall suit the size
of site, depth of excavation, expected working ranges and required loads
of equipment and materials. Crane shall be equipped with camera/s on
the boom, providing clear view for the crane operator.
(c) If a conveyor system is to be used, it shall be designed to operate safely
and quietly while withstanding all operating and wind loads. The systems
shall be designed to minimize spillage and control dust and noise. The
Contractor shall guard all idlers, pulleys, and drives that are accessible
unless specific safety procedures are established for work around
unguarded components.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 10 of 13
(d) Street sweeping and dust control equipment will be required. The
Contractor shall be responsible to maintain the cleanliness of
surrounding roadways to the satisfaction of the City.
EXECUTION
3.1 GENERAL
(a) Cap Beam construction and the installation of a safety guardrail shall be
completed prior to bulk excavation.
(b) Tag-in / Tag-out board shall be established prior to bulk excavation
commencing so that the Contractor can ensure that above-ground
personnel can determine an accurate count of the number of persons
underground in the event of an emergency.
(c) Conduct all operations to minimize the impact of noise in accordance
with the Agreement. Equipment shall be equipped with noise
suppressors such as silencers or mufflers.
(d) The method of excavating within the support of excavation is at the
option of the Contractor.
(e) Ensure personnel within the support of excavation stay a minimum of
2 m away from the face of the slurry wall.
(f) Coordinate all bulk excavation activities with the installation works for the
walers and struts, installation of tiebacks, and installation of tie anchors.
(g) Excavate to the lines, grade, and dimensions shown on the Drawings.
Remove excavated materials in accordance with the requirements of this
Specification Section and Specification Section 31 20 01 – Muck and
Excavated Materials Disposal.
(h) Temporary stockpiles, whether on surface or within the support of
excavation, shall be of a manageable size; configured with stable slopes
and shall be designed to protect excavated materials from precipitation,
runoff, and erosion.
(i) Bulk excavation works within the support of excavation shall not cause
damage to dewatering wells for entrapped groundwater, observation
wells or any other geotechnical instruments including instruments
installed in the slurry wall or around the perimeter of the support of
excavation.
(j) Protect instruments from being inundated with spoils during bulk material
handling.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 11 of 13
(c) The maximum elevation difference of the excavation between the North
Shaft and the South Shaft shall not exceed 2 m and / or one row of
installed tiebacks or one row of installed tie anchors.
(d) The maximum elevation difference of the excavation contained within an
entire Wide Section shall not exceed 2 m and / or one row of installed
tiebacks.
(e) The installation of a level of struts, a row of tiebacks and a row of tie
anchors shall be fully completed and tested, if required, before
proceeding with the next lift of the excavation. This requirement applies
in both the horizontal and vertical directions.
(f) The maximum temporary slope angle within the excavation shall not
exceed 1V:1H. The Contractor is responsible for maintaining the safety
and stability of excavated soil within the support of excavation.
(g) The Contractor shall ensure adequate dewatering of the entrapped
groundwater and surface run-off from precipitation within the support of
excavation is provided in accordance with Specification Section 31 23 19
– Shaft Dewatering and Groundwater Disposal.
(h) Protection around dewatering wells, associated pipework and
observation wells shall be provided.
(i) Protection around temporary sumps within the excavation shall be
provided.
3.5 OBJECTS CAST INTO AND PROTRUDING FROM THE SLURRY WALL
(a) Objects Protruding from the Slurry Wall:
(i) When objects such as boulders are encountered that have been
cast into the wall and protrude past the surface of the wall,
document the location, nature and size of the protrusion and notify
the Metrolinx Representative.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 16
RFP-2022-CCPC-416 Shaft Excavation
June 2023 Page 13 of 13
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 19
RFP-2022-CCPC-416 Shaft Dewatering and Groundwater Disposal
June 2023 Page 1 of 12
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for the removal of entrapped
groundwater during the bulk excavation within the support of excavation,
maintaining the groundwater level below the base of excavation until
handing over the dewatering system to Metrolinx, and the discharge of
groundwater to the City of Toronto drainage system.
(b) To remove entrapped groundwater within the support of excavation, a
dewatering system may be required. Any such system, if required, shall
be designed, installed and operated by experienced professionals with
expertise in dewatering systems.
(c) This scope also covers the requirement for transitioning to managing
nuisance water upon completion of the bulk excavation within the
support of excavation and the discharge of water to the City of Toronto
drainage system.
(iii) Design and Shop Drawings, including plans, sections and details,
installation details, and any other required details of the proposed
type of dewatering system, showing the arrangement, locations
and depths of components of the system including but not limited
to dewatering wells and pumps, observation wells, piping locations,
collection tank and treatment plant locations, and insulation and
heat trace requirements.
(iv) The system shall be designed to prevent ground loss or erosion
where water is removed, pumped, or discharged.
(v) Proposed pump specifications.
(vi) Proposed location(s) of points of discharge of water to the City
system.
(vii) Schedule for installation including well development, testing and
implementation of the dewatering system.
(viii) Testing and acceptance requirements.
(ix) Details of the operation of the system including sampling and
measuring requirements, and for monitoring water levels in the
observation wells.
(x) Chemical storage provisions with details on how safety and
security will be maintained.
(xi) Contingency plans to address potential emergencies such as
power failure, overflow and parameters exceeding OWRA
discharge limits for volumes or sampled chemicals or parameters.
(b) Prior to completion of the bulk excavation, submit a Dewatering
Transition Plan, which details how the system will be transitioned to
managing nuisance water once the bulk excavation has been completed.
Details shall also include the temporary period during which the SOE
base slab is being constructed and until the system is handed over to
Metrolinx in operational condition. Plan shall include:
(i) Equipment used to pump, treat and discharge the site or nuisance
water.
(ii) Proposed City discharge location.
(iii) Details of what portions of the dewatering system will be
decommissioned and removed and what will remain and be
repurposed.
(iv) Details of the operation of the system including sampling and
measuring requirements.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 19
RFP-2022-CCPC-416 Shaft Dewatering and Groundwater Disposal
June 2023 Page 7 of 12
PRODUCTS
2.1 GENERAL
(a) Provide materials that are new or in serviceable condition, free of defects
that could impair their performance.
(b) Materials and products shall comply with the design provided by the
Contractor’s Engineer for removal of entrapped groundwater and
managing disposal of on-site non-potable water.
2.2 MATERIALS
(a) All documentations for the materials required for the systems provided
for the removal of entrapped groundwater and managing disposal of on-
site non-potable water shall be submitted to the Metrolinx
Representative.
(b) Geotechnical and Water Level Monitoring equipment shall comply with
the Specification Section 31 09 13 – Geotechnical Instrumentation and
Monitoring.
2.3 EQUIPMENT
(a) All documentations for the systems provided for the removal of
entrapped groundwater and managing disposal of on-site non-potable
water shall be submitted to the Metrolinx Representative. Any equipment
required shall be determined by the Contractor’s Engineer.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 19
RFP-2022-CCPC-416 Shaft Dewatering and Groundwater Disposal
June 2023 Page 9 of 12
EXECUTION
3.1 GENERAL
(a) All work to be conducted in accordance with all permits and approvals,
including Permit To Take Water or EASR registration, and Sewer
Discharge Agreement.
(b) Obtain approvals from the City for the permit to discharge into the City
system in accordance with the Construction Agreement, Schedule 10 –
Environmental Obligations.
3.2 PREPARATION
(a) Stormwater runoff and surface runoff shall be prohibited from entering
excavations.
3.3 INSTALLATION
(a) The water treatment system and / or collection tank, all associated
piping, controls, electricals works and back-up power provisions shall be
carried out by the Contractor’s Dewatering Installer / Operator for the
dewatering system.
(b) The designer is required to inspect the installation of the dewatering
system and certify that installation and operation is in accordance with
design during the testing and acceptance phase.
(c) Installation of all dewatering wells and observation wells to be carried out
in accordance with the drilling procedure for wells, the well installation
procedure and well development procedures submitted by the
Contractor’s Dewatering Installer/Operator for the dewatering system.
(d) During duration of operation, maintain dewatering systems safely to
prevent hazard to public and in accordance with regulations and
requirements of City authorities.
(e) Minimize obstruction to pedestrian and vehicular traffic during installation
of dewatering system, and during subsequent operation of system.
(f) For any installation provisions outside of the excavation, and in public
areas, install components such as pipes, headers and other dewatering
equipment in covered trenches, or protect by acceptable means, to keep
streets, sidewalks, walkways, driveways, fences and existing facilities
unobstructed for their intended use.
(g) Clearly identify locations of dewatering system installations and install
barricades and signs necessary to ensure safety to public, construction
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 19
RFP-2022-CCPC-416 Shaft Dewatering and Groundwater Disposal
June 2023 Page 10 of 12
3.4 DEWATERING
(a) Operate dewatering system in accordance with the operation procedures
and any other requirements listed in the Shop Drawings.
(b) Supply, install and operate additional dewatering measures or measures
to control nuisance water necessary to carry out Work.
(c) Store and / or treat water to allow sedimentation prior to discharge into
appropriate City system.
(d) The dewatering system shall:
(i) Maintain entrapped groundwater a minimum of 1 m below the
lowest excavation line at any time during the bulk excavation.
(ii) Maintain the groundwater level below the completed shaft
excavation a minimum of 1 m below the bottom of the SOE base
slab at all times until handing over the dewatering system to
Metrolinx.
(iii) Be kept in operational condition at all times to maintain a dry,
stable working condition and to prevent uplift pressure on the
completed base slab. Metrolinx will coordinate ongoing
management, operation and maintenance of the dewatering
system upon Final Completion. Contractor shall provide Metrolinx
will all manuals, certificates, procedures and records at Handover.
(e) The requirements of Clause 3.4(d)(i), (ii) and (iii) apply to both the Pape
Station shafts and the Sammon Avenue Headhouse shaft.
(f) Monitor intake water regularly for signs of high sediment and adjust
dewatering system as needed to prevent ground loss.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 23 19
RFP-2022-CCPC-416 Shaft Dewatering and Groundwater Disposal
June 2023 Page 11 of 12
(g) Water taking rate shall not exceed the maximum rate indicated on any
applicable PTTW or EASR registration.
the excavation such as any wells that extend beyond the elevation of the
SOE Base Slab.
(i) Decommission in accordance with Ontario Regulation 903 and
MOE's recommended method for plugging wells and to the
acceptance of the Metrolinx representative.
(ii) Prepare records for decommissioning of monitoring wells and
submit to Metrolinx.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 25 00
RFP-2022-CCPC-416 Erosion and Sedimentation Controls
June 2023 Page 1 of 13
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for the installation,
maintenance, monitoring and removal of temporary erosion and sediment
control (ESC) measures.
PRODUCTS
2.1 MATERIALS
(a) Straw and Straw Bales:
(i) Straw shall be either wheat or oat straw.
(ii) Straw bales shall be dry and firm, be tied tightly in at least two (2)
places, show no evidence of straw or tie decay, and be free of
sediment.
(iii) They shall be of agricultural, rectangular formation and dimensions,
as specified in the Specifications and Drawings.
(b) Geosynthetics:
(i) Geotextile:
A. Geotextile shall be free of holes, tears, and punctures.
(ii) Silt Fence Geotextile:
A. Geotextile for silt fence shall be according to OPSS 1860,
Table 3.
B. Geotextile for silt fence may be separate from the stakes used
to install it as a sediment barrier.
(iii) Berm Barrier and Rock Flow Check Dam Geotextile:
A. Geotextile for berm barriers and rock flow check dams shall be
woven, Class II geotextile according to OPSS 1860.
B. The filtration opening size (FOS) shall be no greater than
300 µm.
(iv) Filter Bags:
A. Geotextile for filter bags shall be non-woven, polypropylene,
Class I in accordance with Table 1 of OPSS 1860.
(v) Catch basin sediment traps:
A. Filter fabric for silt control shall be Terra Fix 270R or approved
equal.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 25 00
RFP-2022-CCPC-416 Erosion and Sedimentation Controls
June 2023 Page 6 of 13
EXECUTION
3.1 GENERAL
(a) Erosion and sediment control measures shall be implemented prior to,
and maintained during all construction phases to prevent entry of
sediment into the existing sewer systems. All damaged erosion and
sediment control measures shall be repaired or replaced within 24 hours
of inspection.
