Professional Documents
Culture Documents
HArmonics Notingham
HArmonics Notingham
Assessment
Quality Assurance
TNEI is registered with BS Quality Assurance Limited (Registration Number FS 27760) as compliant with BS EN ISO
9001. All work conducted by TNEI, its subsidiary companies and its subcontractors is carried out in accordance with
in-house procedures and documentation.
Disclaimer
THE CONTENTS OF THIS DOCUMENT ARE FOR THE CONFIDENTIAL USE OF ONLY THOSE PERSONS TO WHOM IT IS
INTENDED, AND MAY NOT BE REPRODUCED OR CIRCULATED IN WHOLE OR IN PART.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 3 of 27
CONTENTS
1 INTRODUCTION ....................................................................................... 4
2 NETWORK MODEL .................................................................................... 5
2.1 NOTTINGHAM EXPRESS TRANSIT (NET) PROJECT .................................................... 5
2.2 WPD NETWORK MODEL ............................................................................. 7
2.2.1 Background Harmonics .................................................................... 8
2.3 TRACTION SYSTEM MODEL ........................................................................... 8
2.3.1 Depot Supply .............................................................................. 10
3 STUDY SCENARIOS AND METHODOLOGY .......................................................11
3.1 G5/4 HARMONIC COMPLIANCE ..................................................................... 11
3.2 STUDY SCENARIOS .................................................................................. 11
3.2.1 Methodology ............................................................................... 12
4 HARMONIC VOLTAGE ASSESSMENT RESULTS ..................................................13
4.1 TRACTION SUBSTATIONS ............................................................................ 13
4.2 WPD PRIMARY SUBSTATIONS ....................................................................... 13
4.3 DEPOT (OFF-PEAK) ASSESSMENT ................................................................... 17
5 CONCLUSIONS ........................................................................................18
6 APPENDIX A – MODEL DATA .......................................................................19
7 APPENDIX B – SIMULATION RESULTS FOR 11KV TSS .........................................22
8 APPENDIX B – SIMULATION RESULTS FOR 11KV WPD PRIMARIES ..........................25
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 4 of 27
1 Introduction
Alstom Transport Systems have commissioned TNEI Services Ltd, to carry out
harmonic analysis of the impact of the Nottingham Express Transit Phase 2 (NET2)
tram project on the WPD distribution network.
Harmonic compliance studies were carried out for each point of common coupling,
PCC, (i.e. traction and primary substations) on the WPD 11kV network, based on a
simplified Engineering Recommendation G5/4 Stage 3 methodology.
This document reports the harmonic analysis that has been carried out in FAPS,
using the WPD network model and rolling stock snapshots and track data (ELBAS
input files) provided by Alstom Transport Systems.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 5 of 27
2 Network Model
2.1 Nottingham Express Transit (NET) Project
Nottingham Express Transit (NET) project consists of two phases, as shown in
Figure 2.1 and Figure 2.2. “Line B” and “Line-C” represent the second phase of
NET and the G5/4 harmonic compliance of WPD 11kV traction substation (TSS)
infeeds located along those tracks is assessed in this report. The existing NET1
tracks and substations were also included in the model.
Figure 2.1 - Single-line diagram of the NET1 and NET2 track kilometre-points (KP)
(Existing)
L1-2 Phoenix Park Highbury Vale 4.600 5.879
(Junction 1)
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 6 of 27
Figure 2.2 - Single-line diagram of the NET tracks with WPD substation locations
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 7 of 27
The TSS infeeds and fault level data provided by WPD are summarised in Table
2-1. The lowest fault levels for NET2 project are at the Clifton P&R and Wilford
Junction TSS.
Harmonic compliance will be assessed both at the TSS as well as the 11kV-side of
the WPD primary substations, in case multiple TSS are fed from common primary
(e.g. Nottingham North and Clifton).
