TABEL 1.

PERHITUNGAN VOLUME PEKERJAAN


No Jenis Pekerjaan Perhitungan Volume Jumlah
a b c d
I PEKERJAAN PERSIAPAN
1.1 Pembersihan Lokasi Panjang = 17625 mm 278.65 m2
= 17.63 m
Lebar = 15810 mm
= 15.81 m
Volume = pxl
15.8

= 17.6 x 15.8
= 278.65 m2

17.6

1.2 Pemasangan Bowplank Panjang = 17.63 + (2 x 1) 74.87 m'


= 19.63 m
Lebar = 15.81 + (2 x 1)
= 17.81 m
P.Bowplank = 2 (p + l)
15.8

= 2 (19.6 + 17.8)
= 74.87 m'

17.6

1.3 Pembuatan Bedeng Panjang = 3000 mm 15.00 m2


= 3.00 m
Lebar = 5000 mm
= 5.00 m
Volume = pxl
5.0

= 3x5
= 15.00 m2
3.0

II PEKERJAAN TANAH DAN PONDASI


2.1 Galian tanah
A jml.Footplat = 25.00 bj 37.50 m3
Galian tanah pondasi footplat
P.Galian = 1.00 m
-0.30 L.Galian = 1.00 m
Tinggi Galian = 1.50 m
Volume = jml (p x l x t)
= 37.50 m3

-1.30
-2.00

1.00
B
Galian tanah pondasi Batu Kali (A)
P.Galian = 87.97 m 114.36 m3
-0.3 L.Galian = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 114.36 m3
-1.30

1
C
Galian tanah pondasi Batu Kali (B)
P.Galian = 51.06 m 66.38 m3
-0.3 L.Galian = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 66.38 m3
-1.30

1
2.2 Urugan Tanah
A Galian footplat = 37.50 m3 37.08 m3
Urugan tanah kembali footplat
Total Vol.Footplat = 4.80 m
Total Vol.Kolom pendek = 1.80 m
Volume = {37.5-(5.57+2.09)}x 1.2
= 37.08 m3

B
Urugan tanah kembali Batu kali
Vol. Total galian = 180.74 m 109.41 m3
Vol. Total pondasi = 89.56 m
Volume = (180.74-89.16)x1.2
= 109.41 m3

C Urugan tanah peninggi elevasi


Lantai rumah Luas lt. 1 = 181.07 m 65.18 m3
Tinggi/Tebal = 0.30 m
Volume = (181.07 x 0.3)x 1.2
= 65.18 m3

D
Urugan tanah peninggi elevasi
Luas lt. teras = 10.54 m 2.53 m3
lantai teras, KM, dan gudang
Tinggi/Tebal = 0.20 m
Volume = (10.54x0.2) x 1.2
= 2.53 m3

2.3 Urugan Pasir


A jmlh footplat = 25.00 bj 2.50 m3
Urugan pasir bawah footplat
Panjang = 1.00 m
Lebar = 1.00 m
Tinggi/Tebal = 0.10 m
Volume = 25 x (1x1x0.1)
= 2.50 m3

B
Urugan pasir bawah anstamping
Lebar = 1.00 m 13.90 m3
Batu Kali A dan B
Tinggi/Tebal = 0.10 m
Panjang Pondasi = 139.03 m
Volume = (1 x 0.1 x 139.03)
= 13.90 m3

C Urugan pasir bawah lantai


Luas Lt.1 = 191.61 m 19.16 m3
Tinggi/Tebal = 0.10 m
Volume = (191.61 x 0.1)
= 19.16 m3
2.4 Pasangan Batu Kali
A Lebar = 1.00 m 20.85 m3
Anstamping Pondasi A dan B
Tinggi/Tebal = 0.15 m
Panjang = 139.03 m
Volume = (1 x 0.15 x 139.03)
= 20.85 m3

B LGB = 0.80 m 35.55 m3


Pasangan Pondasi Bt. Kali A
LGA = 0.30 m
Tinggi/Tebal = 0.75 m
Panjang = 87.97 m
Volume kolom pendek = 1.80 m3
Volume
= {1/2 x (0.8+0.3) x 0.75} x 87.97 - 1.8
= 35.55 m3