(b) Filter fabric shall be placed under grates on all catch basins to trap
sediment. Silt traps shall be cleaned regularly and shall not be removed
until such time as the curbs are constructed and the boulevards are
sodded or landscape areas graded and sodded.
(c) All activities, including maintenance procedures, shall be controlled to
prevent the entry of petroleum products, debris, rubble, concrete, or other
deleterious substances into the water. Vehicular refueling and
maintenance shall be conducted a minimum of 30m from water coarses
or drainage swales.
(d) Street sweeping, catch basin cleaning, and dust control are the
responsibility of the Contractor and shall be maintained on all roadways
to the satisfaction of the City.
(e) Erosion and Sediment Control (ESC) Plan is to be implemented to
minimize erosion and prevent off-site sediment transport.
(f) Construction activities shall be limited to the work area, and, as
necessary, sensitive features shall be demarcated if they are located
immediately adjacent to the work zone.
(g) The contractor shall implement a Spill Prevention and Response Plan in
accordance with Schedule 10 – Environmental Obligations.
(h) Spill response kits shall be kept safe and accessible on site.
(i) All sediment and erosion control measures shall be in proper working
order prior to the removal of any topsoil.
(j) All construction shall be per OPSS 182 and OPSS 805. Where there is a
conflict between the OPSS and the Drawings and Specifications, the
Drawings and Specifications shall take precedence.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 25 00
RFP-2022-CCPC-416 Erosion and Sedimentation Controls
June 2023 Page 8 of 13
3.3 DEWATERING
(a) General:
(i) Dewatering effluent shall be controlled to prevent passage of
sediment into environmental features or onto adjacent properties.
Discharge of dewatering effluent to sediment traps for dewatering
shall be controlled to avoid exceeding trap capacity and to prevent
scour and washout.
(b) Sediment Traps:
(i) Sediment traps shall be constructed to prevent sediment passage
from the upstream to the downstream side of the trap and so that
the majority of the sediment is collected in the excavated basin.
(ii) Sediment traps shall be constructed as a single control measure
consisting of an excavated basin.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 25 00
RFP-2022-CCPC-416 Erosion and Sedimentation Controls
June 2023 Page 9 of 13
(iii) The shape of the excavated basin may be varied to suit the
characteristics of the area surrounding it.
3.5 MAINTENANCE
(a) All temporary erosion and sediment control measures shall be
maintained in an effective, functioning, stable condition.
(b) All temporary erosion and sediment control measures in frozen
conditions shall be reconstructed once the ground has thawed to the
depth of the measure being placed.
END OF SECTION
Section 31 25 00
EROSION AND SEDIMENTATION CONTROL
SCHEDULE E1
Contract
Location: Company:
Conduct an inspection of all Erosion and sedimentation control measures implemented onsite each week and
following any significant storm event (12.7 mm (0.5") of precipitation or greater). Record any maintenance or
repair performed in Schedule E2 – ESC Inspection Log.
Photographs of each measure must be taken immediately following installation, in-situ, and at the end of
construction.
Date of Photo
Silt Fence
Inlet Protection
Stabilized Construction
Entrance
Rolled Erosion Control
Products
Surface Roughening
Sedimentation Basin
Temporary Seeding
Outlet Protection
GENERAL
1.1 SCOPE
(a) This Specification provides the requirements for construction of jet grout
soil-cement columns in subsurface soils for the extent, both on plan and
in elevation, as indicated in the Drawings. Jet grouting will be required
for:
(i) The TBM break-in and break-out blocks at the Pape slurry wall
shaft end walls.
(ii) Vertical and inclined jet grout columns alongside and beneath the
existing TTC structure at Pape Station.
(b) Contractor is responsible for jet grout design, construction (jet grout
column development), quality testing, verification and corrective action to
achieve the performance criteria requirements.
(c) Contractor is responsible for spoil containment, collection and disposal.
(d) Pre-production verification in-situ jet grouting (trial jet grouting to develop
test columns) and a core drilling program will be required to verify jet
grouted column development and overlaps, perform in-situ testing, and
to recover cores for inspection and compressive strength testing.
(e) For details of SOE elements of the Contract and the elements that can
be adjusted by the Contractor versus what cannot be changed and must
remain as indicated in the Drawings and Specifications, refer to
Appendix A – SOE Elements that Contractor is Permitted to Change, of
this Specification Section.
(b) Payment:
(i) Payment will be made for the following items:
A. Item C.2.2 – ‘Jet Grouting - Alongside Head Wall and TTC
(Vertical)’ (Pape Station North SOE).
B. Item C.2.3 – ‘Jet Grouting - Beneath TTC / Underpinning Zone
(Inclined)’ (Pape Station North SOE).
C. Item C.2.4 – ‘Jet Grouting - TBM Break Out - Stage 1 & 2
(Gertrude Place)’ (Pape Station North SOE).
D. Item C.3.2 – ‘Jet Grouting - Alongside Head Wall and TTC
(Vertical)’ (Pape Station South SOE).
E. Item C.3.3 – ‘Jet Grouting - Beneath TTC / Underpinning Zone
(Inclined)’ (Pape Station South SOE).
F. Item C.3.4 – ‘Jet Grouting - TBM Break In - Stage 1 & 2
(Danforth Ave)’ (Pape Station South SOE).
(ii) Payment for each lump sum Item shall be as follows:
A. 10% upon review of the Work Plan, Shop Drawings, Soil-
Cement Column Submittals and upon acceptance of the test
program.
B. 70% on account of the number of jet grout columns (min. 2 m
diameter) installed and measured up to the total number of
columns shown in the Drawings or the number of columns
required to achieve the minimum jet grout block dimensions
within the theoretical limits shown on the Drawings (whichever
is greater). There will be no additional payment for jet grouting
column counts should the actual number of columns exceed
that indicated on the Drawings.
C. 20% upon receipt and acceptance of all quality control
documentation, field testing and daily production reports.
A. Project Manager shall have not less than five (5) years of
recent experience working on projects of similar type, size,
and complexity.
B. Superintendent shall have not less than five (5) years of recent
experience working on projects of similar type, size, and
complexity.
C. Supervising Engineer shall have not less than three (3) years
of recent experience working on projects of similar type, size,
and complexity.
(vi) Laboratory testing shall be performed by a firm with an established
record in the specific tests that are required for the jet grouting.
(b) Closeout Submittals:
(i) As-built drawings of all jet grout columns.
(ii) Coring process documentation and core sample test results.
TBM break-in /
Granular 600 3.0 10.0
break-out blocks
(b) Design jet grout diameters and patterns to meet contract requirements.
The jet grout column diameter shall be 2.0 m nominal. Jet grout columns
shall have 30% overlap minimum.
(c) Jet grout testing and quality control shall demonstrate that soil-cement
elements conform to performance requirements stated herein.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 43 00
RFP-2022-CCPC-416 Jet Grouting
June 2023 Page 8 of 16
PRODUCTS
2.1 MATERIALS
(a) Materials shall be defined and supplied by the Contractor.
(b) Water: Potable and free of impurities that could affect grout gelling
characteristics and strength to ASTM C1602/C1602M.
(c) Admixtures: Non-toxic and compatible with other mix components.
(d) Cement: Type 1 ordinary Portland cement for general use.
(e) The ratios of the material components shall be proposed by the
Contractor and confirmed during the pre-production testing program.
Once accepted by the Metrolinx Representative, the grout slurry shall not
be changed unless requested in writing through project correspondence
or a field change request mechanism such as an RFI.
2.2 EQUIPMENT
(a) Provide equipment with proven satisfactory performance history.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 43 00
RFP-2022-CCPC-416 Jet Grouting
June 2023 Page 9 of 16
(b) The field laboratory shall be equipped with two sets of Marsh funnel
viscometers and mud cups, fluid density mud balance scales and pH
testing tape.
(c) Drill bits capable of advancing through subsurface conditions including
concrete, asphalt pavement, clay, silt, sand, cobbles, boulders and
timber obstructions.
(d) Portable cement grout batch plant with storage cribs, weather protection,
sheds, calibrated scales, calibrated flow meters, pumps, mixers, valves,
gauges, and regulating devices required to measure and mix grout.
(e) Jetting system:
(i) Utilize radially oriented jet nozzles to separately inject cement
grout, water, and air.
(ii) Provides continuous positive return flow to ground surface using
sacrificial casing or retractable pipe casing.
(iii) Capable of variable rotation and withdrawal rates within ranges to
complete Work and produce continuous soil-cement columns.
(iv) Allows continuous monitoring and recording of data throughout jet
grouting. Automatically record pressures of cement grout, water
and air, rate of flow, total volume of grouting fluids for each
developed column, and rate of rotation and withdrawal versus
depth and time.
(v) RPM shall be set by the driller then automatically controlled by the
drill rig during the entire jet grouting process and recorded on the
jet grout installation log.
(vi) All the data monitored and recorded, as described in (above) shall
be made available to the Engineer in a format previously agreed to
prior to the Work.
(vii) The jetting system shall be compatible with software that is
capable of processing the data recorded in a graphical format.
Samples of output of the proposed software shall be included in
the Work Plan.
(viii) Capable of replacing hardened non-conforming columns.
(ix) Maintain jet grout equipment with spare parts.
(x) Able to work on existing ground surfaces without damage.
(f) Drilling:
(i) Use equipment of type and capacity able to drill holes of required
size and depth.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 43 00
RFP-2022-CCPC-416 Jet Grouting
June 2023 Page 10 of 16
(ii) Use for lowering, raising, and rotating monitors to perform Work
within limits as indicated on drawings.
(g) Grout mixing and injection equipment:
(i) Provide required type and capacity for following:
A. Grout mixers.
B. Holding tanks and water supply tanks.
C. Air compressors.
D. Pumps: Sufficient capacity to supply grout, air, and water.
EXECUTION
3.1 GENERAL
(a) Jet grouting works may be completed prior to, or after, the construction
of the slurry wall at all jet grouting locations, except at the headwall area.
Vertical and inclined jet grouting at the headwall locations (Lipton
Avenue) shall be performed before SOE construction.
(b) Schedule and sequence shall be planned to suit Contractor’s desired
sequence and with coordination of partial street closures as required.
Partial street closures shall be limited to one traffic lane that is closed to
traffic at a one time.
(c) Jet grouting column sequencing within any defined jet grouted area can
be revised to suit the Contractor’s means and methods, provided no
adjacent jet grout columns are developed within 24-hours of each other.
The 24-hour period is defined as between the completion of one column
and the start of an adjacent column.
(d) Contractor is required to obtain partial street closure permits for jet
grouting works on Danforth Avenue, Lipton Avenue, Gertrude Place and
Muriel Avenue. Only one lane at a time may be closed on each of the
streets mentioned.
(e) Position equipment for mixing, holding, and pumping grout in secure
location, and operate to minimize spillage.
(f) No spillage permitted to enter storm drains.
(g) Prevent spoil return, stockpiled spoil or grout entering storm drains, or
extending past the site or work zone.
(h) Subsurface strata may contain mixed fill, timber, cobbles, boulders, and
other soil conditions that may cause difficult drilling.
(i) Prevent movement and damage to structures and utilities during drilling.
(j) When jet grout hole is lost, backfill with grout, and drill another hole.
(k) Jet grout hole is considered lost due to equipment failure, inadequacy of
grout, improper air or water supplies, or improper drilling or injection.
(1) Core using wet rotary coring with triple tube core barrels,
face discharge coring bits, and low drilling fluid flow.
(2) Minimum core size: HQ (63 mm diameter) or larger.
(3) For production columns, perform coring at the
intersection of two or more columns.
(4) At completion of the core hole, fill entire test hole with
sand / cement grout of equivalent strength.
B. If rotosonic coring does not yield samples adequate for testing:
(1) Due to low drill fluid, flow rates may provide alternative
indicator of soil-cement continuity.
(2) Where grout is eroded and washed during coring, an
optical or acoustic televiewer borehole imaging may be
used to provide alternate means of assessing continuity,
subject to the approval of the Metrolinx Representative.
(d) Quality Control Submittals:
(i) Quality Control Plan prior to commencement of grouting.
(ii) Jet grout sampling and testing methods.
(iii) Soil-cement test laboratory certification.
(iv) Details for identifying, protecting and maintaining utilities.
(v) Calibration records for all pressure gauges, flow meters and scales
from an approved laboratory testing agency.
(vi) Methods and equipment to measure in real time jet grout
parameters including injection pressure, jet monitor rotation and
withdrawal rates, and grout volumes injected.
