Professional Documents
Culture Documents
Overheads - CW - Sums - Part 2
Overheads - CW - Sums - Part 2
Example 12:
A machine was purchased for Rs. 5 lakhs. The total cost of all machinery inclusive of the new
machine was Rs. 75 lakhs. The following further particulars are available for new machine:
1. Expected life of the machine 10 years
2. Scrap value at the end of the ten years Rs. 5,000.
3. Repairs and Maintenance for the machine during the year Rs. 20,000
4. Expected no of working hours of the machine per year 4,000 hours
5. Insurance premium annually for all the machines Rs. 45,000
6. Electricity consumption for the machine per hour (@ Rs. 4.50 per unit) 25 units
7. Area occupied by the machine 100 sq. ft.
8. Area occupied by other machines 1,500 sq. ft.
9. Rent per month of the department Rs. 8,000.
10. Lighting charges for 20 points for the whole department is Rs. 1200 per month, out
of which 3 points are for this machine.
Compute the machine hour rate for the new machine on the basis of the data given above.
Example 13:
Work out the Machine Hour rate for the following machine whose scrap value is nil:
Details Amounts (Rs.)
Insurance 20,000
Cost of machine 1,90,000
Freight and installation charges 10,000
Working life Five years
Repairs and maintenance 40% of deprecation
Annual power expenses @ 25 paise p.u 6,000
Eight hourly day charges :
i. Power 24
ii. Lubrication oil 20
iii. Consumable stores 28
iv. Wages 80
Example 14:
Calculate the machine hour rate of a machine with the information given below :
Operating Data:
Total no. of weeks per quarter 13
Total no. of hours per week 48
Stoppage due to maintenance 8 hrs. p.m.
Time taken for set up 2 hrs/week
Cost details:
Example 15:
In a machine shop, the machine hour rate worked out at the beginning of the year on the
basis of 13 weeks period which is equal to 3 calendar months. The following estimates for
operating a machine are relevant:
Total working hours available per week 48 hours
Maintenance time included in above 2 hours
Setting up time included above 2 hours
Cost details:
Operator’s wages p.m. 6,500
Supervisory salary p.m. (Common supervisor for 3 machines) 15,000
W.D.V. of machine (Dep. @ 12% on W.D.V.) 18,00,000
Repairs and maintenance p.a. 160,000
Consumable stores p.a. 300,000
Rent, rates and taxes (for the quarter apportioned) 50,000
Power consumed @15 units per hour @ Rs. 4 per unit. Power is consumed for productive
hours only. Setting up time is part of productive time but no power is required for setting up
jobs. The operator and supervisors are permanent. Repairs and maintenance and
consumable stores are variable.
Work out the machine hour rate also work out the rate for quoting party for utilizing the idle
capacity in the machine shop assuming a profit of 20% above variable cost.
Example 16:
Compute the machine hour rate from the following data :
i. Cost of the new machine to be depreciated is Rs.2,30,000
ii. Life : 10 years
iii. Depreciation to be calculated on straight line basis
iv. Departmental overheads (annual)
Rent – Rs. 50,000
Lighting – Rs. 20,000
Supervision – Rs. 1,30,000
v. Area of the Department with all the machines is 70,000 sq. ft.;
New Machine occupies 2,500 sq. ft. of the total area.
vi. Other annual standing charges for all the machines is Rs. 15,000.
vii. Hours run on production - 1,800.
viii. Hours for setting and adjusting - 200.
ix. Power cost Rs. 0.50 per hour of running time
x. The Indirect Labour rate Rs. 6 per hour.
xi. Indirect Labour :
(a) when setting and adjusting the machines, full time attention is needed
(b) when machine is producing, one man looks after three machines at once.
xii. The department has a total of 26 machines
Example 17: From the following particulars, calculate machine hour rate :
Other information :
Example 18:
The cost accountant of Novo chemicals Ltd. Determined the overhead recovery rate for the
year 2004 (based on direct hours) with the following estimates :
Example 19:
During the year ended 31st March, 2016, the factory overhead costs of three production
departments of an organization are as under :
Department X – Rs. 48,950 ; Y – Rs. 89,200; Z – Rs. 64,500
The basis of apportionment for each department is given below :
X – Rs.5.00 per machine hour for 10,000 hours
Y – 75% of direct labour cost of Rs. 1,20,000.
Z – Rs. 4.00 per piece for 15,000 pieces.
Calculate departmentwise under or over absorption of overheads and present the data in a
tabular form.
Example 20:
a) Calculate the direct labour hour rate of overheads for each department
b) Calculate the extent to which the values of WIP and Finished Goods should be
increased or decreased for each department for the year in view of corrected rates.
c) What will be the impact on total profit of the company in view of the correction
above.
Example 21 :
Separate department overhead application rates based on direct labour hours are being
used by a manufacturing company. At the end of the year, following information is supplied
to you:
a) Calculate the revised overhead application rate in rupee per direct labour hour (in
nearest paise ) in light of actual figures supplied to you for the year.
b) Calculate the total amounts by which the WIP and finished goods stock in each
department will have to be increased or decreased in the light of the revision of the
overhead application rate.
Example 22 :
A machine shop has 8 identical drilling machines by operated 6 operators. The machine
cannot be worked without an operator wholly engaged on it. The original cost of all the
machines works out to Rs. 8 lakh. These particulars are furnished for a 6 month period.
Example 24 :
From the following data relating to a production unit, work out the over absorbed or under
absorbed overhead resulting during the month of review :
The unit having a strength of 20 workmen planned for 290 working days of 8 hours each
with half an hour break. Based on the earlier years trend it is forecasted that average
absenteeism per workman would be 10 days, in addition to the eligibility of 30 days annual
leave.
The budgeted overheads related to the unit for the year amounted to Rs. 75,000 and the
unit follows a system of recovering overheads on the basis of direct labour hours.
The actual overheads during the year amounted to Rs. 71,200 and the following details
regarding actual working of the unit are available :
a) The factory worked 3 extra days to meet the production targets, but one additional
paid holiday has to be declared.
b) There was a severe breakdown of a major equipment leading to a loss of 350 man
hours.
c) Total overtime hours (in addition to 3 extra days worked) amounted to 680 hours.
d) The actual average absenteeism per workman was 12 days.
Example 25 :
The following information is provided on three machines functioning in a manufacturing
department of Suvendhu Private Limited
Note: Supervisor and the attendants are spending equal time on all the three machines.
There are 12 holidays besides Sundays in a year. 2 of the holidays will fall on Saturday and
none on Sunday. The manufacturing department (Machines) works 8 hours on weekdays
and 4 hours on Saturday.
Calculate Machine hour rate for the above machines, after considering the updated
information:
1. As Machines B and C have turned old, consumption of spare parts is estimated to go
up by 25% than the estimated figures
2. Governments decision to ban the imports of spare parts will be resulting in a 15%
increase in the price of spare parts for all the machines
3. Labour unions are constantly demanding hike in wages. The management has
decided to increase the wages of all the Direct and Indirect Labour by 20% above the
estimated rates. However, the above hike is not applicable to the salary of
Supervisors and attendant.