Professional Documents
Culture Documents
0923 OMICRON Article Effective and Efficient Protection Testing
0923 OMICRON Article Effective and Efficient Protection Testing
0923 OMICRON Article Effective and Efficient Protection Testing
Let’s take a glance at the past. In the pre-digital era, protection devices were set up with only a few
parameters (Figure 1). These parameters could be tested easily, while the results were documented by
hand. Then, incredible developments in the field of microelectronics completely changed the game. Over
roughly 30 years, ever-new advancements entered our daily lives. It was only a matter of time until they also
became present in the assets of our power grids and ultimately arrived in protection relays.
Electromechanical and static devices’ parameters were limited, making it possible to test them all. The first
generation of digital devices only had a few additional parameters. So, nothing really changed, as checking
every parameter during commissioning or routine testing was still possible. But soon, new technologies and
the possibilities they offered to protection engineers led to many parameters that could no longer be tested
in the field.
Therefore, sending a test engineer into the field to test a substation’s protection devices is no longer
sufficient. Today, there are far too many things to do before testing and to recognize during a test.
Preparation is vital nowadays and has the most significant potential for efficiency gains.
Before we dive in further, one more thing needs to be defined clearly – the scope of the term protection
testing. This article not only considers a single protection testing task but instead tries to cover the long-term
efforts and potential connected to testing assets within substations over their entire lifespan to create a more
realistic and comparable picture of protection testing. For that reason, the term includes testing strategies
and the full scope of the protection testing task, from preparation to execution to documentation, when
considering effectiveness and efficiency.
As mentioned above, testing all the parameters of a modern protection relay in the field is no longer feasible
for testing engineers. Before they even start testing, they need to know which parameters must be tested to
be effective. An effective protection test requires procedures that contain the necessary steps – nothing
more, nothing less. In simple terms, effectiveness can be described as “Doing the right things.”
As each test has its purpose, not every test needs to be performed regularly. Some tests are only relevant
for a specific phase in the life cycle of a protection device. In contrast, others should be performed more
frequently to ensure the reliable operation of the relay.
Regardless of the test’s purpose, before a test case can be run, it must be defined and prepared
accordingly, as seen in Figure 2. All these tests will be effective if performed correctly, but is this approach
also efficient?
2 Improving Efficiency
Efficiency depends on various factors, from the testing approach, state-of-the-art tools supporting it, and the
test engineer’s experience. However, all of them are subject to change. On the one hand, test objects are
advancing and use new technologies. On the other hand, protection testing solutions add new features, and
test engineers are becoming more experienced. Of course, they could also miss out on catching up on new
developments. These factors must be considered when trying to “Do the right things correctly” which is a
basic definition of efficiency. Or, to say it another way – executing the right test procedures, without
mistakes, in the shortest amount of time.
The two most significant factors for efficiency are usually standardization combined with automation. Once
the most effective testing approach is found, further efficiency gains are highly dependent on eliminating
manual interventions in the testing process. While this clearly can be achieved with automation, the level of
automation is essential. This is where standardization comes into play, as it maximizes automation within or
even across testing approaches. Generally, the more standardized an environment is, the more automation
is possible. Whereas single-function tests can be automated relatively easily, a complete test procedure for
a relay is usually done in parts depending on standardization efforts.
Other quality characteristics may also be relevant depending on the purpose of the test, and their
importance can be assessed differently from company to company.
We've now discussed the essential aspects necessary for taking a closer look at key performance indicators
and to answer the question: How can protection testing efficiency be measured?
Obviously, the KPIcov = 0 is optimal, as zero is the highest reachable value for this KPI. This easy example
shows that having clear references for assessing the measured KPI is essential.