(vii) Equipment and procedures to drill and sample jet grout test holes.
(viii) Procedures to core and test completed jet grout columns.
(ix) Methods and equipment to manage return flow, including
collection, volume measurement, storage, transport and disposal.
(x) Forms to be used for recording jet grouting performance data.
(xi) Procedures and materials to remediate low permeability zones.
(e) Quality Control Plan shall include:
(i) Core sampling to confirm design compliance to ASTM D420.
(ii) Methods to confirm soil-cement compressive strength.
(iii) Methods to control and verify vertical limits and grout column overlap.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 43 00
RFP-2022-CCPC-416 Jet Grouting
June 2023 Page 16 of 16
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Section: 31 43 00 Jet Grouting
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A2: SOE Elements that Contractor is Permitted to Change : for Specification Section 31 43 00 – Jet Grouting
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(see Note 2) ‘(B)’ applies to both of the sites
Jet grouting – Design Yes No No (P) OLTA design includes jet grout column size and spacing / overlap
(P) OLTA design provides performance requirements as per the Specification
Jet grouting – Installation Sequence No Yes, with N/A (P) Vertical and inclined jet grouting at the headwall locations (Lipton Avenue) shall be
conditions performed before SOE construction
(P) No adjacent jet grout columns can be developed within 24-hours of each other
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 1 of 33
GENERAL
1.1 SCOPE
(a) This Specification provides requirements for construction of:
(i) Tieback anchors that support the SOE walls of the Pape Station
shafts.
(ii) Tie anchors between the Head Walls of the Pape Station South
Shaft and North Shaft, within the envelope for the future
underpinning (including the row above the underpinning pipe
canopy at EL 97.0 and the row below the underpinning pipe
canopy at EL 78.8). Underpinning works will be performed by
others.
(iii) For details of SOE elements of the Contract and the elements that
can be adjusted by the Contractor versus what cannot be changed
and must remain as indicated in the Drawings and Specifications,
refer to Appendix A – SOE Elements that Contractor is Permitted
to Change, of this Specification Section.
B. Pape Station North & South SOE between North and South
Head Walls:
(1) Item C.2.17 – ‘Tie Anchors (between Head Walls)’.
C. Pape Station South SOE:
(1) Item C.3.15 – ‘Tie Back Anchors (Soil)’.
(2) Item C.3.16 – ‘Tie Back Anchors (Rock)’.
(ii) Where measured quantities exceed those in Items in Clause
1.3.b.i. payment will be made for the following Provisional Items:
A. Item F.1.1 – ‘Additional Tie Back Anchors’.
B. Item F.1.2 – ‘Additional Tie Anchors’.
(iii) No Unit Price adjustment will be made for the Provisional items
unless actual quantities vary from those shown in Appendix A of
this Schedule by greater than ± 25%.
(ee) Test Load: The test load that the stand anchor is taken to and represents
the anchor factored Design Load (DL). The factored design load will
depend upon type of test and whether the anchor is a production anchor
or a pre-production (sacrificial) anchor.
(ff) Tieback (also Strand Anchor or Tendon): An anchor consisting of
bundles of steel wire strands that are prestressed to support, and limit
the lateral movements, of an earth retaining structure. Tiebacks may be
anchored into rock, or into a suitable soil unit, at one end and anchored
to the earth retaining structure at the other. Tiebacks are typically
installed at a medium angle of inclination.
(gg) Tie Anchor: A strand anchor installed horizontally between the Head
Walls of the Pape Station South Shaft and North Shaft within the future
underpinning zone (including the row above the underpinning pipe
canopy at EL 97.0 and the row below the underpinning pipe canopy at
EL 78.8). The anchor is installed within permanent perforated steel
casing with a head assembly at each end and is prestressed from one
end prior to grouting..
(hh) Total Anchor Length: The unbonded length plus the tendon bond length.
(ii) Trumpet Pipe: Pipe cast into the wall intended to permit the installation of
a Tieback through the wall and the transfer of the Tieback load to the
wall. The trumpet pipe will be temporarily filled with a block-out material
during wall construction to prevent the ingress of concrete.
(jj) Unbonded Length (Stressing Length): The length of the tendon which is
not bonded to the grout and surrounding ground. This length is free to
elongate during stressing. The grout surrounding the unbonded length is
a void filler and provides corrosion protection.
(kk) Wedge: A wedge shaped sleeve that fits around the end of a single
strand anchor and is used to lock off the prestressing load. Each strand
anchor is fitted with a wedge and all wedges for the tendon once locked
off seat in the wedge plate to maintain the prestressing load in the
tendon.
(ll) Wide Section: The section of shaft closest to the Head Wall and
perpendicular to the Head Wall that is used to perform and
accommodate the underpinning works for tunnelling beneath the existing
TTC structure.
(mm) Zone of Influence (ZOI): An area in proximity to active construction
deemed to potentially have an effect on the movement of existing
structures, buildings and utilities. See Section 02 22 00 Existing
Conditions Assessment.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 7 of 33
(xii) Method to verify rock condition for Tieback anchorage bonded into
Type 17 bedrock.
(xiii) Method of placing and centering anchors over design bond length.
(xiv) For Tie anchors:
A. Method of drilling through the slurry wall
B. Method demonstrating how slurry wall will be drilled without
conflicts with the slurry wall panel reinforcement bars.
C. Method for determining and maintaining drill alignment when
drilling the tie rods so as to minimize drill deviation.
(xv) Grout mixing procedure, installation method and grout pressures.
(xvi) Anchor stressing schedule, working loads and test loads.
(xvii) Anchor stressing equipment and test method.
(xviii) Anchor stressing calibration records of gauges and jacks.
(xix) Procedure to monitor load and movement during anchor testing.
(xx) As-built plans, elevations and sections showing anchor locations,
spacing, orientation, free stressing length, design load, unique
identification number for each anchor, couplers and components.
(b) Quality Assurance Submittals:
(i) Anchor mill test certificates for prestressing steel as delivered to
site.
(ii) Prestressing strand bond capacity test results prior to work
commencement.
(iii) Coupler strength capacity.
(iv) Strength testing results for anchor bond stress.
(v) Anchor hole construction and grouting information record.
(vi) Anchor repair methods if required during installations.
(c) Tieback anchor as-built record drawings must include:
(i) Unique Tieback identification number.
(ii) Anchor hole diameter, total length and free-stressing length.
(iii) Anchor bond length.
(iv) Soil, rock and groundwater conditions encountered.
(v) Time to drill the anchor hole.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 9 of 33
PRODUCTS
2.1 MATERIALS
(a) Preferred Tieback suppliers in Ontario:
(i) Multi-Strand Anchors by DYWIDAG Systems Inter. Canada Ltd.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 10 of 33
from the top of the hole. Centralizers shall be made of PVC or other
suitable non-corrosive materials.
(g) Spacers: Spacers shall be used to separate elements of a multi-strand
tendons and shall permit grout to freely flow around the tendon and up
the drillhole. Spacers shall be fabricated from plastic, steel or material
which is nondetrimental to the prestressing steel. Wood shall not be
used. Spacers shall be provided at maximum intervals of 3 m and may
be combined with centralizers. Spacers shall be made of HDPE or other
suitable non-corrosive materials.
(h) Cement Grout:
(i) High minimum early compressive strength grout.
(ii) Minimum grout strength:
A. 40 MPa at 7 days.
B. 50 MPa at 28 days.
(iii) Resistant to water wash-out and dilution in wet ground conditions.
(iv) Pumpable and thixotropic to reduce loss in fractured ground.
(v) Resistant to bleeding and sulphate attack.
(vi) Cement type is suitable for the expected ground conditions.
(vii) Grout is neat, free of aggregates, with no accelerators.
(viii) Grout bleeds less than 2% when allowed to stand for 1 hour.
(ix) Use high speed mixer to ensure uniform grout-water mixture.
(x) Replace Type I cement in high sulfate ground to avoid grout
deterioration and steel corrosion. Replace with cement Types II, V,
and V with pozzolan, for sulfate contents 0.1%-0.2%; 0.2%-2.0%;
and +2%, respectively.
(i) Anchorage (Strand Anchors):
(i) Anchorage components meet guaranteed minimum ultimate
capacity.
(ii) Wedge anchor head for prestressing strands uniformly engages
strand with no notch or pinching effects.
(iii) Wedge plate, steel bearing plate, and angle adjustments shall
conform to CSA G40.20/G40.21 minimum Grade 350W.
(iv) Fabricate the trumpet from steel pipe to ASTM A53/A53M, or
tubing in accordance with ASTM A500/500M.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 12 of 33
(v) Hydraulic jack shall allow anchor to be lift-off tested to confirm the
lock-off load.
(vi) Provide current calibration curves for jacks.
(o) Anchor Testing Equipment:
(i) Furnish dial gauge, dial gauge support, load cell, hydraulic jack
and pump, stressing anchorage, pressure gauges.
(ii) A dial gauge or Vernier scale capable of measuring to 0.025 mm
shall be used to measure the anchor movement. The movement
measuring device shall have a minimum travel of 75 mm or equal
to the theoretical elastic elongation of the total anchor length at the
maximum test load and it shall have adequate travel so the strand
anchor movement can be measured without resetting the device at
an interim point.
(iii) A calibrated reference pressure gauge shall also be kept at the site
to periodically check the production (primary pressure) gauge. The
reference gauge shall be calibrated with the test jack and primary
pressure gauge. The reference pressure gauge shall be stored
indoors and not subjected to rough treatment.
(iv) Provide current calibration curves for all gauges.
(p) Stressing Equipment:
(i) All stressing equipment shall be preferably power driven, and shall
be accepted before use. The power unit shall be so adjusted that
the rate of stressing is within the limits recommended or directed.
(ii) The stressing equipment shall be capable of being placed over the
anchor tendon in such a manner that the jack, bearing plates, and
stressing anchorage are axially aligned with the tendon and the
tendon is centered within the equipment.
(iii) The stressing equipment shall be set up and used strictly in
accordance with the manufacturer’s operating instructions.
(iv) Stressing equipment shall preferably be capable of stressing the
whole tendon in one stroke to the specified Test Load and the
equipment shall be capable of stressing the tendon to the
maximum specified Test Load within 75 % of the rated capacity.
The pump shall be capable of applying each load increment in less
than 60 seconds.
(v) The equipment shall permit the tendon to be stressed in
increments so that the load in the tendon can be raised or lowered
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 15 of 33
EXECUTION
3.1 GENERAL
(a) Tiebacks:
(i) Vertical distance between two rows of Tiebacks shall not exceed
2.0 m or as shown on the Drawings. Horizontal distance between
two adjacent Tiebacks shall not exceed 2.3 m.
(ii) Height between lowest Tieback row to excavation bottom is a
maximum of 4.7 m (prior to the SOE base slab being placed).
(iii) The angle of declination for rock Tiebacks may be decreased to
accommodate construction conflicts with other SOE elements
provided the specified bonded length and preload is maintained,
which will depend upon the soil and rock unit that the Tiebacks are
located within). The angle of declination shall be within the range of
15 to 45 degrees. Tiebacks shall not have a bonded length within
the weathered bedrock unit (Type 16 Bedrock).
(iv) The Contractor shall submit any changes of Tieback location to the
Metrolinx Representative for their review and approval.
(v) Design load on drawings shall match the calculated design load
from the Contractor’s Engineer for each row of Tiebacks to ensure
that excessive Tieback force is not applied to the wall.
(vi) Tieback design load shall be specified on Shop Drawings with
safety factor 2.0.
(vii) Minimum distance from potential failure surface to anchor zone is
0.15 x excavation height.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 16 of 33
(vii) The Contractor shall submit any changes of Tie anchor location to
the Metrolinx Representative for their review and approval.
3.4 FABRICATION
(a) Strand anchors shall be either shop or field fabricated from materials
conforming to the requirements in this Specification Section. The whole
assembly together with grout pipes and spacers shall be placed in the
sheath only after inspection and acceptance.
(b) Prestressing steel shall be cut with an abrasive saw or, with the approval
of the prestressing steel supplier, an oxyacetylene torch.
(c) All of the tendon bond length must be free of dirt, manufacturers'
lubricants, corrosion-inhibitive coatings, or other deleterious substances
that may significantly affect the grout-to-tendon bond or the service life of
the tendon.