C LGB = 0.80 m 19.26 m3


Pasangan Pondasi Bt. Kali B
LGA = 0.30 m
Tinggi/Tebal = 0.75 m
Panjang = 51.06 m
Volume kolom pendek = 1.80
Volume
= {1/2 x (0.8+0.3) x 0.75} x 51.06 - 2.09
= 19.26 m3

III PEKERJAAN BETON


3.1 Pek. beton non-struktur
A Lantai kerja Footplat Jmlah Footplat = 25.00 bh 0.80 m3
Panjang = 0.80 m'
Lebar = 0.80 m'
Tinggi/Tebal = 0.05 m'
Volume = 25 (0.8 x 0.8 x 0.05)
= 0.80 m3

B Rabatan Tidak ada


3.2 Pek. Beton bertulang
A Pondasi Footplat Jmlah footplat = 25.00 bh 1.50 m3
LGB = 0.80 m
LGA = 0.30 m
Tinggi/Tebal = 0.25 m
- Volume footplat = 25 (0.8 x 0.3 x 0.25)
= 1.50 m3

- Volume Bekisting
Jmlah footplat = 25.00 bh 24.00 m2
Panjang = 0.80 m
Tinggi/ Tebal = 0.30 m
Volume = 4 (0.8 x 0.3) x 25
= 24.00 m2

B Kolom Pendek
Jmlah Footplat = 25.00 bh 1.80 m3
Panjang kolom = 0.15 m'
Lebar kolom = 0.30 m'
Tinggi/Tebal = 1.60 m'
Volume = 25 (1.6 x 0.3 x 0.15)
= 1.80 m3

- Volume Bekisting = 4 (1.6 x 0.3)x29 24.00 m2


= 24.00 m2

C
Balok Sloof Batu Kali A dan B
Lebar = 0.15 m 5.91 m2
Tinggi/Tebal = 0.30 m
Panjang sloof = 131.44 m
Volume = 131.44 (0.3 x 0.15)
= 5.91 m2

- Volume Bekisting
Panjang sloof = 131.44 m 78.86 m2
Tinggi/Tebal = 0.30 m
Volume = 2 (131.44 x 0.3)
= 78.86 m2

D Kolom Induk Lt. 1


Jmlh Kolom = 25.00 bh 4.50 m3
Panjang = 0.30 m'
Lebar = 0.15 m'
Tinggi = 4.00 m'
Volume = 25 (0.15 x 0.3 x 4)
= 4.50 m3

- Volume Bekisting
Jlmh Kolom induk = 25.00 bh 30.00 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.3) x 28
= 30.00 m2

E Kolom praktis Lt. 1


Jmlh Kolom = 14.00 bh 1.26 m3
Panjang = 0.15 m'
Lebar = 0.15 m'
Tinggi = 4.00 m'
Volume = 14 (0.15 x 0.15 x 4)
= 1.26 m3

- Volume Bekisting
Jlmh Kolom induk = 14.00 bh 16.80 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.15) x 14
= 16.80 m2

F Balok Induk Lt. 1


Jmlh kolom induk = 25.00 bh 3.88 m3
Panjang Balok = 147.43 m'
Lebar Balok = 0.15 m'
Tinggi Balok = 0.30 m'
Lebar kolom induk = 0.15 m'
Tebal Plat = 0.12 m'
Volume
- Volume Kolom tertabrak
= 25 (0.15 x (0.3 - 0.12) x 0.15)
= 0.10 m3
- Volume balok induk
= 147.43 x 0.15 (0.3 - 0.12)
= 3.98 m3
- Volume Total = (3.98 - 0.10)
= 3.88 m3

- Volume Bekisting
Jlmh bekisting = 2.00 bh 132.68 m2
Panjang Balok = 147.43
Tinggi = 0.30 m'
Lebar = 0.15 m'
Volume = 3 (147.43 x 0.3)
= 132.68 m2

