Professional Documents
Culture Documents
Cycle Time January 2021
Cycle Time January 2021
Shotcrete
Breaker Material & Fill Sandbag
Break
Steel Support For Shoring
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Jan 5 Charge + Blast
Chainage Muck
Scal
Steel Support
Shotcre
Wiremesh te 6
Shotcrete 6 Kubik
Rockbolt/Forepole Kubik
Shotcrete
Day Wed Drill
Date Jan 6 Charge + Blast
Chainage Muck
Scal
No Acti
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Tue Drill
Mixing Material Shotcrete
6
Date Jan 7 Charge + Blast
Chainage Muck Setting K
Cleaning
Mixing
u
Break
Scal Normed +
Material
Waiting b
Steel Support Shotcrete
Material i
Wiremesh Shotcrete 6 k
Rockbolt/Forepole Kubik
Shotcrete
Day Fri Drill
Date Jan 8 Charge + Blast
Cleaning Normed
Chainage Muck
Scal
Break Cleaning Normed
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Sat Drill
Date Jan 9 Charge + Blast
Chainage Muck Repair
Break
Scal Normed &
Steel Support Setting
Legdrill
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Day Sun Drill
Date Jan 10 Charge + Blast
Chainage Muck Install RRS
BREAK
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete Rebar 36 Btg
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Diversion Activity
Tim
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
Day Mon Drill
Date Jan 4 Charge + Blast Fabrikasi Rebar
Chainage Muck
BREAK
Scal / Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Concrete Invert
Shotcrete
Day Thu Drill
Date Jan 5 Charge + Blast
Cleaning Lantai
Chainage Muck
BREAK
Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete Concrete STA 240 - 267
Day Wed Drill Concrete Invert STA 208.9 -
Fabrikasi Rebar
Date Jan 6 Charge + Blast 220.1
Chainage Muck
BREAK
Breaker
Steel Support
Wiremesh JI Survey KMH
BREAK
Rockbolt/Forepole
Shotcrete
Day Tue Drill
Date Jan 7 Charge + Blast
Chainage Muck Breaker Crown STA 280 Breaker Wall STA 280
BREAK
Breaker
Steel Support
Wiremesh Rebar STA 220,1 - 231.3
Rockbolt
Shotcrete
Day Fri Drill
Date Jan 8 Charge + Blast
Chainage Muck Breaker Crown STA 290
BREAK
Scal/Breaker
Steel Support JI Survey KMH
Wiremesh Concrete Invert STA 220.1 -
Finishing Invert
Rockbolt 231.3
Shotcrete
Day Sat Drill Cleaning Lantai + Lansir
Date Jan 9 Charge + Blast Material to Tunnel Pasang Stop Cor + Water stop
Chainage Muck
BREAK
Breaker
Steel Support Breaker STA 300
Wiremesh
Rockbolt
Elevation Shotcrete Install Rebar 231.3 - 242.5
Day Sun Drill
Date Jan 10 Charge + Blast
Chainage Muck
BREAK
Breaker
Steel Support Breaker Wall STA 30 - 20
Cleaning Lantai +
Wiremesh Persiapan Concrete + JI
Rockbolt Survey Finishing Invert + Fabrikasi
Shotcrete Concrete Invert STA 231.3 - 242.5 Rebar
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Chainage Muck
Scal
Steel Support
Prepare Shotcret
Wiremesh
Rockbolt/Forepole Shotcrete 12 Kubik
Shotcrete
Day Thu Drill Survey
Date Jan 5 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Survey
Date Jan 6 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt
Shotcrete
Day Tue Drill
Survey
Date Jan 7 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Fri Drill Survey
Date Jan 8 Charge + Blast
Chainage Muck
Scal
Break
Steel Support
Wiremesh
Rockbolt
Shotcrete
Day Sat Drill Survey &
Date Jan 9 Charge + Blast Marking
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Day Sun Drill Survey & Survey &
Date Jan 10 Charge + Blast Marking Marking
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Dewatering + Survey
Date Jan 4 Charge + Blast Marking
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Jan 5 Charge + Blast
Chainage Muck
Scal
Cr
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Jan 6 Charge + Blast
Chainage Muck
Survey
Scal
Crew Focused On Upstream
Steel Support
Wiremesh
Rockbolt Safety Sh
Shotcrete
Day Tue Drill
Date Jan 7 Charge + Blast
Chainage Muck
Scal
Crew Fo
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Fri Drill
Date Jan 8 Charge + Blast
Chainage Muck
Break
Break
Break
Scal
Break
Steel Support
Wiremesh Survey &
Rockbolt Marking
Shotcrete
Day Sat Drill
Date Jan 9 Charge + Blast
Chainage Muck
Scal Dewatering & Dew
Steel Support Crew Focused On Upstream Crew Focu
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Day Sun Drill
Date Jan 10 Charge + Blast
Chainage Muck
Dewatering &
Scal Dewatering &
Crew Focused On
Steel Support Crew Focused On Upstre
Upstream
Wiremesh
Rockbolt/Forepole
Shotcrete
IME f
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Waiting Shotcrete
erial & Fill Sandbag
For Shoring No Activity
Evaluasi
No Activity
Shotcrete 6
Kubik
Evaluasi
No Activity
Evaluasi
Mixing
Material No Activity
Shotcrete
Evaluasi
Shotcrete tertunda
Mucking terhenti
aning Normed No Activity
Evaluasi
BREAK
Repair
No Activity
Hose Air
Evaluasi
Drilling Dihentikan
Install RRS
BREAK
No Activity
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00 Kegiatan Concrete lebuh lama
Concrete Invert
Evaluasi
