Leganes - Computation
Leganes - Computation
#NAME? #NAME?
1 2 3 4 5 6 7 8 9 10 11 12 13
100(3)b Individual Removal of Trees (Large B 751mm - 900mm@) EA. 4.00 32,214.00 128,856.00 - - 0.00 - 128,856.00
101(2) Removal of Concrete Drainage Structures CU.M 33.27 1,752.20 58,295.69 22.14 22.14 38,793.71 38,793.71 19,501.98
101(3)a.1 Removal of Existing Concrete Pavement & Slab (Incl. Waste Disposal = 1.5KM) SQ.M 70.74 210.29 14,875.91 - - 0.00 - 14,875.91
101(2)a Removal of RCPC (24" DIA.) - 610MM LN.M 36.00 965.73 34,766.28 - - 0.00 - 34,766.28
103(6) Box Culvert & Drainage Excavation CU.M 1,066.02 247.02 263,328.26 448.00 448.00 110,664.96 110,664.96 152,663.30
104(1)a Embankment/Backfill CU.M 407.73 1,333.17 543,573.40 - - 0.00 - 543,573.40
201 Aggregate Base Course CU.M 71.60 2,621.97 187,733.05 - 0.00 - 187,733.05
404(a) Reinforcing Steel Bar, Grade 40 (Box Culvert) KGS 3,420.58 102.55 350,780.48 - 0.00 - 350,780.48
405(a) Structural Concrete Class A (Box Culvert) CU.M 22.26 13,977.43 311,137.59 - 0.00 - 311,137.59
405(1a) Retaining Wall & Couping CU.M 23.69 15,358.23 363,836.47 - 0.00 - 363,836.47
1717(2)a Steel Sheet Piles LN.M 222.60 6,137.81 1,366,276.51 - 0.00 - 1,366,276.51
SPL 1 Lined Canal (covered 0.8m x 0.8m) LN.M 332.40 5,982.49 1,988,579.68 - 0.00 - 1,988,579.68
SPL 2 Lined Canal (open 0.6m x 0.6m) LN.M 384.25 7,373.82 2,833,390.34 - 0.00 - 2,833,390.34
SPL 3 BillBoard UNITS 2.00 6,574.96 13,149.92 - 0.00 - 13,149.92
SPL 4 Mobilization/Demobilization DAYS 10.00 7,136.64 71,366.40 - 0.00 - 71,366.40
SPL 5 Construction Safety & Health Program LUMPSUM 1.00 23,194.08 23,194.08 - 0.00 - 23,194.08
8,553,140.06 - 149,458.67 149,458.67 8,403,681.39
COST OF THIS DATE: 1.75% PHP 149,458.67
PREPARED BY: COST OF PREVIOUS BILLING: 0.00% 0.00%
COST OF THIS BILLING: 1.75% 14945867.00%
``
JANMARIE CONSTRUCTION SERVICE AND SUPPLY
CONTRACTOR
HECTOR P. CABRIANA ZALDY A. GAYOSA RUEL C. TIANCHON, MPA, REA, REB ATTY. ELIORDO U. OGENA
CHIEF - CONSTRUCTION DIVISION CHIEF - PLANNING, PROGRAMMING, & DESIGN DIVISION CITY ENGINEER CITY MAYOR
Project
Project Name : CONSTRUCTION OF LINED CANAL PRK. LEGANES (TO BRIDGE)
Location : Brgy. Zone I, Koronadal City
Original Amount : 7000000
Notice To Proceed
Contractor : SOUTHCAST CONSTRUCTION
NTP Signed : 8/19/2021
Name of Representati: DOMA SORIANO
Contract Time : 195 Calendar Days
Project Covered Date : 8/26/2021
Notice of Award
Contractor's Amount : Php 8,553,140.06
Billing Computation
Date -
Time Extension
Request 10/11/2019 -
New Expiry
days
to 2/6/2021 August 26, 2021 to February 06, 2021
