S.
Unit Description of item of work NO L B D Quantity
No
Excavation in all kinds of soil including boulders upto 0.3 m dia for foundations of
canal cross draniage and other appurtenant structures and placing the excavated
1 Cum
stuff neatly in specified dump area or disposing off the same as directed
etc.,complete with initial lead upto 50 m and initial lift upto 3 m.
As per Cross section 4327.68
Enclosed
4327.68
Formation of Gravel filling including cost, (excluding seigniorage) charges and
conveyance of all materials to work site and spreading in uniform layers by
approved means, on prepared surface and compacting with vibratory roller to
2 Cum
achieve the desired density at OMC etc., complete for finished item of work as per
MoRT&H Specification 401& 408 (5th revision) and as directed by the Engineer-
in-charge.
As per Cross section Enclosed 21912.33
21912.33
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and
4 Cum
compacting with smooth wheel roller of 80 to 100kN / Vibratory Roller 80-100 kN
weight to achieve the desired density including lighting, barricading and
maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical
Specification Clause 406 MORD / MORTH. RBR-SBBS-11.
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.04)
1324.950
As per execution quantity
From Km 0.900 to Km 1.142 1 X 2 242.00 5.50 0.15 399.30
From Km 1.142 to Km 1.162 1 X 2 20.00 6.20 0.15 37.20
From Km 1.162 to Km 1.171 1 X 2 9.00 5.50 0.15 14.85
b/w divider gapFrom Km 0.970 to
1 x 1 27.77 1.20 0.15 5.00
Km 1.171
TOTAL 1781.30
Supply and placing separation membrance of impermeable plastic sheeting 125
5 sqm
micron thick under pavement slab including cost and conveyance etc., complete
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.04)
8833.000
As per execution quantity
From Km 0.900 to Km 1.142 1 X 2 242.00 5.50 2662.00
From Km 1.142 to Km 1.162 1 X 2 20.00 6.20 248.00
From Km 1.162 to Km 1.171 1 X 2 9.00 5.50 99.00
b/w divider gapFrom Km 0.970 to
1 x 1 27.77 1.20 33.32
Km 1.171
TOTAL 11875.32
Vibrated cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) conveyance
of all materials to site and labour charges, centering, machine mixing, laying,
6 cum
vibrating, curing etc., including all other incidental and operational charges of all
T&P etc., complete for finished item of work as per MoRT&H specification 1500,
1700, 2100 & 2702 (5th Revision) and as directed by the Engineer-in-Charge for
C.C Pavement.
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.05)
2296.580
As per execution quantity
From Km 0.900 to Km 1.142 1 X 2 242.00 5.50 (0.32+0.2)/2 692.12
From Km 1.142 to Km 1.162 1 X 2 20.00 6.20 (0.32+0.2)/2 64.48
From Km 1.162 to Km 1.171 1 X 2 9.00 5.50 (0.32+0.2)/2 25.74
b/w divider gapFrom Km 0.200 to
1 x 1 27.77 1.20 (0.32+0.2)/2 8.66
Km 1.050
TOTAL 3087.58
Supply and laying of 110mm dia unplasticized PVC pipes for drainage of water
from median conforming to IS 4985/2000 (3rd rivision ) with bell ends (socket) as
10 Rmt
per specifications in light grey/natural ivory grey/any other colour(except white)
inclusive of transportation, labour charges etc., complete
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.08)
126.000
As per execution quantity
1 x 4 14.00 56.000
182.000
Providing Earth Filling using soil from approved borrow area in layers of 25 to 30
cm before compaction including cost of all materials, machinery, labour, all
operations such as excavation, sorting out, transportation, spreading soil in layer
11 of specified thickness, breaking clods, sectioning,etc.,complete with initial lead
upto 1 km and all lifts.(Goguladinne-I R& R Colony plots filling)Corner numbers:
(493,489,573 and 577:-10 nos)(360,353,412 and 419:-16 no's ) (499,504,562 and
567:12 no's)(361,368,404 and 411: 16 no's)(505,512,544 and 561:-16 no's)
Corner plots no's, 493,489,573 1 X 10 20.00 0.55 1100
and 477 10.00
Corner plots no's, 360,353,412 1 X 13 20.00 0.55 1430
and 419 10.00
Corner plots no's, 499,504,562 1 X 12 20.00 0.55 1320
and 567 10.00
Corner plots no's, 361,368,404 1 X 13 20.00 0.55 1430
and 411 10.00
Corner plots no's, 505,512,544 1 X 20.00 0.55
14 1540
and 561 10.00
6820
Original Estimate No.& Amunt & TS CER NO.06/2019-20 Dt.6.11.2019 Rs. 78,500,000.00
Proceedings No.CE&DWRO/PKM
Revised Estimate&Technical sanction No. and amount DIST/OGL/DEE2/AEE1/ATO/110/Corr.on.Estimates/Vol.3/96 Rs. 56,300,000.00
Dt:28.01.2021
Agreement No and amount 17/2022-23-19, dt. 02.12.2022 Rs. 46,696,659.00
As per Execution (Based on reformulated SOR and Std data for the year 2018-19, after
As per Revised Santioned As per Agreement
As per Original Santioned Estimate implementation of GST) Financial
Estimate1
Sl. No. Description of Work Unit Remarks
PIPE CULVERTS 0.00 0.00 0.00 0 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Earthwork excavation in soils upto SDR by
mechanical means for foundations of structures as per
drawing and technical specification including setting
out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing sides of
1 cum 903 97.82 88352.98 107.00 97.82 10466.74 0.00 0 0.00 107.00 97.82 10467 0.00 0.00 0.00 1891.37 97.82 185014.12 1891.37 174547.38 As Per Site Condition
bottom, back filling the excavation earth to the extent
required etc., complete for finished item of work,
excluding seigniorage charges, as per MoRT&H
specification 304 (5th Revision) and as directed by
the Engineer-in-Charge
Plain Cement Concrete M10 (1:3:6 nominal mix) in
leveling course below open foundation of Head walls
as per drawings & Technical Specification Clause
1109
Providing concrete for plain/reinforced concrete in
2 open foundations using 40 mm nominal size Graded cum 0 0.00 0.00 31.00 4706.58 145903.98 0.00 0 0.00 31.00 4706.58 145904 0.00 0.00 0.00 9.72 4706.58 45747.96 9.72 100156.02 As Per Site Condition
hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH
Bedding for Pipe , (i) Type A (Concrete Cradle)
Bedding. Laying concrete cradle bedding with M15
Grade Cement Concrete as per Clause 1105 (i)
Providing concrete for plain/reinforced concrete in
open foundations using 40 mm nominal size Graded
3 cum 0 0.00 0.00 35.00 4983.25 174413.75 0.00 0 0.00 35.00 4983.25 174414 0.00 0.00 0.00 90.42 4983.25 450576.99 90.42 276163.24 As Per Site Condition
hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH
Vibrated cement concrete M 15 Grade Concrete
using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to
table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) and
conveyance of all materials to site and all labour
4 cum 0 0.00 0.00 195.00 5432.8 1059396.00 0.00 0 0.00 195.00 5432.50 1059338 0.00 0.00 0.00 312.13 5432.80 1695712.70 312.13 636375.20 As Per Site Condition
charges , centering, machine mixing, laying in
position, Compacting, Vibrating and curing including
all other incidental and all other operational charges of
T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (5th Revision) for Sub
Structure (body Walls)
Filling in between body walls with gravel including
cost and conveyance of all materials to site etc.,
complete as per Clause 710.1.4 of IRC : 78 and as
5 cum 0 0.00 0.00 82.00 595 48790.00 0.00 0 0.00 82.00 595.00 48790 0.00 0.00 0.00 81.37 595.00 48412.17 81.37 377.83 As Per Site Condition
per MoRT&H Specification No. 2200 & 2907 (5th
Revision) and as per Drawing and technical
specifications for finished item of work.
As per Execution (Based on reformulated SOR and Std data for the year 2018-19, after
As per Revised Santioned As per Agreement
As per Original Santioned Estimate implementation of GST) Financial
Estimate1
Sl. No. Description of Work Unit Remarks
IRR-CCDW-6-7
Vibrated cement concrete M 15 Grade Concrete using
site and all labour charges for machine mixing,laying cum 193 5632.92 1086251.73 0.00 0.00
all materials to site and all labour charges for cum 217 5950.87 1290743.70 0.00 0.00
Wearing Coat
68794708 57586257 2655414 54930784 2584187 50494483 1396088.94 5883920 As Per Site Condition
NEW ITEMS As Per Site Condition
Formation of Gravel filling including cost, (excluding
seigniorage) charges and conveyance of all materials
to work site and spreading in uniform layers by
approved means, on prepared surface and
1 compacting with vibratory roller to achieve the desired CUM 24000.00 346.97 8327280.00 8327280.00 As Per Site Condition
density at OMC etc., complete for finished item of
work as per MoRT&H Specification 401& 408 (5th
revision) and as directed by the Engineer-in-
charge( VIBRATORY ROLLER 8-10T)
Working Items Total 68794708 57586257 2655414 54930784 2584187 58821763 9723369 5883920
51268835 10987823
As per Execution (Based on reformulated SOR and Std data for the year 2018-19, after
As per Revised Santioned As per Agreement
As per Original Santioned Estimate implementation of GST) Financial
Estimate1
Sl. No. Description of Work Unit Remarks
Execution with ECV rates 61405950 Executed value with tender discount and LS Provisions 65678248
Difference 3247171
% Excess 6.63%
14
RATE ANALYSIS
A. MATERIALS: Unit: 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 Earth 807.00 109.00 87963.00
Total cost of Materials Rs: 87963.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1395.70 3768.39
Fuel / Energy charges Hour 2.70 801.70 2164.59
2 Shovel 0.85 cum capacity Hour 8.00 1388.50 11108.00
Fuel / Energy charges Hour 8.00 1145.70 9165.60
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 363.50 14540.00
Fuel / Energy charges Hour 40.00 393.70 15748.00
Total hire charges of Machinery Rs: 56494.58
C. LABOUR:
ABSTRACT:
A. Cost of Materials Rs: 87963.00
B. Hire charges of Machinery Rs: 56494.58
C. Cost of Labour Rs: 11828.18
Total Rs: 156285.76
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 21278.31
MA @ 20% 20% 2365.64
Total cost for 807.00 cum Rs: 179929.70
Rate
per cum (A+B+C+D)/807 Rs: 222.96
Name of Work-Providing infrastructure facilities such as formation of Internal CC roads, CC Drains and Slab culverts in R&R center of
Goguladinne-II Village of Markapur Mandal to the Pula Subbaiah Veligonda Project Displaced families of Gottipadia (Par
SI. DESCRIPTON
UNIT Qty Cum Qty of Metal Qty of sand Qty of gravel/Earth Total
No OF METERIAL
SI. DESCRIPTON
UNIT Qty Cum Qty of Metal Qty of sand
No OF METERIAL
12672.00
19750.50 cement
12870.00 36036.00 286 405.00 115830
68458.50
Executive Engineer
VGP Division
Markapur
cement
2316.6 451737 286.00 405 115830 2316.6 550424.2
Difference #REF!