Install Water Stop &
Breaker Wall
No Activity
Evaluasi
abrikasi Rebar
No Activity
No Activity
Evaluasi
BREAK
No Activity
Pasang
Stop Cor
&
Waterstop
Evaluasi
Finishing Invert
Evaluasi
top Cor + Water stop
BREAK
No Activity
Evaluasi
BREAK
No Activity
er Wall STA 30 - 20
ng Invert + Fabrikasi
Rebar
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey & Marking
Evaluasi
Survey
Evaluasi
Survey
Survey & Marking
Evaluasi
Survey
Evaluasi
Survey
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Evaluasi
Evaluasi
Crew Focused On
Upstream
Evaluasi
Evaluasi
Dewatering
Dewatering
Dewatering &
Crew Focused On Upstream
Survey Evaluasi
Dewatering &
rew Focused On Upstream Dewatering &
Crew Focused On Upstream
Shotcrete 6 Kubik
Evaluasi Kendala Headrace Adit 1 Activity
Downstream
Day Mon Drill
Date Jan 4 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Thu Drill
Date Jan 5 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Wed Drill
Date Jan 6 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Tue Drill
Date Jan 7 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Fri Drill
Shotcrete tertunda Normed Rusak Date Jan 8 Charge + Blast
Mucking terhenti Kegiatan Mucking Downstream Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Sat Drill
Date Jan 9 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Evaluasi Kendala Day Sun Drill
Drilling Dihentikan Water Pomp Jumbo Trouble Date Jan 10 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala
Adit 2 Activity
atan Concrete lebuh lama Batching Plan Sempat Trouble
Day Mon Drill
Date Jan 4 Charge + Blast
Chainage Muck
Scal/Excavation
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Thu Drill
Date Jan 5 Charge + Blast
Chainage Muck
Scal/Excavation
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Wed Drill
Date Jan 6 Charge + Blast
Chainage Muck
Excavation
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Tue Drill
Date Jan 7 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Fri Drill
Date Jan 8 Charge + Blast
Chainage Muck
Scal/ Ekskavasi
Steel Support
Wiremesh
Forepole
Shotcrete
Evaluasi Kendala Day Sat Drill
Date Jan 9 Charge + Blast
Chainage Muck
Excavation/Scal
Steel Support
Wiremesh
Forepole
Elevation Shotcrete/Grouting
Evaluasi Kendala Day Sun Drill
Date Jan 10 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala
End Portal Activity
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
+ Survey&+&
Charge + Blast
Manual &
Andhang
Install
Marking
Marking
Pipa
Steel Support Angin &
Scaling
Scalling
Air
Setting
Wiremesh
Rockbolt/Forepole
Shotcrete
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Survey+ Setting Legdrill
Charge + Blast
+ Moving Andang
+ Moving Andang
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
+ Marking Setting Legdrill
Moving Andang + Setting
Charge + Blast
Clearing Smoke
Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang + Marking
Charge + Blast
Moving
+ Setting Legdrill
Andang &
Survey +
Steel Support Marking +
Setting
Wiremesh
Legdrill
Rockbolt/Forepole
Shotcrete
ang + Survey +
etting Legdrill
Moving An
+ Setti
Moving Andang + Survey +
+ Setting Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Prepare Maintenance
Steel lagging Jumbo Drill Access
Steel Support + Prepare
Wiremesh Shotcrete Shotcrete 5
Rockbolt/Forepole Kubik
Shotcrete
Charge + Blast
Prepare
Break
for
Steel Support & Dewatering
Shotcrete Dewatering
Wiremesh Shotcrete 5
Rockbolt/Forepole Kubik
Shotcrete
Excavation
untuk
Steel Support Kaki
Wiremesh Shotcrete Steelrib
Scalling crown
4 Kubik
+ Install Steelrib
Tambah
Galian
Prepare Shot
Break
untuk
Kaki
Shotcrete Steelrib
Scalling crown
4 Kubik
Rockbolt/Forepole + Install Steelrib
Shotcrete
Charge + Blast
Repair Ducting
Install Steelrib 1
BREAK
Set
Steel Support
Shotcrete
Wiremesh Shotcrete 6
2 Kubik
Rockbolt/Forepole Kubik
Shotcrete
4
Charge + Blast
K
Scal/ Ekskavasi Prepare Wet u
Oper Shift Shotcrete b
Steel Support
i
Wiremesh k
Shotcrete
Charge + Blast
BREAK
Excavation/Scal Prepare
Steel Support Shotcrete Shotcret
e6
Wiremesh Kubik
Shotcrete/Grouting
Charge + Blast
Prepare
face + Mobilisasi Drilling
Steel Support Shotcrete
Shotcrete Material dari Mahor Forepoling
Wiremesh 6 Kubik
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Preparation Mucking
Charge + Blast
Drilling Face &
Rockbolt 7 Pcs
Cleaning
Cleaning
Cleaning
Scal/ Excavation
Preparatio
Steel Support n Mucking
7 Kubik
Preparation Muck
Rockbolt 7 Pc
Drilling Face
Cleaning
Cleaning
Cleaning
Preparatio
n Mucking
Wiremesh 7 Kubik
Rockbolt/Forepole
Shotcrete
Mucking
Preparation Mucking
Charge + Blast
Rockbolt 13 Pcs
Drilling Face &
Cleaning
Cleaning
Excavation
Preparatio
Preparation
Steel Support n Mucking
Wiremesh 7 Kubik
Rockbolt/Forepole
Shotcrete
Charge + Blast
Survye & Top Up
Hydraulic Oil
Prepar
Excavation ation
Steel Support Mucki
ng
Wiremesh 3 Kubik 3 Kubik
Shotcrete
Prepartion Mucking
Preparation Mucking
Scal/ Excavation
