Professional Documents
Culture Documents
Remediation Strategy Report
Remediation Strategy Report
Remediation Strategy Report
July 2014
Comments
Our Markets
Property & Buildings Transport & Infrastructure Energy & Utilities Environment
Disclaimer
This report has been prepared by Waterman Energy, Environment & Design Limited, with all reasonable
skill, care and diligence within the terms of the Contract with the client, incorporation of our General
Terms and Condition of Business and taking account of the resources devoted to us by agreement with
the client.
We disclaim any responsibility to the client and others in respect of any matters outside the scope of the
above.
This report is confidential to the client and we accept no responsibility of whatsoever nature to third
parties to whom this report, or any part thereof, is made known. Any such party relies on the report at its
own risk.
Contents
1. Introduction .................................................................................................................................1
1.1 Objectives ........................................................................................................................1
1.2 Context of Document .......................................................................................................1
1.3 Regulatory Context ..........................................................................................................2
1.4 Constraints .......................................................................................................................4
2. Remediation Strategy .................................................................................................................5
2.1 Site levels .........................................................................................................................5
2.2 Works Phasing .................................................................................................................5
2.3 Enabling Works – Buildings, Fuel Station and Services ..................................................5
2.4 Archaeological Recording ................................................................................................5
2.5 Further Ground Investigation ...........................................................................................6
2.6 Removal of Redundant Gas Pipework .............................................................................6
2.7 Removal of Structures and Obstructions .........................................................................6
2.8 Heathwall Sewer and Southwestern Storm Relief Sewer ................................................6
2.9 Former Groundwater Abstraction Wells ...........................................................................6
2.10 Impact of residual contaminants on the River Thames....................................................7
2.11 Impact of residual contaminants on Embassy Gardens ..................................................7
2.12 Contaminated Soils ..........................................................................................................7
2.12.1 Treatment of Soil ......................................................................................................7
2.12.2 Soil excavation depths .............................................................................................7
2.13 Final Placement of Soils as part of Remediation Works ..................................................8
2.13.1 Basement Footprints, Service Corridor and Attenuation Tanks ...............................8
2.13.2 Areas outside of the footprint of the proposed basements, attenuation tanks and
service corridor .........................................................................................................9
2.14 Cover Layer ......................................................................................................................9
2.15 Management of Materials ..............................................................................................10
2.15.1 Licensing Issues .....................................................................................................10
2.16 Management of Shallow Groundwater...........................................................................11
2.17 Unforeseen Contamination ............................................................................................11
2.18 Imported Materials .........................................................................................................11
2.19 Protection of Workers and the General Public ...............................................................11
2.20 Management of odours ..................................................................................................11
2.21 Monitoring ......................................................................................................................12
2.22 Unexploded Ordnance ...................................................................................................12
2.23 Laboratory Testing and Accreditation ............................................................................12
2.24 Statutory Approvals ........................................................................................................12
3. Validation Report ......................................................................................................................13
4. Development Mitigation Measures .........................................................................................14
4.1 Permit to Dig System .....................................................................................................14
4.2 Areas of Soft Landscaping .............................................................................................14
4.3 Buried Services ..............................................................................................................14
4.4 Surface Water Drainage ................................................................................................14
4.5 New Foundations ...........................................................................................................14
4.6 Ground Gas and Vapour Protection Measures to new Buildings and Structures ..........15
Tables
Table 1: Reports pertaining to the redevelopment of the SLMC ................................................1
Remediation Strategy
Contents
EED13002-100 S 2 2 10 CWS
Table 2: Summary of criteria controlling soil reuse in the footprint of proposed underground
structures. ....................................................................................................................9
Table 3: Criteria controlling soil reuse outside the foot print of proposed buildings, attenuation
tanks and the service corridor. .....................................................................................9
Appendices
Appendix A Figures
Appendix B Site Specific Target Criteria
Remediation Strategy
Contents
EED13002-100 S 2 2 10 CWS
1. Introduction
1.1 Objectives
Waterman Energy, Environment & Design Limited (“Waterman”) was instructed by M3 Consulting on behalf
of Royal Mail Group to prepare a Remediation Strategy for ground contamination for the proposed
redevelopment of the South London Mail Centre in the Nine Elms district of London (hereafter termed “the
Site”). The Site currently consists of an operational delivery office, collection hub, vehicle service workshop,
vehicle parking and refuelling facilities and a large concrete plinth which occupies the central area. The
plinth is what remains following the recent demolition of the Mail Centre building. Plans showing the current
and proposed layout of the Site are presented in Appendix A.
