ECLOS INSTALLATION FLOWCHART – PAGE #1

SECTION 1 SECTION 7
System delivery. Check the brake and encoder assemblies.
Uncrate and inspect system components and move to Manually rotate the gantry and inspect for cable
the room. clearance, smooth operation, abnormal noise, etc.
Note: Be sure to thoroughly inspect the large cover Place Speaker, X-Ray Generator, Console desk and
crate for all items (approximately 11). Image Processor in place using Standard Details.
Review system order documentation and verify all line Refer to Installation Guide – Page #10 through #12
items have been delivered to the site.
Contact Kyndrea Kub (X 2627) regarding any missing
items.
SECTION 8
Position the table templates. Mark the notches and
check how level the floor is.
SECTION 2 Install the gantry front cover.
Position the system components in the room per the Refer to Installation Guide – Page #12 and #13
dimensions in the site planning drawing.
Document any site condition/problems not indicated on
the pre-installation checklist.
SECTION 9
Refer to Installation Guide – Page #1
Position the table on the marks made in Section 8.
Install the foot switch assembly.
Connect all cables between the table and gantry base.
SECTION 3 Inspect the table for damage and remove the shipping
Remove the shipping wheels and lower shipping brackets.
brackets (do not remove the rotation shipping Refer to Installation Guide – Page #13 through #15
brackets yet).
Level the gantry base then drill through the holes in the
base and install the concrete anchors.
SECTION 10
Refer to Installation Guide – Pages #1 and #2
Run the power cable to the X-Ray Generator cabinet.
Route system cables between the Gantry, X-Ray
Generator and Image Processor using the interconnect
SECTION 4 diagram as a guide.
Remove the remaining gantry shipping brackets (do not Refer to Installation Guide – Page #15 and #16
remove the rotation shipping brackets yet).
Save the top rotation shipping bracket next to the heat
exchanger side (used for X-Ray Tube changes).
SECTION 11
Refer to Installation Guide – Page #2
Connect all cables in the X-Ray Generator cabinet.
Connect the X-Ray Warning lamp cable.
Connect the door switch cable (if present). If the door
SECTION 5 switch is not used the contacts must be jumpered out.
Note: Starting with Serial Number 50XX the X-Ray Refer to Installation Guide – Page #16
Tube and Heat Exchanger will come pre-
installed on the system.
Assemble and mount the X-Ray Tube crane and hoist.
Install the X-Ray Tube and Heat Exchanger. SECTION 12
Install oiled wafers on the end of the High Voltage Connect all cables at the gantry (Joint Base).
Cables. Refer to Installation Guide – Page #17 and #18
Connect the High Voltage cables to the X-Ray Tube.
Connect the rotor and power cables to/from the Tube.
Install the tube safety bracket.
Install the bracket between the Tube and Heat SECTION 13
Exchanger. Connect all cables in the Image Processor.
Secure all cable/oil lines coming from the X-Ray Tube. Install all desktop components.
Install the cover plate over the cables. Refer to the Installation Guide – Page #17 through #18
Install the FSD motor.
Refer to Installation Guide – Page #3 through #7
SECTION 14
Perform the system power up checks.
SECTION 6 Complete the gantry and table checks.
Note: Starting with Serial Number 50XX the Detector Calibrate the Gantry tilt motion.
will come pre-installed on the system. Run the Gantry speed checks.
Unpack and install the Detector assembly and all Refer to Installation Guide – Page #18 and #19
cables.
Remove the remaining shipping brackets (save the
bottom slip ring bracket for X-Ray Tube changes).
Refer to Installation Guide – Page #7 through #10 To Page #2
ECLOS INSTALLATION FLOWCHART – PAGE #2
From Page #1

SECTION 15 SECTION 23
Perform Sections 1, 2 and 3 of the ECLOS Calibration Complete the installation and perform functional checks.
Procedure (QS4-59608). Check all gantry and table motions.
Refer to the Installation Guide – Page #19 Verify there are no cover or cables binding, rubbing or
creating noises, scrapes, etc.
Clean the system for customer use.
Refer to Installation Guide – Page #22
SECTION 16
Level the Table front to back and side to side.
Complete the X-Ray Tube Maintenance Warm-up.
Complete the final table alignment.
Check the table levelness. The End
Drill and install the floor anchors in the table.
Calibrate the table motion.
Refer to Installation Guide – Page #19 and #20

SECTION 17
Complete the Laser alignment and verification.
Refer to Installation Guide – Page #20 and #21

SECTION 18
Perform Sections #4 through #16 of the ECLOS
Calibration Procedure (QS4-59608).
Note: If the X-Ray Tube and Detector came pre-
installed the following calibrations do not have
to be done: Section 6.0, Section 9.0, Section
10.0, Section 13.0, Section 14.0.
Refer to Installation Guide – Page #21

SECTION 19
Complete the ECLOS Installation Data Record QSF-
54037).
Complete the FDA Form 2579.
Refer to Installation Guide – Page #21

SECTION 20
Check system software configuration.
Install option software as required.
Refer to the Installation Guide – Page #21

SECTION 21
Complete the Network and DICOM configurations.
Test the Network functionality.
Test the DICOM functionality.
Refer to Installation Guide – Page #21

SECTION 22
Perform the Daily QC procedure 5 times.
Record the average ROI values on the Daily QC
Phantom.
Refer to Installation Guide – Page #22