241.0714
Price difference for cost of Cement
As per actual Estimate As per New cement policy
Cement Cement
DESCRIPTON Concrete Total cement
Unit Qty 1 Qty per Rate Amount Rate Amount
OF METERIAL Qty Qty
cum bag
1 M10 cum 9.72 220 2138 42.768 195 8339.76 241.07 10310.08
2 M15 cum 3470.10 275.3333 955435 19108.71 195 3726198.00 241.07 4606536.16
3 M30 cum 3659.58 405 1482132 29642.63 195 5780313.31 241.07 7145949.38
9514851 11762796
Abstract M
Agreemen Agt
Sl.No Book Description of Items Unit Rate Up to date
t Item no Quantity
Reference
Gross Amount
Rate
Quantity (in Rs)
CC ROADS
Construction of granular sub-base by providing coarse
199 MRK graded material, spreading in uniform layers with
1 3 Rdr of page motor grader on prepared surface, mixing by mix in 1298 Cum 2248.96 883.30 1986506.37
No.3 place method with rotavator at OMC, and compacting
with vibratory roller to achieve the desired dens
Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
199 MRK
2 4 Rdr of page including premixing the material with water at OMC in 1947 Cum 2976.84 1324.95 3944164.16
No.4
mechanical mixer (Pug Mill), carriage of mixed
material by tipper to site, laying in uniform layers
199 MRK Supply and placing separation membrance of
3 5 Rdr of page impermeable plastic sheeting 125 micron thick under 14080 Sqm 17.33 8833.00 153075.89
No.4 pavement slab including cost and conveyance etc.,
complete
Vibrated cement concrete M 30 grade using 20mm &
10mm HBG crushed stone aggregate (Coarse
199 MRK
aggregate conforming to table 1000-1 and fine
4 6 Rdr of page 3375 Cum 6383.48 2296.58 14660172.50
aggregate conforming to table 1000-2) including cost,
No.5
(excluding seigniorage) conveyance of all materials to
site a
Providing 25.4 mm mastic pads for Longitudinal joints,
199 MRK Transversal expansion joints and Construction joints of
5 7 Rdr of page approved quality including cost, conveyance and 496 sqm 953.00 257.40 245302.20
No.6 placing in position, etc., complete as directed by the
Engineer-in-charge.
Supply and laying of 110mm dia unplasticized PVC
199 MRK pipes for drainage of water from median conforming to
6 10 Rdr of page IS 4985/2000 (3rd rivision ) with bell ends (socket) as 209 Cum 184.06 126 23191.56
No.8 per specifications in light grey/natural ivory grey/any
other colour(except white) inclusive of
CC DRAINS 0
Earth work in excavation in all kinds of soils of
foundation of structures/Drains as per drawing and
199 MRK
technical specification, including setting out,
8 1 Rdr of page 1529 Cum 97.82 1529 149566.78
construction of shoring and bracing, removal of
No.9
stumps and other deleterious matter, dressing of
sides
Earth filling inside of divider walls including cost of all
199 MRK
materials, machinery, labour,spreading to specified
9 2 Rdr of page 972 Cum 144.1 472.23 68048.343
thickness etc., complete with initial lead upto 50 m and
No.9
all lifts.
Vibrated cement concrete M 15 Grade Concrete using
40mm , 20mm and 10mm size HBG crushed stone
199 MRK
aggregate (Coarse aggregate conforming to table
10 3 Rdr of page 1130 Cum 5632.92 913.836 5147565.08112
1000-1 and fine aggregate conforming to table 1000-2)
No.10
including cost and conveyance of all materials to site
a
Vibrated cement concrete M 15 Grade Concrete using
40mm , 20mm and 10mm size HBG crushed stone
199 MRK
aggregate (Coarse aggregate conforming to table
11 4 Rdr of page 2031 Cum 5950.87 1447.146 8611777.72
1000-1 and fine aggregate conforming to table 1000-2)
No.11
including cost,seignorage and conveyance of all
materia
Providing 12.7 mm mastic pads for Longitudinal joints,
199 MRK Transversal expansion joints and Construction joints of
12 5 Rdr of page approved quality including cost, conveyance and 93 Sqm 546 58.32 31842.72
No.12 placing in position, etc., complete as directed by the
Engineer-in-charge.
PIPE CULVETRS 0
Earthwork excavation in soils upto SDR by
199 MRK mechanical means for foundations of structures as per
14 1 Rdr of page drawing and technical specification including setting 107 Cum 97.82 107 10466.74
No.14 out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing sides
Plain Cement Concrete M10 (1:3:6 nominal mix) in
leveling course below open foundation of Head walls
199 MRK as per drawings & Technical Specification Clause
15 2 Rdr of page 31 Cum 4706.58 9.72 45747.9576
No.15 1109
Providing concrete for plain/reinforced concrete in
open foundations using 40 mm nominal size Graded
Bedding for Pipe , (i) Type A (Concrete Cradle)
Bedding. Laying concrete cradle bedding with M15
199 MRK
Grade Cement Concrete as per Clause 1105 (i)
16 3 Rdr of page 35 Cum 4983.25 27.216 135624.132
Providing concrete for plain/reinforced concrete in
No.16
open foundations using 40 mm nominal size Graded
hard stone
Vibrated cement concrete M 15 Grade Concrete using
40mm , 20mm and 10mm size HBG crushed stone
199 MRK
aggregate (Coarse aggregate conforming to table
17 4 Rdr of page 195 Cum 5432.8 136.72 742772.416
1000-1 and fine aggregate conforming to table 1000-2)
No.17
including cost, (excluding seigniorage) and
conveyance o
Filling in between body walls with gravel including
199 MRK cost and conveyance of all materials to site etc.,
18 5 Rdr of page complete as per Clause 710.1.4 of IRC : 78 and as 82 Cum 595 81.365 48412.175
No.18 per MoRT&H Specification No. 2200 & 2907 (5th
Revision) and as per Drawing and technical specif
Manufacture, Supply and Delivery of R.C.C. Socket
199 MRK and Spigot pipes conforming to B.I.S. 458/2003 at ex-
19 6 Rdr of page 63 Rmt 7027.09 62.5 439193.125
No. factory (rate per meter of effective length) Excluding
transportation and all taxes. 1000MM dia NP-3 Class
TOTAL 36443429.86
Tender discount(-14.99%) -5462870.1361849
( Rupees Three Crores Nine lakhs Eighty Thousand Five Hundred and Sixty only) 30980560
Rmt
DATA SHEET
Name of Work:Laying of CC roads in R&R center of Goguladinne Village of Markapur Mandal to the Pula Subbaiah Veligonda Project
Displaced families of Gottipadia (Part) Village of Markapur Mandal, Prakasam district.
2 RBR-SBBS-2
Formation of Gravel filling including cost, (excluding seigniorage) charges and conveyance of all materials to work site and
spreading in uniform layers by approved means, on prepared surface and compacting with vibratory roller to achieve the desired
density at OMC etc., complete for finished item of work as per MoRT&H Specification 401& 408 (5th revision) and as directed by
the Engineer-in-charge. ( Vibratory roller 8-10T)
A. LABOUR:
Sl No Description Unit Quantity Rate
1 Mazdoor skilled day 2.40 440.00
2 Mazdoor unskilled day 8.00 400.00
Total cost of Labour Rs:
B. Machinery:
Sl No Description Unit Quantity Rate
1 Dozer hr 6.00 2454.60
2 Vibratory roller 8-10T hr 6.00 2736.20
3 Water tanker 6 kl capacity hr 3.00 655.20
Total cost of Machinery Rs:
C. Material:
Sl No Description Unit Quantity Rate
1 Gravel cum 384.00 157.53
Total cost of Material Rs:
ABSTRACT:
A. Cost of Labour
B. Hire charges of Machinery
C. Cost of Material
IRR-PMW-3Providing Earth Filling using soil from approved borrow area in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as excavation, sorting out,
(For Minor transportation, spreading soil in layer of specified thickness, breaking clods, sectioning,etc.,complete with
initial lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: Unit: 807.00
Sl No Particulars Unit Quantity Rate
in Rs.
1 Earth 807.00 109.00
Total cost of Materials Rs:
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Angle dozer 90 hp Hour 2.70 1395.70
Fuel / Energy charges Hour 2.70 801.70
2 Shovel 0.85 cum capacity Hour 8.00 1388.50
Fuel / Energy charges Hour 8.00 1145.70
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 363.50
Fuel / Energy charges Hour 40.00 393.70
Total hire charges of Machinery Rs:
C. LABOUR:
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs.
MA @ 20% 20%
Total cost for 807.00 cum Rs:
Rate
per cum (A+B+C+D)/807 Rs:
cum
Amount
1056.00
3200.00
4256.00
Amount
14727.60
16417.20
1965.60
33110.40
Amount
60491.11
60491.11
4256.00
33110.40
60491.11
97857.51
13323.30
851.20
112032.01
373.44
to 30 cm before compaction
as excavation, sorting out,
ectioning,etc.,complete with
cum
Amount
in Rs
87963.00
87963.00
Amount
in Rs
3768.39
2164.59
11108.00
9165.60
14540.00
15748.00
56494.58
Amount
in Rs
694.98
2059.20
7724.00
550.00
800.00
11828.18
87963.00
56494.58
11828.18
156285.76
21278.31
2365.64
179929.70
222.96
ecutive Engineer
VGP Division
Markapur
LEAD STATEMENT
Name of Work:Laying of CC roads in R&R center of Goguladinne Village of Markapur Mandal to the Pula Subbaiah Veligonda Project Displaced families of Gottipadia (Part) Village
of Markapur Mandal, Prakasam district.
Conveyyance
Intial Cost Charges Machine
S SS Item Source of Lead excluding Conveyanc excluding Blasting Crushing
Name of the Material Unit
No No. Supply in Km Seigniorag e charges 13.615% Charges Charges
e Contractor @25%
profit
1 2 3 4 5 6 7 9 10 11
4 Gravel M-008 Cum Local 5 110.00 54.00 -6.47
5 Earth Cum Local 5 55.00 54.00 -6.47
Certificate:
1) Certified that the above leads are verified and found correct to the best of my knowledge.
Total
(7+8+9-10)
12
157.53
102.53
DETAILED ESTIMATE FOR CC DRAINS
S.
Unit Description No L B D Quantity
No.