The Remediation Strategy puts the focus on removal of sources of contamination and contaminative
infrastructure that could further and/or prolong the impact the on water quality beneath the Site This is
intended to have the effect of reducing the mass of contamination underlying the Site and thereby
significantly improving the subsurface contamination status of Site and surrounding areas. With the
exception of managing water to facilitate safe and well managed excavations specific groundwater
remediation will not be a component of the remedial works.
The objective of this document is to describe the overarching strategy that will govern how the remedial
works are delivered during the works. For operational reasons during the remediation works the Site has
been divided into Phase 1 and Phase 2. Remediation works will commence in the Phase 1 area and will
be directly followed by remediation works in the Phase 2 area. The Remediation Strategy outlined in this
document relates to both the Phase 1 and Phase 2 areas, i.e. the whole Site. A plan showing the Phase 1
and Phase 2 areas of the Site is presented in Appendix A.
A portion of the Site which is currently within the Royal Mail demise and will form a new road referred to as
New Mill Lane will be remediated prior to the rest of the Site. This work will be carried out by Ballymore in
agreement with the Environment Agency and Wandsworth Council.
This document should be read in conjunction with the reports listed in the following table.
Remediation Strategy
Page 1 of 15
EED13002-100 S 2 2 10 CWS
This document was been prepared using information presented in the Generic Environmental Risk
Assessment Report (Reference EED13002-100 5.2.6_JC), the Controlled Waters Detailed Quantitative
Risk Assessment Report (Reference EED13002-100_7.2.5_FA) and following a meeting with the
Environment Agency and Wandsworth Council held on the 3 October 2013. The latter reports relate to the
whole Site and were prepared following an intrusive site investigation completed in July 2013. Both reports
have been submitted to Wandsworth Council in relation to Condition 41 of Planning Permission 2011/2462.
During the site investigation, completed in 2013, access to several areas of the Site was not available due
to Royal Mail operations. Therefore as part of the remediation of the Site, and as referenced in Section 2.5
of this document, supplemental site investigation will take place. The locations of the individual
supplemental site investigation positions have been agreed with the Environmental Agency and
Wandsworth Council and are presented in Appendix A.
On completion of the supplemental site investigation an interpretive report detailing the findings of the work
will be prepared and submitted to Wandsworth Council in relation to Condition 41. Also, if required, the
Remediation Strategy will be updated to reflect how previously unforeseen contamination will be
remediated. The updated Remediation Strategy will be submitted to Wandsworth Council in relation to
Condition 41. Remediation in the areas covered by the supplemental site investigation will not take place
without approval from Wandsworth Council and the Environment Agency.
Remediation Strategy
Page 2 of 15
EED13002-100 S 2 2 10 CWS
affected by contamination or land stability issues, responsibility for securing a safe development rests with
the developer and/or landowner.
Planning policies and decisions should ensure that:
the site is suitable for its new use taking account of ground conditions and land instability, including from
natural hazards or former activities such as mining, pollution arising from previous uses and any
proposals for mitigation including land remediation or impacts on the natural environment arising from
that remediation;
after remediation, as a minimum, land should not be capable of being determined as contaminated land
under Part IIA of the Environmental Protection Act 1990; and
Adequate site investigation information, prepared by a competent person, is presented.
In doing so, local planning authorities should focus on whether the development itself is an acceptable use
of the land and the impact of the use, rather than the control of processes or emissions themselves where
these are subject to approval under pollution control regimes. Local planning authorities should assume
that these regimes will operate effectively. Equally, where a planning decision has been made on a
particular development, the planning issues should not be revisited through the permitting regimes operated
by pollution control authorities.”
