SRA SUPPLY ENTERPRISE(CA 0368959 - U)

NO 54 KAMPUNG SUNGAI ULAR


26080 KUANTAN
PAHANG DARUL MAKMUR

QUOTATION
TMM ENGINEERING SERVICES SDN BHD
TMM SOLARIS
LOT 50274 BUKIT TENGAH
LABOHAN
DATE : 27/10/2023REF. NO :
24300 KERTEH,KEMAMAN 16102023-01
TERENGGANU DARUL IMAN
TEL : +609-8251872

PROJECT TITLE : 12INCH ACID PIPE LINE REPLACEMENTWORK


Dear Sir/Mdm,
Our rates/price as per below : -
ITEM# DESCRIPTION NO(S) UNIT PRICE TOTAL AMOUNT
PERSONAL PROTECTIVE EQUIPMENT
MEDICAL CHECK UP 20 RM100.00 RM2,000.00
WORKING COVERALL 20 RM450.00 RM9,000.00
A
SAFETY SHOES 20 RM200.00 RM4,000.00
SAFETY GLASS 20 RM100.00 RM2,000.00
SAFETY HELMET 20 RM50.00 RM1,000.00
RM18,000.00
EQUIPMENT
WELDING MACHINE 8 RM1,000.00 RM8,000.00
GRINDER 4" 8 RM150.00 RM1,200.00
GRINDER 7" 4 RM180.00 RM720.00
RESPIRATOR 0 RM100.00 RM-
EXTENSION CABLE 20 RM300.00 RM6,000.00
GRINDING DISC 50 RM50.00 RM2,500.00
CUTTING DISC 50 RM55.00 RM2,750.00
B
MAGNETIC DRILL 0 RM150.00 RM-
ELECTROD (KG) 20 RM145.00 RM2,900.00
FILLER ROD (KG) 20 RM220.00 RM4,400.00
ARGON HOSE(100 METER) 100 RM30.00 RM3,000.00
ARGON REGULATOR 8 RM70.00 RM560.00
FIRE BLANKET(ROLLS) 2 RM500.00 RM1,000.00
FIRE EXTINGUSHER 6 RM160.00 RM960.00
COLD CUT CUTTING (JOINT) 2 RM2,500.00 RM5,000.00
RM38,990.00
MANPOWER
SITE SUPERVISOR 1 RM30.00 RM30.00
WORK LEADER 1 RM20.00 RM20.00
WELDER 8 RM28.00 RM224.00
RIGGER/SEMI SKILL 6 RM20.00 RM120.00
C
FITTER 6 RM23.00 RM138.00
SEMI SKILL WORKER 0 RM15.00 RM-
DURATION (DAYS) 20
WORKING HOURS 11
RM117,040.00
TOTAL RM174,030.00
DISCOUNT RM20,000.00
FINAL AMOUNT RM 154,000.00
TERMS AND CONDITIONS

1
SRA SUPPLY ENTERPRISE(CA 0368959 - U)
NO 54 KAMPUNG SUNGAI ULAR
26080 KUANTAN
PAHANG DARUL MAKMUR

1. Quotation validity : 15 days


2. Work to commence, 7 working days after LOA received
3. Any deviation from approved BOQ/BQ will be charges accordingly including
a) Any delay documentation related to work activity
b) If project delay by TMM in term of material delivery. SRA to back charge on
daily rate to apply.
4. Payment terms as follows
a) 50% with L.O.A (RM77,000.00)
b) 20% at 50% on site progress (RM30,800.00)
c) 30% at 100% on site progress (RM46,200.00)
5. PAYMENT TO BE MADE TO : SRA SUPPLY ENTERPRISE
MAYBANK
563028664744

We are looking forward on your favourable reply on the quotation given. Do call us for any
clarification on or about rates or equipment quoted

Thank you