Rockb
Steel Support olt 6
Shotcrete
Wiremesh Pcs
3 Kubik
Forepoling
Shotcrete
Survey
Preparation Mucking
Excavation
Steel Support
Wiremesh 3 Kubik
Rockbolt/Forepole
Shotcrete
Repair Compressor Genset
Drillin
Preparation Mucking
Cleaning
r +
BREAK
Excavation Rockb
v Rockb
Steel Support olt 13
e olt 13
Pcs
Wiremesh y Pcs 3 Kubik
Rockbolt/Forepole
Shotcrete
Drillin
Charge + Blast
g Face
+
Cleaning
Rockb
No Activity
olt 6
Pcs
leaning
Drillin
g Face
+
Cleaning
Excavation Rockb
No Activity
Steel Support olt 6
Pcs
Wiremesh
Cleaning
3 Kubik
Rockbolt/Forepole
Shotcrete
Moving Andang + Survey
+ Marking Setting Legdrill
Moving Material to Side
Wall
Moving Scafolding
Setting Andhang & &
Scaling Manual &
Marking
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Mucking Terhenti
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Welding Forepoling
Break
Evaluasi
Gali & Pasang Kaki
Pekerjaan Terhambat
Steelrib + Steel
Legging
Break
Evaluasi
Scalling dan Instal R Steelrib Terhenti
Break
Shotcrete 5
Kubik
Break
Shotcrete 5
Kubik
Evaluasi
Cleaning
Housekeeping, buat lantai
sumpit & Moving Untuk
Pompa Persiapan
Concrete
Evaluasi
Shotcrete Terhambat
Break
Shotcrete 10 Kubik
Evaluasi
prepare Shotcrete lama
Shotcrete Terhambat
Evaluasi
Shocrete Machine
Prepare & Setting
Welding
Break
Forepoling for
Steelrib
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Rockbolt 13 Pcs
Drilling Face &
Cleaning
3
Kubik
Rockbolt 13 P
Drilling Face
Cleaning
3
Kubik
Evaluasi
Cleaning
Drilling & Instal Rockbolt
Break
15 Pcs
Evaluasi
Preparation Drilling &
Driling
&
Install
Survey
Break
Rockbo
lt 26
Pcs
Evaluasi
Driling
&
Install
Rockb
olt 13
3 Kubik Pcs
Evaluasi
Pengupasan Lantai Untuk Pemasangan
Precast
Break
6 Kubik
Evaluasi
Prepare Mucking
Evaluasi
BREAK
No Activity
No Activity BREAK
Kendala
Kendala
Kendala
Pelindung Ban Lepas
Kendala
Howo 29,16,19 Trouble
Kendala
Hose water supply broken
Hose water supply terlepas 2 x
Kendala
Kendala
Kendala
Kendala
Kondisi air tinggi di depan face
Kendala
Ukuran R Rib lebih besar erhalang pipa
forepoling
Kendala
Kendala
Saluran Accelerator tersumbat material
Shotcrete
Kendala
Seal Sanchin Robek
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Kubik
Material
Steel Support Shotcrete
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Jan 12 Charge + Blast
Chainage Muck
Setting Normed &
Scal
Waiting Material
Steel Support Shotcrete
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Setting Grouting Machine
Breaker
Shotcrete 12
Steel Support
Kubik
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Tue Drill
6
Setting Normed for
ing Cleaning
Scal u
Mate Normed +
b
Steel Support rial Break
i
Wiremesh Fro
k
BP
Rockbolt/Forepole Grouting Rockbolt
Shotcrete
Day Fri Drill
Date Jan 15 Charge + Blast
Chainage Muck
Break
Breaker
Steel Support
Wiremesh
Shotcrete 18 Kubik
Rockbolt
Shotcrete
Prepare Jumbo for Drilling
Day Sat Drill
Date Jan 16 Charge + Blast
Chainage Muck Driling Rockbolt 493
- 497 ( 11 Hole) Driling Rockbolt 210 - 245
Break
Scal Install Install 68 Pcs STA 332 -
Install 17 Pcs STA
Steel Support 303 - 308 350
Wiremesh
Rockbolt
Elevation Shotcrete
Day Sun Drill
Date Jan 17 Charge + Blast
Chainage Muck
Scal
No Acti
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Tim
Diversion Activity
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
Day Mon Drill
Date Jan 11 Charge + Blast
Chainage Muck
BREAK
Scal / Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Jan 12 Charge + Blast
Chainage Muck
BREAK
Breaker
No Activ
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Jan 13 Charge + Blast
Chainage Muck
Breaker Demonstrasi
Steel Support Warga
Wiremesh
Demonstrasi
Warga
Rockbolt/Forepole
Concrete Invert STA 242.3 - 253
Shotcrete
Day Tue Drill
Date Jan 14 Charge + Blast
Chainage Muck
BREAK
Breaker
Steel Support Breaker Wall STA 240 -
Wiremesh 260
Rockbolt
Shotcrete Instal Rebar STA 30
Day Fri Drill
Date Jan 15 Charge + Blast
Chainage Muck
BREAK
Scal/Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Sat Drill
Date Jan 16 Charge + Blast
Chainage Muck
BREAK
Breaker
Concete Invert STA 30
Steel Support Breaker Bottom STA
Wiremesh 250 + Pasang Stop Cor
Rockbolt/Forepole & Waterstop + JI
Survey
Elevation Shotcrete
Day Sun Drill
Date Jan 17 Charge + Blast
Chainage Muck
BREAK
Breaker
No Acti
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Chainage Muck
Survey + Marking
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Survey &
Marking
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Jan 13 Charge + Blast
Chainage Muck
Scal
Crew
Steel Support
Wiremesh
Rockbolt
Shotcrete
Survey & Marking
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00 Kegiatan Terhambat
No Activity
Evaluasi
No Activity
Evaluasi
Shotcrete Lebih Lama
Shotcrete 12 No Activity
Kubik
Evaluasi
Cleaning
Grouting No Activity
Machine
Evaluasi
No Activity
Shotcrete 18 Kubik
No Activity
Evaluasi
Drilling Terhambat