G Balok anak Lt. 1


Jmlh kolom induk = 25.00 bh 0.23 m3
Panjang Balok = 54.08 m'
Lebar Balok = 0.15 m'
Tinggi Balok = 0.15 m'
Lebar kolom praktis = 0.15 m'
Tebal Plat = 0.12 m'
Volume
- Volume Kolom tertabrak
= 25 (0.15 x (0.15 - 0.12) x 0.15)
= 0.02 m3
- Volume balok induk
= 54.08 x 0.15 (0.15 - 0.12)
= 0.24 m3
- Volume Total = (0.24 - 0.01)
= 0.23 m3

- Volume Bekisting
Jlmh bekisting = 2.00 bh 24.34 m2
Panjang Balok = 54.08
Tinggi = 0.15 m'
Lebar = 0.15 m'
Volume = 3 (54.08 x 0.15)
= 24.34 m2
H Plat Tangga
Tebal plat tangga = 0.18 m' 2.25 m3
Panjang Sisi samping = 2.40 m'
Sudut tangga bawah A = 34 derajat
Pnjng plat tangga bawah = 2.4/cos 34
= 2.89 m'
Panjang sisi samping B = 4.895 m'
Pnjng plat tangga tengah = 4.895/cos 34
= 5.90 m'
Panjang sisi samping C = 1.95 m'
Panjang plat tangga atas = 1.95/cos 34
= 2.35 m'
Lebar tangga = 0.95 m'
Lebar bordes = 1.00 m'
Volume
- Plat tangga bawah = (2.89 x 0.95 x 0.18)
= 0.50 m3
- Plat tangga tengah = (5.90 x 0.95 x 0.18)
= 1.01 m3
- Plat tangga atas = (2.35 x 0.95 x 0.18)
= 0.40 m3
- Plat Bordes = 2x (0.18 x(0.95 x 1))
= 0.34 m3
Volume total = 2.25 m3

Volume Bekisting
Volume plat 15.34 m2
Bawah = 3.73 m2
Tengah = 7.62 m2
Atas = 3.03 m2
Jumlah = 14.39 m2
Volume bordes = 0.95 m'
Volume = (31.91+0.95)
= 15.34 m2

I Anak tangga Jmlah anak tangga = 21 bh


Panjang = 0.95 m 0.57 m3
Lebar = 0.30 m
Tinggi = 0.19 m
Volume = 21x(1/2x0.95x0.3x0.19)
= 0.57 m3
Volume bekisting
Jumlah = 21 bh 3.79 m2
Tinggi = 0.19 m
Panjang = 0.95 m
Volume bekisting = (21 x 0.19 x 0.95)
= 3.79 m2

J Plat Lantai 2 Volume Plat lantai


Panjang = 15.81 m' 1.47 m3
Lebar = 13.095 m'
Tebal = 0.12 m'
Volume Lubang tangga = 23.38 m3
Volume = (15.81x13.095x0.12)-23.38
= 1.47 m3

Volume bekisting = 2{(15.81x0.12)+(13.095x0.12)


= 5.37 m2 5.37 m2

K Kolom Induk Lantai 2 Panjang = 0.15 m' 4.52 m3


Lebar = 0.30 m'
Tinggi = 4.18 m'
Jumlah = 24 bh
Volume = 24x(0.15x0.3x4.182)
= 4.52 m3

Volume bekisting = {2x(4.182x0.3)}x24 60.22 m2


= 60.22 m2

L Kolom Praktis Lantai 2 Panjang = 0.15 m' 0.85 m3


Lebar = 0.15 m'
Tinggi = 4.18 m'
Jumlah = 9 bh
Volume = 9x(0.15x0.15x4.182)
= 0.85 m3
Volume bekisting = {2x(4.182x0.15)}x9
= 11.29 m2 11.29 m2

M Balok Ring Volume Balok ring


Panjang = 143.40 m' 3.12 m3
Lebar = 0.15 m'
Tinggi = 0.15 m'
Jumlah = 33 bh
Lebar Kolom = 0.15 m'
- Volume kolom tertabrak = 33 x (0.15 x 0.15 x 0.15)
= 0.11 m3
- Volume balok ring = (143.40 x 0.15 x 0.15)
= 3.23 m3
- Volume total = 3.23-0.11
= 3.12 m3

