VARMAX - Installation, Use and Maintenance

SINGLE BOILER Diagram


Secondary networks with existing regulation VX111
communicating by LPB bus or 0...10V page 1 / 3

A. HYDRAULIC DIAGRAM
COMMUNICATING REGULATOR
REGULATEUR COMMUNICANT
NAVISTEM
LMS B3000
OCI345
VERS
OCI345
0/10 VTO
LPBtovers
V SIGNAL
bus
SIGNAL
ou bus
or LPB
0/10

figure 53 - Diagram VX111

B. NECESSARY ADJUSTMENT ACCESSORY

Appliance
Quantity Order No.
reference
Communication kit for LPB bus 1 OCI 345 059572

Edition: 06 / 2014 Page 67 / 136


VARMAX - Installation, Use and Maintenance

Diagram VX111 page 2 / 3

C. CUSTOMER ELECTRICAL CONNECTION


Alarm
relay

}
D. SPECIFIC START-UP PROCEDURE
Mains supply 230 L N Y1 N Y2 L N L N L N
VAC 50 Hz QX2 QX3 QX1 AUX2 AUX1

BX2
Gnd
LPB bus BX3
Gnd
}

DB MB B3
Gnd
B9
Gnd

H1 } Analogue
0...10V
input
Gnd

H5
Gnd

"
"
Fit the accessories and make their electrical connections.

"
Start up the boiler alone.
Make the following settings:
Line No. Value
• Time and date menu
Set the time Time / minute (1) HH.MM
Set the date Day / month (2) DD.MM
Set the year Year (3) YYYY

For a demand via input 0...10V


• Configuration menu
ConÞgure input H1 Input function H1 (5950) Demand from
circulation circuit
1 10V
Voltage value 1 H1 (5953) 0.0
Function value H1 (5954) 0
Voltage value 2 H1 (5955) 10.0
Function value 2 H1 (5956) 1000 (for 10 V = 100
°C equivalence)

Page 68 / 136 00BNO9061-E


VARMAX - Installation, Use and Maintenance

Diagram VX111 page 3 / 3

Line No. Value


For a demand via LPB (LPB network menu)
• LPB network menu
Check that the boiler has been deÞned Appliance address (6600) 1
as the master generator Segment address (6601) 0
Bus supply function (6604) Automatic
Clock function (6640) Slave with
adjustment
E. ELECTRICAL AND HYDRAULIC VALIDATION
For a demand via input 0...10V
• Input/output test menu
Voltage in H1 Voltage signal H1 (7840) To validate with
the voltage sent
by the boiler room
machine
For a demand via LPB
If the boiler room regulator is conÞgured as the master clock, the boiler
command table must recover the date and time.

In both cases
• Configuration menu
Check the hydraulic diagram Generator 1 check (6212) 14
Generator 2 check (6213) 0
Information on DHW (6215) 0
Information on heating circuits 3, 2 and 1 (6217) 0

F. OPTIMISATION OF SETTINGS

Maintenance optimisation:
It is possible to generate a maintenance message without harming the boiler. This maintenance
message may appear when the 3 following meters have elapsed:
• Time since last maintenance (or commissioning): set parameter 7044 to 12 months
• Operating hours of the burner (parameter 7040)
• Number of start-ups (parameter 7042)
The last 2 parameters depend on the boiler room's hydraulic installation. It is recommended to
use at least parameter 7044 for yearly maintenance.

Edition: 06 / 2014 Page 69 / 136