Rockbolt 210 - 245
BREAK
tall 68 Pcs STA 332 - No Activity
350
Evaluasi
No Activity BREAK
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
BREAK
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
No Activity
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
No Activity
Evaluasi
BREAK
Evaluasi
BREAK
No Activity
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey &
Marking
Survey + Marking
Survey + Markin
Survey & Survey & Evaluasi
Marking Marking
hotcrete 12 Kubik
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey & Marking
Dewateri
Dewatering ng &
Standby
Evaluasi
Survey & Marking
Dewatering
Evaluasi
Survey & Marking
Evaluasi
Survey & Marking
Evaluasi
ey & Marking
Crew Focused On
m & Dewatering Upstream &
Dewatering
Survey & Marking
Crew Focused On
m & Dewatering Upstream &
Dewatering
Evaluasi
Survey + Marking
Dewatering & Standby
Evaluasi
Survey + Marking
Dewaterin Dewaterin
g+ g+
Shotcrete 6 Standby Standby
Kubik
Evaluasi Kendala Headrace Adit 1 Activity
Kegiatan Terhambat Demonstrasi Warga Downstream
Day Mon Drill
Date Jan 11 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Thu Drill
Date Jan 12 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Wed Drill
Shotcrete Lebih Lama Nozzle tersumbat batu Date Jan 13 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Tue Drill
Date Jan 14 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Fri Drill
Date Jan 15 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Sat Drill
Drilling Terhambat Engine Jumbo Drill Trouble Date Jan 16 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Evaluasi Kendala Day Sun Drill
Date Jan 17 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala
Adit 2 Activity
Evaluasi Kendala
End Portal Activity
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Charge + Blast
+ Survey
No Activity
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
rem Loader
+ Survey
No Activity ( Demonstrasi Warga)
Steel Support
Repair
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang & Marking
+ Survey
Warga
Steel Support Demonstrasi
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang & Marking +
Charge + Blast
Survey
O
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Marking + Setting Legdrill
Setting Andang & Survey
Charge + Blast
Setting Andang &
Marking
Break
Oper Shift
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Setting Andang & Survey Marking + Setting Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Marking + Setting Legdrill
Charge + Blast
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Time
Activity
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Charge + Blast
Prepare
Scal/Excavation
Break
Charge + Blast
Material
Scal/Excavation Demo
Steel Support nstrasi
Wiremesh Shotcrete 6
Rockbolt/Forepole Kubik
Shotcrete
Charge + Blast
BREAK
Excavation
Steel Support
Wiremesh Shotcrete 6
Kubik
BREAK
Shotcrete 6
Rockbolt/Forepole Kubik
Shotcrete
Charge + Blast
Setting Compressor
Dewatering Install Shotcrete trouble
Survey + Timbun
BREAK
Lantai Untuk Forepolin
Steel Support Dudukan Jumbo g
Wiremesh
Rockbolt/Forepole
Shotcrete
Scal/ Ekskavasi
Oper Shift
Steel Support
Wiremesh Dewatering
Shotcrete
Charge + Blast
Excavation/Scal
Brea
Steel Support k
Wiremesh Shotcrete 6 1 Set
Rockbolt/Forepole Kubik
Shotcrete
Timbun Lantai
Untuk Dudukan
Jumbo drill Ban Pecah
Timbun
Steel Support Lantai
Wiremesh Preparation & 6 Kubik
Rockbolt/Forepole Shotcrete 6 Kubik
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Preparation Mucking
Preparation Mucking
Charge + Blast
Scal/ Excavation
Steel Support
Shotcrete
Shotcrete
Shotcrete
Shotcrete
Shotcrete
Shotcrete
Wiremesh
Wiremesh
Wiremesh
Wiremesh
Wiremesh
Wiremesh
Excavation
Excavation
Excavation
Excavation
Steel Support
Steel Support
Steel Support
Steel Support
Steel Support
Charge + Blast
Charge + Blast
Charge + Blast
Charge + Blast
Charge + Blast
Charge + Blast
Scal/ Excavation
Rockbolt/Forepole
Drilling & Install Drilling & Install
Rockbolt 23 Pcs Rockbolt 6 Pcs Preparation Mucki
Preparation Mucking
Break BREAK
4 Kubik
Drilling & Install Cleaning
Break +
Mucking
Rockbolt 17 Pcs
Preparation
3 Kubik
Cleaning
3 Kubik
3 Kubik
Cleaning + Prepare
Drilling Preparation Mucking
Survey
6 Kubik
Cleaning
3 Kubik
3 Kubik
Drilling & Install Preparation Mucking
3 Kubik
No Activity
Drilling & Install
Rockbolt 17 Pcs
Break
Excavation
No Activity
Steel Support
Wiremesh
3 Kubik
Shotcrete
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00 Mucking Lebih Lama
drilling Terhambat
No Activity
Evaluasi
Moving Andang + Survey
+ Setting Legdrill
Evaluasi
Evaluasi
Oper Shift
Evaluasi
Marking + Setting Legdrill
Setting Andang & Survey
Evaluasi
Evaluasi
Moving Andang Survey +
Drilling Lama
setting Legdrill
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Shotcrete Lebih Lama
Demonstrasi
Evaluasi
Cleaning Equipment
Shotcrete Terhambat
Break
Shotcrete 6
Kubik