3.5 DRILLING
(a) Drillholes shall be located so the longitudinal axis of the drillhole and the
longitudinal axis of the tendon are parallel. The drillhole shall not be
drilled in a location that requires the tendon to be bent to enable the
bearing plate to be connected to the structure.
(b) The Contractor shall be responsible for using a drilling method to
establish a stable hole of adequate dimensions. Holes may be drilled
with either percussion type drills or by rotary type diamond drills.
(c) Contractor shall use duplex drilling to advance the drillhole such that the
drill rods and casing are installed simultaneously.
(d) During drilling, continuous records of penetration rates shall be kept by
the Contractor. Any sudden advance in drilling or a sudden increase in
penetration rate shall be noted, together with the depth at which the
variations occur. The location of clay seams, open cracks, soft or broken
ground, water loss, water inflows and other relevant information shall be
recorded. Drilling records that contain a description of materials
encountered during drilling shall be included in the shift reports.
(e) Drillholes for strand anchors shall be drilled at the locations and to the
length, inclination and diameter shown on the Drawings.
(f) The minimum drill hole diameter shall be 200 mm for installation of
anchors consisting of the 15.7 mm diameter prestressing steel strands.
Drillhole diameters shall be selected to successfully install fully-
assembled anchors to the bottom of the drilled hole for the full length of
the anchor. The nominal diameter of the drillholes shall be in accordance
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 20 of 33
3.9 GROUTING
(a) General:
(i) Confirm temperature conditions are acceptable for grouting. During
freezing weather conditions, grout shall not be allowed to freeze or
partially freeze until fully cured.
(ii) Provide grout tubes for proper grout injection and air venting. Grout
and vent tubes are to be kink free, unblocked and protected from
damage prior to grout installation.
(b) Tiebacks:
(i) Contractor shall determine the appropriate grout mix, submitted to
the Metrolinx Representative for approval.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 23 of 33
(ii) All Tiebacks shall be pressure grouted with cement grout. Pressure
grouting shall be carried out such that the drillhole shall be sealed
and that the grout is injected until a minimum 3.5 bar grout
pressure (measured at the top of the drill hole) can be maintained
on the grout column for at least five (5) minutes.
(iii) Ensure the strand anchor remains centralized within the drilled
hole during grouting.
(iv) The strand anchor grout shall remain undisturbed after grouting for
a minimum of three days or until the grout has cured. Testing and
stressing of the anchors shall not be performed until strength tests
on the grout indicate sufficient curing has occurred.
(v) The grouting shall be carried out for the full length of the hole at
pressures directed by the Metrolinx Representative.
(vi) Grout shall be injected from the lowest point of the drillhole in one
continuous operation after installation of the assembled anchor.
The grout may be pumped through grout tubes. The grout tube
may remain in the hole upon completion of grouting if the tube is
filled with grout.
(vii) The quantity of the grout and the grout pressures shall be
recorded. The grout pressures and grout takes shall be controlled
to prevent excessive heave or fracturing.
(viii) After the tendon is installed, the drillhole may be filled in one
continuous grouting operation except that pressure grouting shall
not be used in the free length zone. The grout at the top of the
drillhole shall not contact the back of the structure or the bottom of
the trumpet.
(c) Tie Anchors:
(i) Tie anchors are not required to be pressure grouted since the
grouted tendon is not in contact with the surrounding native soil.
(ii) Contractor shall determine the appropriate grout mix, submitted to
the Metrolinx Representative for approval.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 24 of 33
(b) For secondary grouting, grout mixtures and grouting methods used shall
be in accordance with the following:
(i) Plastic, semi-rigid grout and air bleed tubes shall be used to grout
the Tieback anchor. The grout tube shall extent to the deepest part
of the hole and the bleed tube shall either be short or absent.
(ii) These Tie anchors shall be sacrificial and shall not be included as
a working SOE element. Pre-production Tie anchors shall satisfy
the minimum requirements of the performance testing. Pre-
production Tie anchors shall be detensioned and cut off at the
wedge plate / head assembly after completion of testing. Additional
requirements may be provided by the Metrolinx Representative for
testing.
Cycle 1 AL 0.25 DL AL
Cycle 8 AL 0.25 DL 0.50 DL 0.75 DL 1.00 DL 1.25 DL 1.50 DL 1.75 DL 2.00 DL* AL
Where:
AL = Alignment Load.
DL = Design Load of Tieback or Tie anchor.
* At 2.00 DL, maintain the load for a minimum of 2 hours.
(ii) Maintain each load for a minimum of 10 minutes or until the rate of
displacement is not greater than 2 mm per log cycle.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 27 of 33
(ii) Prior to setting the dial gauges, the Alignment Load (AL) shall be
accurately placed on the tendon. The magnitude of AL depends on
type and length of the tendon.
(iii) If the extension of the jack is not sufficient to fully stress the anchor
in one operation to locking off, the re setting of jacks shall be done
carefully to minimize damage to the strands.
(iv) Regripping of strands, which would cause overlapping wedge
bites, or wedge bites on the tendon below the anchor head, shall
be avoided.
(v) Stressing and testing of multiple element tendons with single
element jacks is not permitted.
(vi) Stressing shall not begin before the grout has reached the 28 day
strength of the grout as evidenced by test reports.
(d) Performance Testing:
(i) The first three (3) Tiebacks and the first three (3) Tie anchors,
followed by 5% of the remaining Tiebacks and 5% of the remaining
Tie anchors, shall be performance tested in accordance with the
procedures described in this Specification System. The Metrolinx
Representative shall select the anchors to be performance tested
and shall advise if additional Tiebacks or Tie anchors shall be
performance tested. The remaining anchors shall be tested in
accordance with the proof test procedures described in this
Specification Section.
(ii) The performance test shall be performed by incrementally loading
and unloading the anchor to a maximum test load of 133% of the
DL in accordance with the following loading schedule.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 29 of 33
From Table 8.1 – Performance Test Steps, of PTI DC35.1-14 – Post Tensioning Institute,
Recommendations for Prestressed Rock and Soil Anchors
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 51 00
RFP-2022-CCPC-416 Tieback and Tie Anchors
June 2023 Page 30 of 33
From Table 8.2 – Proof Test Steps, of PTI DC35.1-14 – Post Tensioning Institute,
Recommendations for Prestressed Rock and Soil Anchors
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Section: 31 51 00 Tiebacks and Tie Anchors
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A3: SOE Elements that Contractor is Permitted to Change : Specification Section 31 51 00 – Tiebacks and Tie Anchors
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(see Note 2) ‘(B)’ applies to both of the sites
Tieback and Tie Anchor – Design Yes No Yes, with (P) Plan length shall consider easement constraints
conditions (P) Contractor’s design shall ensure SOE deformations are maintained within TTC
deformation criteria
Tieback – Location Yes No Yes, with (P) Tiebacks are specified in locations where Struts cannot be relied upon for support (all
conditions Struts at EL 87.5, Struts in the Wide Section at EL 93.5 and EL 83.5) because they will
be removed during Contract 2 works for the TBM passage, the pipe canopy installation
and the underpinning works
Tieback – Spacing Yes No Yes, with (P) Minimum spacing (minimum, to prevent influence on adjacent Tieback), Narrow
conditions Section: 2.0 m spacing (horizontally) and 2.0 m spacing (vertically) with a maximum area
of 4 m2 per Tieback
(P) Minimum spacing (minimum, to prevent influence on adjacent Tieback), Wide Section:
2.3 m spacing (horizontally, due to Slurry Wall T-section panels) and 2.0 m spacing
(vertically) with a maximum area of 4.6 m2 per Tieback
(P) Number of Tiebacks per row shown on Drawings shall be taken as the minimum
number of Tiebacks at that elevation
(P) Number of Tiebacks provided shall ensure SOE deformations are maintained within
TTC deformation criteria
Tieback and Tie Anchor – Design Yes Yes Yes, with (P) Tieback and Tie Anchor design details such as Tieback sleeves, anchor plate and
Details (provided as a (for shop conditions Tieback seats as shown on the Drawings are indicative. Design details shall have the
base design) drawings and capacity for the forces that these components carry. Detailing shall be included in
detailing) Contractor’s Shop Drawings, signed-and-sealed by a Professional Engineer licensed in
the province of Ontario
(P) Tieback and Tie Anchor penetrations through the wall must prevent entry of water
and soil. Tieback and Tie Anchor temporary seal details and procedures shall be
included with the design details.
Tie Anchor – Location Yes No Yes, with (P) Cannot be in envelope of top and bottom of the future Contract 2 pipe canopy, EL
conditions 96.5 to EL 93.5 and EL 81.5 to EL 79.5 (Pipe canopy is NIC)
(P) Tie Anchor locations shall ensure SOE deformations are maintained within TTC
deformation criteria
Tie Anchor – Spacing Yes No Yes, with (P) Design assumes up to 2.8 m spacing (horizontally, due to Slurry Wall T-section
conditions panels) and up to 2.2 m spacing (vertically)
(P) Number of Tie Anchors per row shown on Drawings shall be taken as the minimum
number of Tie Anchors at that elevation
(P) Number of Tie Anchors provided shall ensure SOE deformations are maintained
within TTC deformation criteria
Tieback and Tie Anchor – Installation Partial Yes, with N/A (P) Comply with requirements to not expose TTC structures to unbalanced loading from
Sequence (Establishing overall conditions the excavation sequence
sequence criteria
with respect to (P) If there is a deviation from the from OLTA overall sequence criteria contained in the
excavation depth) Specification and shown on the Drawings, installation sequence must be considered in
Contractor’s analysis for excavation and support stages to ensure deformations are
maintained within TTC deformation criteria
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 53 00
RFP-2022-CCPC-416 Struts and Walers
June 2023 Page 1 of 12
GENERAL
1.1 SCOPE
(a) This Specification provides requirements for design, fabrication and
installation of walers and struts that provides an internal support system
to brace the SOE walls of the Pape Station shafts and Sammon Avenue
Headhouse shaft.
(b) For details of SOE elements of the Contract and the elements that can
be adjusted by the Contractor versus what cannot be changed and must
remain as indicated in the Drawings and Specifications, refer to
Appendix A – SOE Elements that Contractor is Permitted to Change, of
this Specification Section.
(o) Should the Contractor elect to modify the strut and waler arrangement,
the modified design must consider stresses due to temperature
variations.
(p) Struts must be protected from stress variations induced by temperature
fluctuations. This shall be achieved by a system that can cater for, or
protect from, the effects of temperature changes. This can include the
use of smart jacks, insulation, or temperature control. Each strut must
have monitoring devices that can report the load in the strut jacks and
temperature through real time monitoring and datalogging, transmitted to
a cloud data and storage system that can be accessed through an
internet-based portal.
PRODUCTS
2.1 MATERIALS
(a) Structural Steel:
(i) Minimum Grade 350W, in accordance with CSA G40.20/G40.21.
(ii) Expansion Bearings - The PTFE layer in expansion bearings shall
be made from pure virgin PTFE resin satisfying the requirements of
ASTM D 4894. The PTFE layer shall be fabricated as reinforced
sheets containing random or woven glass fibres, uniformly blended
with PTFE resin. The maximum fiber content shall be 25%. Woven
PTFE shall be attached to a metallic substrate by a method which
will provide for a shear force resistance of at least 0.10 times the
applied compressive force.
(iii) Struts - ASTM A252-10(2018) Standard Specification for Welded
and Seamless Steel Pipe Piles – Grade 3 (modified to 345 MPa
yield strength). Pipe may be manufactured by ERW Stright Seam,
Spiralweld or Rolled & Welded processes.
(iv) Stud Shear Connectors - ASTM A108-18 Standard Specification
for Steel Bar, Carbon and Alloy, Cold-Finished.
(vi) Make provisions for permanently fixing each member with steel
shims or wedges welded into place.
(vii) Include in preloading the means to determine, within 5% of the
amount of preload induced into bracing members.
(viii) Do not use wooden wedges to preload bracing member.
(ix) Strut height above excavation shall not exceed maximum vertical
distance above top of excavation indicated in the drawings.
(x) Reduce vertical distance between bracing levels when excessive
ground movement occurs.
(xi) Preloading procedure shall be as follows:
A. Do not start preload procedure until non-shrink grout between
structural support bracket and slurry wall has reached 7-day
strength of 35 MPa or 28-day strength of 40 MPa.
B. Take a reading of the slurry wall monitoring point(s) on the top
of the slurry wall panel(s) where the strut that is about to be
preloaded is located. Take reading within 24 hours of
commencing preload activity.