Volume Bekisting
Jumlah = 2.00 bh 64.53 m2
Panjang = 143.40 m
Lebar = 0.15 m
Volume Bekisting = 3 x (143.40 x 0.15)
= 64.53 m2

IV PEKERJAAN PASANGAN DINDING


4.1 Trasram rumah (1:2) Panjang dinding = 32.41 m 4.36 m2
Panjang lubang kusen = 22.72 m
Lebar = 0.15 m
Tinggi = 3.00 m
Volume = (32.41-22.72) x 3 x 0.15
= 4.36 m2

4.2 Pasangan Dinding


A Panjang = 116.41 m 426.54 m2
Pasangan Dinding Lt.1 (1:6)
Tinggi = 4.00 m
Luas trasram = 4.36 m2
Luas lubang pintu jendela
= 34.72 m2
dan ventilasi
Luas = (116.41 x 4)-(4.36 + 34.72)
= 426.54 m2

B Panjang = 133.71 m 500.31 m2


Pasangan Dinding Lt.2 (1:6)
Tinggi = 4.00 m
Luas trasram = 4.36 m2
Luas lubang pintu jendela
= 30.17 m2
dan ventilasi
Luas = (133.71 x 4 )-(4.36 + 30.17)
= 500.31 m2

C Panjang = 12.80 m 1.44 m2


Dinding kamar mandi Lt.1 (1:4)
Tinggi = 1.00 m
Luas lubang pintu = 11.36 m2
Luas = (12.80 x 1) - 11.36
= 1.44 m2

D Panjang = 19.61 m 8.25 m2


Dinding kamar mandi Lt.2 (1:4)
Tinggi = 1.00 m
Luas lubang pintu = 11.36 m2
Luas = (19.61 x 1) - 11.36
= 8.25 m2

4.3 Pek. Plesteran dan Acian


A Luas dinding Lt.1 = 426.54 m2 1342.27 m2
Plesteran dinding rumah (1:6)
Luas dinding KM Lt. 1 = 1.44 m2
Luas dinding Lt.2 = 500.31 m2
Luas dinding KM Lt.2 = 8.25 m2
Luas Plesteran
=(2 [(426.54 - 1.44)+(500.31 - 8.25)]
= 1342.27 m2

B Luas dinding luar KM Lt.1 9.69 m2


Plesteran dinding luar KM (1:4)
= 1.44 m2
Luas dinding luar KM Lt.2
= 8.25 m2
Luas plesteran = 1.44 + 8.25
= 9.69 m2

C Panjang KM Lt.1 = 12.80 m 106.92 m2


Plesteran dinding dalam KM (1:4)
Tinggi KM Lt.1 = 4.00 m
Panjang KM Lt.2 = 19.61 m
Tinggi KM Lt.2 = 4.00 m
Luas lubang pintu Lt.1 = 11.36 m2
Luas lubang pintu Lt.2 = 11.36 m2
Luas
=[(12.8 x 4)-11.36]+[(19.61 x 4)-11.36]
= 106.92 m2

D Acian Luas plesteran dinding rumah 1458.88 m2


= 1342.27 m2
Luas plesteran dinding (luar) kamar mandi
= 9.69 m2
Luas plesteran dinding (dalam) kamar mandi
= 106.92 m2
Luas acian = 1149.79 + 9.69 + 106.92
= 1458.88 m2

E Benangan Dalam Benangan dalam Lt.1 = 192.00 m' 404.00 m'


Benangan dalam Lt.2 = 212.00 m'
Panjang = 192 + 212
= 404.00 m'

F Benangan Luar Benangan luar Lt.1 = 44.00 m' 72.00 m'


Benangan luar Lt.2 = 28.00 m'
Panjang = 44 + 28
= 72.00 m'

G Sopi-sopi Alas = 10.654 m 13.14 m2


Tinggi = 2.467 m
Luas = 1/2 x a x t
= 13.14 m2

V PEKERJAAN ATAP DAN PENUTUP ATAP


5.1 Pekerjaan Kuda-kuda
Panjang bentang = 10.654 m' 16.24 m2
Rangka Kuda-kuda Baja Ringan
Lebar bentang = 15.810 m'
Tinggi Rangka = 3.049 m'
Kemiringan = 30 Derajat
Total kuda-kuda = luas rangka x jumlah
= 259.87
Luas rangka kuda-kuda = 1/2 x a x t
= 16.24 m2

