Professional Documents
Culture Documents
TR335 7 Embankment Dams
TR335 7 Embankment Dams
2019
05/05/2019 2
Course contents
1) Foundations: Design and construction considerations.
2) Deep foundations: Types, analysis, design and construction
considerations.
3) Retaining walls: Types, design and construction aspects.
4) Excavations: Design and methods of excavation.
5) Seepage: Flow of water through soils.
6) Dewatering of soils: Methods of dewatering and pressure relief,
design of dewatering systems, filter requirements.
Chapter contents
1) Introduction
9) Construction processes
05/05/2019 4
Learning Outcomes:
Students will be able to design reservoirs and river structures, understand their
performance under different conditions of flow
5) Sediment retention
The two requirements are contrary properties for a single soil type.
This implies for the same impounded water height you will need
approx. 6 times the volume of earthfill than concrete for the dam
wall.
05/05/2019 8
Diaphragm dam
Rockfill dams
05/05/2019 12
Economical when;
1) Large quantities of rock are available or will be excavated in
connection with the project.
The abutments should consist of sound rock with safe slopes and
no faults.
8. All the above have to be met with a minimum total cost giving
considerations to both the initial construction cost as well as the
maintenance costs.
Design considerations
Some/ all of the following can be adopted in the design of the dam
cross-section;
Inclination of slopes; safety factors upstream slope F ≥ 1.3,
downstream slope F ≥ 1.5.
Design of the impervious element; central or sloping core, never too
thin; data of soil material;
The coefficient of permeability k = 10-4 – 10-6mm/s.
Max. grain size about 100mm.
Layers of twice max. grain size compacted after Proctor.
If possible with a stable grain size distribution.
Attention to segregation while placing.
05/05/2019 22
Some/ all of the following can be adopted in the design of the dam
cross-section;
Width of the crest: With zoned dams about 10m (core and filter
zones have to be properly protected).
9. The pore pressure or pressure head along the phreatic surface is zero
so total head equals elevation head along this surface. The
equipotentials will then cut this surface at equal vertical distances
which can be marked off and used in the flow net construction.
05/05/2019 29
Mwananchi Newspaper