C. Apply alignment load (AL) and then apply an initial load of 5%
of the total preload (PL) value (AL + 0.05 PL).
D. Hold load increment for at least 2 minutes.
E. Apply 25% of PL (0.25 PL) and hold load increment for at least
2 minutes.
Continue load increments at 25% of PL to 0.75 PL, holding
each load increment a minimum of 2 minutes.
F. Apply final load increment to 1.00 PL and hold for 30 minutes.
Verify that the jack pressure remains steady and does not lose
more than 1% of the total applied preload, otherwise the load
shall be removed, the jack maintained / replaced, and the test
restarted.
G. After 30 minutes, take another reading of the slurry wall
monitoring point(s) on the top of the slurry wall panel(s) where
the strut is located.
H. Summary of load increments for preloading:
(1) AL + 0.05 PL, 0.25 PL, 0.50 PL, 0.75 PL, 1.00 PL.
I. Lock off jack at 1.00 PL.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 31 53 00
RFP-2022-CCPC-416 Struts and Walers
June 2023 Page 12 of 12
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Section: 31 53 00 Struts and Walers
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A4: SOE Elements that Contractor is Permitted to Change : Specification Section 31 53 00 – Struts and Walers
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(Unless changed by (see Note 2) ‘(B)’ applies to both of the sites
Contractor)
Struts – Design and member sizing Yes No Yes, with (P) For Pape Station Shafts, Strut design, location and configuration shall ensure SOE
conditions deformations are maintained within TTC deformation criteria
(S) For Sammon Avenue Headhouse Shaft, ensure SOE deformations are maintained
within deformation criteria presented in the Instrumentation and Monitoring Drawings and
are to the satisfaction of the City
Struts – Location Yes No Yes, with (P) Struts at EL 93.5m, 87.5m and 83.5m (Levels 5 to 7) in Wide Section cannot be
conditions changed. These Struts provide necessary stiffness prior to installation of the SOE base
slab. These Struts are to be removed during Contract 2 works due to space required for
pipe canopy (EL 96.5 to EL 93.5) and for Contract 2 TBM passage (EL 92.0 to EL 82.0)
(P) Struts at elevation of 87.5m (Level 6) in Narrow Section cannot be changed. These
Struts provide stiffness prior to installation of SOE base slab for Contract 2 TBM passage
(S) Contractor is recommended to follow the location and elevation of Struts as shown in
the Sammon SOE Drawings. The next contract may need to adjust bracing to suit their
SEM cross-cut cavern design and excavation sequence
Struts – Configuration Yes No Yes, with (P) Strut design, location and configuration shall ensure SOE deformations are
conditions maintained within TTC deformation criteria
(S) Strut design, location and configuration shall ensure SOE deformations are
maintained within deformation criteria presented in the Instrumentation and Monitoring
Drawings and are to the satisfaction of the City
(S) Contractor is recommended to follow the configuration, location and elevation of
Struts as shown in the Sammon SOE Drawings. The next contract may need to adjust
bracing to suit their SEM cross-cut cavern design and excavation sequence
Walers Yes No Yes, with (B) Can be changed, as long as the Waler strength (in terms of kN/m) and Waler total
conditions shear and flexural deflection are not reduced
Struts and Walers – Walers to Slurry Yes Yes Yes, with (B) Connection design shall have the capacity for the forces and moments the connection
Wall Connections (provided as a (for shop conditions carries. Detailing shall be included in Contractor’s Shop Drawings, signed-and-sealed by
base design) drawings and a Professional Engineer licensed in the province of Ontario
detailing)
Struts and Walers – Strut to Waler Yes Yes Yes, with (B) Connection design shall have the capacity for the forces and moments the connection
Connections (provided as a (for shop conditions carries Detailing shall be included in Contractor’s Shop Drawings, signed-and-sealed by a
base design) drawings and Professional Engineer licensed in the province of Ontario
detailing)
Struts and Walers – Detailing Yes Yes Yes, with (B) Detailing shall be included in Contractor’s Shop Drawings, signed-and-sealed by a
(provided as a (for shop conditions Professional Engineer licensed in the province of Ontario
base design) drawings and
detailing)
Strut and Waler – Installation Partial Yes, with N/A (P) Comply with requirements to not expose TTC structures to unbalanced loading from
Sequence (Establishing overall conditions the excavation sequence
sequence criteria
with respect to (B) If there is a deviation from the OLTA overall sequence criteria, installation sequence
excavation depth) must be considered in Contractor’s analysis for excavation and support stages to ensure
deformations are maintained within TTC deformation criteria (Pape Station); or the
deformation criteria presented in the Instrumentation and Monitoring Drawings and are to
the satisfaction of the City (Sammon)
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 53 99
RFP-2022-CCPC-416 Strut Temperature Control System
June 2023 Page 1 of 7
GENERAL
1.1 SCOPE
(a) This Specification covers the requirements for a Strut Temperature
Control System for the struts in the Wide Sections of the North and
South Shafts of Pape Station SOE intended to control strut thermal
movements and resulting restraint forces at locations adjacent to the
support of excavation (SOE) Head Walls.
(b) The Specification Section shall supplement the supply and installation of
the strut system required as SOE elements that are detailed under
Specification Section 31 53 00 – Struts and Walers.
PRODUCTS
2.1 MATERIALS
(a) Insulation and Jacketing:
(i) Insulation shall have a flame spread index of 25 and smoke-
development index not exceeding 450.
OL North Civil Works Schedule 9 – Specifications and Drawings
Pape Segment Support of Excavation Section 31 53 99
RFP-2022-CCPC-416 Strut Temperature Control System
June 2023 Page 5 of 7
2.2 EQUIPMENT
(a) System designer shall provide all equipment needed for a fully functional
system according to the proposed configuration. Equipment shall include
but is not limited to following:
(i) Heat Pumps.
(ii) Power Supply.
(iii) Temperature Sensors.
(iv) Pumps for Heat Transfer Fluid.
(v) Monitoring System for Strut Temperature Control System.
(vi) Back-up Generator(s).
(vii) Wireless Communication Components.
EXECUTION
3.2 INSTALLATION
(a) Install and set-up, the strut system, strut temperature control system
including piping, heat tracing, insulation and associated controls and
equipment as required for the proposed system for the struts identified
on the Drawings.
END OF SECTION
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 1 of 31
GENERAL
1.1 SCOPE
(a) This Specification covers requirements for the installation of reinforced
concrete support of excavation (SOE) walls constructed by the slurry trench
method (“slurry walls”) utilizing “hydrofraise”, (also known as “hydromill”)
techniques for the construction of the Pape Station SOE and Sammon
Avenue Headhouse SOE.
(b) Scope includes all Labour, Products, Equipment and services necessary
to construct reinforced concrete structural wall for the support of
excavation walls.
(c) Scope includes developing shop drawings for slurry wall details, and
other structural elements of the SOE system, including the bracing and
tiebacks and tie anchors. The shop drawings package shall be prepared
by the Contractor’s Design Engineer. The shop drawings and details
shall suit the Contractor’s preferred means and methods of construction,
working within the performance requirements stipulated in the Drawings
and Specifications, including the TTC movement criteria from the TTC
Technical Review Submission Requirements (for MetroLinx Ontario
Line), Table 2.4 which is contained in the Agreement under Schedule 4 –
Review Requirements, Appendix B, Attachment 2. All Drawings and the
Work Plan shall be signed and sealed by a Professional Engineer
licensed in the province of Ontario.
(d) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR)
for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings. The Contractor shall develop fabrication and
construction details to suit their means and method of construction,
which shall be made as a shop drawings submittal to OLTA as the
Engineer of Record. Calculations will be required to accompany the
Shop Drawings for any structural elements. The Contractor’s SOE
submittals shall be made in accordance with the Drawing requirements
and the relevant Specifications and shall be signed-and-sealed by the
Contractor’s Design Engineer. During construction, the Contractor shall
be responsible for ensuring that the SOE remains within the deflection
criteria, supplementing the SOE with additional support elements if
required. After Contract award, OLTA will provide its modeling and
analysis files electronically to the Contractor if requested. OLTA will use
its modeling and analysis files for the review and checking process of the
Contractor’s SOE fabrication and construction details during the
submittal review period.
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 2 of 31
(e) For details of SOE elements of the Contract and the elements that can
be adjusted by the Contractor versus what cannot be changed and must
remain as indicated in the Drawings and Specifications, refer to
Appendix A – SOE Elements that Contractor is Permitted to Change, of
this Specification Section.
(f) Jet grouting at Lipton Avenue along the SOE Headwall locations shall be
performed before SOE slurry wall construction in that location.
(g) Schedule and sequence of slurry wall construction shall be planned to
suit Contractor’s desired panel sequence and with coordination of partial
street closures on Danforth Avenue, Lipton Avenue, Gertrude Place and
Muriel Avenue.
(i) Narrow Section: The section of shaft closest to the End Wall that is used
to receive or launch the TBM.
(j) NIC: Not in Contract.
(k) NTE: Not to Exceed.
(l) OLTA: Ontario Line Technical Advisor. The Engineer of Record for the
project, on behalf of Metrolinx.
(m) Primary Panel: Slurry wall panel excavated through soil and rock using
one or more passes of the slurry wall excavation equipment with no
adjacent panels. At the Pape shafts, for the Wide Section of the support
of excavation, Primary Panels will be T-sections panels.
(n) Secondary Panel: Slurry wall panel excavated between two Primary
Panels or adjacent to the Primary panel with one or more passes of the
excavating equipment.
(o) Side Wall: The sections of slurry wall running the length of the Pape
Station shafts (the sections of slurry wall running parallel to Pape
Avenue). Side Walls apply to both the Wide Section and the Narrow
Section slurry walls.
(p) Slurry: Water-based drilling fluid used to provide temporary earth support
during trench excavation for slurry walls.
(q) Slurry Wall: Reinforced concrete slurry wall panel constructed below
ground using the slurry method of trench stabilization. Slurry walls are
structural walls.
(r) Stop End: A fabricated steel element used temporarily as a joint former
between the separate panels of a slurry wall and to incorporate a
waterstop across the joint. Stop ends are often shaped to provide and
effective interlock between individual concrete panels. Stop end
elements are installed at both ends of the panel and have the same
width as the slurry wall panel thickness. During installation, they are
coupled together using stop end tubes. Stop end elements are typically
removed after the initial setting of the concrete.
(s) Support of Excavation (SOE): A temporary earth retaining system
intended to control the ground to facilitate a safe and efficient space for
construction.
(t) Theoretical Excavation Line (Slurry Walls): The theoretical line or plane
of the excavation to accommodate the design thickness of the slurry wall
without consideration of any allowances such as an excavation or
construction allowance or unintended over excavation.
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 7 of 31
PRODUCTS
2.1 MATERIALS
(a) Cast-in-Place Concrete:
(i) Proportion the mixes to achieve the following properties:
A. Guide walls: per Section 03 30 00 – Cast-in-Place Concrete.
B. Slurry Walls: In accordance with CSA A23.1-09/A23.2-09 and
per Section 03 30 00 – Cast-in-Place Concrete.
(b) Reinforcement:
(i) Steel Reinforcement: As per Section 03 20 00 – Concrete
Reinforcing.
(ii) Glass Fibre Reinforcement: As per Section 03 21 21.11 – Glass
Fibre Reinforced Polymer Reinforcement Bars.
(iii) Spacers: industry-standard precast concrete spacers with
minimum concrete compressive strength of 35 MPa.
(iv) Lap splice couplers: Drop forged U-bolt and saddle type wire rope
clips, or approved equal, certified and tested for rebar used.
(v) Mechanical couplers: Lenton standard and transition couplers or
approved equal. Couplers on adjacent reinforcement mats shall be
staggered / offset or arranged such that they allow the placement
of concrete around the reinforcement.
(c) Slurry:
(i) Sodium bentonite (sodium montmorillonite) and water suspension
to API RP 13A, Section 4, meeting the following requirements:
A. Bentonite slurry shall be employed for excavation utilizing
hydrofraise / hydromill techniques.
B. Slurry additives: As approved by the Metrolinx Representative
through the submittal procedures.
C. Water: Water shall be as per API RP-13B-1 and shall exclude
saline water or water contaminated by salt.
D. Design Criteria:
(1) Initial Slurry Properties:
a. Minimum unit weight: 1,050 kg/m3.
