Professional Documents
Culture Documents
Bill of Engineering Measurement and Evaluation (Beme) A Case Study of Critical
Bill of Engineering Measurement and Evaluation (Beme) A Case Study of Critical
Bill of Engineering Measurement and Evaluation (Beme) A Case Study of Critical
--------------------------------------------------------------------------------------------------------------------------------------
Submitted: 02-02-2021 Revised: 15-02-2021 Accepted: 18-02-2021
----------------------------------------------------------------------------------------------------------------------
ABSTRACT: A bill of engineering measurement evaluation of work executed routinely or
and evaluation list the total material quantities periodically for the purpose of control of the
needed to complete a civil engineering project. In project and as a guard for preparing interim and
this presentation, the project is a box culvert. At the final payment certificates during work-in progress
end, a near total cost of constructing the culvert and at completion of project. It also serves the
will be known in a summary table that will display purpose dispute settlement document regarding
all quantities of each item of activities, unit compensation.
measurement, rate. For accuracy, a market survey
for on-going present rates of material within the ii) Objectives
project location must be carried out. a) It provides rates and prices that enable
Keywords: Bill, measurement, Evaluation, units, negotiation for variation and extra work
Quantities, Asphalt, concrete, Reinforcement, executed
timber, granite, cement, BEME format, Box b) It enables comparison of pricing of vendors
culvert, highyield steel, wall, apron, material during tendering process.
quantities, grand total, highway, rates, pricing, c) It gives an idea of the cost of the project.
standard methods of measurement, code of d) Provides information for planning as it
practice, milestone phase, activities, market survey, involves available budget.
first principle. e) To determine if cost is to be reviewed to
accommodate available fund.
I. INTRODUCTION f) To achieve the purpose and objective of
The BEME which can also be referred to BEME, the activities are broken in milestones
as the bill, is a measurement and evaluation tool or phases and in each miles stone the activities
which is used as means of assessing and valueing are itemized.
the cost of construction project/works and
comprising of the works’ materials, equipments, Measurement and estimation
labour and any other resource needed for the This is the taking off process in which the items or
satisfactory completion of the works unlike the activities of works are identified and measured
BOQ which is usually for building projects such as which are later priced.
residential, schools, recreational buildings,
hospitals and industrial building works. The BEME a) Standard method of measurement.
is basically an evaluation tool for civil engineering This usually varies from region to region
works like roads, retaining walls, drainages, depending on the region code of practice. During
bridges, culverts, dams and railways amongst this stage, the elements of work are identified and
others. then broken into activities and separately measured
and then describe with expression of the units of
II. OBJECTIVE AND PURPOSE the quantities of each of the items. The usefulness
i) Purpose of the standard method of measurements includes:
The purpose for BEME preparation is to i) It provides very comprehensive detailed
provide the quantities of the work items for pricing guidelines for the measurement of the works.
to make available a priced bill to be used for
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 184
International Journal of Advances in Engineering and Management (IJAEM)
Volume 3, Issue 2 Feb 2021, pp: 184-189 www.ijaem.net ISSN: 2395-5252
ii) As a result, reduces the possibility of important to carefully check for omissions and
measurement related disputes before and possible errors before putting the estimated
during construction stages. quantities in BEME format table which must
iii) It contains a comprehensive list of work include the item description, quantity, unit, rate and
activity items. sometime labour and then amount.
iv) It provide uniform competitive platform for the
bidders The presentation format
v) Reduces pricing risks for the bidders. There is usually a professionally
acceptable format for BEME presentation but
b) Estimating and Evaluation depending on the purpose. The presentation format
After the taking-off process in which for BEME comes in tabular form just like it is for
measurement of the works items are now known, BOQ. Depending on the engineer, the BEME table
estimating and evaluation begins with the known could depict the units either in volume, area,
measurement and the known rates. At this stage, kilogram, bag; length, number etc which depend on
the drawings must be well understood; calculation whether the BEME is of a material quantity or the
of the quantities must be accurate. The format must conventional bill of quantity format. The following
be develop into milestone or phrase. Each phase table explains this better.
must define the quantity of material item. Then it is
N K
3
The activity M
M2
K
N K
Understanding As required Bag, Amt per material in
the activity from site length, specific of number of
for trip, etc items
example:
how many
bags of
cement,
trip of sand
, trip of
granite etc
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 185
International Journal of Advances in Engineering and Management (IJAEM)
Volume 3, Issue 2 Feb 2021, pp: 184-189 www.ijaem.net ISSN: 2395-5252
Table 4: Whether conventional or any other innovative format, the BEME table may also include the
calculation or take-off column.
Item Taking-off using Description Qty Unit Rate Amount
results from scoping
N K
e.g vol. = bxlxh
No. of bars =
l
+1
spacing
Market survey for rate fixing of cement in bags per cubic meter of concrete
This should be done within the location in our mixture now becomes:
that the project is located. For the purpose of this 1.25
iii) (1) bags of cement
7x0.037
presentation’s case study, the survey should be on 1.25 20 1.25 1.25
ongoing rate of reinforcement, cement, granite, + 1: +
7x0.037 100 7x0037 7
timber for formwork, asphalt, concrete cast rate per 201001.2572: 1.257+201001.2574
cubic metre of concrete, iron bending works rate,
carpentry work rate amongst others. = 5.791 bags: 0.43m3 sand : 0.86m3 (granit
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 186
International Journal of Advances in Engineering and Management (IJAEM)
Volume 3, Issue 2 Feb 2021, pp: 184-189 www.ijaem.net ISSN: 2395-5252
7000mm
200
c
c
Y10mmθ @300 /c Y16mmθ @200 /c
0
c
Y10mmθ @300 /c
Concrete of 3000
1:2:4 mix
c
Y16mmθ @200 /c
Figure 1: Box culvert as a case study for the preparative of bill of engineering measurement and evaluation.
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 187
International Journal of Advances in Engineering and Management (IJAEM)
Volume 3, Issue 2 Feb 2021, pp: 184-189 www.ijaem.net ISSN: 2395-5252
Table 6: Bill of Engineering Measurement and Evaluation (BEME): a case study of critical component of
a box culvert constant construct across an asphalt pavent highway
Ite Taking off Description Qty Unit Rate Amount Remark
m
N K
1. Clear site of all
unsuftable materials
and cartaway including
removal of all stamps
2. Add any other
preliminaries
3. Excavation for
foundation to receive
culvert walls u to 2.4m
depth as re drawing
including shorting
application
4. 3.4x7=24 Provide form work 52 M2
2x2x7=28
52m2
5. 7x3.6x0.05 = 14m3 Provide concrete grade 1.4 M3
15(1:3:6) 50mm thick
blinding to receive
bottom slab
6. 2(3.4+2)2 =10.8 Provide and place 15. M3
= 10.8 x 6.2x7 concrete grade 2
15.12m3 25(1:2:4) in box culvert
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 188
International Journal of Advances in Engineering and Management (IJAEM)
Volume 3, Issue 2 Feb 2021, pp: 184-189 www.ijaem.net ISSN: 2395-5252
DOI: 10.35629/5252-0302184189 Impact Factor value 7.429 | ISO 9001: 2008 Certified Journal Page 189