2022-FEE-57-BROWNFIELD MODIFICATIONS CURRENT Por item 03-Dec-23 23:41

Activity ID Activity Name Actual Start Finish December 2023 January 2024 February 2024
Duration 24 01 08 15 22 29 05 12 19 26 02
2022-FEE-57-BROWNFIELD MODIFICATIONS 117 13-Jun-23 A 11-Jan-24
Lot 1 - Overboard Water Elimination Project 90 20-Jul-23 A 11-Jan-24
00 Start/Finish Milestone 0 28-Dec-23 28-Dec-23 28-Dec-23
OWEP.01 DESKTOP SAFETY REVIEW (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.02 PROCESS CONTROL NARRATIVE (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.05 RAINWATER PUMP PIPING & INSTRUMENTATION DIAGRAM (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.11 CAUSE & EFFECT DIAGRAMS FOR PROCESS SAFETY SYSTEM (ICH-2DEL) 55 07-Sep-23 A 11-Dec-23
OWEP.13 PROCESS DESCRIPTION (ICH-2DEL) 0 28-Nov-23 11-Dec-23
OWEP.15 INPUT / OUTPUT LIST - PROCESS CONTROL SYSTEM (ICH-2DEL) 0 28-Nov-23 11-Dec-23
OWEP.16 INSTRUMENT CABLE SCHEDULE (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.17 INSTRUMENT DATA SHEET PRESSURE GAUGES (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.18 INSTRUMENT DATA SHEET PRESSURE TRANSMITTERS (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.19 INSTRUMENT DATA SHEET LEVEL TRANSMITTERS (ICH-2DEL) (CANCELLED) 0 24-Nov-23 02-Jan-24
OWEP.20 INSTRUMENT DATA SHEET SHUT-OFF VALVES (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.21 INSTRUMENT DATA SHEET PRESSURE REGULATOR VALVES (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.22 INSTRUMENT DATA SHEET ON-OFF VALVES (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.23 INSTRUMENT DATA SHEET DIFFERENTIAL PRESSURE INDICATORS (ICH-2DEL) 0 24-Nov-23 07-Dec-23
OWEP.24 INSTRUMENT MTO (ICH-2DEL) 0 04-Dec-23 15-Dec-23
OWEP.25 PROCESS INSTRUMENT CABLE ROUTING DRAWING (ICH-2DEL) 1/4 0 24-Nov-23 07-Dec-23
OWEP.26 PROCESS INSTRUMENT CABLE ROUTING DRAWING (ICH-2DEL) 2/4 0 24-Nov-23 07-Dec-23
OWEP.27 PROCESS INSTRUMENT CABLE ROUTING DRAWING (ICH-2DEL) 3/4 0 24-Nov-23 07-Dec-23
OWEP.28 PROCESS INSTRUMENT CABLE ROUTING DRAWING (ICH-2DEL) 4/4 0 24-Nov-23 07-Dec-23
OWEP.29 JUNCTION BOX DIAGRAM (ICH-2DEL) 0 04-Dec-23 26-Dec-23
OWEP.30 CONTROL LOOPS DIAGRAMS - PROCESS CONTROL SYSTEM (ICH-2DEL) 0 28-Nov-23 11-Dec-23
OWEP.31 CONTROL LOOPS DIAGRAMS - PROCESS SAFETY SYSTEM (ICH-2DEL) 0 28-Nov-23 11-Dec-23
OWEP.32 3D MODEL (ICH-2DEL) 0 05-Dec-23 27-Dec-23
OWEP.33 LINE LIST (ICH-2DEL) 0 05-Dec-23 18-Dec-23
OWEP.34 TIE-IN LIST (ICH-2DEL) 0 05-Dec-23 18-Dec-23
OWEP.35 PIPING BULK MTO (ICH-2DEL) 0 05-Dec-23 18-Dec-23
OWEP.36 VALVE MTO (ICH-2DEL) 0 05-Dec-23 18-Dec-23
