Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Benefits Assessment of Fault Current Limiters in a Refinery Power Plant:

a Case Study.
A. Cali S . Conti F. Santonoceto G. Tina
DipartimentoElettrico, Elettronico e Sistemistico
UniversitA degli Studi di Catania
Viale A. Dona, 6 1-95 125 Catania, Italy
E-Mail: gtina@dees.unict.it

Abstract: Growth of industrial power plants and load increasing of grounding transformers. However, another heavy
typically result in increased available short circuit currents that problem remains unsolved that is the high short circuit
can easily exceed the interrupting capacity of the installed circuit current present in the plant.
breakers, whose capacity is also limited by aging. Complete In [l] the need for replacement of the 14.4kV breakers
replacement of the existing breakers, whose characteristicsare no
longer suitable to that application, may not be economical and has been highlighted and claims attention not only due to
can require customized breakers, as in the case of the actual the higher and higher values of the prospective short circuit
industrial plant studied in this paper. currents; in fact, the difficulty in finding proper spare parts
m e r describing the refinery power system the results of accurate (by now out of production) and the high maintenance
short circuit calculation in compliance with both IEC and charges would suggest a similar solution.
ANSI7IEEE Standards are reported; considerations on selection On the other hand, the replacement of about fifty MV
of appropriate breakers for the analysed installation and issues of breakers, unless through a preliminary effective solution to
short circuit current limitation are highlighted; a cost effective the short circuit current limitation problem, would be
solution in then proposed based on the use of CLiPs (Current unfeasible, because proper breakers could not be mass
Limiting Protectors), along with criteria for the correct choice
trigger level and peak let-thru values. Economical evaluation of products but only customized items (due to the high value
the proposed solution supplement the work. of the required percentage d.c. component).
In [ 13 the conducted study proposes to install between the
Keywords: Circuit breaker, Electronically Triggered Current generators and the 14.4kV busses some insulation
Limiter, Distribution System, Short Circuit. transformers. This would allow the neutral grounding,
insulating at the same time the generators fiom the network
I. THE REFINERY POWER PLANT and impro.ing the system stability as well as generators
life eqectation. The proposed solution, however, is not
AGIP Petroli oil refinery was built during the 70s and economically attractive because, besides the high
covers an area of 5km2. The thermoelectric power plant purchasing and installation costs of the new transformers,
(TPP) provides steam and electric energy to the whole the reduction in the three-phase short circuit currents (with
industrial plant and to the Electric Utility (ENEL) as well.
Vcc=22%, for the insulation transformers) is not great
The TPP consists of four turboaltemators connected in enough to significantly reduce the expenses due to the
parallel, by means of A, B, C and D 14.4kV busbars and unavoidable replacement of the 14.4kV breakers.
R1, R2, R3 limiting reactors (Fig. l), with the primary Thus, the present work aims at performing a technical
distribution system (14.4kV); the neutral wire is and economical analysis concerning the use of
ungrounded. electronically triggered hses in order to limit the short
In normal operating conditions the TPP is connected in circuit currents; this solution, in turn, would lead to the use
parallel with two ENEL lines (“ENEL Gela” and “ENEL of mass production breakers with limited costs.
San Cono”) through two 87.5MVA transformers (referred
to as TRl and TR2 in Fig. 1) sited at a 150kV substation.
11. LOADFLOW
This connection with the grid is exploited to provide
energy to the Utility, during normal operation, and as
Load flow calculations for the considered power plant
back-up source in case of partial or total TPP outage.
have been performed by ETAP (Electromagnetic Transient
In the industrial plant the electric distributions is realised
Analyser Program) on the simplified single-line diagram
by a secondary selective system. At present, the TPP
described in Fig. 1. In the plant operation considered for
configuration involves G1 and G2 generators connected in
the load flow calculation, the power system’is divided into
parallel through a reactance (Rl) (eastern section of the
two sub-systems (referred to as eastern and western
plant) and G3 and G4 generators parallel by R3 (western
section). The analysed configuration, characterised by the
section). These two sections are connected in parallel with
connection of TRI and TR2 with A and D busses,
the 150kV stage and with the Utility lines by means of
respectively, is the typical configuration in normal
TRl and TR2, respectively.
operating conditions. The power supplied by the generators
The described industrial plant has been subject to various
and drawn by the loads are reported in Tab.1
studies during the least years (the last one dates back to
1995 [l]) in order to identify technical solutions able to Tab. 1 Power supplied by the generatorsand draw by the loads.
avoid, or at least, to limit, the periodical heavy outages
mainly due to overvoltages at the 14.4kV stage following G1 6 2 63 64 L1 L2 LJ L4
intermittent arcs (due to ungrounded neutral wire). ActivePowerIMWj 60 60 67 40 57.9 59.3 26 12.2
The problem has been overcome thanks to the adoption ReactivePowerlMVARl 39 39 53 35 39.7 51.3 26 5.4