Evaluasi
Break
Shotcrete 6
Kubik
Break
Shotcrete 6
Kubik
Evaluasi
Install Stelrib Terganggu
Welding Forepoling
Break
Shotcre
te 6
Kubik
Evaluasi
Break
Evaluasi
Break
Forepoling 47 Pcs
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Shotcrete terhambat
Break
Break
3 Kubik
Evaluasi
Shotcrete terhambat
Kegiatan Terhenti
3 Kubik
Evaluasi
Kegiatan Terhenti
Tyre
BREAK
Howo
Problem
3 Kubik
Evaluasi
Cleaning
BREAK
3 Kubik
Evaluasi
Preparation Mucking
Drilling & Install
Rockbolt 6 Pcs
BREAK
Evaluasi
Preparation Mucking
Evaluasi
BREAK
No Activity
BREAK
No Activity
Kendala
Menggunakan 2 Howo + Mucking Material Sisa
Pipa Angin Pecah
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
V Cut 3.5 M dan Cut Hole 3 Metr
Cycle Tercepat
Week 46
Adit 1 Down
Drilling 90 Minutes
Charging + Blasting 60 Minutes
Mucking 150 Minutes
Scaling 30 Minutes
Survey + marking 40 Minutes
Mapping 30 Minutes
Kendala
Trouble Aliva
Normed Repairing
Kendala
Kendala
Kendala
Galian Bannyak Air
Kendala
Kondisi air banyak
Kendala
Kendala
Kendala
Aliva Machine Problem
Hose Shotcrete Problem
Kendala
Fuel Sistem trouble
Solar Habis
Kendala
Solar Habis
Kendala
Kendala
Kendala
Kendala
Cycle Tercepat Cycle Terlama
Adit 3 Up Adit 3 Down Adit 1 Down Adit 3 Up Adit 3 Down
90 80 180 Minutes 330 330
20 20 120 Minutes 40 40
90 90 320 Minutes 330
30 30 90 Minutes 40 40
30 30 60 Minutes 30 30
20 20 30 Minutes 30 30
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Grouting
Scal
Break
Rockbolt STA
Steel Support 350 - 380( 111
Wiremesh Pcs)
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Jan 19 Charge + Blast
Chainage Muck
Break
Breaker
Steel Support Rockbolt STA 380 - 407 ( 76
Wiremesh Pcs)
Scal
Shotcrete 6 Kubi STA 151 -
Steel Support Shotcrete 6 Kubi
154
STA 151 - 154
Wiremesh
Rockbolt
Shotcrete
Day Fri Drill
Prepare Install Rockbolt
6 Kubik
Break
Breaker
Steel Support
Wiremesh
Rockbolt 18 Kubik STA 161 - 182
Elevation Shotcrete
Day Sun Drill
Date jan 24 Charge + Blast
Break
Breaker
Steel Support Grouting Grouting Rockbolt & Shotcrete 12
Wiremesh Rockbolt Kubik
Rockbolt
Shotcrete 6 Kubik
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Diversion Activity
Tim
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
Day Mon Drill
Date Jan 18 Charge + Blast
Chainage Muck
BREAK
Scal / Breaker
Steel Support
JI Survey
Wiremesh
Rockbolt/Forepole Concrete Invert STA 264 -
Concrete Invert STA 264 - 276
Shotcrete 276
Breaker
Steel Support
Concrete Invert STA 40 Finishing Invert STA 40
Wiremesh - 60 & Breaker Wall - 60 & Breaker Wall
Rockbolt/Forepole STA 260 STA 260
Shotcrete
Moving Rebar to Tunnel +
Day Wed Drill
Install FormBox Dinding
Date Jan 20 Charge + Blast STA 164 - 186
Chainage Muck
BREAK
Scal
Steel Support Breaker Bottom STA 310 - Breaker Bottom STA 310 -
Wiremesh 281 281
BREAK
Rockbolt/Forepole
Shotcrete
Day Tue Drill
Date Jan 21 Charge + Blast
Chainage Muck
BREAK
Scal
Steel Support
Wiremesh
Rockbolt
Shotcrete
Day Fri Drill
Date jan 22 Charge + Blast
Chainage Muck
BREAK
Scal/Breaker No Activ
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Sat Drill
breaker lantai
Date Jan 23 Charge + Blast
Chainage Muck Cleaning
Lantai +
BREAK
Breaker
langsir
Steel Support Material
Wiremesh Ke Tunnel
Rockbolt/Forepole
Elevation Shotcrete
Day Sun Drill
Date jan 24 Charge + Blast
Chainage Muck
BREAK
Breaker
Steel Support Breaker STA 300 - 320
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Fri Drill Survey &
Date jan 22 Charge + Blast Marking
Chainage Muck
Break
Scal
Steel Support
Survey &
Wiremesh Marking
Rockbolt
Shotcrete
Day Sat Drill
Preparation SHotcrete
Steel Support
Marking
Safety Shotcrete
Wiremesh 12 Kubik
Rockbolt/Forepole
Elevation Shotcrete
Day Sun Drill Survey & Survey &
Date jan 24 Charge + Blast Marking Marking
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
No Activity
6 Kubik
Evaluasi
No Activity
kbolt STA 380 - 407 ( 76
Pcs)
Evaluasi
No Activity
Grouting
Rockbolt
Evaluasi
g Rockbolt STA
431 ( 17 Btg)
6 Kubi STA 151 - BREAK No Activity
154
Evaluasi
No Activity
k + Grouting
Evaluasi
No
No Activity
Activity
Evaluasi
No Activity
g Rockbolt & Shotcrete 12
Kubik
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
BREAK
Finishing
No Activity
Invert
Evaluasi
BREAK
No Activity
Invert STA 40
Breaker Wall
TA 260
Evaluasi
No Activity
ottom STA 310 -
281
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
Cleaning
BREAK
No Activity
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey &
Marking
Survey & Survey &
Evaluasi
Marking Marking
Evaluasi
Survey & Marking
Evaluasi
Survey & Marking
Survey + Marking
Safety Shotcrete
12 Kubik
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Surve
y&
Mark
ing
Crew Focused
On Upstream
Evaluasi
Survey & Marking
Evaluasi
Crew
Focused
On
Upstream Survey +
Marking
Evaluasi
Evaluasi
Crew Focused On
Upstream
Crew Focused On
Upstream
Survey &
Marking
Evaluasi
Evaluasi
Crew
Focus
Crew Focused On