OWEP.37 PIPING PLAN ARRANGEMENT MAIN DECK (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.38 PIPING PLAN ARRANGEMENT CELLAR DECK (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.39 CANCELLED - GENERAL ARRANGEMENT MAIN DECK EL. (+) 94' - 0'' / (+) 28.651 M (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.40 CANCELLED - GENERAL ARRANGEMENT CELLAR DECK EL. EL. (+) 69' - 0'' / (+) 21.031M (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.41 CANCELLED - ISOMETRIC DRAWINGS (DESTRUCT) (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.42 ISOMETRIC DRAWINGS (CONSTRUCT) (ICH-2DEL) 0 05-Dec-23 02-Jan-24
OWEP.43 PIPING SUPPORTS DRAWINGS (ICH-2DEL) 0 05-Dec-23 18-Dec-23
OWEP.46 TECHNICAL BID EVALUATIONS (ICH-2DEL) 0 05-Dec-23 11-Jan-24
OWEP.47 DESKTOP SAFETY REVIEW (POKOCH) 0 30-Nov-23 21-Dec-23
OWEP.50 RAINWATER PUMP PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 24-Nov-23 07-Dec-23
OWEP.55 INSTRUMENT AIR DISTRIBUTION PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 24-Nov-23 07-Dec-23
OWEP.56 ISOMETRIC DRAWINGS (DESTRUCT) (POKOCH) 0 05-Dec-23 11-Jan-24
OWEP.57 ISOMETRIC DRAWINGS (CONSTRUCT) (POKOCH) 0 05-Dec-23 11-Jan-24
OWEP.60 TECHNICAL BID EVALUATIONS (POKOCH) 0 05-Dec-23 11-Jan-24
OWEP.61 DESKTOP SAFETY REVIEW (TUMUT-A) 0 24-Nov-23 07-Dec-23
OWEP.62 PROCESS CONTROL NARRATIVE (TUMUT-A) 0 24-Nov-23 02-Jan-24
OWEP.65 RAINWATER PUMP PIPING & INSTRUMENTATION DIAGRAM (TUMUT-A) 0 24-Nov-23 07-Dec-23
OWEP.71 CAUSE & EFFECT DIAGRAMS FOR PROCESS SAFETY SYSTEM (TUMUT-A) 55 07-Sep-23 A 18-Dec-23
OWEP.73 PROCESS AND UTILITIES DESCRIPTION (TUMUT-A) 0 28-Nov-23 11-Dec-23
OWEP.74 PROCESS AND SAFETY INSTRUMENT INDEX (TUMUT-A) 0 24-Nov-23 07-Dec-23
OWEP.75 INPUT / OUTPUT LIST - PROCESS CONTROL SYSTEM (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.76 INSTRUMENT CABLE SCHEDULE (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.77 INSTRUMENT DATA SHEET PRESSURE GAUGES (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.78 INSTRUMENT DATA SHEET PRESSURE TRANSMITTERS (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.79 INSTRUMENT DATA SHEET LEVEL TRANSMITTER MAGNETIC TYPE (TUMUT A) 0 30-Nov-23 13-Dec-23
OWEP.80 INSTRUMENT DATA SHEET SHUT OFF VALVES (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.81 INSTRUMENT DATA SHEET PRESSURE REGULATORS VALVES (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.82 INSTRUMENT DATA SHEET ON-OFF VALVES (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.83 INSTRUMENT DATA SHEET DIFFERENTIAL PRESSURE INDICATOR (TUMUT A) 0 24-Nov-23 07-Dec-23
OWEP.84 INSTRUMENT MTO (TUMUT-A) 0 24-Nov-23 02-Jan-24
OWEP.85 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM (TUMUT-A) 1/3 0 24-Nov-23 07-Dec-23
OWEP.86 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM (TUMUT-A) 2/3 0 24-Nov-23 07-Dec-23
OWEP.87 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM (TUMUT-A) 3/3 0 24-Nov-23 07-Dec-23
OWEP.88 JUNCTION BOX DIAGRAM (TUMUT-A) 0 05-Dec-23 11-Jan-24
OWEP.89 CONTROL LOOPS DIAGRAMS - PROCESS SAFETY SYSTEM (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.90 CONTROL LOOPS DIAGRAMS - PROCESS CONTROL SYSTEM (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.91 3D MODEL (TUMUT-A) 0 05-Dec-23 02-Jan-24
