GENERAL NOTES:

1. ALL DIMENSIONS ARE IN MILLIMETER UNLESS SPECIFIED OTHERWISE.

5x7m DSS LAYOUT 2. ALL SIZESOF CONCRETEFOUNDATIONFOR EQUIPMENTSARETO BE VERIFIEDON SITE PRIORTO
STARTING OF WORK.
3. DETAILSSHOWNARE FOR DESIGNINTENT.CONTRACTORSHALLPREPAREDETAILEDDRAWINGS

WITHOUT AND SUBMIT FOR CLIENT'S APPROVAL / CLIENT APPROVED ENGINEER.


4. ALL BLINDING CONCRETE SHALL BE C15.
5. ALL STRUCTURALCONCRETESHALL BE C40 (OPC). CONCRETEFOUNDATIONSNEAR COASTAL
TRANSFORMER AREASSHALLBE SRC-TYPE.CONCRETETESTINGTO BE CARRIEDOUT BY THE CONTRACTORAS
PER BS CODE. .
6. ALL REINFORCEMENTFOR CONCRETEWORKS SHALL BE IN ACCORDANCETO BS 4449 R-MILD
STEEL & T-HIGH YIELD STEEL (460 MPA). USE EPOXY-COATEDREINFORCEMENTFOR COASTAL
AREA PROJECTS.
7. SELECTEDBACKFILLSHALLBE PLACEDEVENLYIN LAYERSOF 200MMTHICKNESSAND SHALLBE
COMPACTED.THE SOIL BACKFILLSHALLBE APPROVEDBY ENGINEERFROMAPPROVEDBORROW
PIT. THE DEGREEOF COMPACTIONOF BACKFILLSHALLBE 95% OF THE MAXIMUMDRY DENSITY
AT OPTIMUM MOISTURE CONTENT OBTAINED BY THE MODIFIED PROCTOR COMPACTION TEST.
8. FL. DENOTES AS THE FINISH LEVEL OF NEAREST ASPHALT ROAD AS A REFERENCE OF ELEVATION.
9. THE BLOCK WALL, CONCRETECOLUMN& BEAM SHALL BE CEMENTPLASTERFINISH (SMOOTH)
WITH 1:4 CEMENT-SAND MIX.
A B C A B C 10. ALL EQUIPMENT PAD MUST BE BOLTED TO CONCRETE FOUNDATION. (CAST IN PLACE BOLT)
11. PROVIDE HANDRAIL AT STAIRCASE FOR FGL RAISED AT 1.0M & ABOVE FROM THE FL.
12. PROVIDE CORNER BEADS FOR CORNER EDGE OF CONCRETEIN PERIMETERSIDE OF MAIN
ENTRANCE DOOR.
13. THE TOTALNUMBEROF STEPSIN STAIRCASESHALLBE DETERMINEDFROMTHE APPROVEDFGL.
THREAD=300mm & RISE MAY VARY FROM 150-190mm.
14. THESIZESOF EQUIPMENTFOUNDATIONSSHOWNIN THIS DRAWINGARE BASEDON THE EXISTING
AVAILABLEDATA.IF APPROVEDEQUIPMENTSDOESNOT MATCHWITH THE DRAWING,THE SIZES
SHOWNHERE MAY BE MODIFIEDBY THE CONTRACTORTO MATCHTHE SIZE OF THE APPROVED
EQUIPMENTS.
15. PAINTCOLORSSHALLBE AS PER NAMASTANDARD.ALL PAINTSSHALLBE WEATHERRESISTANT
WATER-BASED PAINTS WITH TEXTURED PAINT FINISH.
16. ACTUALLAYOUTMAY BE TAKENAS A MIRROROF THE STANDARDLAYOUTTO SUIT ACTUALSITE
CONDITION.
1 17. DURING EXECUTION,PROJECTENGINEERHAS THE FLEXIBILITYTO REARRANGETHE SLEEVE
LOCATION AS PER SITE REQUIREMENT.

MINIMUM COVER TO STEEL BARS & STIRRUPS:


EP EP EP EP a. FOUNDATION = 75MM
b. COLUMNS = 40MM
c. BEAMS = 40MM

LEGENDS:
FGL - FINISH GROUND LEVEL TOC - TOP OF CONCRETE
NGL - NATURAL GRADE LINE TOW - TOP OF WALL
FL - FINISH LEVEL C/C - CENTER TO CENTER
RMU-3 RMU-1 RMU-3 RMU-1 ARL
PB
- ASPHALT ROAD LEVEL
- PLINTH BEAM
GI
TYP
- GALVANIZED IRON
- TYPICAL
LB - LINTEL BEAM THK - THICK

OLU-2 OLU-1 OLU-2 OLU-1


PREPARED BY:

2 CIVIL-STRUCTURAL ENGINEER

VERIFIED BY:

ELECTRICAL ENGINEER

RMU-4 RMU-2 RMU-4 RMU-2 CHECKED BY:

HEAD OF DESIGN

HEAD OF SURVEY

APPROVED BY:

MANAGER - DESIGN & SURVEY

FOR REFERENCE ONLY

REV. NO. : DATE : DESCRIPTION : BY: CHK: APPD:


CLIENT NAME :

NA SD NA SD
01 02 SCALE 1:60 02 02 SCALE 1:60 SHEET CONTENTS :

GENERAL LAYOUT PLAN


CABLE TRENCH ROUTE

DRAWING TITLE :

STANDARD DISTRIBUTION SUBSTATION

You might also like