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including
1 Cum setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom and backfilling with approved material. Depth upto 3m.
DRAINS& Divider
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.9) 1986.770
As per execution quantity
From Km 0.000 to 0.025 L/s 1 X 1 25.00 1.50 (0.50+0.53)/2 19.50
From Km 0.025 to 0.050 L/s 1 X 1 25.00 1.50 (0.53+0.56)/2 20.63
From Km 0.050 to 0.075 L/s 1 X 1 25.00 1.50 (0.56+0.58)/2 21.37
From Km 0.075 to 0.097 L/s 1 X 1 22.00 1.50 (0.58+0.60)/2 19.47
From Km 1.000 to 1.025 L/s 1 X 1 25.00 1.50 (0.79+0.89)/2 31.50
From Km 1.025to 1.050 L/s 1 X 1 25.00 1.50 (0.89+0.78)/2 31.50
From Km 1.050to 1.075L/s 1 X 1 25.00 1.50 (0.78+0.98)/2 33.00
From Km 1.075to 1.100 L/s 1 X 1 25.00 1.50 (0.98+0.91)/2 35.63
From Km 1.100to 1.125 L/s 1 X 1 25.00 1.50 (0.91+0.85)/2 33.00
From Km 1.125to 1.150L/s 1 X 1 25.00 1.50 (0.85+0.68)/2 28.88
From Km 1.150to 1.175 L/s 1 X 1 25.00 1.50 (0.89+0.88)/2 33.38
From Km 1.175to 1.180 L/s 1 X 1 25.00 1.50 (0.88+0.66)/2 28.88
From Km 1.000 to 1.025 R/s 1 X 1 25.00 1.50 (1.1+1.12)/2 41.63
From Km 1.025to 1.050 R/s 1 X 1 25.00 1.50 (1.12+0.99)/2 39.75
From Km 1.050to 1.075R/s 1 X 1 25.00 1.50 (0.99+1.06)/2 38.63
From Km 1.075to 1.100 R/s 1 X 1 25.00 1.50 (1.06+0.9)/2 36.75
From Km 1.100to 1.125 R/s 1 X 1 25.00 1.50 (0.9+1.11)/2 37.88
From Km 1.125to 1.150R/s 1 X 1 25.00 1.50 (1.11+1.05)/2 40.50
From Km 1.150to 1.175 R/s 1 X 1 25.00 1.50 (1.05+0.85)/2 35.63
From Km 1.175to 1.180 R/s 1 X 1 25.00 1.50 (0.85+0.71)/2 29.25
Divider
From Km 0.000 to 0.097 1 X 1 97.00 1.40 0.23 31.234
From Km 1.000 to 1.142 1 X 1 142.00 1.40 0.23 45.724
2700.45
Earth filling inside of divider walls including cost of all materials, machinery, labour,spreading to specified thickness etc.,
2 Cum
complete with initial lead upto 50 m and all lifts.
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.9) 472.230
As per execution quantity
From Km 0.000 to 0.097 1 X 1 97.00 (0.40+0.80)/2 0.90 52.38
From Km 1.000 to 1.142 1 X 1 142.00 (0.40+0.80)/2 0.90 76.68
601.29
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost and
3 Cum conveyance of all materials to site and all labour charges for machine mixing,laying in position, Compacting , Vibrating and
curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2100,2700 (5th Revision) for for bed concrete
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.10) 913.836
As per execution quantity
From Km 0.000 to 0.097 for drains 1 X 2 97.00 1.50 0.23 66.93
From Km 1.000 to 1.1800 for drains 1 X 2 180.00 1.50 0.23 124.2
From Km 0.000 to 0.097 for divider 1 X 1 97.00 1.40 0.23 31.234
From Km 1.000 to 1.150 for divider 1 X 1 150.00 1.40 0.23 48.3
Total 1184.50
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate
4 Cum (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,seignorage
and conveyance of all materia
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.11) 1447.146
As per execution quantity
From Km 0.000 to 0.097 for drains 2 X 2 97.00 (0.40+0.20)/2 0.90 104.76
From Km 1.000 to 1.180 for drains 2 X 2 180.00 (0.40+0.20)/2 0.90 194.4
From Km 0.000 to 0.097 for divider 1 X 2 97.00 (0.40+0.20)/2 0.90 52.38
From Km 1.000 to 1.142 for divider 1 X 2 142.00 (0.40+0.20)/2 0.90 76.68
Divider gaps round shapes 1 x 19 (1.2+1.8)/2 (0.40+0.20)/2 0.90 7.695
1883.06
Providing 25.4 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of approved
Rmt
quality including cost, conveyance and placing in position, etc., complete as directed by the Engineer-in-charge.
5 As per Execution quantity( Reference MB.No.199 mrk R&R Page No.12) 58.320
As per execution quantity
Drain 10 x 6 (0.40+0.20)/2 0.90 16.2
Divider 10 x 4 (0.40+0.20)/2 0.90 10.8
85.32
Manufacture, Supply and Delivery of R.C.C. Socket and Spigot pipes conforming to B.I.S. 458/2003 at ex-factory (rate per
Rmt meter of effective length) including transportation and all taxes. NP-2 Class (For Water pipe line and Cables crossing at
Road junctions)
6 As per Execution quantity( Reference MB.No.199 mrk R&R Page No.12) 58.320
As per execution quantity 58.320
1 Cum specification, including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3m.
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.14) 342.14
As per execution quantity
Front left side Protection wall 1 X 1 10.95 1.8 2.00 72.93
Front right side Protection wall 1 X 1 9.15 1.8 2.00 60.94
back Left side Protection wall 1 X 1 12 1.8 2.00 79.92
Back right side Protection wall 1 X 1 11.5 1.8 2.00 76.59
Apron
Upstream 1 X (27.50+25.40+9.70)/3
1 (4.05+5.25+3.00)/3 (0.2+0.40)/2 25.67
Cutoff 1 X 1 31.55 0.3 0.30 2.84
Vagu portion 1 X 1 20 30 0.50 300.00
Downstream 1 X 1 (26+25+9.70)/3
(2.80+4.50+3.00)/3 (0.2+0.40+0.6)/3 27.76
Cutoff 1 X 1 28.8 0.3 0.30 2.59
Vagu portion 1 X 1 50 30 0.60 900.00
Total 1891.37
Plain Cement Concrete M10 (1:3:6 nominal mix) in leveling course below open foundation of Head walls
as per drawings & Technical Specification Clause 1109
Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size Graded
2 Cum hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including
curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203
MORD and 1500, 1700 & 2100 MORTH
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.15) 9.72
TOTAL 10
Bedding for Pipe , (i) Type A (Concrete Cradle) Bedding. Laying concrete cradle bedding with M15 Grade
Cement Concrete as per Clause 1105 (i) Providing concrete for plain/reinforced concrete in open
3 Cum foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.16) 27.22
Protectin wall
Front left side Protection wall 1 X 1 10.95 1.8 0.30 5.91
Front right side Protection wall 1 X 1 9.15 1.8 0.30 4.94
back Left side Protection wall 1 X 1 12 1.8 0.30 6.48
Back right side Protection wall 1 X 1 11.5 1.8 0.30 6.21
Apron
Upstream 1 X 1
(27.50+25.40+9.70)/3
(4.05+5.25+3.00)/3 0.20 17.11
Cutoff 1 X 1 31.55 0.3 0.30 2.84
Downstream 1 X 1 (26+25+9.70)/3
(2.80+4.50+3.00)/3 0.20 17.11
Cutoff 1 X 1 28.8 0.3 0.30 2.59
Total 90.42
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
4 Cum aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,
centering, machine mixing, laying in position, Compacting, Vibrating and curing including all other
incidental and all other
As per Execution operational
quantity( charges
Reference of T&P required
MB.No.199 mrk R&Retc.,
Pagecomplete
No.17) as per MoRT&H Specification
136.72
1500,1700, 2200 (5th Revision) for Sub Structure (body Walls)
Front left side Protection wall 1 X 1 10.95 (1.50+0.5)/2 4.05 44.35
Front right side Protection wall 1 X 1 9.15 (1.50+0.5)/2 4.05 37.06
back Left side Protection wall 1 X 1 12 (1.50+0.5)/2 4.00 48.00
Back right side Protection wall 1 X 1 11.5 (1.50+0.5)/2 4.00 46.00
TOTAL 312.13
Filling in between body walls with gravel including cost and conveyance of all materials to site etc.,
5 complete as per Clause 710.1.4 of IRC : 78 and as per MoRT&H Specification No. 2200 & 2907 (5th
Revision) and as per Drawing and technical specifications for finished item of work.
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.17) 81.37
81.37
Manufacture, Supply and Delivery of R.C.C. Socket and Spigot pipes conforming to B.I.S. 458/2003 at ex-
6 Rmt
factory (rate per meter of effective length) Excluding transportation and all taxes. 1000MM dia NP-3 Class
As per Execution quantity( Reference MB.No.199 mrk R&R Page No.18) 62.50
62.50
Name of Work:Part of balance work of " Providing infrastructure facilities such as formation ofinternal CC roads, CC Drains and Slab culverts in R&R
center of Goguladinne Village of Markapur Mandal to the Pula Subbaiah Veligonda Project Displaced families of Gottipadia (Part) Village of Markapur
Name of work:-
Mandal, Prakasam district'' deleted under clause PS 60C of APDSS from the scope of agreement no.01/2020-21 date.03.06.2020 supplemental agrrement no.
52/2020-21 date.01.02.2021.
CC ROADS
Excavation for road work in soil with hydraulic excavator of 0.90 Cum bucket capacity including cutting and
1 2138 loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross 79.79 170591
2 7370 work site and spreading in uniform layers by approved means, on prepared surface and compacting with 284.91 2099787
4 1947 including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed 2976.84 5795907
6 3375 conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding 6383.48 21544245
9 2048 materials to work site and spreading in uniform layers by approved means, on prepared surface and 284.91 583496
CC DRAINS 0
Earth work in excavation in all kinds of soils of foundation of structures/Drains as per drawing and technical
1 1529 specification, including setting out, construction of shoring and bracing, removal of stumps and other 97.82 149567
deleterious matter, dressing of sides
Earth filling inside of divider walls including cost of all materials, machinery, labour,spreading to specified
2 972 144.1 140065
thickness etc., complete with initial lead upto 50 m and all lifts.
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
3 1130 aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) 5632.92 6365200
4 2031 aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) 5950.87 12086217
PIPE CULVERTS 0
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
1 107 and technical specification including setting out, construction of shoring and bracing, removal of stumps and 97.82 10467
Bedding for Pipe , (i) Type A (Concrete Cradle) Bedding. Laying concrete cradle bedding with M15 Grade
3 35 Cement Concrete as per Clause 1105 (i) Providing concrete for plain/reinforced concrete in open foundations 4983.25 174414
using 40 mm nominal size Graded hard stone
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
4 195 aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) 5432.8 1059396
including cost, (excluding seigniorage) and conveyance o
Filling in between body walls with gravel including cost and conveyance of all materials to site etc., complete
5 82 as per Clause 710.1.4 of IRC : 78 and as per MoRT&H Specification No. 2200 & 2907 (5th Revision) and as 595 48790
per Drawing and technical specif
Manufacture, Supply and Delivery of R.C.C. Socket and Spigot pipes conforming to B.I.S. 458/2003 at ex-
6 63 7027.09 442707
factory (rate per meter of effective length) Excluding transportation and all taxes. 1000MM dia NP-3 Class
Laying and jointing 1000 mm dia. NP- 3 class or IRC standard hume pipes in CM 1 : 2 proportion by volume
7 20 including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with 906.49 18130
hemp, finishing, curing etc., comple
Contractor
Executive Engineer
Investigation Division
Cumbum
DATA WITH REFORMULATED SSR 2016-17
S. Measurements
Description of work Nos Quantity Unit
No. L B D
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back
1
filling the excavation earth to the extent required etc., complete for finished item of work,
excluding seigniorage charges, as per MoRT&H specification 304 (5th Revision) and as
directed by the Engineer-in-Charge
Foundation for Body walls 1 2 30.00 1.90 0.65 74.10
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost and conveyance of all materials to site and all
2
labour charges for machine mixing,laying in position, Compacting , Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete
as per MoRT&H Specification 1500,1700, 2100 (5th Revision) for foundation .