ed On
Upstream
Upstre
Survey
am
Evaluasi Kendala Headrace Adit 1 Activity
Downstream
Day Mon Drill
Date Jan 18 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Thu Drill
Date Jan 19 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Wed Drill
Date Jan 20 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Tue Drill
Date Jan 21 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Fri Drill
Date jan 22 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala Day Sat Drill
Date Jan 23 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Elevation Shotcrete
Evaluasi Kendala Day Sun Drill
Date jan 24 Charge + Blast
Chainage Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Evaluasi Kendala
Adit 2 Activity
Evaluasi Kendala
End Portal Activity
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Charge + Blast
Marking
Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Charge + Blast
Legdrill
Marking
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang + Survey &
Charge + Blast
Legdrill
Marking
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang & Setting
Charge + Blast
Sholat Jumat
Legdrill
Legdrill
Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang & Setting
Legdrill
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Charge + Blast
Prepare Shotcrete
Scal/Excavation Welding
Steel Support Forepoling
Shotcrete 4
Wiremesh Kubik
Rockbolt/Forepole 6 Kubik
Shotcrete
Charge + Blast
Prepare Shotcrete
Prepare Shotcrete
Break
Excavation
Steel Support Shotcret
Wiremesh e6
Rockbolt/Forepole 6 Kubik Kubik
Shotcrete
Charge + Blast
Prepare Shotcrete
Steel Support
Kaki Kanan
Wiremesh Ribs + R Shotcrete 6
Ribs Kubik
Prepare Shot
Kaki Kanan
Ribs + R Shotcrete 6
Rockbolt/Forepole Ribs Kubik 10 Kubik
Shotcrete
Cleaning Equipment +
Charge + Blast
Moving
Timbun Lantai
Waterpum
BREAK
p+
No Activity
Steel Support Mixing
Material
Wiremesh
Shotcrete 6 Kubik
Rockbolt/Forepole
Shotcrete
Charge + Blast
Prepare Shotcrete
Scal/ Ekskavasi
Oper Shift
Steel Support
Wiremesh
6 Kubik
Shotcrete
Waitin
Machine
BREAK
3
Install Ducting
Welding Forepoling
Charge + Blast
Welding K
BREAK
Forepoling & u
Prepare b
Steel Support
Shotcrete i
Wiremesh k
Forepoling
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Preparation Mucking
Preparation Mucking
Charge + Blast
Scal/ Excavation
Steel Support
4 Kubik
Preparation Mucki
Preparation Muck
Wiremesh
4 Kubik
Shotcrete
Cleaning
Excavation 346 347
RIb
Steel Support
4
Wiremesh Kubik
Rockbolt/Forepole
Shotcrete Concrete LC Worshop
Bringout Jumbo
5 Kubik
Break
Preparation Mucking
Charge + Blast
Bringout Jumbo
Cleaning
BREAK
Scal/ Excavation
Steel Support
Wiremesh Shotcrete Shotcrete
Forepoling 7 Kubik 3 Kubik
Shotcrete
Preparation Shotcrete +
Preparation Mucking
Cleaning Filter Solar
Charge + Blast
Cleaning
BREAK
BREAK
Genset
Excavation + Prepare
Steel Support Install
Steelrib
Wiremesh Shotcrete
7 Kubik
Shotcrete
Hydraulic Hose Breaker
Preparation Mucking
Charge + Blast
Install Rockbolt
Hydraulic
Cleaning
Excavation 352
2 Kubik
Shotcrete
Charge + Blast
Shotcrete
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00 Mucking Terhambat
Briefing & Moving andang
+ survey + Setting Legdrill
Evaluasi
Moving Andang & Setting
Evaluasi
Moving Andang & Setting
Evaluasi
Mucking Terhambat
Evaluasi
Repair Road Access
Evaluasi
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Shotcrete Terhambat
Break
Evaluasi
Break
Evaluasi
Evaluasi
Break
Evaluasi
Break
Evaluasi
Prepare
Break
Jumbo
Drill
Evaluasi
Setting Shotcrete
Break
Evaluasi
24.00 01.00 02.00 03.00 04.00 05.00 06.00
Cleaning
Break
3
Kubik
ity
Break Preparation Shotcrete BREAK BREAK Break Break
BREAK
Prepare Install Steel Rib Prepare Install Steel Rib Install Bondex
Install Rockbolt
21 Pcs
Kubik
Preparation Shotcrete
350
349
Shotcrete 6
Prepare Shotcrete
3
Kubik
4 Pcs
Drilling
+ Install
Forepoli
Rockbolt
ng 28 Pcs
Forepolin
g 17 Pcs +
Kubik
Shotcrete 6 Cleaning
6 Kubik
Shotcrete
Install Bondex Install Bondex
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
ity
BREAK
Kendala
PLN Padam
Howo 17 & 20 Breakdown
Kendala
Howo 15,17,20 Breakdown
Kendala
Menghabiskan Material Sisa Blasting
Sebelumnya
Howo 16, 17, 20 Trouble
Kendala
Wheel Loader 18 Trouble
Howo 29 Bocor
Kendala
Week 47
Week 47
Kendala
Drilling
Charging + Blasting
Mucking
Scaling
Survey + marking
Mapping
Kendala
Kendala
Kompressor Trouble Hose Radiator Lepas
Shtcrete Tabung angin tersumbat material
Shotcrete
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Cycle Tercepat Cycle Terlama
Adit 1 Down Adit 3 Up Adit 3 Down Adit 1 Down Adit 3 Up Adit 3 Down
90 Minutes 90 80 150 Minutes 330 330
60 Minutes 20 20 90 Minutes 40 40
150 Minutes 90 90 320 Minutes 330
30 Minutes 30 30 150 Minutes 40 40
40 Minutes 30 30 60 Minutes 30 30
30 Minutes 20 20 30 Minutes 30 30
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Setting Normed
Chainage Muck
Breaker