In order to assess the contamination status of the Site, with respect to the proposed end use, it is necessary
to assess whether the Site could potentially be classified as “Contaminated Land”, as defined in Part IIA of
the Environmental Protection Act 1990 and Contaminated Land Statutory Guidance 2012. This is assessed
by the identification and assessment of potential pollutant linkages. The linkage between the potential
sources and potential receptors identified needs to be established and evaluated.
To fall within this definition, it is necessary that, as a result of the condition of the land, substances may be
present in, on or under the land such that:
a) significant harm is being caused or there is a significant possibility of such harm being caused; or
b) significant pollution of controlled waters is being caused, or there is significant possibility of such
pollution being caused.
It should be noted that DEFRA has advised (Ref. Section 4, DEFRA Contaminated Land Statutory
Guidance 2012) Local Authorities that land should not be designated as “Contaminated Land” where:
a) the relevant substance(s) are already present in controlled waters;
b) entry into controlled waters of the substance(s) from land has ceased; and
c) it is not likely that that further entry will take place.
These exclusions do not necessarily preclude regulatory action under the Environmental Permitting
(England and Wales) Regulations 2010, which make it a criminal offence to cause or knowingly permit a
water discharge of any poisonous, noxious or polluting matter to controlled waters. In England and Wales,
under The Water Resources Act 1991 (Amendment) (England and Wales) Regulations 2009, a works notice
may be served by the regulator requiring appropriate investigation and clean-up.
Remediation Strategy
Page 3 of 15
EED13002-100 S 2 2 10 CWS
1.4 Constraints
This assessment was undertaken in accordance with the scope agreed between Waterman and Royal Mail
Group and the Professional Services agreement and Framework Agreement.
The benefit of this report is made to Royal Mail Group.
Waterman has endeavoured to assess all information provided to them, but makes no guarantees or
warranties as to the accuracy or completeness of this information.
The scope of this strategy includes an assessment of the presence of asbestos containing materials in the
ground at the Site but not within buildings or structures or below ground structures (basements, buried
service ducts and the like).
The conclusions resulting from this study are not necessarily indicative of future conditions or operating
practices at or adjacent to the Site.
The Remediation Strategy is based on the findings and recommendations of the Generic Quantitative
Environmental Risk Assessment report for the Site completed in July 2013 and the Controlled Waters
Detailed Quantitative Risk Assessment completed in September 2013. The environmental assessment
comprised a review of documentation and information pertaining to the Site, including recent ground
investigations undertaken by ESG and previous intrusive ground investigations undertaken by others.
Remediation Strategy
Page 4 of 15
EED13002-100 S 2 2 10 CWS
2. Remediation Strategy
Remediation Strategy
Page 5 of 15
EED13002-100 S 2 2 10 CWS
archaeological investigation will be carried out as part of the remediation contract. Archaeological work will
be carried out prior to other work commencing which may damage any archaeological remains.
Archaeological investigation works will be supervised by a suitability qualified archaeologist.
Remediation Strategy
Page 6 of 15
EED13002-100 S 2 2 10 CWS
capped off in accordance with Environment Agency guidance note “Good practice for decommissioning
redundant boreholes and wells” (2012).
Remediation Strategy
Page 7 of 15
EED13002-100 S 2 2 10 CWS
Above the water table the necessity to excavate contaminated soil will be governed by Site Specific Target
Criteria (SSTC) which have been generated to protect the River Thames from the contaminants of concern,
a document explaining the derivation of the SSTC is presented in Appendix B. Where validation testing
indicates that contaminants are below the relevant site specific criteria the excavation depth will be deemed
sufficient providing the requirement in relation to buried obstructions have been met.
Where an excavation has reached the groundwater and the results of the validation testing show an
exceedance(s) a visual assessment of the excavation by a suitably qualified environmental engineer will
take place. This inspection will record the nature of the exposed soils including details of the visual
appearance of the soils e.g. discolouration, oily sheens and any malodour e.g. fuel odours, coal tar.
Following the inspection if required the excavation will continue by up to 1.0m below the groundwater table.