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 19 of 31
2.2 EQUIPMENT
(a) Slurry wall excavation equipment:
(i) General: The equipment used shall be capable of excavating
through the range of the expected ground conditions as described
in the geotechnical information contained in the Agreement.
(ii) Accuracy: equipment must have demonstrable capability of
excavating trench walls to a vertical tolerance of 1 in 200.
(iii) Slurry wall excavation equipment shall be equipped with data
recording equipment to record the horizontal and vertical position
of excavation equipment and operating parameters. The data
recording equipment shall be maintained in a fully operational state
at all times during slurry wall excavation.
(b) Slurry plant:
(i) General: All slurry plant and piping to be designed and located to
prevent leakage and spillage, and to facilitate handling of wet and
dry materials. Facilities shall include provisions to prevent slurry
plant operations from freezing. Facilities shall enable inspection
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 21 of 31
EXECUTION
3.1 GENERAL
(a) Contractor shall refer to Specific Section 00 17 30 – Project Specific
Conditions, and the Drawings for TTC surcharge constraints above and
in the vicinity of TTC structures
(b) Perform check, including utility locator check, to ensure all utility
relocations have been completed.
(c) Employ construction methods and procedures that prevent spillage of
excavated materials, slurry or concrete onto utilities, streets, sidewalks or
other facilities.
(d) Prior to the start of construction, ensure all environmental protection
measures are in place and functioning to ensure compliance with all
regulatory and specification requirements, especially measures related to
the capture and containment of excess slurry as well as measures
relating to the disposal of slurry.
(e) Contractor shall ensure that adequate resources and equipment are
provided to meet the Schedule Completion Dates defined in the
Agreement, Schedule 1 – Definitions and Interpretation.
(f) Contractor shall ensure that adequate resources are available, and
equipment is available and in good working order, prior to starting critical
operations. Do not start a critical operation unless it can be completed
with the available resources and equipment.
(g) Monitor settlements and heave in accordance with Section 31 09 13,
Geotechnical Instrumentation and Monitoring. In the event that ground
movement reaches the Review Level or Alert Levels as specified in the
Geotechnical Instrumentation and Monitoring Drawings and as specified
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 22 of 31
(b) Excavation:
(i) Do not begin excavation of the slurry walls until all geotechnical
instrumentation for monitoring ground movements is installed and
baseline readings have been taken.
(ii) Excavate by Hydromill methods. Use such means that will
minimize over-excavation and loosening and caving of material
outside the designed trench width. Be prepared with equipment
such that if obstructions are encountered in excavating for panels,
the obstructions can be removed. Pump slurry containing
excavated material to a central processing plant.
(iii) Provide the number of hydromills and associated support
equipment to suit the sequence and construction schedule.
(iv) Perform excavation continuously from ground surface to the
required depth. Excavate in a manner that minimizes movement
and loss of ground
(v) Excavate panels to the dimensions indicated on the Drawings,
within allowances for vertical and horizontal tolerances
(vi) The depth of panel excavation shall extend to the toe level over the
full plan area of the panel. The Contractor must account for any
additional excavation required as a result of the equipment
selected
(vii) Perform excavation through the slurry, adding or replacing slurry
as necessary to maintain slurry within specified limits no more than
1 m below the top of the guide wall. Slurry level should be at least
0.3 m above the bottom of the guide wall
(viii) Do not commence excavation of a new panel until the concrete in
the adjacent panels has achieved sufficient strength, and not less
than 7 MPa, to enable it to withstand the effects of the excavation.
(ix) Unless otherwise accepted by the Metrolinx Representative, the
construction of any single panel shall be continuous once
excavation has commenced. Excavated panels or part panels shall
not be left open during weekends or statutory holidays.
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 25 of 31
(c) Reinforcement:
(i) Fabricate reinforcing assemblies in accordance with the Shop
Drawings, ensuring they are free from distortion. Assemblies
fabricated off site are to be checked for distortion prior to use. Add
additional bars, stiffeners and struts as required to resist distortion
loads associated with transporting and erecting the assemblies.
The front and rear of reinforcement cages shall be properly marked
on Site to identify them during placement.
(ii) Install guides and spacers to ensure minimum cover is maintained
between reinforcing steel and face of excavation. Maximum
spacing of spacers: 2.5 m vertical; 0.6 m horizontal.
(iii) Check location of, secure and protect blockouts to prevent damage
and displacement by flotation.
(iv) Use lap splice couplers to connect reinforcement assemblies when
both assemblies are in the vertical position. Use mechanical ties
per 03 20 00 - Concrete Reinforcing. Use a sufficient number of
couplers to ensure a factor of safety of five against slippage under
the dead weight of the reinforcing assembly or flotation where fiber
reinforced polymer reinforcement is used. Ensure correct vertical
alignment and lap lengths are maintained.
(v) Reinforcement shall be designed and erected to enable concrete
placement by tremie pipe without honeycombs, slurry-filled voids,
or other defects.
(vi) Clean the bottom of the trench of all loose material and inspect the
trench to determine that the required depth and width of excavation
has been achieved utilizing the following sequence or modified
methodology approved by the Metrolinx Representative. This is a
critical stage and required to be a Hold Point. Each step shall be
executed as noted below and documentation shall be submitted to
the Metrolinx Representative.
A. Three hours before placement of the reinforcing steel clean
the bottom of the excavation by air lifting, or other approved
method.
B. Verify that the required trench width and depth has been met.
C. Verify that the trench is clean, the thickness of the sediment at
the bottom of the slurry wall does not exceed 12 mm prior
concreting, and the slurry at excavation bottom has the
required properties and contains no impurities such as sand or
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 26 of 31
(iv) Tremie pipe shall remain embedded in the concrete at all times.
The pipe shall be kept no less than 2.5 m below the concrete level
when the concrete level reaches 3 m above the slurry wall toe.
Equip the tremie pipe with a ball check valve or other device to
prevent mixing of the slurry with concrete inside the tremie pipe.
(v) Use a minimum of one tremie pipe for each 2.5 m of panel length.
Tremie pipes shall be evenly distributed along the panel length.
(vi) Concrete shall be placed in such a manner that the concrete
displaces the slurry progressively from the bottom and rises
uniformly to the surface, and that concrete and slurry do not
intermix. Ensure concrete / slurry interface remains horizontal.
(vii) Place concrete in a continuous operation until the slurry wall panel
is completely concreted to the required elevation.
(viii) The tremie pipe shall have an internal diameter of not less than
250 mm for concrete with 20 mm maximum size aggregate. The
tremie pipe shall have no internal projections and external
projections shall be minimized. The receiving hopper for the tremie
pipe shall have a capacity at least equal to that of the tremie pipe.
(ix) At all times the end of the tremie pipe shall be kept clear of the
reinforcement, any embedded steel section and box out and the
side of the foundation, to prevent segregation of the concrete
(x) Concrete shall be placed continuously to ensure that entrapment of
air within the tremie pipe is minimized and at all times a sufficient
quantity of concrete shall be maintained within the tremie pipe to
ensure that the pressure from it exceeds that from the slurry or
support fluid.
(xi) Construction joint at the top of the slurry wall shall be finished and
prepared to promote good bond and interlocking with the
subsequent concrete pours of the capping beam. Demolish poor
quality concrete at the top of the slurry wall back to sound
concrete.
(e) Stop ends and joints:
(i) Stop ends, inserted before placement of concrete in the panel,
shall be clean and have a smooth regular surface. Stop ends shall
ensure the installation of continuous waterstop along the whole
length of two adjacent panels as shown on the Drawings. Where
stop ends are inserted in sections, adequate joint connections
must be provided to ensure verticality of the complete stop end.
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 28 of 31
(ii) The extraction of the stop ends shall be carried out at such a time
in such a manner that no damage is caused to the concrete placed
against them, to the joint waterstop, or to the adjacent soil and
structures. Contractor to review concrete strength gain and pay
attention to changes any changes in mix design or concreting
operations to determine optimum time to remove stop ends.
(iii) Joint waterstops shall be installed over the whole panel length, less
the last 2 m within the socket length and secured by stop ends until
the panel geometry is checked and panel filled with in-trench slurry
and shall have a minimum width of 225 mm. Waterstops shall
maintain the minimum cover to the slurry wall reinforcement at all
times.
(iv) Where concrete is cast against previously completed wall panels,
the previously formed concrete shall be cleaned as much as
practically possible so that solid substances are removed before
the joint is formed.
(b) The Contractor shall propose which panels shall have sonic logging PVC
casing and this shall form part of the shop drawings submittal. At a
minimum, PVC casing for CSL testing shall be installed within the panels
shown in Table 4.
(c) The Contractor shall engage a CSL Specialty Engineer to perform the
CSL testing and shall be a Professional Engineer having at least three
years of experience in CSL testing.
(d) Perform CSL testing in accordance with Table 4 as shown below.
Table 4: Cross Hole Sonic Logging (CSL) Testing Requirements
Panel Type CSL Tube Installation Requirements
(e) Perform CSL tests between 72-hours and 28 calendar days after slurry
wall concrete placement.
(f) Perform the CSL tests with the source and receiver probes in the same
horizontal plane. Continuously record CSL signals at depth intervals of
50 mm from the bottom of the tubes to the top of each panel.
(g) Concrete compressive strength shall achieve a minimum of 20 MPa prior
to CSL testing.
(h) Verify PVC casing is free of obstructions and in good condition at least
24-hours prior to CSL testing. If PVC casing does not provide access
over its full length, repair the casing or core a new hole for CSL testing.
(i) Perform CSL testing for all slurry panels where PVC CSL tubes are
installed or as directed by the Metrolinx Representative.
(j) The CSL tubes used for testing each panel shall be selected by the
Contractor and approved by the Metrolinx Representative. Selection of
CSL tubes shall consider the direct straight line path though the concrete
and the maximum horizontal distance of 1.8 m between CSL tubes.
(k) Depending on the results of the first ten CSL tests, the Contractor can
propose a reduction to the total number of CSL tests for the acceptance
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 30 of 31
by the Metrolinx Representative, but no less than 30% of all slurry wall
panels per shaft shall be tested using CSL testing techniques.
3.8 FINISHING
(a) During excavation, after the placement of the slurry wall, clean the
interior wall face as it is exposed utilizing sand blasting, power washing,
or similar approved alternative cleaning methods to remove slurry
caking, soils, and film materials and expose a clean surface.
(b) Repair defects in accordance with the approved ‘Repair Plan’. Remove
bulges on the interior face of the wall to bring surface irregularities within
specified tolerances as excavation proceeds.
(c) Infiltration / Seepage:
(i) If during excavation, readings on any instrumentation indicate that
deformations, groundwater levels or porewater pressures are
outside the limits established, immediately take remedial steps to
OL North Civil Works Schedule 9 - Specifications and Drawings
Pape Segment Support of Excavation Section 31 56 00
RFP-2022-CCPC-416 Slurry Walls
June 2023 Page 31 of 31
END OF SECTION
OL North Civil Works Appendix A
Pape Segment Support of Excavation Applicable Section: 31 56 00 Slurry Walls
RFP-2022-CCPC-416 SOE Elements that Contractor is Permitted to Change
June 2023 Page 1 of 2
1. (B) Ontario Line Technical Advisor (OLTA) is the Engineer of Record (EOR) for the Project on behalf of Metrolinx and has prepared signed-and-
sealed Drawings.
2. (B) “Contractor’s ability to change” results in the design responsibility for that SOE element being transferred to the Contractor.
3. (P) Reference to Pape Station Shafts “Wide Section” and “Narrow Section” refers to both the North Shaft and South Shaft.
4. (P) Slurry Wall T-panels, Jet Grouting and Tiebacks are not applicable to Sammon Avenue Headhouse Shaft.
5. (B) For SOE elements that the Contractor proposes to change, the Contractor is required to consult with their Design Engineer and prepare a
“Narrative of Proposed SOE Changes” for provisional approval by Metrolinx prior to commencing detailed analysis and design.
6. (B) Changes to the design that are initiated by the Contractor shall be at no cost to Metrolinx.
7. (P) Changes to the Pape Station SOE design that are initiated by the Contractor are required to be submitted to TTC for their review and approval. If
the Contractor elects to proceed with an alternative design, this may introduce some degree of schedule risk and uncertainty. The Contractor will not
be granted any additional time to complete the analysis and design work resulting from additional TTC reviews due to Contractor initiated design
changes.