OWEP.94 PIPING BULK MTO (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.95 VALVE MTO (TUMUT-A) 90 20-Jul-23 A 22-Dec-23
OWEP.96 PIPING PLAN ARRANGEMENT (TUMUT-A) 0 05-Dec-23 18-Dec-23
OWEP.97 PIPING GENERAL ARRANGEMENT EL +62.664' + 19.100 M (TUMUT-A) 0 05-Dec-23 02-Jan-24
OWEP.98 PIPING GENERAL ARRANGEMENT (ELEVATION) EAST VIEW (TUMUT-A) 0 05-Dec-23 11-Jan-24
OWEP.99 PIPING GENERAL ARRANGEMENT EL +48.425' + 14.760 M (TUMUT-A) 0 05-Dec-23 02-Jan-24
OWEP.100 ISOMETRIC DRAWINGS (DESTRUCT) (TUMUT-A) 0 05-Dec-23 11-Jan-24
OWEP.101 ISOMETRIC DRAWINGS (CONSTRUCT) (TUMUT-A) 0 05-Dec-23 11-Jan-24
OWEP.102 PIPING SUPPORTS DRAWINGS (TUMUT-A) 0 05-Dec-23 27-Dec-23
OWEP.105 TECHNICAL BID EVALUATIONS (TUMUT-A) 0 05-Dec-23 11-Jan-24
OWEP.107 GRAPHIC PAGES UPDATE SPECIFICATION (ICH-2DEL) 0 28-Nov-23 04-Jan-24
OWEP.108 GRAPHIC PAGES UPDATE SPECIFICATION (TUMUT-A) 0 28-Nov-23 04-Jan-24
Lot 2 - Flare Scrubber Pumps Project 117 13-Jun-23 A 02-Jan-24
FSPP.01 FLARE SCRUBBER PUMPS PIPING & INSTRUMENTATION DIAGRAM (ICH-2DEL) 117 13-Jun-23 A 07-Dec-23
FSPP.02 FLARE SCRUBBER PUMPS SEALS PLAN PIPING & INSTRUMENTATION DIAGRAM (ICH-2DEL) 0 04-Dec-23 15-Dec-23
FSPP.03 PUMPS CALCULATIO N/SIZ ING REPORT (ICH-2DEL) 93 17-Jul-23 A 07-Dec-23
FSPP.08 ISOMETRIC DRAWINGS (DESTRUCT) (ICH-2DEL) 0 30-Nov-23 21-Dec-23
FSPP.09 ISOMETRIC DRAWINGS (CONSTRUCT) (ICH-2DEL) 0 30-Nov-23 21-Dec-23
FSPP.10 TECHNICAL BID EVALUATIONS (ICH-2DEL) 0 08-Dec-23 02-Jan-24
FSPP.11 CAPEX ESTIMATE (ICH-2DEL) 0 08-Dec-23 02-Jan-24
FSPP.12 WORKS SPECIFICATIO N (ICH-2DEL) 0 24-Nov-23 02-Jan-24
FSPP.13 FLARE SCRUBBER PUMPS PIPING & INSTRUMENTATION DIAGRAM (POKOCH 1 DEL) 117 13-Jun-23 A 07-Dec-23
FSPP.14 FLARE SCRUBBER PUMPS SEALS PLAN PIPING & INSTRUMENTATION DIAGRAM (POKOCH 1 DEL) 0 04-Dec-23 15-Dec-23
FSPP.15 PUMPS CALCULATIO N/SIZ ING REPORT (POKOCH 1 DEL) 93 17-Jul-23 A 07-Dec-23
FSPP.20 ISOMETRIC DRAWINGS (DESTRUCT) (POKOCH) 0 24-Nov-23 02-Jan-24
FSPP.21 ISOMETRIC DRAWINGS (CONSTRUCT) (POKOCH) 0 24-Nov-23 02-Jan-24
FSPP.22 TECHNICAL BID EVALUATIONS (POKOCH) 0 08-Dec-23 02-Jan-24
FSPP.23 CAPEX ESTIMATE (POKOCH) 0 08-Dec-23 02-Jan-24
FSPP.24 WORKS SPECIFICATIO N (POKOCH) 0 24-Nov-23 02-Jan-24
FSPP.25 ELECTRICAL FACILITY VERIFICATION REPORT (ICH-2DEL) 0 24-Nov-23 02-Jan-24
Lot 4 - Chemical Injection System Project 0 29-Nov-23 05-Jan-24
CISP.01 CHEMICAL INJECTION SYSTEM PROCESS FLOW DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.02 CORROSION/SCALE INHIBITOR STORAGE TANK PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.03 CHEMICAL AND DEMULSIFIER STORAGE TANK PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.04 ANTIFOAM STORAGE AND INJECTION SYSTEM PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
0 30-Nov-23
CISP.05 DOWNHOLE CHEMICAL AND CORROSION INHIBITOR STORAGE TANKS PIPING & INSTRUMENTATION DIAGRAM 21-Dec-23