Table 2-1 – Fault level and circuit impedance data for 11kV traction substations
FL Eqv. Impedance Equivalent
Circuit Impedance
at Primary Fault Level
(pu on 100MVA)
(pu on 100MVA) at TSS
WPD
Traction Fault Level
Phase Primary X1 R1 X1 R1
Supply (MVA)
Substation
University
NET2 Beeston 0.593 0.037 0.126 0.249 129.3
Boulevard
NET1 Butlers Hill 0.3437 0.517 95.0
Bullwell 0.553 0.035
NET1 Moorbridge 0.1797 0.27 126.0
NET2 Chilwell Cator Lane 0.502 0.058 0.0849 0.166 159.2
NET2 Clifton Centre 0.0185 0.026 164.4
Clifton 0.586 0.041
NET2 Clifton P & R 0.2277 0.494 102.7
North
NET2 Lenton Lane 0.435 0.018 0.0737 0.105 191.2
Wilford
NET2 Basford 0.0662 0.165 214.9
Wilkinson
NET2 0.108 0.158 199.4
Nottingham Depot (F04)
0.362 0.018
North Wilkinson
NET2 0.1052 0.168 199.0
Depot (F13)
NET1 Highbury Vale 0.1479 0.254 173.2
NET1 Sneinton Middle Hill 0.467 0.042 0.1135 0.08 168.7
NET2 Toton Inham Road 0.431 0.031 0.1407 0.281 153.5
West Wilford
NET2 0.554 0.028 0.3033 0.485 100.1
Bridgford Junction
Wollaton
NET1 The Forest 0.435 0.025 0.3424 0.593 100.7
Road
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 8 of 27
WPD has provided the background harmonic measurements at the 11kV-side of the
relevant primary substations, as shown in Figure 2.3. NET traction system uses 12-
pulse converters hence the most critical harmonics for this project are the 12n±1
(i.e. 11, 13, 23, 25, etc..), which are well below the G5/4 planning limits as
shown in Figure 2.3.
3.50 Clifton
North Wilford
3.00
Nottingham North
2.50 Toton
1.00
0.50
0.00
THD 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
Figure 2.3 – Background harmonic measurements at WPD Primary substations for NET2
(11kV, 95 percentile, 10 minute average)
A model of the complete NET tracks and supply arrangements were provided by
Alstom Transport Systems in ELBAS format, which was then converted within FAPS
as shown in Figure 2.5. The location and power of each train was also provided by
Alstom in the form of 1-second resolution snapshots for the peak two-hour window
(i.e. total of 7650 snaphsots).
The feeders are inter-connected (i.e. all load-break switches closed) and
continuous at all the junctions. The harmonics at the existing NET1 traction
substations on Line 1-1 and Line 1-2 are not assessed in this report. However the
effective impedance at these existing substations has an impact on the harmonic
flows of the nearby substations, as the track DC-feeder is interconnected across
all tracks. Therefore both NET1 and NET2 traction networks and all 11kV WPD
infeeds are modelled explicitly.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 9 of 27
PCC
PCC
12-pulse
converter
Links to tracks
Figure 2.4 – FAPS diagram of typical traction substations fed from the same WPD primary
Figure 2.5 – NET traction network modelled in FAPS based on ELBAS data (TSS and
junction connections are not shown)
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 10 of 27
1) When all trams are out on the tracks (no load in the depot stabling area) –
worst-case peak-hours are simulated using FAPS.
2) When trams are back in the depot during the night consuming auxiliary
load, ~45kW for both Incentro and Citadis tram types.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 11 of 27
The harmonic voltage assessment across the peak two-hour train snapshots was
carried out by using the traction network simulation tool, FAPS.
Based on the information provided by Alstom two study scenarios have been
identified as follows:
The first scenario considers all rolling stock on the tracks for the worst
case two-hour peak window (i.e. assessed by each individual snaphsots)
and the depot stabling area load is negligible.
The second scenario studies specifically the Depot stabling area, when
there is no rolling stock on the tracks and all trams are consuming
auxiliary load (45kW) at the Depot during the night.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 12 of 27
The ELBAS traction network model files included the following information for
each train at each time snapshot:
Train position,
Train power consumption/re-generation.
Based on each train’s position and track number FAPS calculates the
sharing of power amongst the traction/depot substations.
The harmonic current injection from the TSS converters and auxiliary
loads were calculated, and added onto the existing background harmonic
voltages at the PCC and compared against the G5/4 planning limits.