Foundation for Body walls 1 2 30.00 1.90 0.30 34.20
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
3 including cost and conveyance of all materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other incidental and all other operational charges of
T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision)
for Body walls 1 2 30.00 (1.5+0.5)/2 1.10 66.00
22.50
culverts 2 nos 1 22.50
Say 22.50 RM
Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to site and
labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and
5
operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement. for foundations
Bed concrete 1 1 30.00 (6.22+6.08)/2 0.10 15.69
15.69
15.69
culverts 2 nos 2 15.69
Say 16.00 Cum
Providing and laying insitu vibrated M-30 (28 days cube compressive strength not less than 30 N/sq mm)
grade cement conrete using 20mm down size approved, clean, hard, graded aggregates for CC 8 Road
6 Pavements including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing
in position, levelling.vibrating, finishing, curing,etc., Complete with initial lead upto
50M and all lifts.
c 1 1 30.00 7.50 0.200 45.00
45.00
45.00
S. Measurements
Description of work Nos Quantity Unit
No. L B D
Earthwork excavation in soils upto SDR by mechanical means for foundations of
structures as per drawing and technical specification including setting out,
construction of shoring and bracing, removal of stumps and other deleterious
1 matter, dressing sides of bottom, back filling the excavation earth to the extent
required etc., complete for finished item of work, excluding seigniorage charges,
as per MoRT&H specification 304 (5th Revision) and as directed by the Engineer-
in-Charge
Foundation for Body walls 1 2 45.00 1.90 2.40 410.40
22.50
Say 22.50 RM
Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying,
5 Vibrating, curing etc., including all other incidental and operational charges of all T&P etc.,
complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th
Revision) and as directed by the Engineer-in-Charge for base coarse below CC Pavement.for
foundations
Bed concrete 1 1 39.40 (6.30+6.22)/ 0.10 24.66
2 24.66
24.66
Say 25.00 Cum
Providing and laying insitu vibrated M-30 (28 days cube compressive strength not less than 30
N/sq mm) grade cement conrete using 20mm down size approved, clean, hard, graded
6 aggregates for CC 8 Road Pavements including cost of all materials, machinery, labour,
formwork, cleaning, batching, mixing, placing in position, levelling.vibrating, finishing,
curing,etc., Complete with initial lead upto 50M and all lifts.
1 1 45.00 7.50 0.200 67.50
67.50
67.50
Say 68.00
Cum
S. Measurements
Description of work Nos Quantity Unit
No. L B D
1 Earthwork excavation in soils upto SDR by mechanical means for
foundations of structures as per drawing and technical specification
including setting out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing sides of bottom, back
filling the excavation earth to the extent required etc., complete for
finished item of work, excluding seigniorage charges, as per MoRT&H
specification 304 (5th Revision) and as directed by the Engineer-in-
Charge
Foundation for Body walls 1 2 55.00 1.90 2.50 522.50
22.50
Say 22.50 RM
6 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG
crushed stone aggregate and fine aggregate conforming to table 1000-2 of
MoRT&H including cost, conveyance of all materials to site and labour
charges, centering, machine mixing, laying, Vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision)
and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
7 Providing and laying insitu vibrated M-30 (28 days cube compressive strength
not less than 30 N/sq mm) grade cement conrete using 20mm down size
approved, clean, hard, graded aggregates for CC 8 Road Pavements including
cost of all materials, machinery, labour, formwork, cleaning, batching, mixing,
placing in position, levelling.vibrating, finishing, curing,etc., Complete with initial
lead upto 50M and all lifts.
For slab 1 1 55.00 7.50 0.200 82.50
82.50
82.50
Say 83.00
Cum
PIPE CULVERTS 2
Executive Engineer
Investigation Division
Cumbum
Err:540
380325.00
22788.20
Err:540
63,81,228
63,81,228 ###
4 WMM
From Km 0.097 to 0.100 L/s 1 X 1 3.00
From Km 0.100 to 0.125 L/s 1 X 1 25.00
From Km 0.125 to 0.150 L/s 1 X 1 25.00
From Km 0.150 to 0.175 L/s 1 X 1 25.00
From Km 0.175 to 0.200 L/s 1 X 1 25.00
From Km 0.200 to 0.225 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.200 to
1 1 1 0.70
0.225 L/s
From Km 0.225 to 0.250 L/s 1 X 1 25.00
From Km 0.250 to 0.275 L/s 1 X 1 25.00
From Km 0.275 to 0.300 L/s 1 X 1 25.00
From Km 0.300 to 0.325 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.300 to
1 1 1 6.10
0.325 L/s
From Km 0.325 to 0.350 L/s 1 X 1 25.00
From Km 0.350 to 0.375 L/s 1 X 1 25.00
From Km 0.375 to 0.400 L/s 1 X 1 25.00
From Km 0.400 to 0.425 L/s 1 X 1 25.00
b/w divider gap From Km 0.400
1 1 1 0.55
to 0.425 L/s
From Km 0.425 to 0.450 L/s 1 X 1 25.00
From Km 0.450 to 0.475 L/s 1 X 1 25.00
From Km 0.475 to 0.500 L/s 1 X 1 25.00
From Km 0.500 to 0.525 L/s 1 X 1 25.00
b/w divider gap From Km 0.500
1 1 1 6.70
to 0.525 L/s
From Km 0.525 to 0.550 L/s 1 X 1 25.00
From Km 0.550 to 0.575 L/s 1 X 1 25.00
From Km 0.575 to 0.600 L/s 1 X 1 25.00
From Km 0.600 to 0.625 L/s 1 X 1 25.00
b/w divider gap From Km 0.600
1 1 1 0.50
to 0.625 L/s
From Km 0.625 to 0.650 L/s 1 X 1 25.00
From Km 0.650 to 0.675 L/s 1 X 1 25.00
From Km 0.675 to 0.700 L/s 1 X 1 25.00
From Km 0.700 to 0.725 L/s 1 X 1 25.00
b/w divider gap From Km 0.700
1 1 1 0.42
to 0.725 L/s
From Km 0.725 to 0.750 L/s 1 X 1 25.00
From Km 0.750 to 0.775 L/s 1 X 1 25.00
From Km 0.775 to 0.800 L/s 1 X 1 25.00
From Km 0.800 to 0.825 L/s 1 X 1 25.00
From Km 0.825 to 0.850 L/s 1 X 1 25.00
b/w divider gap From Km 0.825
1 1 1 0.50
to 0.850 L/s
From Km 0.850 to 0.875 L/s 1 X 1 25.00
From Km 0.875 to 0.900 L/s 1 X 1 25.00
From Km 0.900 to 0.925 L/s 1 X 1 25.00
From Km 0.925 to 0.950 L/s 1 X 1 25.00
b/w divider gap From Km 0.925
1 1 1 11.80
to 0.950 L/s
From Km 0.950 to 0.975 L/s 1 X 1 25.00
From Km 0.975 to 1.000 L/s 1 X 1 25.00
From Km 1.000 to 1.025 L/s 1 X 1 25.00
From Km 1.025to 1.050 L/s 1 X 1 25.00
b/w divider gap From Km 1.025to
1 1 1 0.50
1.050 L/s
From Km 1.050to 1.075L/s 1 X 1 25.00
From Km 1.075to 1.100 L/s 1 X 1 25.00
From Km 1.100to 1.125 L/s 1 X 1 25.00
From Km 1.125to 1.142L/s 1 X 1 17.00
From Km 1.142to 1.162 L/s 1 X 1 20.00
From Km 1.162to 1.171 L/s 1 X 1 9.00
From Km 0.097 to 0.100 R/s 1 X 1 3.00
From Km 0.100 to 0.125 R/s 1 X 1 25.00
From Km 0.125 to 0.150 R/s 1 X 1 25.00
From Km 0.150 to 0.175 R/s 1 X 1 25.00
From Km 0.175 to 0.200 R/s 1 X 1 25.00
From Km 0.200 to 0.225 R/s 1 X 1 25.00
From Km 0.225 to 0.250 R/s 1 X 1 25.00
From Km 0.250 to 0.275 R/s 1 X 1 25.00
From Km 0.275 to 0.300 R/s 1 X 1 25.00
From Km 0.300 to 0.325 R/s 1 X 1 25.00
From Km 0.325 to 0.350 R/s 1 X 1 25.00
From Km 0.350 to 0.375 R/s 1 X 1 25.00
