Aldahmi 2019

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

2019 IEEE 2nd International Conference on Power and Energy Applications

Assessment of Al Ain Distribution Network Capacitor Banks and Power Factor


Enhancement Study

Maha AlDahmi, Omar Al Ahmad, and Ezzat Ahmad


AlAin Distribution Company
AlAin, United Arab Emirates
e-mail: Maha.aldahmi@aadc.ae

Abstract—Enhancing capacitor banks' performance in Al Ain through installed capacitor banks. Capacitor banks act as
Distribution Company (AADC) network will lead to power reactive power generators to reduce the drawn KVAR and
factor and related network improvements. The aim of this then reduce the total amount of current a system draws from
study is to optimize the existing capacitor banks and obtain the the grid [3]. Also, the underground cables behave like
maximum benefits by evaluating the capacitor banks' status capacitor banks due to the nature of their design since a cable
&condition, controllers' settings, and analyzing their has two electrodes: the core of the cable and the sheath
functionalities in conjunction with network assets based on real separated by dielectric material [4].
time measurements. The analysis was divided into two Some 11kV feeders in AADC network are suffering from
different approaches based on capacitor banks locations in
low power factor (PF), where the capacitor banks are located
AADC network, as the capacitor banks operation concept is
in different locations at 11kV OHL feeders only. Also,
totally different between the banks installed in primary
substations (directly connected to 11kV busbars consisting of around 45% of primary substations (PRY) have capacitor
several stages) and the ones installed at 11kV overhead lines banks at 11 kV side. The capacitor bank logic is acting
(OHL) of one stage and usually smaller in capacity size. In this according to the controller settings which has been tuned to
paper, the classification is done based on network fixed value (more details will be discussed in analysis
characteristic and banks' controller types as well as section). So, improving the P.F. by optimizing the existing
operational concept. AADC has more than 350 capacitor banks capacitor banks can lead to the following benefits to AADC
installed in primary substations and 11kV OHLs with network:
approximately 930MVAR installed capacity providing high 1) Optimize the electrical network performance,
potential of reaching high power factor if operated and increase its efficiency and maximize the utilization
controlled well. The paper also explores the economic impact of existing assets.
of the expected capacitor banks operation enhancement by 2) Reduction in maximum demand (MVA).
saving energy and reducing power losses. 3) Increase system capacity (free up capacity on the
network component).
Keywords-AADC-Al Ain Distribution Company; P.F.- Power
Factor; Capacitor Banks; Loss Reduction; DMS
4) Improve the voltage and reduce the voltage drop.
5) Reduce the power and energy losses.
6) Reduce carbon footprint.
I. INTRODUCTION 7) Meet the Regulatory Obligations, Electricity
Al Ain Distribution Company (AADC) is one of the two Transmission Code (ETC) for power factor at
distribution companies under Department of Energy in the interface point with Abu Dhabi Transmission &
United Arab Emirates (UAE). AADC is the supplier of Dispatch Company (TRANSCO) at least 0.91.
Electricity and Water in Al Ain City with an area of 13,444 This section of the paper provides an overview of AADC
sq.km. The company is responsible for operating and network and the importance of P.F. improvement. The
maintaining the power distribution network of voltage levels following section presents the used methodology to evaluate
0.4kV up to/including 33kV in eastern region of Abu Dhabi the existing capacitor bank. The third section analyzes the
emirate. The power network covers about 168 nos. 33/11kV capacitor bank statues in both primary substation and OHL,
primary / package units substations and about 16000 nos. while the fourth section illustrates the power and energy
11/0.4kV distribution substations. AADC always strive to losses saving resulted from P.F. improvement in AADC
meet its prime objective of providing safe and secure power network from economic perspective. Then future plan for
supply to its customers, with recorded peak load of 2.3GW in further P.F. enhancement was highlighted, and the final
2018 [1]. sections cover the recommendation and conclusion.
Power factor is defined as the ratio between the KW
(actual load power) and the KVA (apparent load power) II. POWER FACTOR ENHANCEMENT AND CAPACITOR
drawn by an electrical load. It is simply a measure of how BANK OPTIMIZATION
efficiently the electrical power is being converted into useful The Capacitor Banks (CPBK) of AADC existing network
work output [2]. Technically, the P.F. is improved by is analyzed in this section. The analysis is based on the
reducing the consumed reactive power by supplying KVAR