In order to obtain a sufficiently adequate sample across the two-hour window (i.e.
7650 snapshots with 1-sec resolution), the harmonic penetration studies were
carried out for every 5th scenario (i.e. every 5 sec, total of 1530 snaphsots) from
the provided batch file.
The results of the studies were compared against the 11kV planning limits of the
Engineering Recommendation G5/4-1. For presenting the results in graphical
format, the following methodology was followed:
The THD and harmonic voltage values have been presented for each 11kV
TSS and WPD primary substation.
The THD and individual harmonic voltage values have been presented in
graphical format with the highest values observed representing the “worst
case” snapshot scenario.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 13 of 27
The resultant total harmonic voltage profile at the TSS, including the background
harmonics, is shown in Figure 4.2 and all harmonics are within the G5/4 planning
limits, even for the worst-case single snapshot.
The variation of the highest incremental harmonic voltage (11 th order) with time
and the incremental rolling 1-min and 10-min averages are shown in Figure 4.5 for
Clifton P&R TSS, Figure 4.6 for WPD primary Clifton, Figure 4.7 for WPD primary
Nottingham North. The 10-min average harmonic distortion is 3-4 times lower
than the worst-case instantaneous snapshot value.
The total instantaneous and average 11th order harmonic voltage magnitude plots
are shown in Appendix B for each TSS and Appendix C for each WPD primary
substation.
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 14 of 27
3.00%
Basford
CatorLane
2.50% CliftonCentre
Harmonic Voltage (% of fund.)
CliftonP&R
2.00% Depot
InhamRoad
LentonLane
1.50% UniBlvd
WilfordJunct
1.00% G5/4 Limits
0.50%
0.00%
5 7 11 13 17 19 23 25 35 37 47 49
Harmonic Order
4.00%
Basford
3.50% CatorLane
CliftonCentre
Harmonic Voltage (% of fund.)
3.00% CliftonP&R
Depot
2.50%
InhamRoad
2.00% LentonLane
UniBlvd
1.50% WilfordJunct
G5/4 Limits
1.00%
0.50%
0.00%
THD 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
Harmonic Order
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 15 of 27
3.00%
Beeston
Chilwell
2.50%
Harmonic Voltage (% of fund.)
Clifton
North Wilford
2.00%
Nottingham North
1.50%
Toton
West Bridgford
1.00% G5/4 Limits
0.50%
0.00%
5 7 11 13 17 19 23 25 35 37 47 49
Harmonic Order
4.50%
Beeston
4.00% Chilwell
Harmonic Voltage (% of fund.)
3.50% Clifton
North Wilford
3.00%
Nottingham North
2.50% Toton
2.00% West Bridgford
G5/4 Limits
1.50%
1.00%
0.50%
0.00%
THD 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
Harmonic Order
Figure 4.4 - Total harmonic voltages (background + incremental) at 11kV-side of WPD
Primary substations (worst-case snapshot)
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 16 of 27
0.80%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.70%
Harmonic Voltage (% of fund.)
0.60%
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 4.5 – Clifton P&R TSS incremental 11th harmonic voltage
0.70%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.60%
Harmonic Voltage (% of fund.)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
th
Figure 4.6 –WPD Clifton Primary incremental 11 harmonic voltage
0.60%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
Harmonic Voltage (% of fund.)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
th
Figure 4.7 – WPD Nottingham North Primary incremental 11 harmonic voltage
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 17 of 27
The harmonic contribution of the rolling stock at the Depot TSS and at Nottingham
North Primary is less than case when the trains are on the tracks during the peak
two-hour window (Figure 4.8 vs. Figure 4.1). Considering that the total harmonics
are within the G5/4 planning limits during the peak operating scenario, the off-
peak depot scenario is also within the limits.
3.00%
Existing Depot TSS (F04)
2.50%
Harmonic Voltage (% of fund.)
