Project,contract 1 Tercha-Weldehane-Wereb
Consultant:Transnational Engineers(TNE)
Revised Work Program
Contractor: China Railway Seventh Group(CRSG)
Activity ID Activity Name Original Start Finish 2021 2022 2023 2024 2025
Duration
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec JanFeb
1164Junction
Design and Build of Tercha-Weldehane-Omonade 01-Jul-21 A Road
06-Sep-24
Project,contract 1 Tercha-Weldehane-Wereb 06-Sep-24, Design and Build of Ter cha-Weldehane-Omon
1.Survey, Investigation and Design 1158 01-Jul-21 A 31-Aug-24 31-Aug-24, 1.Survey, Investigation and Design
A1050 Terrain Classification Report 123 01-Jul-21 A 31-Oct-21 A Terrain Classification Report
A1060 Design Quality Management Plan/Design Standard 92 01-Jul-21 A 30-Sep-21 A Design Quality Management Plan/Design Standard Report
Report
A1080 Detail Geometric Design (Plan Profile, Design Data, 123 01-Jul-21 A 31-Oct-21 A Detail Geometric Design (Plan Profile, Design Data, X-section Templa tes, etc ) and Engineering Design Report
X-section Templates, etc) and Engineering Des ign
Report
A1090 Hydrology/Hydrualics Design and Report 123 01-Jul-21 A 31-Oct-21 A Hydrology/Hydrualics Design and Report
A1100 Structural Design and Report 123 01-Jul-21 A 31-Oct-21 A Structural Design and Report
A1110 Geotechnical Investigation and Geotechnical Report 123 01-Jul-21 A 31-Oct-21 A Geotechnical Investigation and Geotechnical Report
A1130 Pavement Design and Report 123 01-Jul-21* 31-Oct-21 Pavement Design and Report
A1140 Particular Technical Specif ic ation 123 01-Jul-21* 31-Oct-21 Particular Technical Specif ic ation
A1150 Design Stage ESIA, ROW, RAP, preparation and 123 01-Jul-21 A 31-Oct-21 A Design Stage ESIA, ROW, RAP, preparation and Reports
Reports
A1170 Design Schedule of Ancilary Works 123 01-Jul-21* 31-Oct-21 Design Schedule of Ancilary Works
A1180 As-Built Drawings 62 01-Jul-24* 31-Aug-24 As-Built Drawings
1.4 Mobilization Of Remaining Critical Equipment 138 01-Jul-21 A 30-Nov-21 A 30-Nov-21 A, 1.4 Mobilization Of Remaining Critical Equipment
A1830 Machinery/Equipment Mobilization 138 01-Jul-21 A 30-Nov-21 A Machinery/Equipment Mobilization
1.5 Quarry Area 929 15-Aug-21 A 29-Feb-24 A 29-Feb-24 A, 1.5 Quarry Area
A1850 Identification Of Quarry Areas 11 15-Aug-21 A 25-Aug-21 A Identification Of Quarry Areas
A1860 Identification Of Obstructions,if any 17 27-Aug-21 A 12-Sep-21 A Identification Of Obstructions,if any
A1870 Removal of Obstructions 18 13-Sep-21 A 30-Sep-21 A Removal of Obstructions
A1880 Quarry Production 882 01-Oct-21 A 29-Feb-24 A Quarry Production
1.6 Crushing 868 15-Dec-21 30-Apr-24 30-Apr-24, 1.6 Crushing
A1890 Production Of Basecourse & Asphalt Concrete 670 01-Jul-22* 30-Apr-24 Production Of Basecourse & Asphalt Concrete
A1900 Erection and Commissioning Crusher Plant For 65 15-Dec-21* 17-Feb-22 Erection and Commissioning Crusher Plant For Base Course
Base Course
A1910 Erection and Commissioning Crusher Plant For 49 15-Dec-21* 01-Feb-22 Erection and Commissioning Crusher Plant For Asphalt Aggregate
Asphalt Aggregate
1.7 Pipe Production 156 29-Aug-21 A 31-Jan-22 A 31-Jan-22 A, 1.7 Pipe Production