0-7803-6338-8/00/$10.00(~)2000IEEE 1505
111. SHORT CIRCUIT CURRENTS CALCULATION IV. CIRCUIT BREAKERS SELECTION
The considered plant configuration is characterised by The breakers that are more liable to stress are those
the connection of TRl and TR2 with A and C busses, installed at the 14.4 kV A and C buses to protect the
respectively; this configuration is of interest in our study feeders.
as it involves the maximum short circuit currents due to If a short circuit occurred downstream the terminals,
the paralleling of G3 generator, which has the highest rated these breakers would have to interrupt the highest fault
power, with TR2 transformer, without the interposition of current, due to the contribution of both a generator and a
R3 reactor. HVMV transformer, and of the adjacent bus through the
As said before, the short circuit currents calculation has tie-reactor as well, supplied by a further generator.
been carried out by ETAP, according to both IEC and The stress assessment (according to IEC 909) the
ANSVIEEE standards; then, a comparison has been made breakers must withstand during a three-phase short circuit
between the results obtained following the two different has been made assuming a minimum breakers delay, t,,,,*, of
guidelines. In the following some observations have been 100 ms. The characteristics of the existing breakers are
reported: derived by ETAP according to IEC 56, based on the data
Comparing the,Yalues of the initial qmmetrical short included in Tab. 2.
circuit current, I , , (IEC) and the first-cycle duty. &,
(ANSI). the differences are quite small. in the order of a Tab. 2 Characteristics of the breakers presently installed and short circuit
few percentage points, whichever point in the circuit our current values.
calculation is referred to; &vice Capacity (U) Short Circuit Current (kA)
These differences are due to the approximations that are Making I I~ I I& ~ ’ r I i, I I b I bc
intrinsic to the empirical calculation followed by both IEC 155 I 62.00 I 9.67 72.44 I
204 I 57 I 41
and ANSVIEEE methods; in particular, the results
obtained through the European Norm are higher than those In [l] it is suggested to replace the 14.4 kV breakers with
obtained through the American Standard. Similar results others whose characteristics are reported in Tab. 3 (where
can be observed in [2], where a compared analysis the characteristics of the presently installed breakers and
IEC/ANSI is carried out; those prospected in the present work are also indicated).
Comparing peak short circuit current, ip, e first-cycle Based on the performed calculations (Tab. 2), proper
peak fault current, the values calculated by IEC are always ratings for required breakers without any limitation on fault
higher, in accordance to [2]. currents are indicated in Tab. 3.
As for a comparison in terms of the ratio X/Rbetween In particular, the proposed percentage d.c. component
IEC and ANSYZEEE there is no reference in .[2]. On the (calculated on the proposed breaking capacity of 63kA) is
other hand, this comparison could be meaningless as the 46.7% for tmi,=lOOms.The realization of a suitable breaker
two standards *perform the calculation of X/R in rather could only be possible subject to a specific agreement with
different ways: in the IEC method an equivalent the manufacturer to guarantee the breaker ability to
impedanceis worked out and a correction factor is used; in interrupt the calculated I b together with the percentage dc
the ANSVIEEE method, separate networks are employed component of 46.7%. In some network points, our results
to calculate the equivalent resistance and reactance and related to the peak short circuit current (ip) calculation are
each circuit is derived by applying empirical correction higher then 160 kA, calculated by [11.
factors indicated by the Standard.