0.50%
0.00%
5 7 11 13 23 25 35 37 47 49
Harmonic Order
Figure 4.8 - Incremental harmonic voltage contribution when all trains are at the Depot
Stabling area during the night
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 18 of 27
5 Conclusions
Harmonic assessment of the Nottingham NET2 traction network was carried out in
order to demonstrate compliance with ER G5/4-1.
A detailed model of the traction network was modelled together with a fault level
equivalent of the 11kV WPD network for each traction substation. Incremental
harmonic contributions from overall NET were calculated based on 1530
snapshots, with a 5 sec resolution, across the peak two-hour window.
The harmonic distortion when all trains are at the depot stabling area
during the night is less than scenario when the trains are on the tracks
during the peak two-hour window.
All resultant total harmonics are well within the G5/4-1 planning limits at
each TSS and WPD primary substations, even for the worst-case single
snapshot.
Recommendation
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 19 of 27
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 20 of 27
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 21 of 27
200kVA auxiliary transformer, 4% impedance, assumed X/R = 1.7 based on similar projects.
Table 6-3 – Auxiliary LV loads at each TSS and assumed harmonic injection profile
Total Aux LV Harmonic
Load (kVA) Harmonic current Angle
Toton Lane TSS 108.2 Order (% of fund) (deg)
Cator Lane TSS 105.5 3 5.76% 76
University Blvd TSS 93.8 5 3.21% 10
Lenton Lane TSS 87.8 7 0.63% 37
Middle Hill TSS 30.4 9 0.42% 31
Clifton P&R TSS 93.4 11 0.27% 36
Clifton Centre TSS 63.6 13 0.18% 47
Wilford Lane TSS 128.4 15 0.15% 20
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 22 of 27
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.1 – Basford TSS total (NET + BG) 11th harmonic voltage
0.50%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.45%
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.2 – Cator Lane TSS total (NET + BG) 11th harmonic voltage
0.80%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.70%
Harmonic Voltage (% of fund.)
0.60%
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.3 – Clifton Centre TSS total (NET + BG) 11th harmonic voltage
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 23 of 27
0.90%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.80%
Harmonic Voltage (% of fund.)
0.70%
0.60%
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.4 – Clifton P&R TSS total (NET + BG) 11th harmonic voltage
0.70%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.60%
Harmonic Voltage (% of fund.)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.5 – Existing Depot TSS total (NET + BG) 11th harmonic voltage
0.50%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.45%
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.6 – Inham Road TSS total (NET + BG) 11th harmonic voltage
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 24 of 27
0.40%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.35%
Harmonic Voltage (% of fund.)
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.7 – Lenton Lane P&R TSS total (NET + BG) 11th harmonic voltage
0.50%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.45%
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.8 – University Boulevard TSS total (NET + BG) 11th harmonic voltage
0.60%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.50%
Harmonic Voltage (% of fund.)
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 7.9 – Wilford Junction TSS total (NET + BG) 11th harmonic voltage
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 25 of 27
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.1 – Beeston Primary total (NET + BG) 11th harmonic voltage
0.45%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.2 – Chilwell Primary total (NET + BG) 11th harmonic voltage
0.70%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.60%
Harmonic Voltage (% of fund.)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 26 of 27
0.35%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.30%
Harmonic Voltage (% of fund.)
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.4 – North Wilford Primary total (NET + BG) 11th harmonic voltage
0.70%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.60%
Harmonic Voltage (% of fund.)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.5 – Nottingham North Primary total (NET + BG) 11th harmonic voltage
0.45%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.6 – Toton Primary total (NET + BG) 11th harmonic voltage
8553_NET2_Harmonic_Assessment.docx
Nottingham NET2 Harmonic Assessment 05 June 2013
Report No 8553-01-R0 Page 27 of 27
0.45%
11th harm - Instantaneous (5-sec resolution) 11th harm - 1-min avg 11th harm - 10 min avg
0.40%
Harmonic Voltage (% of fund.)
0.35%
0.30%
0.25%
0.20%
0.15%
0.10%
0.05%
0.00%
0 200 400 600 800 1000 1200 1400
Snapshot number (5-sec resolution)
Figure 8.7 – West Bridgford Primary total (NET + BG) 11th harmonic voltage
8553_NET2_Harmonic_Assessment.docx