PREPARED BY
ENGINEERING DEPARTMENT
SKEB‐ED‐MS‐001 SANKEN CONSTRUCTION (PVT) LTD
WMS FOR SETTING OUT WORK
TABLE OF CONTENTS
1. OBJECTIVE
2. INTRODUCTION
3.1 MATERIAL
3.2 MACHINERY & EQUPIMENTS
4. RESPONSIBILITIES
6. PROCEDURE
8. SAFETY PLAN
1
WMS FOR SETTING OUT WORK
1.0 OBJECTIVE
The objective of this method statement is to inform the consultants and the client the
relevant methods and procedures that Sanken Construction (Pvt.) Ltd. shall follow for
the Setting‐out works and to ensure all engineers and workers at the site are following
the well‐defined and safe methods and procedures.
2.0 INTRODUCTION
This document outlines the work methods involved for the safe and proper execution of
setting out works.
2
WMS FOR SETTING OUT WORK
3. Crow bars 4. Chipping hammer
3
WMS FOR SETTING OUT WORK
4.0 RESPONSIBILITIES
The Following diagram shows the survey work responsibility
Project Manager
Construction Manager
Site Engineer
Licensed Surveyor
(Time to Time)
Surveyors
Survey Helpers
4
WMS FOR SETTING OUT WORK
QA /QC Inspection
Not OK
Proceed Work
5
WMS FOR SETTING OUT WORK
6.0 PROCEDURE
It is necessary to establish Control Points correctly set up at the proposed
building in suitable locations.
With Respect to these Control Points, three or more control points will be
established on the lowest level of the structure in order to carry out all setting
out work of the building accurately and conveniently until project completion.
All these control points will be used to set out Grid Lines at base level, and it will
be used to observe and check the other structural entities to place in the correct
position or to check whether they have been placed in the correct Position with
respect to the Design.
The required lines for excavation, lean concrete shall be marked using
marking Code.
Pile cap centerline and the edge lines shall be marked using total station with
respect to the main grid lines.
Grid off setlines will be then marked using the TL and the measuring tape.
The center point of the columns shall be marked using the total station.
The verticality of the columns shall be checked using the Center Plumb‐Bob
and measuring tape at the stage of formwork prior to concrete & after
concrete.
The grid lines shall be transferred to the upper floors by using the Center
Plumb‐Bob and Total station.
From the original grid lines 500mm offset shall be marked.
The Auto Level (Calibrated) in Good working condition will be used to transfer
the elevations between Survey Control Points and to the respective floors.
The elevation will be transferred to higher floors either running a Level Line
through the Staircase or through the core wall by accurate tape measurements.
6
WMS FOR SETTING OUT WORK
The Location of the initial/existing Survey Control Points will be checked by the
Licensed Surveyor and the Control Traverses and Control Level Lines will be run
by the Licensed Surveyor with suitable Adjustments according to the as build pile
drawing.
All these Control Points will be monitored periodically (once a month) and
Proper Recording method will be used for comparison.
For the purpose of quality controlling, the inspection will be carried out and keep the
records (Check list for structural work). All the criteria’s will be addressed and checked,
so that the construction work will have the same quality throughout the project.