Steel Support Install Rockbolt 94 batang ( STA 431 - 462) & Shotcrete 36 Kubi
Wiremesh (STA 191 - 213)
Rockbolt/Forepole
Shotcrete
Day Thu Drill
Date Des 26 Charge + Blast
Chainage Muck
Breaker
Steel Support Install Rockbolt 34 Btg ( STA 462 - 474) +
Wiremesh Shotcrete 24 Kubik ( STA 213 - 242)
Setting Normed
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Des 27 Charge + Blast
Setting
Chainage Muck Normed
Scal
Steel Support Install Rockbolt 37 Btg ( STA 474 - 487) + Shotcr
Wiremesh 12 Kubik ( STA 245 - 252)
Rockbolt/Forepole
Shotcrete
Day Tue Drill
Seting + Prepare install
Scal
Steel Support Shotcrete 24 Kubik ( STA 212 - 228 ) + Install Rockbolt 45 Btg (
Wiremesh STA 487 - 497)
Rockbolt/Forepole
Shotcrete
Day Fri Drill
Date Des 29 Charge + Blast
Cleaning Normed
Chainage Muck
Breaker Cleaning Area Upstream +
No Activity
Steel Support Breaker Floor
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Sat Drill
Date Des 30 Charge + Blast
Setting Normed
Chainage Muck
Break
Breaker
Steel Support
Cleaning
Wiremesh
Material
Rockbolt Breaker
Elevation Shotcrete
Day Sun Drill
Date Des 31 Charge + Blast
Shotcre
Chainage Muck te 7
Prepare
Breaker Kubik
Drilling Marking Area Steelrib
Steel Support STA 60
Anchoor Stelrib
- 65
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Diversion Activity
Tim
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
Day Mon Drill
Concrete invert STA 60 - Concrete invert STA 60 -71
Date Des 25 Charge + Blast
71
Chainage Muck
BREAK
Scal / Breaker
Steel Support Clearing
Wiremesh Floor +
Rockbolt/Forepole Instal water
stop
Shotcrete
Day Thu Drill
Date Des 26 Charge + Blast
Chainage Muck
BREAK
Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Des 27 Charge + Blast
Chainage Muck
BREAK
Scal
Steel Support
Wiremesh
BREAK
Rockbolt/Forepole
Shotcrete
Day Tue Drill
Date Des 28 Charge + Blast
Chainage Muck
BREAK
Scal
Steel Support
Wiremesh Breaker Wall STA 280 + Breaker Wall STA 280 + Install
Rockbolt Install Besi STA 164 Besi STA 164
Shotcrete
Day Fri Drill
Date Des 29 Charge + Blast
Chainage Muck
BREAK
Scal/Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Sat Drill
Date Des 30 Charge + Blast
Chainage Muck
BREAK
Breaker
Steel Support Concrete Invert STA 164 - Breaker Bottom STA
Wiremesh 175 Concrete Invert STA 164 -
Rockbolt/Forepole 175
Elevation Concrete
Day Sun Drill
Date Des 31 Charge + Blast Cleaning Lantai + Install Install Rebar STA 173 - 184
Chainage Muck Rebar STA 173 - 184
BREAK
Breaker
Steel Support
Wiremesh
Rockbolt/Forepole
Repair Acces Road
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Chainage Muck
Scal
Steel Support
Survey & Markin
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Thu Drill Survey &
Date Des 26 Charge + Blast Marking
Chainage Muck
Scal
Dewaterin
Steel Support Survey g
Wiremesh &
Rockbolt/Forepole Markin
g
Shotcrete
Day Wed Drill
Date Des 27 Charge + Blast
Chainage Muck
Survey & Marking
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Chainage Muck
Scal
Standby
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Wed Drill
Date Des 27 Charge + Blast
Chainage Muck
Scal Prepare
Steel Support Shotcrete
Wiremesh
Rockbolt Shotcrete 12 Kubik
Shotcrete
Day Tue Drill
Date Des 28 Charge + Blast
Survey & Marking
Chainage Muck
Scal
Standby & Dewatering
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Day Fri Drill
Date Des 29 Charge + Blast
Chainage Muck
Crew Focused
On Upstream
Scal Crew Focused
Steel Support On Upstream
Wiremesh
Rockbolt
Shotcrete
Day Sat Drill
Date Des 30 Charge + Blast
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Evaluasi
Evaluasi
No Activity
g ( STA 474 - 487) + Shotcrete
( STA 245 - 252)
Evaluasi
Prepare Lebih Lama
No Activity
nstall Rockbolt 45 Btg (
Evaluasi
No Activity
Cleaning
Material
Breaker
Evaluasi
Drilling Rockbolt
STA 399 - 401 ( 9
Prepare Driling
Holes)
No Activity
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
No Activity
No Activity
Evaluasi
BREAK
No Activity
Evaluasi
No Activity
Evaluasi
BREAK
No Activity
r Bottom STA
Invert STA 164 -
175
Evaluasi
bar STA 173 - 184
Cleaning
BREAK
No Activity
r Acces Road
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey &
Marking
Survey + Marking
Survey & Marking Survey + Markin
Mixer Trouble
Survey & Marking
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
IME
OWER PROJECT
Time Evaluasi
17.00 18.00 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Survey & Marking
Crew Focused On
Upstream
Evaluasi
Crew
Standby Focused On
Survey & Upstream
Marking
Survey
Evaluasi
Shotcrete 12 Kubik
Evaluasi
Survey & Marking
Dewatering
Evaluasi
urvey & Marking
Evaluasi
Evaluasi
Elevation
Evaluasi Kendala Day Sun
Date Des 31
Chainage
Evaluasi Kendala
Adit 2
Day Mon
Date Des 25
Chainage
Elevation
Evaluasi Kendala Day Sun
Date Des 31
Chainage
Evaluasi Kendala
End Portal
Day Mon
Date Des 25
Chainage
Evaluasi Kendala Day Thu
Date Des 26
Chainage
Elevation
Evaluasi Kendala Day Sun
