Construction Overview SQM
Construction Overview SQM
Sr No. Site Location Scop of Work Qty Unit Current status Additional
status
1 Survey and levels L.S No.s Completed
2 Pile Drilling 12 No.s Completed
3 Steel reinforcement 12 No.s Completed
4 Pile concrete works 12 No.s Completed
5 Chipping 12 No.s Completed
6 Shuttering 12 No.s Completed
7 Stub and template settings 12 No.s Completed
8 Stub and template installations 12 No.s completed
9 2nd stage concrete
10 A+0 1 1 Completed
11 E+0 1 1 Completed
12 E-S + 0 1 1 Completed
13 Gantry foundations excavation 2 No.s Completed
14 Quswirah Gantry foundations installations 2 No.s Completed
15 Assembling of Towers
16 A+0 1 No.s Completed
17 E+0 1 No.s Completed
18 E-S + 0 1 No.s Completed
19 Assembling of gantries
20 G2C T1 1 No.s Installed at site
21 G2CT2 1 No.s Installed at site
1 tower HOLD
because
Tower and gantries Erection LS No.s completed of stub pullout
22 test