(POKOCH)
CISP.06 INJECTION PUMP CORROSION / SCALE INHIBITOR PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
0 30-Nov-23
CISP.07 SPARE INJECTIO N PUMP CORROSION / SCALE INHIBITOR PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 21-Dec-23
CISP.08 PRODUCTION HEADER INJECTION PUMP PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.09 DOWNHOLE CHEMICAL INJECTION PUMP PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.10 SPARE DOWNHOLE CHEMICAL INJECTION PUMP PIPING & INSTRUMENTATION DIAGRAM (POKOCH) 0 30-Nov-23 21-Dec-23
CISP.12 CHEMICAL INJECTION SYSTEM REPORT (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.13 CHEMICAL INJECTION SKID DATA SHEET (POKOCH) 0 29-Nov-23 27-Dec-23
CISP.15 PSV SIZING REPORT (POKOCH) 0 18-Dec-23 02-Jan-24
CISP.16 HAZOP (POKOCH) 0 29-Nov-23 05-Jan-24
CISP.17 PROCESS AND SAFETY INSTRUMENT INDEX (POKOCH) 0 19-Dec-23 03-Jan-24
CISP.19 INSTRUMENT CABLE SCHEDULE (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.20 INSTRUMENT DATA SHEET PRESSURE GAUGES (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.21 INSTRUMENT DATA SHEET PRESSURE TRANSMITTERS (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.22 INSTRUMENT DATA SHEET LEVEL TRANSMITTERS (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.23 INSTRUMENT DATA SHEET SHUT-OFF VALVES (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.24 INSTRUMENT DATA SHEET PRESSURE REGULATOR VALVES (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.25 INSTRUMENT DATA SHEET ON-OFF VALVES (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.26 INSTRUMENT DATA SHEET DIFFERENTIAL PRESSURE INDICATORS (POKOCH) 0 26-Dec-23 03-Jan-24
2022-FEE-57-BROWNFIELD MODIFICATIONS CURRENT Por item 03-Dec-23 23:41
Activity ID Activity Name Actual Start Finish December 2023 January 2024 February 2024
Duration 24 01 08 15 22 29 05 12 19 26 02
CISP.27 INSTRUMENT DATA SHEET SAFETY AND RELIEF VALVES (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.29 PROCESS INSTRUMENT CABLE ROUTING DRAWING (POKOCH) 1/4 0 26-Dec-23 03-Jan-24
CISP.30 PROCESS INSTRUMENT CABLE ROUTING DRAWING (POKOCH) 2/4 0 26-Dec-23 03-Jan-24
CISP.31 PROCESS INSTRUMENT CABLE ROUTING DRAWING (POKOCH) 3/4 0 26-Dec-23 03-Jan-24
CISP.32 PROCESS INSTRUMENT CABLE ROUTING DRAWING (POKOCH) 4/4 0 26-Dec-23 03-Jan-24
CISP.37 CHEMICAL INJECTION PUMPS INSPECTION DATA SHEET (POKOCH) 0 29-Nov-23 27-Dec-23
CISP.38 CHEMICAL INJECTION PUMPS REQUIRED DOCUMENT DATA SHEET (POKOCH) 0 29-Nov-23 27-Dec-23
CISP.39 CHEMICAL INJECTION SKID MECHANICAL SPECIFICATION (POKOCH) 0 11-Dec-23 03-Jan-24
CISP.41 SINGLE LINE DIAGRAM (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.42 ELECTRICAL LOAD CALCULATION (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.43 ELECTRICAL SYSTEM STUDY (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.44 CABLE SIZING CALCULATIONS (POKOCH) 0 26-Dec-23 03-Jan-24