Enel Gela Enel S. Con0


252-El 252-E2
I 1

150 kV 224-E ‘0

Fig. 1 Single-line diagram ofthe power plant ( n o d operation); the darkened squares represent closed breakers.

1506
The results relative to ip calculation show that the strict reliability requirements and easier to be achieved.
making capacity of the breakers suggested by [11 would
not be sufficient to ensure effective protection.

Tab. 3: Comparison among different breakers characteristics.

a) b) c)
Presently Breakers Breakers
installed breakers proposed proposed in our
in PI
Rated Voltage 17.5 kV 17.5 kV 17.5 kV
Symmetrical 53-62kA 63kA 63 kA
breaking capacity
Making Capacity 155 kA 160 kA >205kA
Percentage d.c. ... > 81% 46.7% U 0 05 01 0 15
component TD(s) = looms t [ins]
Fig. 2 Short circuit current at G3 terminals.

On the other hand, these limiting devices are


intrinsically unable to reduce the current peak value.
To accomplish this function the current limiter has to act
in a shorter time, that is less than a quarter of a period.
Let us consider, for instance, a symmetrical short circuit
current with rms value of the prospective current of
27.8kA. Aiming at limiting the peak short circuit current to
16kA (i.e. Let-Thru = 16 kA peak), let us assume a sensing
value of 10 kA [4]. Then:
1
to = -arcsin(=) =8 5 0 ~
0

and
- t o = 1387 - 850 = 5 3 7 p (2)
0

Where:
to, is defined as the first period (0 to to) from the instant
of fault to the time when the trigger level is reached;
0 At,,, is the analysing time required by the electronic
circuitry before a triggering pulse is generated;
0 Atrim,is the limitation time given by the sum of cutting
time of the main conductor, commutation time, fuse
melting time, arcing time.
Then, the limiting device has 537 ps to its disposal, from
V. SHORT CIRCUIT CURRENT LIMITATION the instant of fault, to analyse the current (to avoid
nuisance tripping) and in case to limit it. Limiters have to
The current limiting devices can be classified into two perform with the maximum degree of reliability since a
main categories according to weather the short circuit non-operation on a short circuit condition can result in
current has to be limited and/or interrupted before the first widespread damage of the breaker as it is continuously
peak is reached or after the first zero-crossing. subjected to much higher short circuit currents, above its
In this two different cases issues and benefits related to rating. The main advantages coming from the use of such
the use of a current limiting device are quite different. limiting devices are:
Those devices that act after the first zero-crossing of the 0 The reduction of the cost of breaker replacement due to
fault current, can be used to improve service quality; for lower short circuit current rating requirements;
example, it is possible to limit amplitude and duration of a Reduced safety hazards to personnel;
voltage sag following a fault beneath the levels required by 0 Reduced electrical and mechanical stresses.
sen sible appliances . As for the case of the considered refinery plant, the short
This type of limiter is quite easy to realize and the circuit analysis indicates the installation of limiting devices
longer time available to detect the fault generally allows to (acting before the first current peak is reached) as an
avoid nuisance tripping. effective solution especially for the problems related to the
Limitation of the current after the first zero-crossing high peak value of the fault currents.
allow to divert the current in the limiting device with very
low current values (nearly zero) causing very small VI. FAULT DETECTION METHODS
overvoltages; it is to be noted that such devices concerned
more with service quality than with security will have less The fault must be detected quickly so as to limit the