5.2 Kerangka penutup atap = Luas atap 1/kemiringan 389.00 m2


= 194.50 m2
total luas kerangka penutup atap
= luas atap x jumlah atap
= 389.00 m2

5.3 Penutup atap genting beton = Luas atap 1/kemiringan 389.00 m2


= 194.50
total luas penutup atap = luas atap x jumlah atap
= 389.00 m2

VI PEKERJAAN LISPLANK DAN PLAFOND


6.1 Lisplank Panjang = 31.62 m2 0.28 m2
Uk. Papan Lisplank = 3/30 cm
Volume = 31.62 (0.3 x 0.03)
= 0.28 m2

6.2 Pekerjaan Plafond


A Rangka Plafond Lt. 1 Teras depan = 5.445 x 2.29 203.74 m2
= 12.47 m2
Carport = 8.47 x 3.688
= 31.24 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
KM/WC 1 = 1.775 x 1.75
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Luas Total = 203.74 m2

B Rangka Plafond Lt. 2 Ruang Tidur 1 = 6.061 x 4.65 172.56 m2


= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
KM/WC 1 = 2.0 x 3.38
= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Ruang Keluarga = 5.975 x 10.595
= 63.31 m2
Void = 4.37 x 5.945
= 25.98 m2
Luas Total = 172.56 m2

C Plafond Lt. 1 Teras depan = 5.445 x 2.29 203.74 m2


= 12.47 m2
Carport = 8.47 x 3.688
= 31.24 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
KM/WC 1 = 1.775 x 1.75
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Luas Total = 203.74 m2

D Plafond Lt. 2 Ruang Tidur 1 = 6.061 x 4.65 172.56 m2


= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
KM/WC 1 = 2.0 x 3.38
= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Ruang Keluarga = 5.975 x 10.595
= 63.31 m2
Void = 4.37 x 5.945
= 25.98 m2
Luas Total = 172.56 m2

VII PEKERJAAN KUSEN PINTU DAN JENDELA (ALUMUNIUM)


7.1 Kusen Pintu dan Jendela (PG 1) 1 Lebar = 0.15 m 10.28 m3
Unit Tinggi = 2.40 m
Panjang = 2.78 m
Volume = Jmlh x P x L x T
= 1.00 m3

7.2 Kusen Pintu dan Jendela (PJ 1) 1 Lebar = 0.15 m


Unit Tinggi = 2.40 m
Panjang = 2.18 m
Volume = Jmlh x P x L x T
= 0.78 m3

7.3 Kusen Pintu (P1) 1 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 1.68 m
Volume = Jmlh x P x L x T
= 0.60 m3

7.4 Kusen Pintu (P2) 12 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 0.88 m
Volume = Jmlh x P x L x T
= 3.80 m3

7.5 Kusen Pintu (P 3) 4 Unit Lebar = 0.15 m


Tinggi = 2.14 m
Panjang = 0.78 m
Volume = Jmlh x P x L x T
= 1.00 m3
7.6 Kusen Pintu (P4) 2 Unit Lebar = 0.15 m
Tinggi = 2.40 m
Panjang = 0.88 m
Volume = Jmlh x P x L x T
= 0.63 m3

7.7 Kusen Jendela (J1A) 1 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 1.48 m
Volume = Jmlh x P x L x T
= 0.53 m3

7.8 Kusen Jendela (J2) 8 Unit Lebar = 0.15 m


Tinggi = 1.78 m
Panjang = 0.78 m
Volume = Jmlh x P x L x T
= 1.67 m3

7.9 Kusen Jendela (J3) 2 Unit Lebar = 0.15 m


Tinggi = 0.53 m
Panjang = 1.42 m
Volume = Jmlh x P x L x T
= 0.23 m3

7.10 Kusen Jendela (J4) 1 Unit Lebar = 0.15 m


Tinggi = 0.30 m
Panjang = 0.70 m
Volume = Jmlh x P x L x T
= 0.03 m3
Total Volume Kusen Pintu dan Jendela
= 10.28 m3

