Lodha Upperthane Post-pour Observation/Audit

CLUSTER TOWER DATE FLOOR LEVEL


Points Reviewed by
Sl. No Structure Locations Description Date Date Remarks
Attended QE
Gaps between vertical panel & casted
Column-Slab
1 All slab filled with cement mortar/gunny
Junction
bags/foam needs to be removed CONTRACTOR
Slab/
Grinding & major offsets to be repaired if
2 Column/Beam/Ply All
any
Joint NAME

R wall/ beam/ All tie rode/ tie patti holes need to be


3 All
column filled with CNS 50
SIGNATURE

Verification of location from MEP,


4 Cutout/ Sleeves All
deshuttering & repairing if any
DATE
Slab/Sunken
5 Area/Construction All Leakage treatment
Joint LODHA CM

Wall/Beam
6 All Minor/Major pin holes to be filled if any
/Column/Slab
NAME

Wall/Beam
7 All Nails/pieces of ply has to be removed
/Column/Slab
SIGNATURE

8 Construction Joint All Grinding & offsets to be repaired if any


DATE
External alignment, plumb, inverted
9 Slab/Beam/ Column All beam pending for casting & repair if any
offset found LODHA QA/QC

External alignment, plumb & repair if any


10 beam/ chajja drop All
offset found
NAME

Location, size, Shape & level of sunk has


11 Sunk All
to be as per drawing
SIGNATURE

Safety hook / 'U' Need to be cut below 50mm of slab top


12 All
Bars / steel level & filled with approved material
DATE
Mivan formwork shifting from floor to
Slab Cutout
13 All floor & grid line transfering sleeve has to
(Mivan/Sleave)
be leakage treated.
Damage, corners needs to be repaired if
14 Cornis All
any