1507
current during the first half-cycle. The main parameters the peak value is:
involved in fault detection are: (4)
I2peak f i . I 2 m s , s y m +‘2dc 7
i(t), instantaneous current value;
0 di/dt, rate of current rise [8]. whereas the rms of il(t) e:
Fault detection methods are generally based on the
combined examination of the aforesaid parameters and on
their persistence above a certain threshold value (trigger Under the same peak value, the rms value of
level) for a minimum time, A s e n [5]. symmetrical current is greater than asymmetrical.
Then we can consider the derivatives of il(t) and iz(t).
A. “Instantaneous crest current” sensing method
di,(t)/dt = mI, = ~ f i I l ~ ~ ~ (6)
The threshold sensing method is based on the
measurement of the instantaneous current value. A trigger di2(t)/dt= @ I p =wfi12rms,sym(
l + e -ctg4:++) sin 4 ) (7)
signal is sent to the current limiter only after the fault
current has exceeded a given value, the so called “trigger where I, is the maximum value of i2(t)for a given X/R.
level”, keeping above it for a given time interval, A,,,
(“trip initiation delay”).
In order for the detection method to be effective, the
trigger level and A,,,have to be selected carehlly to avoid where: f ( 4 ) = w( 1 + e
nuisance tripping due to both current spikes (lightening
and capacitive switching, whose duration seldom exceeds Since the ratio X R ranges between 9 and 80 in most of
100 p) and slower transient currents (motor and the industrial plants [6,7], then df(&ranges between 1.71
transformer inrush currents) [SI. The selection of a higher and 1.96. For a given I, ,the differential trigger level has to
trigger level, though favourable to the avoidance of a be selected taking into account to the fault current with the
nuisance tripping, on the other side imposes the reduction maximum DC offset to guarantee effective protection, even
of the trip initiation delay A,,,. if the possibility for nuisance tripping to occur can not be
Considering that symmetrical short circuit current’ can excluded; this is more likely to happen in those plants
be assumed linear with time in the first instants following a where the ratio X/R is higher.
fault, the trigger level can be considered proportional to to; However, as in the case of the “Instantaneous crest
under the hypothesis that the increase in the trigger level current” sensing method, the accurate selection of the
triggering value is on a “trail and error” basis.
does not cause an increase in At,i,, A,,, reduces as much
as to increases (under the same let-thru current).
C. Dual sensing method: i and di/dt.
In any case, the selection of the triggering value is on a
‘’trail and error” basis [6].
This dual sensing method is based on the magnitude of
the fault current and on di(t)/dt, and both these must exceed
B. “Rate of current rise” sensing method.
the set value for operation. This method may prevent
This method is based on the measurement of the nuisance tripping due to high frequency transients without
quantity di/di. A trigger signal is sent to the current limiter using Atsen, required, instead, by the instantaneous crest
only after di/di has exceeded the “differential trigger current sensing method.
The main issue with this method is the correlation
level”, keeping above it during a time interval Asen of
between the two trigger levels for i and di/dt . Such a
about 100 ps.
correlation can be achieved based on (6B) where I, must be
The advantage of di/dt sensing method is due to the
replaced by the selected trigger level.
reduction of to that slightly depends on the d.c. offset but is
Taking into account the current lagging with respect to
deeply influenced by the initial phase of the voltage (for
its derivative (slightly influenced by the d.c. offset) the
instance, to is equal to zero in case of symmetrical fault
following triggering method can be adopted:
current). However, the first derivative peak occurs about a
When the differential trigger level is exceeded then the
quarter of a cycle before the first current peak.
current sensor is activated for a fixed time interval (>5ms).
The differential trigger level must be determined as a
If the magnitude trigger level is also exceeded during this
function of the peak value of the limited fault current.
period, a triggering pulse is sent out to the limiting device.
Some uncertainties affect the choice of the proper
trigger level due to the influence of the d.c. offset and X/R
VII. SHORT CIRCUIT CURRENT LIMITATION IN
ratio.
THE AGIP PETROL1 REFINERY
Let us consider the two currents, ilo) and i2(t), the first
symmetrical and the second asymmetrical (DC offset
Consider the eastern section of the power plant (Fig. 1).
I~deZo),having the same peak (I,), but different rms values.
Due to the relatively high number of 14.4kV feeders, it is
The r m s of iZ(t) during the first cycle is:
economically not feasible to install a Clip for each feeder;
12, =d;- (3) moreover, this solution would not be appropriate since it
would not assure coordination in the protection scheme.
Let consider, then, the possibility to install a CLiP at the
I In case of maximum ’cal c u m 4 the value reached by the bus-tie between A and B busses (Fig. 3 a).
short circuit current is greater,but the current rise rate is slower.