- -
days
STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED
APPROVED BY:
ACCOMPLISHMENT REPORT
PROJECT : CONSTRUCTION OF FROM EXISTING PCCP TO NEW PUBLIC CEMETERY
LOCATION : BRGY. MABINI, CITY OF KORONADAL
SOURCE OF FUND : AIP 2021
CONTRACT AMOUNT : PHP 5,975,390.27
CONTRACTOR : JANMARIE CONSTRUCTION SERVICE AND SUPPLY
PERIOD COVERED : AUGUST 27, 2021 -DECEMBER 26, 2021
DURATION :120 CALENDAR DAYS
PERIOD: AUGUST 27, 2021 - NOVEMBER 25, 2021 (90 CALENDAR DAYS)
PERCENT ACTUAL BAR CHART
ITEM NO. DESCRIPTION TOTAL AMOUNT DESIGNED ACCOMPLISHMENT ACTUAL ACCOMPLISHMENT
ACCOMPLISHMENT 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
PROGRAM
100 Clearing and Grubbing (with Stripping) 36,652.00 0.524128 0.00% 0.000000
ACTUAL
PROGRAM
100(2)b Individual Removal of Trees (Small B 301mm - 500mm@) 15,499.92 0.221651 66.55% 0.147501
ACTUAL
PROGRAM
100(3)b Individual Removal of Trees (Large B 751mm - 900mm@) 6,263.15 0.089564 0.00% 0.000000
ACTUAL
PROGRAM
100(3)b Individual Removal of Trees (Large B 751mm - 900mm@) 15,165.44 0.216868 0.00% 0.000000
ACTUAL
PROGRAM
101(3)a.1 Removal of Existing Concrete Pavement & Slab (Incl. Waste Disposal = 1.5KM) 15,190.86 0.217231 42.03% 0.091292
ACTUAL
PROGRAM
101(2)a Removal of RCPC (24" DIA.) - 610MM 7,749.84 0.110824 0.00% 0.000000
ACTUAL
PROGRAM
102(1) Roadway Excavation (Unsuitable) 58,456.68 0.835937 0.00% 0.000000
ACTUAL
PROGRAM
103(6) Pipe Culvert Excavation 41,618.30 0.595147 0.00% 0.000000
ACTUAL
PROGRAM
104(1)a Embankment 16,492.11 0.235839 0.00% 0.000000
ACTUAL
PROGRAM
105 Sub Grade Preparation 36,565.33 0.522888 0.00% 0.000000
ACTUAL
PROGRAM
201 Aggregate Base Course 196,899.66 2.815688 0.00% 0.000000
ACTUAL
PROGRAM
311(1)a PCC Pavement (PLAIN)- Conventional Method 200MM Thk. 4,278,022.14 61.176216 0.00% 0.000000
ACTUAL
PROGRAM
500(1)a Pipe Culverts, 610MM dia (24" DIA.) 106,540.86 1.523547 0.00% 0.000000
ACTUAL
PROGRAM
506 Stone Masonry (Head Wall) 71,019.51 1.015587 0.00% 0.000000
ACTUAL
PROGRAM
SPL 1 Billboard 1,451,756.86 20.760293 0.00% 0.000000
ACTUAL
PROGRAM
SPL 2 Mobilizaion/Demobilization 498,028.07 7.121860 0.00% 0.000000
ACTUAL
PROGRAM
SPL 3 Construction Safety & Health Program 15,914.96 0.227586 #REF! #REF!
ACTUAL
PROGRAM
SPL 4 Mobilizaion/Demobilization 38,384.20 0.548899 #REF! #REF!
ACTUAL
PROGRAM
SPL 5 Construction Safety & Health Program 86,730.00 1.240249 #REF! #REF!
ACTUAL
6,992,949.89 100.00% #REF!
LEGENDS:
TARGET ACCOMPLISHMENT
ACTUAL ACCOMPLISHMENT
a).TARGET ACCOMPLISHMENT 75.0000%
b).ACTUAL ACCOMPLISHMENT #REF!
c) SLIPPAGE #REF!