VIII PEKERJAAN KERAMIK


8.1 Pekerjaan Tegel Lantai
A Lantai 1 Granit tile (60 x 60) Teras depan = 5.445 x 2.29 166.86 m2
= 12.47 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Total Luas Lantai Granit = 166.86 m2

B Lantai 2 Granit Tile (60 x 60) Ruang Tidur 1 = 6.061 x 4.65 242.02 m2
= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
Ruang Keluarga = 16.975 x 10.037
= 170.38 m2
Total Luas Lantai Granit = 242.02 m2
C Lantai 1 Keramik (40 x 40) KM/WC 1 = 1.775 x 1.75 5.64 m2
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Total Luas Lantai Keramik = 5.64 m2

D Lantai 2 Keramik (40 x 40) KM/WC 1 = 2.0 x 3.38 51.16 m2


= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Teras Belakang = 2.50 x 15.81
= 39.53 m2
Total Luas Lantai Keramik = 51.16 m2

E Carport = 8.47 x 3.688 31.24 m2


Lantai 1 Keramik Kasar (40 x 40)
= 31.24 m2
Total Luas Lantai Keramik = 31.24 m2

8.2 Keramik Dinding


A Tinggi = 3.00 m2 28.90 m2
Keramik Dinding KM Lt.1 (25 x 40)
Luas lubang kusen = 5.68 m2
KM/WC 1 = 2 x (1.775 + 1.75)
= 7.05 m2
Volume = (7.05 x 3) - 5.68
= 15.47 m2
KM/WC 2 = 2 x (1.56 + 1.625)
= 6.37 m2
Volume = (6.37 x 3) - 5.68
= 13.43 m2
Volume Total = 15.47 + 13.43
= 28.90 m2

B Tinggi = 3.00 m2 47.47 m2


Keramik Dinding KM Lt.2 (25 x 40)
Luas lubang kusen = 5.68 m2
KM/WC 1 = 2 x (2.0 + 3.38)
= 10.76 m2
Volume = (10.76 x 3) - 5.68
= 26.60 m2
KM/WC 2 = 2 x (2.075 + 2.35)
= 8.85 m2
Volume = (8.85 x 3) - 5.68
= 20.87 m2
Volume Total = 26.6+20.87
= 47.47 m2

VIIII PEKERJAAN INSTALASI LISTRIK


9.1 Instalasi Listrik Lantai 1
Panjang kabel = 84.10 m
Panel MCB = 1 bh
Meteran Listrik = 1 bh
Saklar Tunggal = 5 bh
Saklar Ganda = 8 bh
Stop Kontak Tunggal = 22 bh
Stop Kontak Ganda = 1 bh
Lampu Gantung = 1 bh
Lampu SL = 36 bh

9.2 Instalasi Listrik Lantai 2


Panjang kabel = 93.13 m
Tv Kabel = 2 bh
Saklar Tunggal = 8 bh
Saklar Ganda = 5 bh
Stop Kontak Tunggal = 20 bh
Stop Kontak Ganda = 6 bh
Lampu Led strip plafond = 7.21 m
Lampu Led strip dipan = 7.00 m
Lampu SL = 33 bh

X PEKERJAAN INSTALASI AIR


10.1 Instalasi air Lantai 1
Pipa air bersih = 59.22 m
Pipa air bekas = 39.01 m
Pipa Pembuangan air AC = 20.53 m
Pipa air kotor = 12.49 m
Kloset duduk = 2 bh
Kran air = 2 bh
Shower = 1 bh
Floor Drain = 2 bh
Kitchen set = 1 unit
Wastafel = 1 bh
AC = 3 bh

10.2 Instalasi air Lantai 2


Pipa air bersih = 31.12 m
Pipa air bekas = 22.98 m
Pipa Pembuangan air AC = 29.19 m
Pipa air kotor = 20.00 m
Kloset duduk = 2 bh
Shower = 2 bh
Floor Drain = 2 bh
Wastafel = 2 bh
Pompa = 1 bh
Toren/Tandon Air = 1 bh
AC = 6 bh