1508
Enel Gela 150 kV Enel S.COM) 150 kV VIII. TRIGGER LEVEL AND PEAK LET-THRU
252-EI 252-E2
Z2+E
The use of Clip allows to install breakers that are
available in mass production. In the studied case, for
example, it has been possible to choose a breaker with the
maximum interrupting rating for a nominal voltage of 17.5

14241 8 14243
kV, SFs type, made by Nuova Magrini Galileo, whose
characteristics are reported in Tab. 5 .
Tab. 5 Breaker ratings in compliance with CEI 17-1 and IEC 56.
Circuit breaker type 17 GL 40
Rated Voltage (50 and 60 Hz) r7.5 kV
Insulating level at power firequency 38 kV
Impulse insulating level I 95kV
Rated current I 1250+4000A
Fig. 3 U) A CLiP is installed at the bus-tie between A and B busses. I Short time Current (3 sec) I 40kA I
Symmtrical breaking capacity (1,J
40 kA
(Operating sequence: 0-0.3sC0-3mC0)
Making Capacity (Im) 100 kA peak
Enel Gela 150 kV End S. Con0 150 kV Opening Time 70 ms
1 I
252-El 252-E2
Then, the breaking current, I b , has to be limited to 40 kA,
while the peak current, ip, to 100 kA.
224-t1 If the short circuit intensity is such to cause CLiPs
tripping, the value of the current, I,, that the breaker will
have to interrupt is equal to the current due to TR-I;
however, the current value will be less then 40 kA, as
indicated by Tab. 5. In fact, the CLiP acts so quickly that
G1 and G2 sources do not contribute to Ib. The same
situation occurs wherever the fault is located (e.g., next to
G1 or G2).
Based on the characteristics of the chosen breaker (Tab.
5 ) it is necessary to determine the appropriate trigger level
Fig. 3 b) Two CLPs are installed between A1 and A2,A2 and B busses and the let-thru current of the two adopted CLiPs (that we
respectively. can assume the same).
The trigger level must be determined when each source
Considered the unequal contribution to the short circuit provides the maximum contribution to the fault current, In
current of each source (Gl, G2 and TRl), the application the considered study this situation is represented by a fault
of a CLiP in the considered position could reduce the at the F point in Fig. 3, where the maximum contribution
prospective short circuit current below the making current by G1 and G2 is limited by the CLiPs trigger level. In this
of both the installed breakers and those proposed in [l], case the following relation holds:
but this would not lead to any substantial economical 2.triglev.
benefit in case of replacement of the installed breakers. In Ik.TR1 5 3 ’ triglev. (9)
fact, the CLiP would limit the short circuit current to about Ji
50 kA due to the solely limitation of G1 contribution to the since 1 ” is~ lower
~ than
~ I”L;,G~ and I ” ~ G * .
fault. This leads to the following relation between l b and I,,
The more appropriate configuration seems, then, to be (rated short circuit current):
the one proposed in Fig. 3 b), where the A bus has been J?i
I 3 .triglev./ IlSc (10)
divided into two parts (A1 ed A2) in such a way to allow fiom (10) it is, finally, possible to define an upper limit
the insertion of a second limiter. In Tab. 4 the short circuit for the trigger level given by:
currents are reported; they are worked out according to
IEC 909, in case of a short circuit occurring at the F point triglev.5 (J?i/3).40z 18.9kApeak (1 1)
(Fig. 3 b), when the bus-tie breakers between Al, A2 and Similarly to the above line of reasoning, we have to find
B busses are closed (for seek of simplicity the contribution the CLiP let-thru current in such a way that the value of I,
of the motors has been neglected). is be lower than the breaker making current (I,,,) (Tab. 5 ) ;
the heaGer case happens when the fault occurs in F and the
Tab. 4 Contribution ofGl and G2 generatorsand TRl transformer to the
CLiPs have opened the circuit.
fault current value at F point, In this case:
i, Iip,Trl+ 2 - peak -let - thru (12)
GI, G2 TRI
r’; 26.8 k ~ m23.2 k ~ m From the above observations it is then possible to obtain
i. 67.5kApeak 63.3 kApeak an upper limit for the peak let-thru value:
L(IO0 ms) 18.3 kAm 23.2 k A m
24.2 kA 15.2kA
peak - let -thru 5 (100 - 63.3)/2 E 18AkApeak (13)
iDC
The adopted triggering criteria is the threshold sensing
method described in Section VI, A.