PERIOD: AUGUST 27, 2021 - NOVEMBER 25, 2021 (90 CALENDAR DAYS)
JANMARIE CONSTRUCTION SERVICES AND SUPPLY HECTOR P. CABRIANA RUEL C. TIANCHON ATTY. ELIORDO U. OGENA
Contractor Chief, Construction Division City Engineer City Mayor
S-CURVE & BAR CHART
PROJECT : CONSTRUCTION OF LINED CANAL PRK. LEGANES (TO BRIDGE)
LOCATION : Brgy. Zone I, Koronadal City
SOURCE OF FUND : AIP 2021
CONTRACTOR : SOUTHCAST CONSTRUCTION
PERIOD COVERED : JANUARY 03, 2022 - FEBRUARY 18, 2022
DURATION : 195 Calendar Days
PERIOD: AUGUST 27, 2021 - NOVEMBER 25, 2021 (90 CALENDAR DAYS)
PERCENT ACTUAL BAR CHART
ITEM NO. DESCRIPTION TOTAL AMOUNT DESIGNED ACCOMPLISHMENT ACTUAL ACCOMPLISHMENT
ACCOMPLISHMENT 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
PROGRAM
100 Clearing and Grubbing (with Stripping) 503,857.77 8.432215 100.00% 8.432215
ACTUAL
PROGRAM
100(2)b Individual Removal of Trees (Small B 301mm - 500mm@) 12,627.00 0.211317 100.00% 0.211317
ACTUAL
PROGRAM
100(3)b Individual Removal of Trees (Large B 751mm - 900mm@) 11,773.00 0.197025 100.00% 0.197025
ACTUAL
Removal of Existing Concrete Pavement & Slab (Incl. Waste Disposal = PROGRAM
101(3)a.1 74,297.90 1.243398 100.00% 1.243398
1.5KM) ACTUAL
PROGRAM
101(2)a Removal of RCPC (24" DIA.) - 610MM 56,168.80 0.940002 50.00% 0.470001
ACTUAL
PROGRAM
102(1) Roadway Excavation (Unsuitable) 131,686.81 2.203819 50.00% 1.101910
ACTUAL
PROGRAM
103(6) Pipe Culvert Excavation 34,611.37 0.579232 50.00% 0.289616
ACTUAL
PROGRAM
104(1)a Embankment 53,863.00 0.901414 0.00% 0.000000
ACTUAL
PROGRAM
105 Sub Grade Preparation 530,341.68 8.875432 50.00% 4.437716
ACTUAL
PROGRAM
201 Aggregate Base Course 753,410.27 12.608553 50.00% 6.304277
ACTUAL
PROGRAM
311(1)a PCC Pavement (PLAIN)- Conventional Method 200MM Thk. 3,632,279.40 60.787317 50.00% 30.393659