From Km 0.375 to 0.400 R/s 1 X 1 25.00
From Km 0.400 to 0.425 R/s 1 X 1 25.00
From Km 0.425 to 0.450 R/s 1 X 1 25.00
From Km 0.450 to 0.475 R/s 1 X 1 25.00
From Km 0.475 to 0.500 R/s 1 X 1 25.00
From Km 0.500 to 0.525 R/s 1 X 1 25.00
From Km 0.525 to 0.550 R/s 1 X 1 25.00
From Km 0.550 to 0.575 R/s 1 X 1 25.00
From Km 0.575 to 0.600 R/s 1 X 1 25.00
From Km 0.600 to 0.625 R/s 1 X 1 25.00
From Km 0.625 to 0.650 R/s 1 X 1 25.00
From Km 0.650 to 0.675 R/s 1 X 1 25.00
From Km 0.675 to 0.700 R/s 1 X 1 25.00
From Km 0.700 to 0.725 R/s 1 X 1 25.00
From Km 0.725 to 0.750 R/s 1 X 1 25.00
From Km 0.750 to 0.775 R/s 1 X 1 25.00
From Km 0.775 to 0.800 R/s 1 X 1 25.00
From Km 0.800 to 0.825 R/s 1 X 1 25.00
From Km 0.825 to 0.850 R/s 1 X 1 25.00
From Km 0.850 to 0.875 R/s 1 X 1 25.00
From Km 0.875 to 0.900 R/s 1 X 1 25.00
From Km 0.900 to 0.925 R/s 1 X 1 25.00
From Km 0.950 to 0.975 R/s 1 X 1 25.00
From Km 0.975 to 1.000 R/s 1 X 1 25.00
From Km 1.000 to 1.025 R/s 1 X 1 25.00
From Km 1.025to 1.050 R/s 1 X 1 25.00
From Km 1.050to 1.075R/s 1 X 1 25.00
From Km 1.075to 1.100 R/s 1 X 1 25.00
From Km 1.100to 1.125 R/s 1 X 1 25.00
From Km 1.125to 1.142R/s 1 X 1 17.00
From Km 1.142to 1.162 R/s 1 X 1 20.00
From Km 1.162to 1.17 R/s 1 X 1 9.00
TOTAL
5 Plastic sheet
From Km 0.097 to 0.100 L/s 1 X 1 3.00
From Km 0.100 to 0.125 L/s 1 X 1 25.00
From Km 0.125 to 0.150 L/s 1 X 1 25.00
From Km 0.150 to 0.175 L/s 1 X 1 25.00
From Km 0.175 to 0.200 L/s 1 X 1 25.00
From Km 0.200 to 0.225 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.200 to
1 1 1 0.70
0.225 L/s
From Km 0.225 to 0.250 L/s 1 X 1 25.00
From Km 0.250 to 0.275 L/s 1 X 1 25.00
From Km 0.275 to 0.300 L/s 1 X 1 25.00
From Km 0.300 to 0.325 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.300 to
1 1 1 6.10
0.325 L/s
From Km 0.325 to 0.350 L/s 1 X 1 25.00
From Km 0.350 to 0.375 L/s 1 X 1 25.00
From Km 0.375 to 0.400 L/s 1 X 1 25.00
From Km 0.400 to 0.425 L/s 1 X 1 25.00
b/w divider gap From Km 0.400
1 1 1 0.55
to 0.425 L/s
From Km 0.425 to 0.450 L/s 1 X 1 25.00
From Km 0.450 to 0.475 L/s 1 X 1 25.00
From Km 0.475 to 0.500 L/s 1 X 1 25.00
From Km 0.500 to 0.525 L/s 1 X 1 25.00
b/w divider gap From Km 0.500
1 1 1 6.70
to 0.525 L/s
From Km 0.525 to 0.550 L/s 1 X 1 25.00
From Km 0.550 to 0.575 L/s 1 X 1 25.00
From Km 0.575 to 0.600 L/s 1 X 1 25.00
From Km 0.600 to 0.625 L/s 1 X 1 25.00
b/w divider gap From Km 0.600
1 1 1 0.50
to 0.625 L/s
From Km 0.625 to 0.650 L/s 1 X 1 25.00
From Km 0.650 to 0.675 L/s 1 X 1 25.00
From Km 0.675 to 0.700 L/s 1 X 1 25.00
From Km 0.700 to 0.725 L/s 1 X 1 25.00
b/w divider gap From Km 0.700
1 1 1 0.42
to 0.725 L/s
From Km 0.725 to 0.750 L/s 1 X 1 25.00
From Km 0.750 to 0.775 L/s 1 X 1 25.00
From Km 0.775 to 0.800 L/s 1 X 1 25.00
From Km 0.800 to 0.825 L/s 1 X 1 25.00
From Km 0.825 to 0.850 L/s 1 X 1 25.00
b/w divider gap From Km 0.825
1 1 1 0.50
to 0.850 L/s
From Km 0.850 to 0.875 L/s 1 X 1 25.00
From Km 0.875 to 0.900 L/s 1 X 1 25.00
From Km 0.900 to 0.925 L/s 1 X 1 25.00
From Km 0.925 to 0.950 L/s 1 X 1 25.00
b/w divider gap From Km 0.925
1 1 1 11.80
to 0.950 L/s
From Km 0.950 to 0.975 L/s 1 X 1 25.00
From Km 0.975 to 1.000 L/s 1 X 1 25.00
From Km 1.000 to 1.025 L/s 1 X 1 25.00
From Km 1.025to 1.050 L/s 1 X 1 25.00
b/w divider gap From Km 1.025to
1 1 1 0.50
1.050 L/s
From Km 1.050to 1.075L/s 1 X 1 25.00
From Km 1.075to 1.100 L/s 1 X 1 25.00
From Km 1.100to 1.125 L/s 1 X 1 25.00
From Km 1.125to 1.142L/s 1 X 1 17.00
From Km 1.142to 1.162 L/s 1 X 1 20.00
From Km 1.162to 1.171 L/s 1 X 1 9.00
From Km 0.097 to 0.100 R/s 1 X 1 3.00
From Km 0.100 to 0.125 R/s 1 X 1 25.00
From Km 0.125 to 0.150 R/s 1 X 1 25.00
From Km 0.150 to 0.175 R/s 1 X 1 25.00
From Km 0.175 to 0.200 R/s 1 X 1 25.00
From Km 0.200 to 0.225 R/s 1 X 1 25.00
From Km 0.225 to 0.250 R/s 1 X 1 25.00
From Km 0.250 to 0.275 R/s 1 X 1 25.00
From Km 0.275 to 0.300 R/s 1 X 1 25.00
From Km 0.300 to 0.325 R/s 1 X 1 25.00
From Km 0.325 to 0.350 R/s 1 X 1 25.00
From Km 0.350 to 0.375 R/s 1 X 1 25.00
From Km 0.375 to 0.400 R/s 1 X 1 25.00
From Km 0.400 to 0.425 R/s 1 X 1 25.00
From Km 0.425 to 0.450 R/s 1 X 1 25.00
From Km 0.450 to 0.475 R/s 1 X 1 25.00
From Km 0.475 to 0.500 R/s 1 X 1 25.00
From Km 0.500 to 0.525 R/s 1 X 1 25.00
From Km 0.525 to 0.550 R/s 1 X 1 25.00
From Km 0.550 to 0.575 R/s 1 X 1 25.00
From Km 0.575 to 0.600 R/s 1 X 1 25.00
From Km 0.600 to 0.625 R/s 1 X 1 25.00
From Km 0.625 to 0.650 R/s 1 X 1 25.00
From Km 0.650 to 0.675 R/s 1 X 1 25.00
From Km 0.675 to 0.700 R/s 1 X 1 25.00
From Km 0.700 to 0.725 R/s 1 X 1 25.00
From Km 0.725 to 0.750 R/s 1 X 1 25.00
From Km 0.750 to 0.775 R/s 1 X 1 25.00
From Km 0.775 to 0.800 R/s 1 X 1 25.00
From Km 0.800 to 0.825 R/s 1 X 1 25.00
From Km 0.825 to 0.850 R/s 1 X 1 25.00
From Km 0.850 to 0.875 R/s 1 X 1 25.00
From Km 0.900 to 0.925 R/s 1 X 1 25.00
From Km 0.925 to 0.950 R/s 1 X 1 25.00
From Km 0.950 to 0.975 R/s 1 X 1 25.00
From Km 0.975 to 1.000 R/s 1 X 1 25.00
From Km 1.000 to 1.025 R/s 1 X 1 25.00
From Km 1.025to 1.050 R/s 1 X 1 25.00
From Km 1.050to 1.075R/s 1 X 1 25.00
From Km 1.075to 1.100 R/s 1 X 1 25.00
From Km 1.100to 1.125 R/s 1 X 1 25.00
From Km 1.125to 1.142R/s 1 X 1 17.00
From Km 1.142to 1.162 R/s 1 X 1 20.00
From Km 1.162to 1.171 R/s 1 X 1 9.00
TOTAL
6 VCC M30
From Km 0.097 to 0.100 L/s 1 X 1 3.00
From Km 0.100 to 0.125 L/s 1 X 1 25.00
From Km 0.125 to 0.150 L/s 1 X 1 25.00
From Km 0.150 to 0.175 L/s 1 X 1 25.00
From Km 0.175 to 0.200 L/s 1 X 1 25.00
From Km 0.200 to 0.225 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.200 to
1 X 1 0.70
0.225 L/s
From Km 0.225 to 0.250 L/s 1 X 1 25.00
From Km 0.250 to 0.275 L/s 1 X 1 25.00
From Km 0.275 to 0.300 L/s 1 X 1 25.00
From Km 0.300 to 0.325 L/s 1 X 1 25.00
b/w divider gapFrom Km 0.300 to
1 X 1 6.10
0.325 L/s
From Km 0.325 to 0.350 L/s 1 X 1 25.00
From Km 0.350 to 0.375 L/s 1 X 1 25.00
From Km 0.375 to 0.400 L/s 1 X 1 25.00
From Km 0.400 to 0.425 L/s 1 X 1 25.00
b/w divider gap From Km 0.400
1 1 1 0.55
to 0.425 L/s
From Km 0.425 to 0.450 L/s 1 X 1 25.00
From Km 0.450 to 0.475 L/s 1 X 1 25.00
From Km 0.475 to 0.500 L/s 1 X 1 25.00
From Km 0.500 to 0.525 L/s 1 X 1 25.00
b/w divider gap From Km 0.500
1 1 1 6.70
to 0.525 L/s
From Km 0.525 to 0.550 L/s 1 X 1 25.00
From Km 0.550 to 0.575 L/s 1 X 1 25.00
From Km 0.575 to 0.600 L/s 1 X 1 25.00
From Km 0.600 to 0.625 L/s 1 X 1 25.00
b/w divider gap From Km 0.600
1 1 1 0.50
to 0.625 L/s
From Km 0.625 to 0.650 L/s 1 X 1 25.00
From Km 0.650 to 0.675 L/s 1 X 1 25.00
From Km 0.675 to 0.700 L/s 1 X 1 25.00
From Km 0.700 to 0.725 L/s 1 X 1 25.00
b/w divider gap From Km 0.700
1 1 1 0.42
to 0.725 L/s
From Km 0.725 to 0.750 L/s 1 X 1 25.00
From Km 0.750 to 0.775 L/s 1 X 1 25.00
From Km 0.775 to 0.800 L/s 1 X 1 25.00
From Km 0.800 to 0.825 L/s 1 X 1 25.00
From Km 0.825 to 0.850 L/s 1 X 1 25.00
b/w divider gap From Km 0.825
1 X 1 0.50
to 0.850 L/s
From Km 0.850 to 0.875 L/s 1 X 1 25.00
From Km 0.875 to 0.900 L/s 1 X 1 25.00