Various steps can be implemented to reach the optimal KPI for the testing process, e.g.:
• Introducing test specifications for each test that must be fulfilled
• Standardizing protection testing tasks by specifying the entire testing procedure to avoid missing steps
• Analyzing the test specifications regularly to monitor the test coverage and minimize system errors
The optimum state for this KPI is also zero. If the KPI is greater than zero, there are two options for
improving the performance of quality aspect repeatability:
• Using test plans to ensure the same test values are used every time the test is performed
• Switching from manual testing to automatic testing
The following considerations focus on the time needed to fulfill all relevant test tasks. The KPI for testing
process efficiency can be defined as:
Although the minimum possible time is unknown in this equation, we know that the optimal state of the
KPIeff = 1. Therefore, this KPI cannot be used to measure the performance of a specific testing task, but it
can be considered for measuring changes in the testing process. Let’s assume a utility performs manual
testing and wants to change to an automated testing approach. The KPIs for these two testing methods are:
𝑇𝑇𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 + 𝑇𝑇𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡
𝐾𝐾𝐾𝐾𝐾𝐾𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 =
𝑇𝑇𝑚𝑚𝑚𝑚𝑚𝑚
for manual testing and
𝑇𝑇𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 + 𝑇𝑇𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡
𝐾𝐾𝐾𝐾𝐾𝐾𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 =
𝑇𝑇𝑚𝑚𝑚𝑚𝑚𝑚
for automated testing. As Tmin is in both equations equal the quotient of the two KPIs describes the KPI for
improving the testing process
as a measured value. This KPI can be used as a basis for assessing actual cost reductions resulting from an
increase in efficiency due to the testing time reduction.
To make this theoretical discussion more tangible, the last part of this article will focus on a practical
example.
Over the lifetime of a substation, the assets installed pass through various phases. The assets must be
tested during each phase with a defined set of tests, as visualized in Figure 4. Preparing and executing the
individual tests can be done separately (as seen in Figure 2) and manually, but that would be the least
efficient approach. Preparation is usually the most time-intensive part of a protection test. It consumes about
50 to 60 percent of the entire test process. In Figure 5, this equals five-time units. Execution accounts for
roughly one-time unit and documentation for another two-time units.
If test plans and automation are introduced instead of a manual approach, the time required is reduced
drastically. At the same time, test coverage and depth can be increased substantially, while test repeatability
can be easily pushed to an optimum level.
Whenever tests are performed for the first time, future requirements are considered during their thorough
preparation and design. Each test can be repeated without changing individual test modules.
Test procedures stored in repeatable test plans allow tests to be performed one-to-one in later phases of an
asset’s life cycle. This pays off once the assets enter their maintenance phases, and the same tests need to
be performed regularly. Such an approach can reduce the needed time by up to 80%.
Let’s focus on an example. Figure 6 shows a section from an industrial power grid. It contains several motors
which are similar in size. These motors are protected with the same protection scheme with similar
protection settings. In most cases, the protection devices are from the same manufacturer, which means that
the differences between the individual protection devices are minor. Differences may be found in specific
parts of the protection scheme (e.g., pickup values, trip times).
On average, we have to deal with approximately 30 different parameters from one protection device to the
next. Therefore, nearly every test case in the protection testing procedure must be recalculated and
overworked for testing the next protection device. A procedure with 30 test cases is required for testing
these 30 parameters and ten more essential ones (e.g., CT and VT settings) for a protection device.
Table 1 displays an average of 3 calculations and 12 altered parameters per test case that can be used to
discuss the efficiency of protection testing.
Hence, preparing the 30 test cases from our example needs 90 calculations and 360 parameters, which
must be changed during the testing of the protection devices used for every motor in Figure 6. If 20 similar
protection devices in this substation need to be tested,1800 calculations must be done, and 7200
parameters must be changed manually.
For automated testing, 90 Calculations, 360 parameters (both steps only need to be done once), and 600
(20 times the 30 varies) parameters have to be entered. For an easier calculation, let’s assume that every
step requires the same amount of time. Using the formula for KPIimprov we get the following:
13500
𝐾𝐾𝐾𝐾𝐾𝐾𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 = = 10
1350
In addition to substantial efficiency improvements, by factors 8,6, and 10 in our examples, two additional
aspects must be highlighted. Firstly, the effort to prepare a manual test procedure is greater than the
preparation time needed to use an automated test plan. Secondly, the manual testing approach increases
the possibility of human error during preparation and execution dramatically. This is why improving efficiency
with automation also enhances the quality of the protection testing process.
This article shows why KPIs are vital to the protection testing field and why they should be implemented if
they’re not being used yet. They improve and optimize working processes by making them measurable.
When using a KPI to compare a manual testing approach to an automated one, its time-saving efficiency
shows that state-of-the-art testing methods can leverage significant improvements. Measurable
improvements by, e.g., a factor of 10, is more than enough reason to examine your own processes more
closely.