1509
Considering the maximum transformer and motor inrush at the tie-locations in order to limit short circuit current
currents, which the current limiter may be subjected to a value, power losses could be limited and the system
trigger level of lOkA, according to [6], is high enough to stability would also be improved.
avoid nuisance trip and at the same time, respects Eq. (1 1); Due to the fact that continuity is crucial to industrial
as proposed in Section VI, At,,, is set to loop. Then, it is facilities with critical processes, like in the studied case,
necessary to check that the peak-let-th of the chosen other cost-effective technical solutions based on CLiP, with
current limiting fuse verifies Eq. (13). This can be higher reliability, should be accounted for to solve the short
accomplished referring to the diagram “let-thru current vs. current limitation problem. A valid solution should avoid
prospective symmetrical short circuit current” available in the possibility that after the CLiP operation part of the load
[9]: according to this, an initial short circuit current of is de-energized or that some generators are overloaded. For
26.8A and a sensing level of lOkA lead to a 16kA instance, for the studied case, we could keep using reactors
(instantaneous) let-thru current, that satisfies Eq. (13). (with a high enough vcc) bypassed with CLiPs. This
However, the choice of the aforesaid trigger level combination maintains the benefits of the reactors without
(1OkA) has a drawback: if a fault were to occur on bus A2, the operation drawbacks (high energy losses and voltage
both CLiPs would need to operate; if a fault were to occur drops). A further study will be performed on this latter
on bus A1 or B, one would want to trip only on CLiP, not solution to allow a technical and economical comparison
both sets. To avoid this, the trigger level should be 18kA, with the one presented by this paper.
but the upper limit for the peak let-thru would be
exceeded; so, in this case a trial and error method should X. REFERENCES
be applied to check the correct application of the CLiP.
I11 CESI REPORT: ELC 95/021240 (1995).
I21 AJ. Rodolakis, “A Comparison of North American (ANSI) and
IX. COST ASSESSMENT AND FINAL REMARKS European (IEC) Fault Calculation Guidelines”, IEEE Transaction
on Industry Application, Vol. 29, No. 3, May/June 1993.
In 1999, two 1516 kV sub-stations have been installed 131 R.E. C o d , T.G. Hazel, G. Thomasset, “IEC mediumvoltage
in the refinery in order to cope with load increasing; thus circuit-breaker interrupting ratings - unstated short circuit
the purchase of two breakers with relative boards, whose considerations”, IEEE Transactions on Industry Applications, Vol.
36, No. 3, May/June 2000, pp. 884-892.
characteristics are indicated by [5], has been necessary. 141 H. M. Pflanz: T. F. Clark, O.J. Albani, ”The Development of the
From this the assessment of the involved costs has been Current Limiting Protector (CLP)”, IEEE Trunsaclion on Power
derived: Apparatus andSystems, Vol. 100, No. 7, July 1981.
151 E. F. King, A Y.Chikhani, R. Hackam, M. M. A Salama, “A
0 #2 breakers: 85.000 € MicroprocessorControlled Variable Impedance Adaptive Fault
#2 boards: 80.000 € Current Limiter”, IEEE Transactions On Power Delivery, Vol. 5 ,
The cost assessment due to replacement of the whole set No. 4, November 1990.
of 14.4kV breakers (50 units) provides an amount of [61 A Y.Wu, Y. Yin, “Fault Current Limiter Applications in Medium
and High Voltage Power Distribution Systems”, IEEE Trunsacrions