From Km 0.900 to 0.925 L/s 1 X 1 25.00
From Km 0.925 to 0.950 L/s 1 X 1 25.00
b/w divider gap From Km 0.925
1 X 1 11.80
to 0.950 L/s
From Km 0.950 to 0.975 L/s 1 X 1 25.00
From Km 0.975 to 1.000 L/s 1 X 1 25.00
From Km 1.000 to 1.025 L/s 1 X 1 25.00
From Km 1.025to 1.050 L/s 1 X 1 25.00
b/w divider gap From Km 1.025to
1 1 1 0.50
1.050 L/s
From Km 1.050to 1.075L/s 1 X 1 25.00
From Km 1.075to 1.100 L/s 1 X 1 25.00
From Km 1.100to 1.125 L/s 1 X 1 25.00
From Km 1.125to 1.142L/s 1 X 1 17.00
From Km 1.150to 1.162 L/s 1 X 1 20.00
From Km 1.150to 1.171 L/s 1 X 1 9.00
From Km 0.097 to 0.100 R/s 1 X 1 3.00
From Km 0.100 to 0.125 R/s 1 X 1 25.00
From Km 0.125 to 0.150 R/s 1 X 1 25.00
From Km 0.150 to 0.175 R/s 1 X 1 25.00
From Km 0.175 to 0.200 R/s 1 X 1 25.00
From Km 0.200 to 0.225 R/s 1 X 1 25.00
From Km 0.225 to 0.250 R/s 1 X 1 25.00
From Km 0.250 to 0.275 R/s 1 X 1 25.00
From Km 0.275 to 0.300 R/s 1 X 1 25.00
From Km 0.300 to 0.325 R/s 1 X 1 25.00
From Km 0.325 to 0.350 R/s 1 X 1 25.00
From Km 0.350 to 0.375 R/s 1 X 1 25.00
From Km 0.375 to 0.400 R/s 1 X 1 25.00
From Km 0.400 to 0.425 R/s 1 X 1 25.00
From Km 0.425 to 0.450 R/s 1 X 1 25.00
From Km 0.450 to 0.475 R/s 1 X 1 25.00
From Km 0.475 to 0.500 R/s 1 X 1 25.00
From Km 0.500 to 0.525 R/s 1 X 1 25.00
From Km 0.525 to 0.550 R/s 1 X 1 25.00
From Km 0.550 to 0.575 R/s 1 X 1 25.00
From Km 0.575 to 0.600 R/s 1 X 1 25.00
From Km 0.600 to 0.625 R/s 1 X 1 25.00
From Km 0.625 to 0.650 R/s 1 X 1 25.00
From Km 0.650 to 0.675 R/s 1 X 1 25.00
From Km 0.675 to 0.700 R/s 1 X 1 25.00
From Km 0.700 to 0.725 R/s 1 X 1 25.00
From Km 0.725 to 0.750 R/s 1 X 1 25.00
From Km 0.750 to 0.775 R/s 1 X 1 25.00
From Km 0.775 to 0.800 R/s 1 X 1 25.00
From Km 0.800 to 0.825 R/s 1 X 1 25.00
From Km 0.825 to 0.850 R/s 1 X 1 25.00
From Km 0.850 to 0.875 R/s 1 X 1 25.00
From Km 0.875 to 0.900 R/s 1 X 1 25.00
From Km 0.900 to 0.925 R/s 1 X 1 25.00
From Km 0.925 to 0.950 R/s 1 X 1 25.00
From Km 0.950 to 0.975 R/s 1 X 1 25.00
From Km 0.975 to 1.000 R/s 1 X 1 25.00
From Km 1.000 to 1.025 R/s 1 X 1 25.00
From Km 1.025to 1.050 R/s 1 X 1 25.00
From Km 1.050to 1.075R/s 1 X 1 25.00
From Km 1.075to 1.100 R/s 1 X 1 25.00
From Km 1.100to 1.125 R/s 1 X 1 25.00
From Km 1.125to 1.142R/s 1 X 1 17.00
From Km 1.142to 1.162 R/s 1 X 1 20.00
From Km 1.162to 1.171 R/s 1 X 1 9.00
TOTAL
7 Mastic Pad
L/s 1 X 90 5.50
R/s 1 X 90 5.50
TOTAL
L/s 1 X 41 5.50
R/s 1 X 41 5.50
8 PVC Pipes
1 X 9 14.00
1 X 4 14.00
CC Drains
S.NO Description No L
1 EWE-Drain
From Km 0.097 to 0.100 L/s 1 X 1 3.00
From Km 0.100 to 0.125 L/s 1 X 1 25.00
From Km 0.125 to 0.150 L/s 1 X 1 25.00
From Km 0.150 to 0.175 L/s 1 X 1 25.00
From Km 0.175 to 0.200 L/s 1 X 1 25.00
From Km 0.200 to 0.225 L/s 1 X 1 25.00
From Km 0.225 to 0.250 L/s 1 X 1 25.00
From Km 0.250 to 0.275 L/s 1 X 1 25.00
From Km 0.275 to 0.300 L/s 1 X 1 25.00
From Km 0.300 to 0.325 L/s 1 X 1 25.00
From Km 0.325 to 0.350 L/s 1 X 1 25.00
From Km 0.350 to 0.375 L/s 1 X 1 25.00
From Km 0.375 to 0.400 L/s 1 X 1 25.00
From Km 0.400 to 0.425 L/s 1 X 1 25.00
From Km 0.425 to 0.450 L/s 1 X 1 25.00
From Km 0.450 to 0.475 L/s 1 X 1 25.00
From Km 0.475 to 0.500 L/s 1 X 1 25.00
From Km 0.500 to 0.525 L/s 1 X 1 25.00
From Km 0.525 to 0.550 L/s 1 X 1 25.00
From Km 0.550 to 0.575 L/s 1 X 1 25.00
From Km 0.575 to 0.600 L/s 1 X 1 25.00
From Km 0.600 to 0.625 L/s 1 X 1 25.00
From Km 0.625 to 0.650 L/s 1 X 1 25.00
From Km 0.650 to 0.675 L/s 1 X 1 25.00
From Km 0.675 to 0.700 L/s 1 X 1 25.00
From Km 0.700 to 0.725 L/s 1 X 1 25.00
From Km 0.725 to 0.750 L/s 1 X 1 25.00
From Km 0.750 to 0.775 L/s 1 X 1 25.00
From Km 0.775 to 0.800 L/s 1 X 1 25.00
From Km 0.800 to 0.825 L/s 1 X 1 25.00
From Km 0.825 to 0.850 L/s 1 X 1 25.00
From Km 0.850 to 0.875 L/s 1 X 1 25.00
From Km 0.875 to 0.900 L/s 1 X 1 25.00
From Km 0.900 to 0.925 L/s 1 X 1 25.00
From Km 0.925 to 0.950 L/s 1 X 1 25.00
From Km 0.950 to 0.975 L/s 1 X 1 25.00
From Km 0.975 to 1.000 L/s 1 X 1 25.00
From Km 1.000 to 1.025 L/s 1 X 1 25.00
From Km 1.025to 1.050 L/s 1 X 1 25.00
From Km 1.050to 1.075L/s 1 X 1 25.00
From Km 1.075to 1.100 L/s 1 X 1 25.00
From Km 1.100to 1.125 L/s 1 X 1 25.00
From Km 1.125to 1.150L/s 1 X 1 25.00
From Km 1.150to 1.175 L/s 1 X 1 25.00
From Km 1.175to 1.180 L/s 1 X 1 25.00
From Km 0.097 to 0.100 R/s 1 X 1 3.00
From Km 0.100 to 0.125 R/s 1 X 1 25.00
From Km 0.125 to 0.150 R/s 1 X 1 25.00
From Km 0.150 to 0.175 R/s 1 X 1 25.00
From Km 0.175 to 0.200 R/s 1 X 1 25.00
From Km 0.200 to 0.225 R/s 1 X 1 25.00
From Km 0.225 to 0.250 R/s 1 X 1 25.00
From Km 0.250 to 0.275 R/s 1 X 1 25.00
From Km 0.275 to 0.300 R/s 1 X 1 25.00
From Km 0.300 to 0.325 R/s 1 X 1 25.00
From Km 0.325 to 0.350 R/s 1 X 1 25.00
From Km 0.350 to 0.375 R/s 1 X 1 25.00
From Km 0.375 to 0.400 R/s 1 X 1 25.00
From Km 0.400 to 0.425 R/s 1 X 1 25.00
From Km 0.425 to 0.450 R/s 1 X 1 25.00
From Km 0.450 to 0.475 R/s 1 X 1 25.00
From Km 0.475 to 0.500 R/s 1 X 1 25.00
From Km 0.500 to 0.525 R/s 1 X 1 25.00
From Km 0.525 to 0.550 R/s 1 X 1 25.00
From Km 0.550 to 0.575 R/s 1 X 1 25.00
From Km 0.575 to 0.600 R/s 1 X 1 25.00
From Km 0.600 to 0.625 R/s 1 X 1 25.00
From Km 0.625 to 0.650 R/s 1 X 1 25.00
From Km 0.650 to 0.675 R/s 1 X 1 25.00
From Km 0.675 to 0.700 R/s 1 X 1 25.00
From Km 0.700 to 0.725 R/s 1 X 1 25.00
From Km 0.725 to 0.750 R/s 1 X 1 25.00
From Km 0.750 to 0.775 R/s 1 X 1 25.00
From Km 0.775 to 0.800 R/s 1 X 1 25.00
From Km 0.800 to 0.825 R/s 1 X 1 25.00
From Km 0.825 to 0.850 R/s 1 X 1 25.00
From Km 0.850 to 0.875 R/s 1 X 1 25.00
From Km 0.875 to 0.900 R/s 1 X 1 25.00
From Km 0.900 to 0.925 R/s 1 X 1 25.00
From Km 0.925 to 0.950 R/s 1 X 1 25.00
From Km 0.950 to 0.975 R/s 1 X 1 25.00
From Km 0.975 to 1.000 R/s 1 X 1 25.00
From Km 1.000 to 1.025 R/s 1 X 1 25.00
From Km 1.025to 1.050 R/s 1 X 1 25.00
From Km 1.050to 1.075R/s 1 X 1 25.00
From Km 1.075to 1.100 R/s 1 X 1 25.00
From Km 1.100to 1.125 R/s 1 X 1 25.00
From Km 1.125to 1.150R/s 1 X 1 25.00
From Km 1.150to 1.175 R/s 1 X 1 25.00
From Km 1.175to 1.180 R/s 1 X 1 25.00
EWE-Divider
From Km 0.097 to 0.100 1 X 1 3.00
From Km 0.100 to 0.125 1 X 1 25.00
From Km 0.125 to 0.150 1 X 1 25.00
From Km 0.150 to 0.175 1 X 1 25.00
From Km 0.175 to 0.200 1 X 1 25.00
From Km 0.200 to 0.225 1 X 1 25.00
From Km 0.225 to 0.250 1 X 1 25.00
From Km 0.250 to 0.275 1 X 1 25.00
From Km 0.275 to 0.300 1 X 1 25.00
From Km 0.300 to 0.325 1 X 1 25.00
From Km 0.325 to 0.350 1 X 1 25.00
From Km 0.350 to 0.375 1 X 1 25.00
From Km 0.375 to 0.400 1 X 1 25.00
From Km 0.400 to 0.425 1 X 1 25.00
From Km 0.425 to 0.450 1 X 1 25.00
From Km 0.450 to 0.475 1 X 1 25.00
From Km 0.475 to 0.500 1 X 1 25.00
From Km 0.500 to 0.525 1 X 1 25.00
From Km 0.525 to 0.550 1 X 1 25.00
From Km 0.550 to 0.575 1 X 1 25.00
From Km 0.575 to 0.600 1 X 1 25.00
From Km 0.600 to 0.625 1 X 1 25.00
From Km 0.625 to 0.650 1 X 1 25.00
From Km 0.650 to 0.675 1 X 1 25.00
From Km 0.675 to 0.700 1 X 1 25.00
From Km 0.700 to 0.725 1 X 1 25.00
