Professional Documents
Culture Documents
Zegu Cac 414 Practice Questions
Zegu Cac 414 Practice Questions
PRACTICE QUESTIONS
Question 1
A company manufactures two products, L and M, using the same equipment
and similar processes. An extract of the production data for these products
in one period is shown below.
L M
Quantity produced (units) 5,000 7,000
Direct labour hours per unit 1 2
Machine hours per unit 3 1
Set-ups in the period 10 40
Orders handled in the period 15 60
Overhead costs $
Relating to machine activity 220,00
0
Relating to production run set-ups
20,000
Relating to handling of orders 45,00
0
285,00
0
Required
Calculate the production overheads to be absorbed by one unit of each of the
products using the following costing methods.
(a) A traditional costing approach, using a direct labour hour rate to
absorb overheads 13 marks
(b) An activity based costing approach, using suitable cost drivers to trace
overheads to products (17 marks)
(30 marks)
Question 2
The budgeted and actual results of Crunch Co for September were as
follows. The company uses a marginal costing system. There were no
opening or closing stocks.
Fixed budget Actual
Sales and production 1,000 units 700 units
$ $ $ $
Sales 20,000 14,200
Variable cost of sales
Direct materials 8,000 5,200
|]7; 4,000 3,100
Variable overhead 2,000 1,500
14,000 9 800
6 000 44
00 44444444
44444
Required
Prepare a budget that will be useful for management control purposes. 20
marks
What are the Factors to be considered when preparing a flexible budget. 5marks
Selling prices and material costs for each product are as follows.
X 150 80 70
Y 130 40 90
Z 300 100 200
Required
(a) Calculate the profit per day if daily output achieved is 6,000 units of
X, 4,500 units of Y and 1,200 units of Z.
(c) In the absence of demand restrictions for the three products, advise
Corrie's management on the optimal production plan. (25 marks)
Question 5 Group 1
Giving examples of an organization you are familiar with, Discuss the merits
and limitations of zero based budgeting ( 10marks)
Question 6 Group 2
BJS Limited produces and sells the following three products:
Product X Y Z
$ $ $
Selling Price Per Unit 16 20 10
Variable Cost Per Unit 5 15 7
Contribution Per Unit 11 5 3
Budgeted Sales Volume 50,000units 10,000 units 100,000 units
The company expects the fixed cost to be $450,000 for the coming year. Assume the sales
that arise throughout the year in a constant mix.
Required:
(a) Calculate the weighted average C/S ratio for the Products. 5 marks
(b) Calculate the break- even sales revenue required. 10 marks
Calculate the amount of sales revenue required to generate a profit of $ 600,000. 7 marks
(c) Draw a multi-product profit- volume chart assuming the budget is achieved. 8
marks
QUESTION 7 group 2
Blessed Co. produces 3 components with the following information available:
A B C
Production (units) 20,000 40,000 80,000
Direct Material Cost Per unit 0.80 1.00 0.40
Direct Labour Cost Per unit 1.60 1.80 0.80
Direct Overhead Cost Per unit 0.40 0.60 0.20
Fixed cost per unit 0.80 1.00 0.40
Sales Price per unit 4.00 5.00 2.00
Imported Price 2.75 4.20 2.00
Required:
(i)Should Blessed Co. make or buy each of the components it sells?
(ii)If the components are all made by Blessed Co. how much profit will be made?
(iii)If your recommendation in part (i) is taken up how much profit will be made?
(iv)What other factors should be considered before this decision is made?
(20 MARKS)
QUESTION 8 group 3
Sticky Wickets manufactures Cricket Bats. In May 2010 the budgeted sales and production
2b Group 1
(i)Explain the difference between a fixed budget and a flexed budget.
(ii) Discuss the requirements of an effective budgetary control system.
(iii) State any five possible limitations, on the level of activity of a business, that could be
principal’s budget factors. Suggest a way of overcoming each limitation. ( 10 MARKS)
QUESTION 9 All
Aybee Ltd is considering the following projects:
Project A Project B
$ $
Cost 42 000 61 000
Scrap value 2 000 6 000
Useful life 5 years 5 years
Additional information:
Year 1 0,909
2 0,826
3 0,751
4 0,683
5 0,621
Required
(b) Calculate
(i) The Payback period for each project
(ii) the net present value of each project
iii) The accounting rate of return for each project.
(c). Based on your calculations in (b) which project should be undertaken.
Justify your choice (20MARKS)
Question 10 All
WX CO. manufactures two products A and B. both products pass through two production
departments, mixing and shaping. The organization objective is to maximize contribution to
fixed costs.
Product A is sold for $1.50 where product B is priced at $2.00. There is unlimited demand for
product A but demand for B is limited to 13 000 units per annum. The machine hours
available in each department are restricted to 2 400per annum. Other relevant data are as
follows.
The variable cost per unit for A is $1.30 and for Product B is $1.70
Required
Determine the optimal production using linear programming and draw a graph .(25 marks)
Question 11 group 1
Hannah suppliers the following budgeted information for the five months ended 31 Dec 2022
$ $ $ $ $
Provision for
Depreciation office
Equipment 50 000
(iv) Trade Receivables will settle their accounts in the month following the sale
(vii) Inventory will be $21 000 on 1 October and $24 000 on 31 Dec
Required
(b) Prepare a cash budget for each of the three months ending 31 December 2022
(c) Prepare a budgeted Income Statement for the three months ending 31 December 2022
(30 marks)
Question 12 All
Edward Co assembles and sells many types of radio. It is considering extending its product
range to include digital radios. These radios produce a better sound quality than traditional
radios and have a large number of potential additional features not possible with the previous
technologies (station scanning, more choice, one touch tuning, station identification text and
song identification text etc.).
(a) Briefly describe the target costing process that Edward Co should undertake.
(b) Explain the benefits to Edward Co of adopting a target costing approach at such an early
stage in the product development process.
(c) Assuming a cost gap was identified in the process, outline possible steps Edward Co could
take to reduce this gap.
(d) State ways which target costing can improve performance?( 25 marks)