A1920 Preparation Of Molds 1 29-Aug-21 A 30-Sep-21 A Preparation Of Molds
A1930 Re-bar Cutting,Bending & fixing,fixing of mold 147 01-Sep-21 A 25-Jan-22 A Re-bar Cutting,Bending & fixing,fixing of mold
A1940 Casting & Curing of Pipes(including curing time) 153 01-Sep-21 A 31-Jan-22 A Casting & Curing of Pipes(including curing time)
1.8 Stone Masonry Site 897 01-Sep-21 A 14-Feb-24 A 14-Feb-24 A, 1.8 Stone Masonry Site
A1950 Selection of Site 7 01-Sep-21 A 07-Sep-21 A Selection of Site
A1960 Identification of Obstruction,if any & ROW 15 08-Sep-21 A 22-Sep-21 A Identification of Obstruction,if any & ROW Demarcation
Demarcation
Start:01-Jul-21 Critical Work Summary page 1 of 3 Primavera Project Management P6 Critical Path Method
A1280 Chainman and Laboratory Assistants 1164 01-Jul-21 06-Sep-24 Chainman and Laboratory Assistants
A1290 Maintenance and Service for Office, Laboratory and 1164 01-Jul-21 06-Sep-24 Maintenance and Service for Office, Laboratory and ER's
ER's Accomodation
A1300 Maintenance and Service for Survey Equipments 1164 01-Jul-21 06-Sep-24 Maintenance and Service for Survey Equipments and Rad
and Radio Communication System
A1310 Fuel, Service, Driver and Maintenance for ER's 1164 01-Jul-21 06-Sep-24 Fuel, Service, Driver and Maintenance for ER's Vehicles
Vehicles
3. Detour Construction & Traffic Management 1096 01-Jul-21 A 30-Jun-24 30-Jun-24, 3. Detour Construction & Traffic Management
A1320 Traffic Management plan 184 01-Aug-21* 31-Jan-22 Traffic Management plan
A1330 Detour Construction 822 01-Oct-21 A 30-Sep-23 A Detour Construction
A1340 Detour Maintainance 1096 01-Jul-21 30-Jun-24 Detour Maintainance
A1350 Placing temporary traffic control signs & Flagging 1096 01-Jul-21 30-Jun-24 Placing temporary traffic control signs & Flagging
4. Site Clearance and Earthwork 945 01-Jul-21 A 30-Nov-23 30-Nov-23, 4. Site Clearance and Earthwork
A1360 Site Clearing and Grubbing including demolishing 365 01-Jul-21 A 30-Jun-22 A Site Clearing and Grubbing including demolishing and removal of existing structures
and removal of existing structures
A1370 Removal, Replacement of unsuitable material & 638 01-Oct-21 A 31-Mar-23 A Removal, Replacement of unsuitable material & Road Bed Preparation
Road Bed Preparation
A1380 Embankment/Ordinary Fill Work 699 01-Nov-21 A 10-Sep-23 A Embankment/Ordinary Fill Work
A1390 Improved Subgrade/Capping Layer 822 01-Nov-21 A 30-Sep-23 A Improved Subgrade/Capping Layer
A1400 Road way Excavation (Normal/Soft) 669 01-Jul-21 A 30-Apr-23 A Road way Excavation (Normal/Soft)
A1410 Road way Excavation (Weathered/Hard rock) 669 01-Jul-21 A 30-Apr-23 A Road way Excavation (Weathered/Hard rock)
A1420 Slope Flattening 760 01-Nov-21* 30-Nov-23 Slope Flattening
A1430 Sub base Construction 820 01-Dec-21* 28-Feb-24 Sub base Construction
6. Road Base 1053 01-Aug-21 18-Jun-24 18-Jun-24, 6. Road Base
A1440 Base course Construction 869 01-Feb-22* 18-Jun-24 Base course Construction
A1450 Road Base Production 1034 01-Aug-21* 30-May-24 Road Base Production
7. Bituminous surface (Prime Coat and Shoulder) 731 01-Jul-22 30-Jun-24 30-Jun-24, 7. Bituminous surface (Prime Coat and Shoulder)