From Km 0.725 to 0.750 1 X 1 25.00
From Km 0.750 to 0.775 1 X 1 25.00
From Km 0.775 to 0.800 1 X 1 25.00
From Km 0.800 to 0.825 1 X 1 25.00
From Km 0.825 to 0.850 1 X 1 25.00
From Km 0.850 to 0.875 1 X 1 25.00
From Km 0.875 to 0.900 1 X 1 25.00
From Km 0.900 to 0.925 1 X 1 25.00
From Km 0.925 to 0.950 1 X 1 25.00
From Km 0.950 to 0.975 1 X 1 25.00
From Km 0.975 to 1.000 1 X 1 25.00
From Km 1.000 to 1.025 1 X 1 25.00
From Km 1.025to 1.050 1 X 1 25.00
From Km 1.050to 1.075 1 X 1 25.00
From Km 1.075to 1.100 1 X 1 25.00
From Km 1.100to 1.125 1 X 1 25.00
From Km 1.125to 1.142 1 X 1 17.00
TOTAL
3 PCC M15-Drains
From Km 0.097 to 0.100 L/s 1 X 1 3.00
From Km 0.100 to 0.125 L/s 1 X 1 25.00
From Km 0.125 to 0.150 L/s 1 X 1 25.00
From Km 0.150 to 0.175 L/s 1 X 1 25.00
From Km 0.175 to 0.200 L/s 1 X 1 25.00
From Km 0.200 to 0.225 L/s 1 X 1 25.00
From Km 0.225 to 0.250 L/s 1 X 1 25.00
From Km 0.250 to 0.275 L/s 1 X 1 25.00
From Km 0.275 to 0.300 L/s 1 X 1 25.00
From Km 0.300 to 0.325 L/s 1 X 1 25.00
From Km 0.325 to 0.350 L/s 1 X 1 25.00
From Km 0.350 to 0.375 L/s 1 X 1 25.00
From Km 0.375 to 0.400 L/s 1 X 1 25.00
From Km 0.400 to 0.425 L/s 1 X 1 25.00
From Km 0.425 to 0.450 L/s 1 X 1 25.00
From Km 0.450 to 0.475 L/s 1 X 1 25.00
From Km 0.475 to 0.500 L/s 1 X 1 25.00
From Km 0.500 to 0.525 L/s 1 X 1 25.00
From Km 0.525 to 0.550 L/s 1 X 1 25.00
From Km 0.550 to 0.575 L/s 1 X 1 25.00
From Km 0.575 to 0.600 L/s 1 X 1 25.00
From Km 0.600 to 0.625 L/s 1 X 1 25.00
From Km 0.625 to 0.650 L/s 1 X 1 25.00
From Km 0.650 to 0.675 L/s 1 X 1 25.00
From Km 0.675 to 0.700 L/s 1 X 1 25.00
From Km 0.700 to 0.725 L/s 1 X 1 25.00
From Km 0.725 to 0.750 L/s 1 X 1 25.00
From Km 0.750 to 0.775 L/s 1 X 1 25.00
From Km 0.775 to 0.800 L/s 1 X 1 25.00
From Km 0.800 to 0.825 L/s 1 X 1 25.00
From Km 0.825 to 0.850 L/s 1 X 1 25.00
From Km 0.850 to 0.875 L/s 1 X 1 25.00
From Km 0.875 to 0.900 L/s 1 X 1 25.00
From Km 0.900 to 0.925 L/s 1 X 1 25.00
From Km 0.925 to 0.950 L/s 1 X 1 25.00
From Km 0.950 to 0.975 L/s 1 X 1 25.00
From Km 0.975 to 1.000 L/s 1 X 1 25.00
From Km 1.000 to 1.025 L/s 1 X 1 25.00
From Km 1.025to 1.050 L/s 1 X 1 25.00
From Km 1.050to 1.075L/s 1 X 1 25.00
From Km 1.075to 1.100 L/s 1 X 1 25.00
From Km 1.100to 1.125 L/s 1 X 1 25.00
From Km 1.125to 1.150L/s 1 X 1 25.00
From Km 1.150to 1.175 L/s 1 X 1 25.00
From Km 1.175to 1.800 L/s 1 X 1 5.00
From Km 0.097 to 0.100 R/s 1 X 1 3.00
From Km 0.100 to 0.125 R/s 1 X 1 25.00
From Km 0.125 to 0.150 R/s 1 X 1 25.00
From Km 0.150 to 0.175 R/s 1 X 1 25.00
From Km 0.175 to 0.200 R/s 1 X 1 25.00
From Km 0.200 to 0.225 R/s 1 X 1 25.00
From Km 0.225 to 0.250 R/s 1 X 1 25.00
From Km 0.250 to 0.275 R/s 1 X 1 25.00
From Km 0.275 to 0.300 R/s 1 X 1 25.00
From Km 0.300 to 0.325 R/s 1 X 1 25.00
From Km 0.325 to 0.350 R/s 1 X 1 25.00
From Km 0.350 to 0.375 R/s 1 X 1 25.00
From Km 0.375 to 0.400 R/s 1 X 1 25.00
From Km 0.400 to 0.425 R/s 1 X 1 25.00
From Km 0.425 to 0.450 R/s 1 X 1 25.00
From Km 0.450 to 0.475 R/s 1 X 1 25.00
From Km 0.475 to 0.500 R/s 1 X 1 25.00
From Km 0.500 to 0.525 R/s 1 X 1 25.00
From Km 0.525 to 0.550 R/s 1 X 1 25.00
From Km 0.550 to 0.575 R/s 1 X 1 25.00
From Km 0.575 to 0.600 R/s 1 X 1 25.00
From Km 0.600 to 0.625 R/s 1 X 1 25.00
From Km 0.625 to 0.650 R/s 1 X 1 25.00
From Km 0.650 to 0.675 R/s 1 X 1 25.00
From Km 0.675 to 0.700 R/s 1 X 1 25.00
From Km 0.700 to 0.725 R/s 1 X 1 25.00
From Km 0.725 to 0.750 R/s 1 X 1 25.00
From Km 0.750 to 0.775 R/s 1 X 1 25.00
From Km 0.775 to 0.800 R/s 1 X 1 25.00
From Km 0.800 to 0.825 R/s 1 X 1 25.00
From Km 0.825 to 0.850 R/s 1 X 1 25.00
From Km 0.850 to 0.875 R/s 1 X 1 25.00
From Km 0.875 to 0.900 R/s 1 X 1 25.00
From Km 0.900 to 0.925 R/s 1 X 1 25.00
From Km 0.925 to 0.950 R/s 1 X 1 25.00
From Km 0.950 to 0.975 R/s 1 X 1 25.00
From Km 0.975 to 1.000 R/s 1 X 1 25.00
From Km 1.000 to 1.025 R/s 1 X 1 25.00
From Km 1.025to 1.050 R/s 1 X 1 25.00
From Km 1.050to 1.075R/s 1 X 1 25.00
From Km 1.075to 1.100 R/s 1 X 1 25.00
From Km 1.100to 1.125 R/s 1 X 1 25.00
From Km 1.125to 1.150R/s 1 X 1 25.00
From Km 1.150to 1.175 R/s 1 X 1 25.00
From Km 1.175to 1.800 R/s 1 X 1 5.00
DIVIDER
From Km 0.097 to 0.100 1 X 1 3.00
From Km 0.100 to 0.125 1 X 1 25.00
From Km 0.125 to 0.150 1 X 1 25.00
From Km 0.150 to 0.175 1 X 1 25.00
From Km 0.175 to 0.200 1 X 1 25.00
From Km 0.200 to 0.225 1 X 1 25.00
From Km 0.225 to 0.250 1 X 1 25.00
From Km 0.250 to 0.275 1 X 1 25.00
From Km 0.275 to 0.300 1 X 1 25.00
From Km 0.300 to 0.325 1 X 1 25.00
From Km 0.325 to 0.350 1 X 1 25.00
From Km 0.350 to 0.375 1 X 1 25.00
From Km 0.375 to 0.400 1 X 1 25.00
From Km 0.400 to 0.425 1 X 1 25.00
From Km 0.425 to 0.450 1 X 1 25.00
From Km 0.450 to 0.475 1 X 1 25.00
From Km 0.475 to 0.500 1 X 1 25.00
From Km 0.500 to 0.525 1 X 1 25.00
From Km 0.525 to 0.550 1 X 1 25.00
From Km 0.550 to 0.575 1 X 1 25.00
From Km 0.575 to 0.600 1 X 1 25.00
From Km 0.600 to 0.625 1 X 1 25.00
From Km 0.625 to 0.650 1 X 1 25.00
From Km 0.650 to 0.675 1 X 1 25.00
From Km 0.675 to 0.700 1 X 1 25.00
From Km 0.700 to 0.725 1 X 1 25.00
From Km 0.725 to 0.750 1 X 1 25.00
From Km 0.750 to 0.775 1 X 1 25.00
From Km 0.775 to 0.800 1 X 1 25.00
From Km 0.800 to 0.825 1 X 1 25.00
From Km 0.825 to 0.850 1 X 1 25.00
From Km 0.850 to 0.875 1 X 1 25.00
From Km 0.875 to 0.900 1 X 1 25.00
From Km 0.900 to 0.925 1 X 1 25.00
From Km 0.925 to 0.950 1 X 1 25.00
From Km 0.950 to 0.975 1 X 1 25.00
From Km 0.975 to 1.000 1 X 1 25.00
From Km 1.000 to 1.025 1 X 1 25.00
From Km 1.025to 1.050 1 X 1 25.00
From Km 1.050to 1.075 1 X 1 25.00
From Km 1.075to 1.100 1 X 1 25.00
From Km 1.100to 1.125 1 X 1 25.00
From Km 1.125to 1.142 1 X 1 17.00
TOTAL
4 WALLS M15-Drains
From Km 0.097 to 0.100 L/s 1 X 2 3.00
From Km 0.100 to 0.125 L/s 1 X 2 25.00
From Km 0.125 to 0.150 L/s 1 X 2 25.00
From Km 0.150 to 0.175 L/s 1 X 2 25.00
From Km 0.175 to 0.200 L/s 1 X 2 25.00
From Km 0.200 to 0.225 L/s 1 X 2 25.00
From Km 0.225 to 0.250 L/s 1 X 2 25.00
From Km 0.250 to 0.275 L/s 1 X 2 25.00
From Km 0.275 to 0.300 L/s 1 X 2 25.00
From Km 0.300 to 0.325 L/s 1 X 2 25.00
From Km 0.325 to 0.350 L/s 1 X 2 25.00
From Km 0.350 to 0.375 L/s 1 X 2 25.00
From Km 0.375 to 0.400 L/s 1 X 2 25.00
From Km 0.400 to 0.425 L/s 1 X 2 25.00
From Km 0.425 to 0.450 L/s 1 X 2 25.00
From Km 0.450 to 0.475 L/s 1 X 2 25.00
From Km 0.475 to 0.500 L/s 1 X 2 25.00
From Km 0.500 to 0.525 L/s 1 X 2 25.00
From Km 0.525 to 0.550 L/s 1 X 2 25.00
From Km 0.550 to 0.575 L/s 1 X 2 25.00
From Km 0.575 to 0.600 L/s 1 X 2 25.00
From Km 0.600 to 0.625 L/s 1 X 2 25.00
From Km 0.625 to 0.650 L/s 1 X 2 25.00
From Km 0.650 to 0.675 L/s 1 X 2 25.00
From Km 0.675 to 0.700 L/s 1 X 2 25.00
From Km 0.700 to 0.725 L/s 1 X 2 25.00
From Km 0.725 to 0.750 L/s 1 X 2 25.00
From Km 0.750 to 0.775 L/s 1 X 2 25.00
From Km 0.775 to 0.800 L/s 1 X 2 25.00
From Km 0.800 to 0.825 L/s 1 X 2 25.00
From Km 0.825 to 0.850 L/s 1 X 2 25.00
From Km 0.850 to 0.875 L/s 1 X 2 25.00