978-1-7281-1596-2/19/$31.00 ©2019 IEEE 159


collected data from different source such as 24 hours reading The figure illustrates the logic of CPBK controller at
on peak day, Distribution Management System (DMS) and PRY substations which can drive a bank stages (1 stage =
received feedback from concerned sections. The analysis is 1.25 KVAR, No of. stages = 3 to 4) and switch them ON to
divided into two main parts based on capacitor bank location reach the desired P.F. value based in two main conditions:
as following: 1) P.F is less than the controller set value (0.95).
2) The reactive power at transformer 11 kV side
A. Capacitor Banks at Primary Substations (required Q to enhance PF to the set value 0.95) is ≥
Analysis& Findings: There are 79 (out of 170) primary 60% of Qc of a stage value (in case of 1.25MVAR
(PRY) substations in AADC network that contains capacitor stage size it equals 0.75 MVAR).
bank with total 170 units (with capacity of 856 MVAR) were Based on the above-mentioned two conditions and
evaluated in this study, to investigate the functionality status measured Qc max (MVAR), all existing capacitor banks
of capacitor bank to assure that the PF is within the desired performance at PRY substation were reviewed to evaluate
setting value 0.95. and categorize them based on their functionality. The
As the capacitor bank controller at primary substations is following Table 1 shows samples of some analyzed 11kV
driven by the PF of the feeding Power Transformer (PTR), PTR feeders at different PRY substations along with the
the load profile of each related PTR is studied and analyzed. findings that includes required actions. The details and actual
The line graph in below Fig. 1 shows real MW, MVAR of a PRY substation names in this analysis are not shown for
specific PTR at AADC network. In this example, connected brevity and confidentiality.
CPBK is not functioning as desired; however, the PTR
MVAR value is simulated, and the corrected value is shown TABLE I. SAMPLES OF SELECTED ANALYZED 11KV FEEDERS AT
PRY SUBSTATIONS
based on well-functioning condition of the said banks.

After reviewing all capacitor banks at PRY substations,


the following summary in Table 2 can be concluded:
TABLE II. TOTAL NO OF CAPACITOR BANK UNITS BASED ON THEIR
STATUS
Figure 1. Load curve of a PRY substation with and without CPBK impact.
Number of
CPBK Units Condition/Status
The automatic power factor correction device is CPBK Units
developed based on embedded system having 89S52 Capacitor Banks functioning as desired and meeting
125 (74%)
target PF.
microcontroller at its core. The voltage and current signal Capacitor Banks connected to lightly loaded power 9
from the system is sampled and taken as input to measure the transformer and private primary.
power factor and if it falls short of the specified value by Disconnected Banks, no free panels at PRY
7
utility, then the device automatically switch on the capacitor substation.
banks to compensate for the reactive power [5]. In order to Banks require correction Action (Faulty stage/unit,
29
understand the well-functioning status that achieves desired controller, settings, Circuit Breaker, etc.)
Total Number of Banks 170
and required values, the controller of substation's CPBK is
illustrated in Fig. 2 showing SLD of controller circuit and its From the above table it can be noticed that 74 % of
inputs. Capacitor bank units are well functioning; however, 7 units
are either disconnected or no free spare panels and need efforts
by planning team, while 29 units need corrective actions by
maintenance team to rectify problems of the said stages/units
as well as issues in controllers or accessories after
conducting site survey.
B. Capacitor Banks at 11kV Overhead Line (OHL)
Analysis & Findings: Similar to PRY substations’
Capacitor Banks, OHL banks are being protected through
two different schemes that involve protection of the bank
against faults occurring within the bank itself including those
inside the capacitor units and the compartment; and
protection of the bank against system disturbances and faults
Figure 2. Capacitor bank’s controller logic at PRY substation.

