Professional Documents
Culture Documents
Second Draft Version of Communication Schedules and Protocols
Second Draft Version of Communication Schedules and Protocols
Video or In-person
Verify task1-3 details 1 1 100%
meeting
Prepare the playground
1 2 4 The CP
space
Check the flatness Email or Video
8 5 100%
condition conference
Video or In-person
2 Perform soil tests 8 5 The CP Check the soil condition 15 5 100%
meeting
Purchase commercial
The CP and The
5 liability insurance and get 15 26 Check on progress All of three 12 36 100%
FP
the proof
Identify community
The CP and The
7 resources to prepare in-kind 64 12 Check on progress All of three 64 12 0%
FP
contributions
Safety monitoring and The CP and The Repair and maintenance Email or Video
11 92 60 92 60 0%
maintenance of site PV services conference
Communication duration %Communication Complete STAKEHOLDERS: CP FP PV
WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13
April 17-April 23 April 24-April 30 May 1-May 7 May 8-May 14 May 15-May 21 May 22-May 28 May 29-July 4 July 5-July 11 July 12-July 18 July 19-July 25 July 26-June 2
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93
Page 2 of 2
The project and communication table present the time schedule for 11 tasks and
communication arrangements in each task in form of a Gandhi chart. The Gandhi table
comprises two main parts. The first part records specific content on the left, and the second
part visualizes the time bar on the right. This project spans 90 days, beginning on April 3rd
and concluding on July 2nd. The construction week is scheduled to start on day 85, June 26th.
The right section displays the number of days, weeks, and associated dates marked above for
a 90-day project, with attached legends for reference. Here are some details for
communication schedules.
Preparatory meeting
For most of the tasks, we hold a communication meeting with the stakeholders on the Friday
of the week prior to the start of the task. We mainly aim to confirm the content and schedules’
details of the next task. Before build week, we’ll even take a week out to communicate with
stakeholders and volunteers. All parties are well prepared for the work and potential risks
during the build week.
This memo comes mainly to explain the main reflections on second draft of
communication schedules. There are two main changes. The first is additional explain
and that I refined some of the header notes and explanations in the table. The second
is that I've included more explanation after the table to help its readers understand it.