From Km 0.875 to 0.900 L/s 1 X 2 25.00
From Km 0.900 to 0.925 L/s 1 X 2 25.00
From Km 0.925 to 0.950 L/s 1 X 2 25.00
From Km 0.950 to 0.975 L/s 1 X 2 25.00
From Km 0.975 to 1.000 L/s 1 X 2 25.00
From Km 1.000 to 1.025 L/s 1 X 2 25.00
From Km 1.025to 1.050 L/s 1 X 2 25.00
From Km 1.050to 1.075L/s 1 X 2 25.00
From Km 1.075to 1.100 L/s 1 X 2 25.00
From Km 1.100to 1.125 L/s 1 X 2 25.00
From Km 1.125to 1.150L/s 1 X 2 25.00
From Km 1.150to 1.175 L/s 1 X 2 25.00
From Km 1.175to 1.800L/s 1 X 2 5.00
From Km 0.097 to 0.100 R/s 1 X 2 3.00
From Km 0.100 to 0.125 R/s 1 X 2 25.00
From Km 0.125 to 0.150 R/s 1 X 2 25.00
From Km 0.150 to 0.175 R/s 1 X 2 25.00
From Km 0.175 to 0.200 R/s 1 X 2 25.00
From Km 0.200 to 0.225 R/s 1 X 2 25.00
From Km 0.225 to 0.250 R/s 1 X 2 25.00
From Km 0.250 to 0.275 R/s 1 X 2 25.00
From Km 0.275 to 0.300 R/s 1 X 2 25.00
From Km 0.300 to 0.325 R/s 1 X 2 25.00
From Km 0.325 to 0.350 R/s 1 X 2 25.00
From Km 0.350 to 0.375 R/s 1 X 2 25.00
From Km 0.375 to 0.400 R/s 1 X 2 25.00
From Km 0.400 to 0.425 R/s 1 X 2 25.00
Deduction 1 X 1 1.20
From Km 0.425 to 0.450 R/s 1 X 2 25.00
From Km 0.450 to 0.475 R/s 1 X 2 25.00
From Km 0.475 to 0.500 R/s 1 X 2 25.00
From Km 0.500 to 0.525 R/s 1 X 2 25.00
From Km 0.525 to 0.550 R/s 1 X 2 25.00
From Km 0.550 to 0.575 R/s 1 X 2 25.00
From Km 0.575 to 0.600 R/s 1 X 2 25.00
From Km 0.600 to 0.625 R/s 1 X 2 25.00
From Km 0.625 to 0.650 R/s 1 X 2 25.00
From Km 0.650 to 0.675 R/s 1 X 2 25.00
From Km 0.675 to 0.700 R/s 1 X 2 25.00
From Km 0.700 to 0.725 R/s 1 X 2 25.00
From Km 0.725 to 0.750 R/s 1 X 2 25.00
From Km 0.750 to 0.775 R/s 1 X 2 25.00
From Km 0.775 to 0.800 R/s 1 X 2 25.00
From Km 0.800 to 0.825 R/s 1 X 2 25.00
From Km 0.825 to 0.850 R/s 1 X 2 25.00
From Km 0.850 to 0.875 R/s 1 X 2 25.00
From Km 0.875 to 0.900 R/s 1 X 2 25.00
From Km 0.900 to 0.925 R/s 1 X 2 25.00
From Km 0.925 to 0.950 R/s 1 X 2 25.00
From Km 0.950 to 0.975 R/s 1 X 2 25.00
From Km 0.975 to 1.000 R/s 1 X 2 25.00
From Km 1.000 to 1.025 R/s 1 X 2 25.00
From Km 1.025to 1.050 R/s 1 X 2 25.00
From Km 1.050to 1.075R/s 1 X 2 25.00
From Km 1.075to 1.100 R/s 1 X 2 25.00
From Km 1.100to 1.125 R/s 1 X 2 25.00
From Km 1.125to 1.150R/s 1 X 2 25.00
From Km 1.150to 1.175 R/s 1 X 2 25.00
From Km 1.175to 1.1800 R/s 1 X 2 5.00
DIVIDER
From Km 0.097 to 0.100 1 X 2 3.00
From Km 0.100 to 0.125 1 X 2 25.00
From Km 0.125 to 0.150 1 X 2 25.00
From Km 0.150 to 0.175 1 X 2 25.00
From Km 0.175 to 0.200 1 X 2 25.00
From Km 0.200 to 0.225 1 X 2 25.00
Deduction 1 X 2 1.20
From Km 0.225 to 0.250 1 X 2 25.00
From Km 0.250 to 0.275 1 X 2 25.00
From Km 0.275 to 0.300 1 X 2 25.00
From Km 0.300 to 0.325 1 X 2 25.00
Deduction 1 X 2 7.50
From Km 0.325 to 0.350 1 X 2 25.00
From Km 0.350 to 0.375 1 X 2 25.00
From Km 0.375 to 0.400 1 X 2 25.00
From Km 0.400 to 0.425 1 X 2 25.00
Deduction 1 X 2 1.20
From Km 0.425 to 0.450 1 X 2 25.00
From Km 0.450 to 0.475 1 X 2 25.00
From Km 0.475 to 0.500 1 X 2 25.00
From Km 0.500 to 0.525 1 X 2 25.00
Deduction 1 X 2 1.20
From Km 0.525 to 0.550 1 X 2 25.00
From Km 0.550 to 0.575 1 X 2 25.00
From Km 0.575 to 0.600 1 X 2 25.00
From Km 0.600 to 0.625 1 X 2 25.00
Deduction 1 X 2 7.50
From Km 0.625 to 0.650 1 X 2 25.00
From Km 0.650 to 0.675 1 X 2 25.00
From Km 0.675 to 0.700 1 X 2 25.00
From Km 0.700 to 0.725 1 X 2 25.00
Deduction 1 X 2 1.20
From Km 0.725 to 0.750 1 X 2 25.00
From Km 0.750 to 0.775 1 X 2 25.00
From Km 0.775 to 0.800 1 X 2 25.00
From Km 0.800 to 0.825 1 X 2 25.00
Deduction 1 X 2 1.20
From Km 0.825 to 0.850 1 X 2 25.00
From Km 0.850 to 0.875 1 X 2 25.00
From Km 0.875 to 0.900 1 X 2 25.00
From Km 0.900 to 0.925 1 X 2 25.00
Deduction 1 X 2 7.50
From Km 0.925 to 0.950 1 X 2 25.00
From Km 0.950 to 0.975 1 X 2 25.00
From Km 0.975 to 1.000 1 X 2 25.00
From Km 1.000 to 1.025 1 X 1 25.00
From Km 1.025to 1.050 1 X 1 25.00
From Km 1.050to 1.075 1 X 1 25.00
From Km 1.075to 1.100 1 X 1 25.00
From Km 1.100to 1.125 1 X 1 25.00
From Km 1.125to 1.142 1 X 1 17.00
Divider gaps round shapes 1 x 18 (1.2+1.8)/2
TOTAL
5 Mastic pad
L/S Drain 36 X 2 …
R/S Drain 36 X 2 …
Divider 36 X 2 …
TOTAL
L/S Drain 10 x 2
R/S Drain 10 x 2
Divider 10 x 2
Pipe Culvert
S.NO Description No L
1 EWE
Head walls 1 X 2 9.00
Under pipes 1 X 1 9.00
Protectin wall
Front left side Protection wall 1 X 1 10.95
Front right side Protection wall 1 X 1 9.15
back Left side Protection wall 1 X 1 12
Back right side Protection wall 1 X 1 11.5
Apron
Upstream 1 X 1 (27.50+25.40+9.70)/3
Cutoff 1 X 1 31.55
Downstream 1 X 1 (26+25+9.70)/3
Cutoff 1 X 1 28.8
2 PCC M10
Head walls 1 X 2 9.00
3 PCC M15
Under pipes 1 X 1 9.00
Protectin wall
Front left side Protection wall 1 X 1 10.95
Front right side Protection wall 1 X 1 9.15
back Left side Protection wall 1 X 1 12
Back right side Protection wall 1 X 1 11.5
Apron
Upstream 1 X 1 (27.50+25.40+9.70)/3
Cutoff 1 X 1 31.55
Downstream 1 X 1 (26+25+9.70)/3
Cutoff 1 X 1 28.8
5.50 …. 16.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 0.84
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 7.32
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 0.66
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 8.04
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 0.6
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 0.504
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
1.20 0.6
5.50 …. 137.5
5.50 …. 137.5
5.50 137.5
5.50 137.5
1.20 14.16
5.50 137.5
5.50 137.5
5.50 137.5
5.50 137.5
1.20 0.6
5.50 137.5
5.50 137.5
5.50 137.5
5.50 93.5
6.20 124
5.50 49.5
5.50 …. 16.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5 0.73
5.50 …. 137.5 0.74
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5 s
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 137.5
5.50 …. 93.5
6.20 …. 124
5.50 …. 49.5
11737.82 14080 2342.18 17.33
1.20 2.3424
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
1.20 0.2112
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
1.20 2.5728
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
1.20 0.192
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
1.20 0.16128
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75
1.20 0.192
0.32
5.50 (0.32+0.20)/2 35.75
5.50 (0.32+0.20)/2 35.75 (0.32+0.20)/2
5.50 (0.32+0.20)/2 35.75 (0.32+0.20)/2
5.50 (0.32+0.20)/2 35.75 (0.32+0.20)/2
…. (0.32+0.20)/2 128.7
…. (0.32+0.20)/2 128.7
257.4
…. (0.32+0.20)/2 58.63
…. (0.32+0.20)/2 58.63
117.26
TOTAL 375
… …. 126
… …. 56
TOTAL 182
B D Contents
B D Contents
… … 62.50
372130
554663.9
40589.91
1 X 1 -1.20 (0.40+0.80)/2 0.90 -0.648
1822052
GENERAL ABSTRACT
Name of Work-Providing infrastructure facilities such as formation of Internal CC roads, CC Drains and Slab culve
Goguladinne-II Village of Markapur Mandal to the Pula Subbaiah Veligonda Project Displaced families of Gottipad
original As per
Estimate Aggrement
58482381.27
Total:- Rs
19651630.00 0 16698295
1899808.00 0 2009917
58271411 8734884.509
49536526
50998599.00
5944383.18 0 2310982
9943.00 0 180019
-15.30
-15.30
-27.45