A1460 Prime Coat Application 633 04-Oct-22* 27-Jun-24 Prime Coat Application
A1470 AC Surfacing Construction 633 05-Oct-22* 28-Jun-24 AC Surfacing Construction
A1480 Shoulder Construction (DBST) 614 26-Oct-22* 30-Jun-24 Shoulder Construction (DBST)
A1500 Asphalt Concrete aggregate 670 01-Jul-22* 30-Apr-24 Asphalt Concrete aggregate
8. Bridge, Culvert and Drainage 1096 01-Jul-21 A 30-Jun-24 30-Jun-24, 8. Bridge, Culvert and Drainage
8.1 Geotechnical Investigation & Report for Bridges 122 01-Aug-21 A 30-Nov-21 A 30-Nov-21 A, 8.1 Geotechnical Investigation & Report for Bridges
A1490 Geotechnical Investigation & Report for Bridges 122 01-Aug-21 A 30-Nov-21 A Geotechnical Investigation & Report for Bridges
8.2 Construction of Bridges 730 01-Dec-21 A 30-Nov-23 30-Nov-23, 8.2 Construction of Bridges
8.2.1 Sub-structure works including Granular Backfilling 335 01-Oct-22 A 31-Aug-23 A 31-Aug-23 A, 8.2.1 Sub-structure works including Granular Backfilling
A1720Sub-structure works including Granular Backfilling 335 01-Oct-22 A 31-Aug-23 A Sub-structure works including Granular Backfilling
8.2.2 Super-structure works 449 01-Dec-21 30-Nov-23 30-Nov-23, 8.2.2 Super-structure works
A1730Super-structure works 449 01-Dec-21* 30-Nov-23 Super-structure works
Culvert and Drainage 1096 01-Jul-21 A 30-Jun-24 30-Jun-24, Culvert and Drainage
A1740 Pipe Culvert construction and finish 853 01-Oct-21 A 30-Nov-23 A Pipe Culvert construction and finish
A1750 Box Culverts including Granular backfilling, etc 853 01-Oct-21 A 30-Nov-23 A Box Culverts including Granular backfilling, etc
A1760 Slab Culvert including granular backfilling, etc 792 01-Dec-21 A 30-Nov-23 A Slab Culvert including granular backfilling, etc
A1770 Road side Drainage (Rural) 912 01-Jan-22* 30-Jun-24 Road side Drainage (Rural)
A1780 Town Section side Drainage (U-dicthes, Cover, etc 912 01-Jan-22* 30-Jun-24 Town Section side Drainage (U-dicthes, Cover, etc as per typical)
as per typical)
A1790 Underdrain ( Subsurface/Sub-soil drainage in 546 01-Jan-22* 30-Jun-23 Underdrain ( Subsurface/Sub-soil drainage in swampy area)
swampy area)
9.1 Road Furnitures and Road Safety 305 01-Nov-23 31-Aug-24 31-Aug-24, 9.1 Road Furnitures and Road Safety
A1600 Kilometer post & delinator /Erection 305 01-Nov-23* 31-Aug-24 Kilometer post & delinator /Erection
A1610 Guard rail/ Errection 305 01-Nov-23 31-Aug-24* Guard rail/ Errection
A1620 Road marking 305 01-Nov-23* 31-Aug-24 Road marking
Start:01-Jul-21 Critical Work Summary page 2 of 3 Primavera Project Management P6 Critical Path Method
A1650 Plan and Implimentation Provision for STD and 1164 01-Jul-21 06-Sep-24 Plan and Implimentation Provision for STD and HIV/AIDS A
HIV/AIDS Alleviation Program
A1660 Reinstatement of Borrow pits, Quarry Site, Spoil 275 01-Dec-23* 31-Aug-24 Reinstatement of Borrow pits, Quarry Site, Spoil sites, etc
sites, etc
A1700 Noise Pollution control 1158 01-Jul-21 31-Aug-24 Noise Pollution control
10.Project Handover 6 01-Sep-24 06-Sep-24 06-Sep-24, 10.Project Handover
Start:01-Jul-21 Critical Work Summary page 3 of 3 Primavera Project Management P6 Critical Path Method