Groundwater levels on the Site were recorded between 1.02mAOD and -0.87mAOD, with the average
groundwater depth recorded at 0.26mAOD. For the purposes of excavation, reaching groundwater shall
be considered to have occurred when the Contractor and Supervisor both agree that groundwater has been
intercepted in an excavation and is in line with the site investigation information for that area of the Site.
Water within structures will not be considered as groundwater.
As mentioned previously the results of the DQRA have indicated that contaminant concentrations in
groundwater flowing off Site are not significantly impact the River Thames. Therefore the Remediation
Strategy focuses on source removal as the primary remedial method as opposed to groundwater
remediation. On this basis it is considered that removing soil to a depth of 1.0m below groundwater level
is sufficient with respect removing soils that could potentially contribute to further degradation or prolong
the impact on groundwater quality beneath the Site.
This methodology ensures a cost effective approach to the excavation of contamination at depth avoiding
scenarios where extensive stepped excavations or installation of temporary works would be required to
remove this contamination, when this material has been shown not to pose a significant risk to the River
Thames.
Remediation Strategy
Page 8 of 15
EED13002-100 S 2 2 10 CWS
Table 2: Summary of criteria controlling soil reuse in the footprint of proposed underground structures.
3.5m to 2.5m AOD Inert* or non- Site specific criteria to Flint gravel/ granular
hazardous* protect River Thames material
1.5m AOD to the base Inert* Site specific criteria to Flint gravel/other
of excavation protect River Thames granular material
*As defined by waste classification assessment undertaken in accordance with Environment Agency
guidance; Waste acceptance at landfills, Guidance on waste acceptance procedures and criteria
(November 2010).
2.13.2 Areas outside of the footprint of the proposed basements, attenuation tanks and
service corridor
Soil outside the footprint of the proposed basements, attenuation tanks and service corridors will be
required to meet with the remedial target concentrations for the Site. The criteria for these areas are
summarised in Table 3.
Table 3: Criteria controlling soil reuse outside the foot print of proposed buildings, attenuation tanks and the
service corridor.
3.5 to 2.5m AOD Human Health for Residential End-use Flint gravel/other granular
material
Site specific criteria to protect River
Thames
2.5m to 1.5m AOD. Site specific criteria to protect River No particular requirements
Thames
*As defined by waste classification assessment undertaken in accordance with Environment Agency
guidance.
Groundwater levels on the Site were recorded between 1.02mAOD and -0.87mAOD, with the average
groundwater depth recorded at 0.26mAOD. For the purpose of backfilling only, a nominal groundwater
depth across the site is 0.5mAOD will be assumed. This will reduce potential complications associated
with varying and fluctuating groundwater levels that may arise when backfilling takes place.
Remediation Strategy
Page 9 of 15
EED13002-100 S 2 2 10 CWS
services, soft landscaping etc. during the redevelopment works. The design will also take into consideration
the requirement for the Site to be trafficable as a construction Site.
The finished surface of the Site on completion of remedial works will be at the formation level (3.5m AOD)
with the exception of proposed locations the basements, attenuation tanks and service corridors. In these
areas, where material is expected to be removed from the Site as part of the development, levels can be
lower such that do not pose a risk to health and safety as a result of steep or collapsing faces. These areas
will not be at such a level that groundwater is exposed. Also the requirement for the cover layer and the
requirements as outlined in Table 2 will be remain applicable in these areas.
As backfilling takes place the Contractor shall place a marker layer at depth of 2.5mAOD in areas outside
the footprint of the buildings, attenuation tanks and service corridors. The marker layer shall comprise
bright orange barrier fencing which shall be laid with a minimum 200mm overlap (sideways) and a minimum
1000mm overlap (end of roll).
Following completion of the remedial works a permit to dig system would be operated for any deep
excavations that would penetrate the marker layer.
Remediation Strategy
Page 10 of 15
EED13002-100 S 2 2 10 CWS
The reuse, movement and/or treatment of soils on the Site will be completed in accordance with the
CL:AIRE The Definition of Waste: Development Industry Code of Practice April 2011. Alternatively a waste
exemption or permit will be obtained from the Environment Agency for this reuse activity.
