CONSTRUCTION OVERVIEW

PROCUREMENT AND CONSTRUCTION OF FLOWLINES AND WELLHEADS INSTALLATION AT SQM


JUPITER / GALFAR / ADNOC - 2023

Sr No. Site Location Scop of Work Qty Unit Current status Additional
status
1 Survey and levels L.S No.s Completed
2 Pile Drilling 12 No.s Completed
3 Steel reinforcement 12 No.s Completed
4 Pile concrete works 12 No.s Completed
5 Chipping 12 No.s Completed
6 Shuttering 12 No.s Completed
7 Stub and template settings 12 No.s Completed
8 Stub and template installations 12 No.s completed
9 2nd stage concrete
10 A+0 1 1 Completed
11 E+0 1 1 Completed
12 E-S + 0 1 1 Completed
13 Gantry foundations excavation 2 No.s Completed
14 Quswirah Gantry foundations installations 2 No.s Completed
15 Assembling of Towers
16 A+0 1 No.s Completed
17 E+0 1 No.s Completed
18 E-S + 0 1 No.s Completed
19 Assembling of gantries
20 G2C T1 1 No.s Installed at site
21 G2CT2 1 No.s Installed at site
1 tower HOLD
because
Tower and gantries Erection LS No.s completed of stub pullout
22 test

23 Hardwhare / Stringing 1 No.s Not yet started Material pending


24 Precomissioning / comissioning LS No.s Not yet started
Sr No. Site Location Scop of Work Qty Unit Current status Additional
status
1 Survey and levels L.S No.s Completed
2 Pile Drilling 24 No.s Completed
3 Steel reinforcement 24 No.s Completed
4 Pile concrete works 24 No.s Completed
5 Chipping 24 No.s Completed
6 Shuttering 24 No.s Completed
2E1L+6 Hold
Stub and template settings 24 No.s Completed because material
7 not available
2E1L+6 Hold
Stub and template installations 24 No.s Completed material not
8 available
9 Gantry foundations excavation 4 No.s Not yet started marking done
10 Gantry foundations installations 4 No.s Not yet started marking done
11 2nd stage concrete
12 E+3 1 No.s completed
13 2E1 - L+6 1 No.s material not available
14 Mandir D/E + 3 1 No.s completed
15 A+9 1 No.s completed
16 B+6 1 No.s completed
17 E+0 1 No.s completed
18 Assembling of Towers
Mandir

19 E+3 1 No.s completed


20 2E1 - L+6 1 No.s Not yet started Material pending
21 D/E + 3 1 No.s completed
22 A+9 1 No.s completed
23 B+6 1 No.s completed
24 E+0 1 No.s completed
25 Assembling of gantries
26 G2C T1 3 No.s Completed
27 G2CT2 1 No.s completed
28 Tower and gantries Erection LS No.s Not yet started
29 Hardwhare / Stringing 1 No.s Not yet started Material pending
30 Precomissioning / comissioning LS No.s Not yet started