160
[6]. However, AADC OHL banks differ than the ones TABLE IV. TOTAL NO OF CAPACITOR BANK UNITS BASED ON THEIR
STATUS
installed at PRY by KVAR capacity size and being only one
stage. Number of CPBK
CPBK Units Condition/Status
Overall, there are 180 OHL Capacitor banks (CPBK) Units
installed in AADC network in 2016. There are two different Capacitor Banks functioning as desired and
88
ratings of the installed CPBKs. The first type is CPBK with meeting target PF
the capacity of (300 KVAR), where 61% of the Dismantled & recovered Banks 4
commissioning CPBKs in OHL are under this type. In Banks Required relocation/ further evaluation 30
contrast, the remaining 39% of commissioning CPBKs are Banks require EMD Action (status, settings,
58
under second type, which has a capacity of (600 KVAR). In Fuse, etc.
Total Number of Banks 180
fact, installing the CPBKs along the AADC network help to
provide 75MVAR to the network, which in turn helps to
enhance the overall PF in different subnetwork. It’s essential From the above table it can be noticed that just below
to note that controller settings in each bank is 0.99 P.F. with half of OHL Capacitor banks are well functioning; moreover,
maximum daily operation of 10 times per day based on 30 units need joint efforts by maintenance team and network
manufacturer recommendations. And it’s worth to highlight studies team to re-adjust them and assure that they are well
that the number of stage in OHL CPBK used in AADC functioning, while 58 units need purely maintenance team
network is designed to entre one stage only depend on the efforts to rectify problems of those units as well as related
capacity (300/600KVAR). As continuous evaluation of the issues in their controllers or accessories.
existing OHL banks, the PF has been checked with the III. EXPECTED ENHANCEMENT AND SAVING
available measurements of 11kV feeder heads of the
connected OHL on annual basis to evaluate the status in A. Power and Energy Saving Calculation Methodology
addition to physical site inspection once required. The
following figure shows the functionality of the CPBK As far as the power and energy saving economically
controller at OHL feeder. impact is to be considered from all prospective, the saving
from improving the P.F. in AADC network is evaluated. The
following calculations considering all CPBK stage(s) are
functioning well and operating as desired to reach the target
set power factor at primary substation, then summated in
MVAR at related grid stations are deducted from recorded/
consumed MVAR on AADC system Peak Day (12-7-2018).
Hence, the annual saving calculation in this section is based
on the improvement of PF in primary substations only, while
Figure 3. Capacitor bank’s controller logic at OHL. OHL banks related calculations required more field efforts.
Such required evaluation might be conducted later in other
Fig.3 shows that the controller at OHL CPBK is working dedicated study.
to switch a stage ON based in two main conditions: The following equations are used for calculating the
1) P.F is less than the controller set value (0.99). 220/33kV Grid stations enhanced resulted PF and the saving
2) The reactive power at connection point of OHL in MVA and MW were founded:
feeder (required Q to enhance the PF to set value
0.99) is ≥ Qc value (300 or 600KVAR based on E losses (MWH) = P losses (MW) × t × LSF, (1)
CPBK rating).
Based on the above-mentioned two conditions, all LSF= K× LF +(1-K) × LF2 [7] (2)
feeders with OHL capacitor banks have been analyzed, and
corresponding PFs have been evaluated to investigate the LF= Davg/Dmax (3)
condition of the said banks and their functional status.
Samples of analyzed OHL feeders along with PF where:
enhancement impact are shown in Table 3. The details of this E = Annual energy loss.
analysis are not shown for brevity and confidentiality. t = Hrs./year (8760).
K : is factor ranges between 0.1 : 0.3
TABLE III. SAMPLES OF SELECTED ANALYZED 11KV OHL FEEDERS LSF= Loss Factor.
LF= Load Factor.
Davg= Average Demand, Dmax= Maximum Demand.
• Load Factor is calculated from archived load
readings from DMS for one grid as a sample (LF=
0.558, LSF = 0.385) assuming AADC subnetworks
are similar.
After reviewing all existing capacitor banks at 11kV OHL • The cost of annual energy losses is calculated by
feeders, the following summary in Table 4 is concluded: using actual kWh value of AED 0.305($ 0.083) per