Where secondary aggregates are brought onto the Site or generated on the Site (e.g. crushing operations)
these will be completed in accordance with the WRAP Quality Protocol for the production of aggregates
from inert waste. Alternatively a waste exemption or permit will be obtained from the Environment Agency
for this reuse activity.
Remediation Strategy
Page 11 of 15
EED13002-100 S 2 2 10 CWS
include damping down, boundary mist sprays and curtains and use of odour suppression sprays. Air
monitoring will be undertaken to measure the effectiveness of the odour mitigation measures.
There is potential for further mitigation measures to be required, such as provision of an odour tent for
management and treatment of contaminated soils. This could include a fan-forced air-extraction system
that would push expelled air through an odour scrubber before release from the tent.
2.21 Monitoring
Monitoring with respect to sensitive environmental receptors will be undertaken during the works. This will
include the following:
Noise;
Vibration;
Dust; and
Odour.
Remediation Strategy
Page 12 of 15
EED13002-100 S 2 2 10 CWS
3. Validation Report
A Validation Report providing a record of the remediation works described above will be prepared. As a
minimum the Validation Report will include the following information:
Location and volumes of treated soils retained on the Site including records under the relevant
protocols for their reuse;
Location and volumes of recovered concrete from demolition or grubbing out retained on the Site
including records under the relevant protocols for their reuse;
Remedial works undertaken to boundaries and adjacent surface water drainage;
The source of any material imported onto Site, chemical test results, volumes of materials imported
and confirmation of cover layer thickness;
The source of any imported materials and chemical test results, volumes of imported materials and
locations they have been placed on Site;
Details of any unforeseen contamination encountered during the works and subsequent remedial
actions;
Summary of consignment notes and chain of custody documents relating to the disposal of soils,
groundwater and asbestos containing materials from the Site;
Locations and depths of the tops of obstructions left in place following remedial works; and
Relevant approvals from Wandsworth Council and the Environment Agency for the works carried
out.
Remediation Strategy
Page 13 of 15
EED13002-100 S 2 2 10 CWS
4. Development Mitigation Measures
The mitigation measures described below will be incorporated into the design of the proposed development.
Remediation Strategy
Page 14 of 15
EED13002-100 S 2 2 10 CWS
4.6 Ground Gas and Vapour Protection Measures to new Buildings and Structures
Initial assessment of the ground gas regime for the Site indicates that it conforms to a Characteristic
Situation 2 (low risk) after “Assessing risks posed by hazardous ground gases to buildings” (published by
CIRIA in 2007). Gas protection measures will be incorporated into any proposed buildings on Site to break
the potential source receptor linkage between the future Site users and ground gas.
Vapour protection measures will also be incorporated into any proposed buildings on Site to break the
potential source receptor linkage between the future Site users and ground gas.
Given that all the main buildings will include a basement car park that will be provided with a ventilation
system to deal with vehicle exhaust fumes ground gas protection measures will not be required to these
buildings. However, drained cavities to the basement walls and any store rooms or other rooms within the
basement will need to be ventilated.
Other buildings without basements will be provided with ground gas protection measures comprising
protective measures commensurate with the building use in accordance with the guidance provided in
CIRIA 2007 or BS8485. This is envisaged to comprise passive measures incorporating vapour proof and/or
gas proof membranes and passively ventilated below slab layers or voids with all joints and penetrations
sealed.
Remediation Strategy
Page 15 of 15
EED13002-100 S 2 2 10 CWS
Appendix
Remediation Strategy
EED13002-100 S 2 2 10 CWS
Appendix A Figures
Remediation Strategy
EED13002-100 S 2 2 10 CWS
Energy, Environment & Design
N
Project Details EED13002-100: South London Mail Centre
Sub Base
London Clay
Notes:
Historic Borehole
(if found to be grouted)
Sub Base
London Clay
Notes:
Remediation Strategy
EED13002-100 S 2 2 10 CWS
Site Specific Target Criteria
South London Mail Centre, Nine Elms, London
April 2014
Comments
Our Markets
Property & Buildings Transport & Infrastructure Energy & Utilities Environment
Disclaimer
This report has been prepared by Waterman Energy, Environment & Design Limited, with all reasonable
skill, care and diligence within the terms of the Contract with the client, incorporation of our General
Terms and Condition of Business and taking account of the resources devoted to us by agreement with
the client.