4.000.000 €, not including installation cost. on Industry Applicutions, Vol. 34, No. 1, January/February 1998.
On the other hand, the adoption of the solution proposed 171 R. M. Rifiat, “Considerations for Applying IEC Standards in Short
in the present study, that allows to replace the existing Circuit Calculations and Breaker Selections in Cogeneration
breakers with others whose characteristics are summarised Plants”, Proc. of the 1998 IEEE Industry Applications Conkrewe,
pp.205-222.
in Tab. 5 , would have a cost of 1S00.000 € (a breaker plus PI T. Chao, ‘‘Electronically Controlled Current Limiting Fuses”, Proc.
relative board costs 30.000 e). of the 1995 IEEE-IAS Pulp and Paper Industry Tech. Cod., Vol. 3,
The cost of a CLiP, including fault detection devices, pp. 2299-2304.
control circuits and the containing board, is about 75.000 191 G&W, “CLiP - Current Limiting Protector for system rated 2.8kV
through 38kV, currents up to 3000A”, catalogue SG4-31G, March,
€. To apply the proposed modifications to the refinery 1993.
plant, four CLiPs would be necessary (two for the western
section of the plant and two for eastern one). The overall XI. BIOGRAPHIES
cost would be 300.000 €. Since it would also be necessary
to perform some structural changes on the bus system (A Alfred0 Cali was born in Catania (Italy) in 1931. He received a degree
and C busses would be divided into two separate systems in Electrical Engineering h m the University of Pisa in 1963. In 1973 he
(A1 and A2, C1 and C2), some meagre additional costs joined the Department of Electrical and Electronic Engineering at the
have to be taken into account. university of Catania, where he is an assistant professor. He is in charge of
CNR (Centro Nazionale delle Ricerche) Power System Research Group of
The assessment of the required investment to implement Catania and he is a member of CEI Standard coordinating committee on
the proposed solution has, obviously, to be concluded by Electrical Sa&y in LV Distribution (SC64D).
the evaluation of the benefits in terms of short circuit Stefanie Conti (IEEE Student Member) was bom in Catania (Italy) in
1971. In 1997 she received a degree in Electrical EngiOeering with
currents reduction. Firstly, it is to be noted that the peak honours h m the University of Catania, where she is currently working
S.C. current value is halved as it passes fiom more than 200 towards PhD in Electrical Engineering. Her present research interests
kA to less than 100 kA. This implies that the stress that all include optimisation techniques and power system operation.
the devices connected in series to the faulted circuit would Giuseppe Tina (IEEE Member) was bom in Siracusa (Italy), on
January 6, 1964. He received the degree in Electrical Engineering h m
undergo would be enormously reduced. This would result, the University of Catania in 1988 and the W.D degree in 1992. He
in turn, in reduced equipment aging and in increased worked as an electrical engineer in facilities of Agip re6nery in Gela
security for personnel. Secondly, the possibility of buying (Italy) and in ST Microelectronics in Catania h m 1992 to 1996.
mass production breakers, besides reducing purchasing Currently, he is power plant researcher at the Electrical, Electronic and
costs, allows to reduce maintenance charges. Finally, SistemiStic Deparbnent of the University of Catania. His main research
interests are Wind-Electric Conversion Systems, hybrid plants
thanks to the suppression of the reactors presently installed optimisation and Fault Current Limiters.

1510

You might also like