161
kWh as per latest AADC Water and Electricity primary substations and OHL is highly recommended, which
Tariff [8]. includes the following rectification to ensure the CPBK
functionality to obtain the desired power factor value.
B. Benefits Achieved from P.F. Enhancement
1) Rectify the defected capacitor bank units and
In case of implement recommendations of this study and controllers at primary substations by Electricity Maintenance
ensuring all capacitor banks at primary substations are well Department and Testing & Protection Department, where 36
functioning and setting as desired, the following is the
units need correction action to solve the problem.
expected achievements without any additional investment in
the network: 2) Rectify the defected capacitor banks units and
• Increase load carrying capabilities in existing controllers at OHL by Electricity Maintenance Department,
network by approximately 19 MVA, almost equal where 88 units need corrective action to solve the problem.
2/3 firm capacity of new primary substation 3x15/20
VI. CONCLUSION
MVA, hence save new investment about AED 30
Million around ($ 8 Million) based on last contract In conclusion, capacitor banks status in AADC network
value and related generation, transmission cost and for both primary substations and OHL were evaluated in
resulted carbon footprint reduction. order to enhance the power factor. The analysis focused on
• The power and energy losses will be reduced by 17.5 the capacitor bank controller logic to compare the power
MW & 58,929.6 MWH respectively, factor and the amount of reactive power (VAR) from the
• Annual energy loss saving will be around AED 18 source with the desired setting value. Enhancing P.F. values
Million around ($ 5 Million). in AADC network can save at least AED 18 million around
• Meet the Regulatory Obligations at ETC for P.F. at ($ 5 Million) with zero investment. Also, by enhancing the
interface point with Abu Dhabi Transmission & performance of the capacitor banks and achieving the
Dispatch Company (TRANSCO) at least 0.91. expected P.F. improvement, AADC will comply with ETC to
• Optimize the electrical network performance, maintain 0.91 P.F. value at interface points with transmission
increase its efficiency and maximize the utilization company to avoid related penalties. Furthermore, it’s
of existing assets. believed that the voltage profile will be significantly
• Improve the voltage and reduce the voltage drop. improved as the voltage drop values will decrease especially
Ensuring all OHL capacitor banks are well functioning in the OHL capacitor banks feeders. In addition, the network
and setting as desired will add further benefits and annual can get further improvements if the future enhancement plan
saving and will be evaluated later by different study. mentioned in this paper is implemented.
ACKNOWLEDGMENT
IV. FUTURE ENHANCEMENT PLAN
We convey our appreciations and gratitude to AADC
• Set the controller for existing capacitor banks at
management, and all AADC team.
primary substations to 0.97 desired power factor will
add further enhancements and savings. REFERENCES
• Ensure that controller settings for existing capacitor [1] Maha. AlDahmi, “A Review of Factors Affecting Electricity Peak
banks at PRY switch the stage ON if required Demand in Al Ain Area,” 2018 IEEE PES Asia-Pacific Power and
MVAR is 0.5: 0.6 of stage MVAR value to increase Energy Engineering Conference (APPEEC), 2018.
probability to switch on more stages/more time. [2] J. Ware, “Power factor Correction,” IEE Wiring Matters Journal,
• Include re-location the OHL capacitor bank in the Issue 18, PP 22-24, Spring 2006.
scheme of undergrounding the OHL to alternative [3] Yasin Kabir ,Yusuf Mohammad Mohsin, “Automated Power Factor
location for optimal utilization of AADC assets. Correction and Energy Monitoring System,” Second International
Conference on Electrical, Computer and Communication
• Advise technical specifications committee to Technologies (ICECCT), 2017.
evaluate adjustable controller settings for new [4] C L Wadhwa, Electrical Power Systems, 4th edition, Page 204. New
capacitor banks units are at primary substations to Age International Publisher, 2006.
switch the stage ON if required MVAR is 0.4: 0.7 of [5] A. Singh, M. Srivastava, “Power Factor Correction using capacitor
stage MVAR , to increase the probability to switch bank under Variable Load Condition,” INPRESSCO, Vol.8, No.5, PP
on more stages/more time. 1204-1209, Sept/Oct 2018
• For future OHL reactive power compensation [6] Gustavo Brunello, Dr. Bogdan Kasztenny, Craig Wester, Shunt
projects, smaller fixed type units compared with Capacitor Bank Fundamentals and Protection, 2003 Conference for
Protective Relay Engineers-Texas A&M University, April 8-10, 2003,
existing (300, 600 KVAR switchable) to be used. College Station (TX).
V. RECOMMENDATION [7] Shahram Kaykahie , Sina Kowsari “A New Approach For Calculating
Load and Loss Factor Base on Consumer Data With Fuzzy
The improvement of Power Factor can be achieved along Modelling,” 22 nd International Conference on Electricity
with expected saving (AED 18 Million) by utilizing the Distribution, 2013.
existing capacitor banks without any additional investment. [8] AADC offical website Water and Electricity Tariff:
Reviewing the status/condition of existing capacitor https://www.aadc.ae/pdfs/Tariff/Tariff2017Englishwebsite.pdf
banks units, related controller status/condition and settings at

162

You might also like