We disclaim any responsibility to the client and others in respect of any matters outside the scope of the
above.
This report is confidential to the client and we accept no responsibility of whatsoever nature to third
parties to whom this report, or any part thereof, is made known. Any such party relies on the report at its
own risk.
Contents
1. Introduction .......................................................................................................................................... 2
1.1 Objectives ................................................................................................................................. 2
1.2 Constraints ................................................................................................................................ 2
2. Methodology used to determine SSTC ............................................................................................. 4
2.1 Selection of Contaminants of Concern ..................................................................................... 4
2.2 ConSim ..................................................................................................................................... 7
2.1 Physical and Chemical Parameters used in ConSim ............................................................... 8
3. Output of ConSim Model .................................................................................................................... 9
4. Conclusions .......................................................................................................................................10
Tables
Table 1: Reports Pertaining to the Site ................................................................................................... 2
Table 2: Summary of soil leachate concentrations in comparison to GAC ............................................. 4
Table 3: Summary of groundwater concentrations in comparison to GAC ............................................. 5
Table 4: Risk Assessment Input Criteria ................................................................................................. 8
Table 5: Output from ConSim Model ...................................................................................................... 9
Table 6: Confirmed SSTC .....................................................................................................................10
1.1 Objectives
Waterman Energy, Environment & Design Limited (Waterman) was instructed by M3 Consulting on behalf
of the Royal Mail Group to prepare a specification (EED13002-100.S.5.3.1- CWS) for the proposed
remedial works at the South London Mail Centre. Site Specific Target Criteria (SSTC) for the remediation
of soil will be included as part of the Remediation Specification. The SSTC will comprise a list of dry soil
concentrations for the contaminants of concern.
These target criteria will be used:
to govern the concentrations of the contaminants of concern permitted in site won material intended to
reused on Site during the remediation works, and
as validation criteria for the sides and bases of excavation when contaminated material is be
excavated above a depth of -1.0m AOD.
With respect to soil being imported on to the Site a separate set of criteria will apply. These are
presented in specification document EED13002-100.S.5.3.1- CWS.
This document will set out the following:
the appropriate contaminants of concern for which site specific remediation criteria will be generated;
methodology used to derive the criteria; and
a list of the SSTC relevant to the Site.
This document should be read in conjunction with the Controlled Waters Detailed Quantitative Risk
Assessment (EED13002-100-R.7.2.5_FA) which outlines the Conceptual Site Model for the Site following
development. This Conceptual Site Model is also considered to be applicable to deriving the SSTC for
remedial work. This document should also be read in conjunction with the Remediation Strategy
(EED13002-100-S.2.2.5_CWS) which describes the overarching remedial strategy of the proposed
works. A list of all reports pertaining to the Site is provided in Table 1. This report is written assuming the
reader is familiar with the contents of these reports and concepts described therein.
1.2 Constraints
This work was undertaken in accordance with the Deed of appointment between Waterman and Royal
Mail Group.
The benefit of this report is made to the Royal Mail Group.
Waterman has endeavoured to assess all information provided to them during this investigation, but
makes no guarantees or warranties as to the accuracy or completeness of this information.
To enable the quantitative risk assessment to be undertaken, specific parameters are required. Where
available Site specific data has been used, however, some, generic literature based values have also
been used. Data used is presented in Table 4.
FOC of soil in
3.13 % Calculated from on-Site measurements
unsaturated zone
FOC of aquifer
1.47 % Calculated from on-Site measurements
material
Hydraulic
0.0319 – 1.47 m/d Derived from Site permeability tests
conductivity
Effective porosity of
0.28 fraction RTM porosity calculator
aquifer material
Dispersivity
Lateral dispersivity 1% of scale at
1.08 (north off Site) m
borehole BH1
EED13002-100-R-4.1.2-FA
Remediation Strategy
EED13002-100 S 2 2 10 CWS
Remediation Strategy
EED13002-100 S 2 2 10 CWS