ACTUAL
PROGRAM
500(1)a Pipe Culverts, 610MM dia (24" DIA.) 38,820.40 0.649671 50.00% 0.324836
ACTUAL
PROGRAM
506 Stone Masonry (Head Wall) 39,807.27 0.666187 0.00% 0.000000
ACTUAL
PROGRAM
SPL 1 Billboard 6,380.60 0.106781 100.00% 0.106781
ACTUAL
PROGRAM
SPL 2 Mobilizaion/Demobilization 36,600.00 0.612512 100.00% 0.612512
ACTUAL
PROGRAM
SPL 3 Construction Safety & Health Program 58,865.00 0.985124 100.00% 0.985124
ACTUAL
5,975,390.27 100.00% 55.11%
1,493,847.5675
CASHFLOW
- 1,493,847.5675 - -
JANMARIE CONSTRUCTION SERVICES AND SUPPLY HECTOR P. CABRIANA RUEL C. TIANCHON ATTY. ELIORDO U. OGENA
Contractor Chief, Construction Division City Engineer City Mayor
Republic of the Philippines
Province of South Cotabato
City of Koronadal
OFFICE OF THE CITY ENGINEER
0 EA.
ITEM 101(3)a.1 REMOVAL OF CONCRETE PAVEMENT & SLAB (INCL. WASTE DISPOSAL = 1.5KM)
STATION
DIMENSION LENGTH(m) VOLUME TOTAL VOLUME (CU.M)
START END
0+000.00 0+015.00 15.00
0+015.00 0+031.60 16.60 0.00
0+031.60 0+051.60 20.00
0+051.60 0+054.60 3.00 0.00
0+054.60 0+057.60 3.00
0+057.60 0+060.60 3.00 0.00
0+060.60 0+071.60 11.00
19.80
0+071.60 0+075.10 3.50 0.00
0+075.10 0+170.10 95.00
0+170.10 0+175.10 5.00 0.00
0+175.10 0+198.60 23.50
0+198.60 0+204.60 6.00 0.00
0+204.60 0+226.60 22.00 19.80
0+226.60 0+235.10 8.50 0.00
0+235.10 0+237.60 2.50
0+237.60 0+238.60 1.00 0.00
0+238.60 0+262.60 24.00
0+262.60 0+266.60 4.00 0.00
0+266.60 0+317.60 51.00
0+317.60 0+323.60 6.00 0.00
0+323.60 0+372.35 48.75
0+372.35 0+384.35 0.90 12.00 10.80
0+384.35 0+396.35 - 12.00
0+396.35 0+406.35 0.90 10.00 9.00
0+406.35 0+426.25 - 19.90
153 CU.M
FOR: RCBC - 1
WEIGHT TOTAL TOTAL WEIGHT
UNITS
3 B1 2.50
3 B2 2.10
3 B3 2.10
3 B4 2.6
3 B5 0.72
1854.84 1854.84
3 B6 7
1854.84 1854.84
L WASTE IN KG
74.63 3.73 208.75
62.69 3.13 175.35
7m 62.69 3.13 175.35
77.61 3.88 217.10
21.49 1.07 60.12
364.00 18.20 1018.18
CALCULATIONS VOLUME
VOLUME 1 = (Area(culvert) - Area(open)) X Length
VOLUME 1 = ((0.9x0.9)-(0.6x0.6))x42
VOLUME 1 = 9.45 CU.M
11.13
VOLUME 1 = (Area(paving notch) - Area(triangle)) X Length
VOLUME 1 = (0.2x0.25)-(1/2(0.2)(0.1)x42
VOLUME 1 = 1.68 CU.M
298.15
SPL 3 BILLBOARD
2 UNITS
SPL 4 MOBILIZATION/DEMOBILIZATION
10 DAYS
1 LUMPSUM
4 ea.
ITEM 101(3)a.1 REMOVAL OF CONCRETE PAVEMENT & SLAB (INCL. WASTE DISPOSAL = 1.5KM)
STATION
DIMENSION LENGTH(m) VOLUME TOTAL VOLUME (CU.M)
START END
0+000.00 0+015.00 - 15.00
0+015.00 0+031.60 0.90 16.60 14.94
0+031.60 0+051.60 - 20.00
0+051.60 0+054.60 0.90 3.00 2.70
0+054.60 0+057.60 - 3.00
0+057.60 0+060.60 0.90 3.00 2.70
0+060.60 0+071.60 - 11.00
70.74
0+071.60 0+075.10 0.90 3.50 3.15
0+075.10 0+170.10 - 95.00
0+170.10 0+175.10 0.90 5.00 4.50
0+175.10 0+198.60 - 23.50
0+198.60 0+204.60 0.90 6.00 5.40
0+204.60 0+226.60 - 22.00 70.74
0+226.60 0+235.10 0.90 8.50 7.65
0+235.10 0+237.60 - 2.50
0+237.60 0+238.60 0.90 1.00 0.90
0+238.60 0+262.60 - 24.00
0+262.60 0+266.60 0.90 4.00 3.60
0+266.60 0+317.60 - 51.00
0+317.60 0+323.60 0.90 6.00 5.40
0+323.60 0+372.35 - 48.75
0+372.35 0+384.35 0.90 12.00 10.80
0+384.35 0+396.35 - 12.00
0+396.35 0+406.35 0.90 10.00 9.00
0+406.35 0+426.25 - 19.90
407.73 CU.M
FOR: RCBC - 1
WEIGHT TOTAL TOTAL WEIGHT
UNITS
6 B1 2.50
6 B2 2.10
6 B3 2.10
6 B4 2.6
6 B5 0.72
3709.67 3709.67
6 B6 7
3709.67 3709.67
L WASTE IN KG
74.63 3.73 417.49
62.69 3.13 350.69
7m 62.69 3.13 350.69
77.61 3.88 434.19
21.49 1.07 120.24
364.00 18.20 2036.36
CALCULATIONS VOLUME
VOLUME 1 = (Area(culvert) - Area(open)) X Length
VOLUME 1 = ((0.9x0.9)-(0.6x0.6))x42
VOLUME 1 = 18.9 CU.M
22.26
VOLUME 1 = (Area(paving notch) - Area(triangle)) X Length
VOLUME 1 = (0.2x0.25)-(1/2(0.2)(0.1)x42
VOLUME 1 = 3.36 CU.M
23.69 CU.M
222.60 LN.M
332.40 LN.M
384.25 LN.M
SPL 3 BILLBOARD
2 UNITS
SPL 4 MOBILIZATION/DEMOBILIZATION
10 DAYS
1 LUMPSUM