CISP.51 ELECTRICAL LAYOUT & CABLE ROUTING LAYOUT AND SECTIO NS (POKOCH) 0 26-Dec-23 03-Jan-24
Lot 3 - Metering System Carryover Work 0 24-Nov-23 10-Jan-24
MSC.01 TEST SEPARATOR AND PIG LAUNCHERS PROCESS FLOW DIAGRAM (TUMUT-A) 0 08-Dec-23 04-Jan-24
MSC.02 OIL METERING SKID PIPING AND INSTRUMENTATION DIAGRAM (TUMUT-A) 0 08-Dec-23 04-Jan-24
MSC.03 OIL SAMPLING SYSTEM PIPING AND INSTRUMENTATION DIAGRAM (TUMUT-A) 0 08-Dec-23 04-Jan-24
MSC.04 LINE LIST (TUMUT-A) 0 18-Dec-23 04-Jan-24
MSC.05 3D MODEL (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.06 TIE-IN LIST (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.07 PIPING BULK MATERIAL TAKEOFF (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.08 VALVE MATERIAL TAKEOFF (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.09 GENERAL PLOT PLAN (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.10 PIPING GENERAL ARRANGEMENT EL +62.664' + 19.100 M (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.11 PIPING GENERAL ARRANGEMENT (ELEVATION) EAST VIEW (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.12 PIPING GENERAL ARRANGEMENT EL +48.425' + 14.760 M (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.13 ISOMETRIC DRAWINGS (DESTRUCT) (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.14 ISOMETRIC DRAWINGS (CONSTRUCT) (TUMUT-A) 0 22-Dec-23 03-Jan-24
MSC.15 PROCESS AND SAFETY INSTRUMENT INDEX (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.16 INPUT / OUTPUT LIST PROCESS CONTROL SYSTEM (TUMUT-A) 0 25-Dec-23 04-Jan-24
MSC.17 INSTRUMENT CABLE SCHEDULE (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.18 INSTRUMENT DATA SHEET (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.19 INSTRUMENT MATERIAL TAKEOFF (TUMUT-A) 0 25-Dec-23 04-Jan-24
MSC.20 ELECTRICAL HOOK-UPS (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.21 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM 1/3 (TUMUT-A) 0 29-Dec-23 10-Jan-24
MSC.22 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM 2/3 (TUMUT-A) 0 29-Dec-23 10-Jan-24
MSC.23 INSTRUMENT MAIN CABLE AND TRAY ROUTING DIAGRAM 3/3 (TUMUT-A) 0 29-Dec-23 10-Jan-24
MSC.24 JUNCTION BOX DIAGRAM (TUMUT-A) 0 25-Dec-23 04-Jan-24
MSC.31 ELECTRICAL LOAD LIST (TUMUT-A) 0 25-Dec-23 04-Jan-24
MSC.32 POWER CABLE CALCULATION MEMORY 0 25-Dec-23 04-Jan-24
MSC.35 ELECTRICAL CABLE SCHEDULE (TUMUT-A) 0 15-Dec-23 03-Jan-24
MSC.37 HAZARDOUS AREA CLASSIFICATION PLAN (TUMUT-A) 0 18-Dec-23 04-Jan-24
MSC.40 STEPWAY DETAIL DRAWINGS (TUMUT-A) 0 08-Dec-23 08-Jan-24
MSC.44 PROJECT SCHEDULE (TUMUT-A) 0 24-Nov-23 10-Jan-24
Lot 6 - Security systems upgrade 0 24-Nov-23 10-Jan-24
SSU.39 SECURITY & TELECOM SYSTEM - SCOPE OF WORK (ICHALKIL 2 DEL / POKOCH 1 DEL) 0 24-Nov-23 10-Jan-24
0 29-Dec-23
SSU.46 PROJECT SCHEDULE FOR SECURITY SYSTEMS UPGRADE (ICHALKIL 2 DEL / POKOCH 1 DEL / TUMUT-A) 10-Jan-24