Date Des 31
Chainage
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
Evaluasi Kendala
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00
Drill
Face
Steel Support Rockbol
t 5 Pcs
Wiremesh
Rockbolt/Forepole
Shotcrete
Drill
Charge + Blast
Muck
Moving Andang
Scal
+Joint Survey +
Steel Support Setting Legdrill
Wiremesh
Rockbolt/Forepole
Shotcrete
Moving Andang + Survey
Moving Andang + Survey
Drill
Charge + Blast
Muck
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Survey + Marking + Setting
Drill
Moving Andang + Survey
Charge + Blast
Muck
Legdrill
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Drill
Survey + Marking +
Charge + Blast
Setting Legdrill
Muck
Break Jumat
Setting Normed
Scal
+ Prepaare Kegiatan di Headrace Upward
Steel Support Shotcrete 12
Wiremesh Kubik
Rockbolt/Forepole
Shotcrete
hang + Setting
drill
Drill
LEgdrill
LEgdrill
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
Drill
LEgdrill
Scal
Steel Support
Wiremesh
Rockbolt/Forepole
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00
Drill
Mixing Material From BP
Charge + Blast
Muck Scalling Wall
Scal/Excavation
Break
Steel Support
Wiremesh Full Shotcrete 10 Shotcrete 6 Kubik
Rockbolt/Forepole Kubik
Shotcrete
Drill
Charge + Blast
Muck Cleaning
Equipm
Break
Scal/Excavation
ent &
Steel Support Dewater
Wiremesh ing
Shotcrete 6
Rockbolt/Forepole Kubik
Shotcrete
Drill
Prepare Pipa Forepoling
Install Pipa Support +
dewatering + setting
Charge + Blast
Muck
Jumbo
Break
Jumbo
Break
Penimbunan Lantai dudukan
Jumbo Drill
Rockbolt/Forepole
Shotcrete
Drill
Charge + Blast
Muck
Continue
Break
Scal Welding
Steel Support Forepoling
Wiremesh
SHotcrte 11 Kubik
Rockbolt/Forepole
Shotcrete
Drill
Charge + Blast
Muck
Scal/ Ekskavasi Oper Shift
Steel Support
Shotcrete 6
Wiremesh
Kubik
Forepole
Shotcrete
Drill
Charge + Blast
Prepare Shotcrete
Muck
BREAK
Excavation/Scal Waiting
Steel Support Mixer
Shotcret Shotcret
Wiremesh e6 e6
Rockbolt/Forepole Kubik Kubik
Concrete
Drill
Charge + Blast
Muck
Cleaning
BREAK
Scal
Steel Support
Survey Install Shotcrete 6
Wiremesh Kaki Kubik
Rockbolt/Forepole Steelrib
Shotcrete
CYCLE TIME
MERANGIN HYDRO POWER PROJECT
Activity
Time
07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00
Drill
Preparation Shotcrete
Concrete LC 6 Kubik
Charge + Blast
Muck
4 Kubik
Cleaning
Track
Break
Scal/ Excavation
Exca
Steel Support Lepas
Concrete LC 6 Kub
Preparation Shotcr
4 Kubik
Cleaning
Track
Break
Exca
Lepas
Wiremesh
Forepole 4 Kubik
Shotcrete
Drill
Preparation Excavasi
BP EMpty Hooper
Charge + Blast
Muck
Break
Excavation
Steel Support Shotcrete
4 Kubik +
Wiremesh 354 Cleaning
Rockbolt/Forepole
Shotcrete
Drill
Charge + Blast
Prepare Mucking
Muck
Break
Excavation
Steel Support
Wiremesh Shotcrete Shotcrete
Rockbolt 3 Kubik 3 Kubik
Shotcrete
Mixing Material Shotcrete
Drill
Preparation Mucking
Charge + Blast
Deicy Probelm
Muck
Scal/ Excavation
Steel Support
3 Kubik
3
Wiremesh Kubi
Forepoling k
Shotcrete
Drill
Preparation Mucking
Charge + Blast
Break Sholat Jumat
Muck
Excavation
Steel Support Shotcrete
Wiremesh Shotcrete 3 Kubik
Forepole 6 Kubik
Shotcrete
Batang Bor Jumbo Bengkok
Drill
Preparation Mucking
Charge + Blast
Muck
Cleaning
break
Excavation 356
Steel Support
Wiremesh
3 Kubik
Rockbolt
Shotcrete
Drill
Charge + Blast
Muck
Tidak Ada Suplay
No Activity
Solar
Excavation Tidak Ada Suplay
No Activity
Steel Support Solar
Wiremesh 3 Kubik
Rockbolt
Shotcrete
Moving Andang + Survey
Moving Andang + Survey
Oper SHift
Moving Andang + Survey
22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
LEgdrill
Evaluasi
Moving Andhang + Setting
Evaluasi
22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00 Mucking Out Lebih Lama
Excavasi Terhambat
Shotcrete Lebih Lama
Break
Install Shotcrete 6
Steelrib 1 Kubik
Set
Evaluasi
Axc 6 Breaker Baut Lepas
setting
water
Pump &
Shotcret + Shotcret
Break e6
Kubik
Evaluasi
Break
shotcrete 4
Install Forepoling 30 Holes
Kubik
Break
Evaluasi
SHotcrte 11 Kubik
Evaluasi
Break
hotcrete 6
Kubik
Evaluasi
Prepare Shotcrete
Break
Shotcret Shotcrete 6
e6 Kubik
Kubik
Evaluasi
Scalling Terkendals
Break
6 Kubik
Evaluasi
22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00
Preparation Install Steelrib
Preparation Mucking
Track
BREAK
Exca
Lepas
Kubik
hotcrete
3 Kubik
Exca
Shotcrete
Track
Lepas
Preparation Install St
Preparation Mucking
No Activity
Break BREAK BREAK
3 Kubik
BREAK
Break Preparation Mucking Preparation Mucking
357
6 Kubik
Shotcrete
3 Kubik
6 Kubik
Preparation Install Steelrib
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
Evaluasi
BREAK
No Activity
Kendala
Kendala
DT Howo Trouble
Kendala
Kendala
Kendala
Kendala
Re, Loader Tidak Ada
Kendala
Howo 29 Pecah Ban + Howo 19 Trouble
Kendala
Genangan air terlalu tinggi
Batuan Keras
Angin Kecil
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Breaker Trouble
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala
Kendala