8. (B) Changes to the design performed by the Contractor’s Design Engineer shall be signed-and-Sealed by a Professional Engineer, licensed in the
province of Ontario.
9. (B) OLTA performing analysis and redesign, including issuing revised IFC drawings to suit the Contractor’s preferred arrangement / configuration of
SOE elements may be possible. This will require further discussion and negotiation regarding level of effort, cost and responsibility between
Metrolinx and the Contractor.
Specifications that Contain an Appendix A for SOE Elements that Contractor is Permitted to Change:
Table A5: SOE Elements that Contractor is Permitted to Change : Specification Section 31 56 00 – Slurry Walls
SOE Element OLTA Contractor Contractor’s Conditions or Remarks
Design Design Ability
‘(P)’ denotes Pape Station Shaft site,
Responsibility Responsibility to Change ‘(S)’ denotes Sammon Avenue Headhouse Shaft site
(see Note 2) ‘(B)’ applies to both of the sites
SOE Method – Slurry Walls Yes No No (B) For Pape Station Shafts, the use of Slurry Walls is a fundamental part of the TTC
design review and approval process. Secant piles are not a viable alternative. The same
method of SOE construction shall be used for the Sammon Avenue Headhouse Shaft
Slurry Wall – Shaft SOE Geometry Yes No No (B) Contractor cannot vary as the shaft internal size is spaceproofed for Contract 2
Slurry Wall – Design Yes No Yes, with (P) Contractor may propose different panel configuration and size for primary and
conditions secondary panels subject to the satisfaction of average gross uncracked stiffness
(uncracked moment of inertia per metre) values as follow (excluding corner panels):
o North and South Head Walls: 0.937 m4/m
o Side Walls, Wide Section: 0.937 m4/m, ± 7%. (Note that having T-panels in the
Wide Section sidewalls is important for resisting the Head Wall forces that push
the sidewalls toward the Narrow Section. Without the sidewall stems, the
movement and torsion in the L-panels between the Wide Section and Narrow
Section could be excessive).
o Side Walls, Narrow Section: 0.281 m4/m
o North and South End Walls: 0.281 m4/m
(S) Contractor may propose different panel configuration and size for primary and
secondary panels subject to the satisfaction of average gross uncracked stiffness
(uncracked moment of inertia per metre): 0.281 m4/m (excluding corner panels)
(P) Monolithic L-panels at corners and at transition locations from Wide Section to Narrow
Section for both South and North Shafts. Any changes in L-panel length / design will
require calculations that indicate Wide Section wall movements do not increase
(P) Any change of design shall ensure SOE deformations are maintained within TTC
deformation criteria
(S) Any change of design shall ensure SOE deformations are maintained within
deformation criteria presented in the Instrumentation and Monitoring Drawings and are to
the satisfaction of the City
Slurry Wall – Panel Configuration Yes No Yes, with (P) Rearranging and resizing of Slurry Wall panels shall:
conditions o Do not install Tiebacks and Tie Anchors within the panel joints
o Provide a minimum 500 mm clearance from the joints (based on the distance
between Tieback / Tie Anchor centreline and panel joint)
o Avoid installing Tiebacks and Tie Anchors into the stem of T-panels.
(B) Any change of panel configuration shall ensure SOE deformations are maintained
within TTC deformation criteria (Pape Station); or the deformation criteria presented in the
Instrumentation and Monitoring Drawings and are to the satisfaction of the City (Sammon)
Slurry Wall – Reinforcement Design Yes Yes Yes, with (B) Contractor is responsible for reinforcement detailing and can change bar arrangement
and Detailing (provided as a (for shop conditions (sizing, number and spacing) to suit means and methods, as long as overall capacity is
base design) drawings and maintained
detailing)
Slurry Wall – Watertightness at Joints Yes No Yes, with (B) Different panel end stop system can be proposed
conditions Milled Slurry Wall joints are not preferred but will be allowed provided the watertightness
performance criteria can be maintained
Slurry Wall – Socket Depth Yes No No (B) OLTA design requires 5 m socket from the lowest elevation of Type 17 bedrock at
each panel location
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 32 – Exterior Improvements
GENERAL
1.1 SCOPE
(a) This Specification covers the Contractor requirements for asphalt paving,
reinstatement and flexible pavement repairs, sealing of cracks and/or
cuts within Gertrude Place, Lipton Avenue, and Danforth Avenue
including bridge deck ramp locations.
(b) The Contractor shall reinstate all asphalt paving damaged during
construction within the City right of way. Reinstatement shall consist of
crack sealing or full replacement where significant damages and/or full
removal have occurred.
(c) The Contractor shall replace all pavement structure where removed
during construction with new pavement structure matching the existing
pavement structure.
1.10 PROTECTION
(a) The Contractor shall protect all existing asphalt and concrete surface to
remain. Use of rubber tire equipment and machinery is recommended for
the project works. Any damage to any existing features due to
Contractor’s operation on site shall be rectified by the Contractor to the
satisfaction of the Metrolinx Representative.
PRODUCTS
2.1 MATERIALS
(a) Asphaltic Concrete: Shall be in accordance with the Specifications and
Drawings conforming with OPSS 1150:
(i) Coarse and fine aggregates: In accordance with OPSS 1010, TS-
1003 and OPSS MUNI 1150.
(ii) Fillers: In accordance with TS-1003.
(iii) Reclaimed asphalt concrete is not permitted.
(iv) Asphaltic emulsion: Type RS, in accordance with OPSS 1103.
(v) Asphalt cement: In accordance with OPSS.MUNI 1101.
(vi) Tack coat: SS-1 emulsified asphalt in accordance with TS-1103.
(vii) Asphaltic concrete surface joint and crack sealer: Hot-poured
rubberized asphalt in accordance with OPSS 1212.
EXECUTION
(b) The Contractor shall allow the appointed testing firm access to the
mixing plant for verification of weights or proportions, character of
materials used and determination of temperatures used in the
preparation of asphalt concrete mix.
(c) The Contractor shall arrange the testing firm to perform laboratory tests
on proposed asphalt pavement mixes to determine conformity with
requirements.
(d) The Contractor shall arrange the testing firm to perform two (2) series of
compaction tests for each asphalt pavement course. Pay for costs of
additional testing as required due to improper performance of work.
finish course areas. Replace with fresh hot asphalt concrete mixture and
re-compact.
(f) Asphalt emulsion: The Contractor shall treat all vertical concrete surfaces
in contact with asphalt pavement.
(g) Asphalt cement: The Contractor shall paint asphalt cement on all
exposed vertical asphalt surfaces of cut perimeter.
(h) The Contractor shall lay mixture only upon dry granular base in weather
conditions specified under OPSS 310.07.06. Immediately after spreading
and screeding, check surface and correct irregularities before
compaction is started.
(i) The Contractor shall adjust widths of courses so that longitudinal joints
above one another do not coincide. Feathering of joints is not
permissible. Form butt or keyed joints at locations where meeting existing
asphalt.
(j) At irregular sections, intersections, turn-outs, or driveways where it is
impractical to spread and finish mixtures by machine methods, the
Contractor shall use either acceptable spreading equipment, or hand
spread mixture.
(k) When hand spreading mixture, the Contractor shall dump loads only as
fast as they can be properly handled. When hand spreading adjacent to
machine-laid areas, carry out operation concurrently with machine laying
to obtain indistinguishable joints.
(l) The Contractor shall have resurfacing in accordance to OPSS 310
including power broom and tack coat.
3.5 MASKING
(a) The Contractor shall clean existing painted lines and adhered graphics
with solvent and remove loose debris. Abrade existing paint for bonding.
(b) The Contractor shall paint over existing lines to be eradicated with two
coats of asphalt sealer extending sealer 25 mm beyond edge of existing
paint.
END OF SECTION
Ontario Line North Civil Works
Pape Segment Support of Excavation
Technical Specifications
Division 33 – Utilities
GENERAL
1.1 SCOPE
(a) This Specification covers the Contractor’s requirements for Work related
to Utilities and associated appurtenances.
PRODUCTS
EXECUTION
(h) The Contractor shall ensure that the performance of the Utility Work
complies with the design and construction criteria and requirements of
the Utility Owners. The Contractor shall:
(i) Provide early identification, communication and approach to
mitigation of impacts to critical Utility construction Work.
(ii) Obtain approval for the impact of the Work on any Utilities with the
appropriate Utility Owners.
(iii) Manage service interruption to customers of the Utility Owners and
property owners to the satisfaction of the Utility Owner and the
Metrolinx Representative.
(iv) Confirm all shutdown and blackout periods with the Utility Owners.
The timing of Utility Work, including relocations, is subject to
operational constraints. The Contractor shall coordinate the
scheduling of all Utility Work with the relevant Utility Owners
accordingly.
(v) Obtain permission for any outage, disconnection or interruption of
the Utility or customer service that may be required to complete the
Work. If permission is granted, the Contractor shall give a minimum
of 3 Working Days prior notice to those users or customers who
will be affected. The Contractor shall make interruptions at such
times and in such a manner as negotiated with the affected Utility
Owner.
(vi) Permit the Utility Owners, from time to time, to review and inspect
the progress of the Utility Work owned or to be owned by the Utility
Owner.
(i) If any Utility Owner requires access to their assets for any reason,
including emergency repair, the Contractor shall co-operate and grant
access to all facilities to the Utility Owner and to any contractor
appointed by the Utility Owner.
(j) Utility Owners may require having their own inspector on Site at all times
during construction or during the Work affecting their assets. The
Contractor shall contact Utility Owners and accommodate the Utility
Owners’ requirements.
(k) The Contractor shall obtain permission from the appropriate Utility
Owners before interrupting their Utility system or building services. The
Contractor shall verify schedule constraints associated with the Work
and shall schedule the Work accordingly.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 00 00
RFP-2022-CCPC-416 General Utilities
June 2023 Page 8 of 10
(l) Coordinate Utility Work such that any planned operations, maintenance,
repair and/or replacement activities undertaken by the Contractor are
notified to Toronto Transit Commission (TTC) a minimum of 10 Business
Days in advance.
may at its own discretion and at the Contractor’s expense repair or direct
the Contractor to repair the damaged Utility to the satisfaction of Utility
Owner.
(e) The Contractor shall replace, or pay the Utility Owner to replace, at the
discretion of the Utility Owner, all surface and subsurface features and
Utility Infrastructure disturbed, damaged or temporarily removed during
the activities related to Utility Work and reinstate in accordance with the
requirements of the Utility Owner’s standard practices.
(f) Where vibration protection is required, the Contractor shall confirm
vibration limits prior to start of the Work and obtain acceptance from the
appropriate Utility Owners for any monitoring and mitigation measures as
proposed by the Contractor.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 05 16
RFP-2022-CCPC-416 Maintenance Holes and Catch Basin Structures
June 2023 Page 1 of 8
GENERAL
1.1 SCOPE
(a) This Specification covers the Contractor requirements for maintenance
holes and catch basin structures.
(b) Labour, products, equipment, and services necessary for maintenance
holes and catch basin structure Work in accordance with the Agreement.
MATERIALS
2.1 MATERIALS
(a) Cast-in-place concrete:
(i) In accordance with TS-1350.
(ii) In accordance with section 03 30 00.
(b) Precast maintenance hole units: to ASTM C478M, circular or oval:
(i) Top sections eccentric cone or flat slab top type with opening offset
for vertical ladder installation.
(c) Precast catch basin sections: to ASTM C478M.
(d) Joints: made watertight using rubber rings.
(e) Mortar:
(i) Masonry Cement: to CAN/CSA-A3002.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 05 16
RFP-2022-CCPC-416 Maintenance Holes and Catch Basin Structures
June 2023 Page 4 of 8
(f) Ladder rungs: to CSA G30.18, No.25M billet steel deformed bars, hot
dipped galvanized to ASTM A123/A123M:
(i) Rungs to be safety pattern (drop step type).
(ii) Adjusting rings: to ASTM C478M.
(g) Fiberglass Reinforced Plastic (FRP) Safety ladder, handrail and Landing:
The contractor shall submit shop drawing detailing exact Maintenance
hole dimensions with ladder, hand rail and landing details.
(i) All FRP shall be manufactured according to CAN/CGSB 41.22-93
or ASTM 3647. Refer to T-1120.05-1 for FRP ladder.
(ii) All wall brackets and mounting brackets shall be molded FRP.
(iii) All bolts, nuts and washers shall be made of 316 grade stainless
steel.
(iv) Maintenance hole depth between 4.5m and 9.0m, landings shall be
placed at midpoint.
(v) Minimum clearance between the landing and benching platform to
be 2.5m.
(vi) Structures exceeding 4.5m in depth to include safety platform
every 4.5m as per OPSD 404.020.
(h) Concrete Brick: to CAN/CSA-A165 Series.
(i) Drop maintenance hole pipe: same as sewer pipe.
(j) Galvanized iron sheet: approximately 2 mm thick.
(k) Steel gratings, I-beams and fasteners: as indicated.
(l) Frames, gratings, covers to dimensions as indicated and following
requirements:
(i) Metal gratings and covers to bear evenly on frames.
A. Frame with grating or cover to constitute one unit.
B. Assemble and mark unit components before shipment.
(ii) Gray iron castings: to ASTM A48/A48M, strength class 30B.
(iii) Castings: coated with two applications of asphalt varnish.
(iv) Maintenance hole frames and covers: to OPSS 407.
(v) Catch basin frames and covers: to OPSS 407.
(m) Granular bedding and backfill: in accordance with Section 31 05 17-
Aggregates, and following requirements:
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 05 16
RFP-2022-CCPC-416 Maintenance Holes and Catch Basin Structures
June 2023 Page 5 of 8
EXECUTION
3.1 EXAMINATION
(a) Verification of Conditions: The Contractor shall verify that conditions of
substrate are acceptable for maintenance holes and catch basin
structures installation in accordance with manufacturer's written
instructions.
(i) Visually inspect substrate in presence of Metrolinx Representative.
(ii) Inform Metrolinx Representative of unacceptable conditions
immediately upon discovery.
(iii) Proceed with installation only after unacceptable conditions have
been remedied and after receipt of written approval to proceed
from the Metrolinx Representative.
3.3 INSTALLATION
(a) The Contractor shall dewater excavation to approval of Metrolinx
Representative and remove soft and foreign material before placing
concrete base.
(b) The Contractor shall set precast concrete base on 150 mm minimum of
granular bedding compacted to 100% corrected maximum dry density.
(c) Precast units: The Contractor shall perform the following:
(i) Set bottom section of precast unit in bed of cement mortar and
bond to concrete slab or base.
(ii) Make each successive joint watertight with Metrolinx
Representative-approved rubber ring gaskets, bituminous
compound, cement mortar, epoxy resin cement, or combination of
these materials.
(iii) Clean surplus mortar and joint compounds from interior surface of
unit as work progresses.
(iv) Plug lifting holes with concrete plugs set in cement mortar or
mastic compound.
(d) For sewers: The Contractor shall perform the following:
(i) Place stub outlets and bulkheads at elevations and in positions
indicated.
(ii) Bench to provide smooth U-shaped channel.
A. Side height of channel to equal to diameter of sewer.
B. Slope adjacent floor at 1 in 8.(vertical to horizontal).
C. Curve channels smoothly.
D. Slope invert to establish sewer grade.
(e) The Contractor shall place lean concrete backfill in accordance with
Section 31 23 00 – Excavation and Fill.
(f) Installing units in existing systems: The Contractor shall perform the
following:
(i) Where new unit is installed in existing run of pipe, ensure full
support of existing pipe during installation, and carefully remove
that portion of existing pipe to dimensions required and install new
unit as specified.
(ii) Make joints watertight between new unit and existing pipe.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 05 16
RFP-2022-CCPC-416 Maintenance Holes and Catch Basin Structures
June 2023 Page 7 of 8
3.6 CLEANING
(a) Leave Work area clean at end of each day.
(b) Final Cleaning: Upon completion, the Contractor shall remove surplus
materials, rubbish, tools and equipment in accordance with
Environmental Obligations.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 42 11
RFP-2022-CCPC-416 Storm Utility Drainage Piping
June 2023 Page 1 of 9
GENERAL
1.1 SCOPE
(a) This Specification covers the Contractor requirements for Storm Utility
drainage piping.
(b) Labour, products, equipment, and services necessary for Storm Utility
Drainage Piping Work in accordance with the Agreement.
PRODUCTS
EXECUTION
3.1 PREPARATION
(a) Temporary erosion and sedimentation control shall be provided as per
Section 31 25 00 – Erosion and Sedimentation Control.
3.2 TRENCHING
(a) The Contractor shall do trenching Work in accordance with Section 31 23
00 – Excavation and Fill.
(b) The Contractor shall protect trench from contents of sewer.
(c) The Contractor shall shape bed true to grade and to provide continuous,
uniform bearing surface for pipe.
(i) Do not use blocks when bedding pipes.
(d) The Contractor shall shape transverse depressions as required to suit
joints.
(e) The Contractor shall compact each layer full width of bed to at least 95%
corrected maximum dry density, maximum density to ASTM D698.
(f) The Contractor shall fill excavation below bottom of specified bedding
adjacent to manholes or catch basins with lean mix concrete.
3.4 INSTALLATION
(a) The Contractor shall lay and join pipes to: ASTM C12.
(b) The Contractor shall lay and join pipe in accordance with manufacturer's
recommendations and to approval of Metrolinx Representative.
(c) The Contractor shall handle pipe using methods approved by Metrolinx
Representative:
(i) Do not use chains or cables passed through rigid pipe bore so that
weight of pipe bears upon pipe ends.
(d) The Contractor shall lay pipes on prepared bed, true to line and grade
with pipe inverts smooth and free of sags or high points.
(i) Ensure barrel of each pipe is in contact with shaped bed
throughout its full length.
(e) The Contractor shall begin laying at outlet and proceed in upstream
direction with socket ends of pipe facing upgrade.
(f) The Contractor shall lay corrugated steel pipe:
(i) With outside circumferential laps facing upgrade and longitudinal
laps or seams at side or quarter points.
(ii) With longitudinal centre line of paved invert coinciding with flowline.
(g) The Contractor shall install joint deflection permitted within limits
recommended by pipe manufacturer.
(h) The Contractor shall have water to flow through pipes during
construction only as permitted by Metrolinx Representative.
(i) Whenever Work is suspended, the Contractor shall install removable
watertight bulkhead at open end of last pipe laid to prevent entry of
foreign materials.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 42 11
RFP-2022-CCPC-416 Storm Utility Drainage Piping
June 2023 Page 7 of 9
(j) The Contractor shall install plastic pipe and fittings in accordance with
CAN/CSA-B1800.
(k) Joints: The Contractor shall provide the following:
(i) Concrete pipe:
A. Install gaskets as recommended by manufacturer.
B. Support pipes with hand slings or crane as required to
minimize lateral pressure on gasket and maintain concentricity
until gasket is properly positioned.
C. Align pipes before joining.
D. Maintain pipe joints free from mud, silt, gravel and other
foreign material.
E. Avoid displacing gasket or contaminating with dirt or other
foreign material. Remove disturbed or dirty gaskets; clean,
lubricate and replace before joining is attempted.
F. Complete each joint before laying next length of pipe.
G. Minimize joint deflection after joint has been made to avoid
joint damage.
H. Apply sufficient pressure in making joints to ensure that joint is
complete as outlined in manufacturer's recommendations.
I. Mortared joints:
(1) Pipe interior: circular pipes 700mm diameter and larger,
and arch or elliptical pipe equivalent to 900mm diameter
or larger shall have interior gap between ends of adjacent
pipes filled with mortar.
Apply mortar minimum 7 Calendar Days after
backfilling has been completed to allow pipe
settlement to occur.
Finish interior surface of joints smooth.
(2) Pipe exterior: for bell and spigot pipe, use mortar to seal
outside of joints. Press and bed mortar into place.
Allow mortar to set minimum of 1 hour before
backfilling.
(l) When any stoppage of Work occurs, the Contractor shall restrain pipes
as directed by Metrolinx Representative to prevent "creep" during down
time.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 42 11
RFP-2022-CCPC-416 Storm Utility Drainage Piping
June 2023 Page 8 of 9
(m) The Contractor shall plug lifting holes with owner Representative
approved prefabricated plugs, set in shrinkage compensating grout.
(n) The Contractor shall cut pipes as required for special inserts, fittings or
closure pieces, as recommended by pipe manufacturer, without
damaging pipe or its coating and to leave smooth end at right angles to
axis of pipe.
(o) The Contractor shall make watertight connections to manholes and catch
basins:
(i) Use shrinkage compensating grout when suitable gaskets are not
available.
(p) The Contractor shall use prefabricated saddles or approved field
connections for connecting pipes to existing sewer pipes:
(i) Joint to be structurally sound and watertight.
(q) The Contractor shall temporarily plug open upstream ends of pipes with
removable watertight concrete, steel or plastic bulkheads.
3.6 BACKFILL
(a) The Contractor shall place backfill material in unfrozen condition.
(b) The Contractor shall place backfill material, above pipe surround, in
uniform layers not exceeding 150mm compacted thickness up to grades
as indicated.
(c) The Contractor shall place lean concrete backfill in accordance with
Section 31 23 00 – Excavation and Fill.
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 42 11
RFP-2022-CCPC-416 Storm Utility Drainage Piping
June 2023 Page 9 of 9
3.8 CLEANING
(a) Progress Cleaning: Leave Work area clean at end of each day.
(b) The Contractor shall perform Final Cleaning: upon completion remove
surplus materials, rubbish, tools and equipment.
END OF SECTION
OL North Civil Works Schedule 9 - Specification and Drawings
Pape Segment Support of Excavation Section 33 44 51
RFP-2022-CCPC-416 CCTV Inspection of Pipeline
June 2023 Page 1 of 4
GENERAL
1.1 SCOPE
(a) This Specification covers the Contractor requirements for CCTV
inspection of pipelines Work.
MATERIALS
2.1 EQUIPMENT
(a) The Contractor shall ensure all camera Equipment, CCTV truck units and
cable requirements are in accordance with TS 409.
EXECUTION
3.1 EXAMINATION
(a) The Contractor shall verify the condition and dimensions of existing Work
upon which this Specification Section 33 44 51 depends and report
defects to the Metrolinx Representative.
(b) The Contractor shall perform a CCTV inspection prior to the start of any
Construction Work for all existing sewers and maintenance holes that are
within the Utility relocation zones of this Project, including sections
upstream and downstream to the next maintenance hole. The CCTV
shall establish the condition of the existing systems to ensure that they
will not be negatively impacted by the Work. The CCTV shall also identify
all the existing lateral connections which will require support and
replacement.
(c) Following connection of any new permanent sewer section, the
Contractor shall perform a CCTV inspection for the sewer and
maintenance holes, including sections upstream and downstream to the
next maintenance hole. The Contractor shall compare the pre- and post-
construction CCTV inspections and shall provide a written report to the
Metrolinx Representative confirming that the new sewers have been
properly constructed and the existing sewers have not been negatively
impacted. The Contractor shall ensure that the sewer condition is to the
satisfaction of Metrolinx and the appropriate regional or municipal
authority.
(d) The Contractor shall perform a CCTV inspection immediately prior to the
Warranty Period for all sewers as described above to ensure that the
sewers are functioning to the satisfaction of Metrolinx.
3.3 INSPECTION
(a) The Contractor shall ensure linear Measurements are accurate to 0.1%
of the inspected length. The Contractor shall ensure minimal amount of
slack in umbilical at all times. The Contractor shall correct the linear
position for the focal length of the camera.
(b) Contractor shall position camera at the central axis of the sewer +/- 10%.
(c) The Contractor shall inspect all sewers at a rate of camera travel not
faster than nine metres per minute.
(d) The Contractor shall provide sufficient lighting to illuminate the sewer at
least two metres beyond the focal point.
(e) The Contractor shall inspect sewers in the direction of flow unless a
reverse set up is required.
(f) The Contractor shall ensure that the start maintenance hole is clearly
visible at the start of the inspection and perform the inspection from the
centre of the start maintenance hole to the centre of the finish
maintenance hole. The Contractor shall ensure that the automatic
distance measurement is displayed on- screen at all times during the
inspection.
(g) The Contractor shall ensure the picture remains in focus during the
inspection. The Contractor shall stop the camera for a minimum of two
seconds at major defects, connections, junctions, and major branches.
The Contractor shall rotate and pan the camera to provide a
perpendicular view of all maintenance holes, major defects, connections,
junctions, and major branches.
(h) The Contractor shall follow all other conditions for sewer CCTV
inspection outlined in TS 409.
END OF SECTION