XI PEKERJAAN FINISHING
11.1 Pekerjaan Pengecatan dinding
Luas dinding Lt.1 = 129.21 m2 461.56 m2
Luas dinding Lt.2 = 153.32 m2
Luas Sopi-sopi = 13.14 m2
Luas kusen = 64.89 m2
Luas Total
= (2 sisi x ((129.21 + 153.32 + 13.14) - 64.89))
= 461.56 m2

11.2 Pekerjaan Pengecatan Lisplank


Panjang = 31.62 m 18.97 m2
Lebar = 0.30 m
Volume = 2 sisi x (p x l)
= 18.97 m2

XII PEKERJAAN LAIN-LAIN


12.1 Pekerjaan Septictank
A Galian tanah Septictank Panjang galian I = 1.00 m 3.50 m3
Lebar galian I = 1.00 m
Dalam galian I = 2.00 m
Volume (I) = 1x1x2
= 2.00 m3
Panjang galian I = 1.00 m
Lebar galian I = 1.00 m
Dalam galian I = 1.50 m
Volume (I) = 1 x 1 x 1.5
= 1.50 m3

Total Volume = 2 + 1.5


= 3.50 m3

B Urugan pasir bawah septictank


Luas sisi septictank = 8.00 m2 0.80 m3
Ketebalan = 0.10 m2
Volume = 8x1
= 0.80 m3

C Balok septictank (15/15)


Jumlah = 2 unit 0.09 m3
Panjang = 2.00 m
Lebar = 0.15 m
Tebal = 0.15 m
Volume = 2 x (2 x x 0.15 x 0.15)
= 0.09 m3

D Plat penutup septictank


Jumlah unit = 2 unit 0.40 m3
Panjang = 2.00 m
Lebar = 1.00 m
Tebal = 0.10 m
Volume = 2 x (2 x 1 x 0.1)
= 0.40 m3

E Trasram septictank (1:2)


Luas sisi septictank = 12.00 m2 3.60 m3
Kedalaman trasram = 0.30 m
Volume = 12 x 0.3
= 3.60 m3
12.2 Pekerjaan Sumur Resapan
A Galian tanah sumur resapan
Diameter = 1.20 m 2.03 m3
Jari-jari = 0.60 m
Kedalaman = 1.80 m
Volume = 3.14 x 0.6 x 0.6 x 1.8
= 2.03 m3

B Plat penutup sumur resapan


Diameter = 1.00 m 0.08 m3
Jari-jari = 0.50 m
Tebal = 0.10 m
Volume = 3.14 x 0.5 x 0.5 x 0.1
= 0.08 m3

12.3 Pekerjaan bak kontrol


A Galian tanah bak kontrol
Jumlah bak kontrol = 2 unit 0.23 m3
Panjang = 0.50 m
Lebar = 0.50 m
Kedalaman = 0.45 m
Volume = 2 x (0.5 x 0.5 x 0.45)
= 0.23 m3

B Plat penutup bak kontrol


Jumlah = 2 unit 0.01 m3
Panjang = 0.30 m
Lebar = 0.30 m
Tebal = 0.05 m
Volume = 2 x (0.3 x 0.3 x 0.05)
= 0.01 m3

12.4 Pekerjaan pipa saluran


A Galian tanah pipa saluran limbah
padat 4" Panjang = 12.49 m 1.22 m3
Kemiringan = 0.03
Kedalaman = 12.49 x 2.5%
= 0.31 m
Volume = 0.3 x 0.3 x 12.49
= 1.22 m3

B Galian tanah pipa saluran limbah


cair 3" Panjang = 22.98 m 1.21 m3
Kemiringan = 0.01
Kedalaman = 22.98 x 1%
= 0.23 m
Volume = 0.2 x 0.2 x 22.98
= 1.21 m3

C Urugan tanah kembali pipa


limbah padat 4" Volume galian = 1.22 m3 1.06 m3
Diameter pipa = 0.114 m
Panjang galian = 12.49 m'
Volume
= [1.22 - (1/4 x 3.14 x 0.114 x 0.114 x 12.49)]
= 1.06 m3

D Urugan tanah kembali pipa


limbah cair 3" Volume galian = 1.21 m3 1.04 m3
Diameter pipa = 0.089 m
Panjang galian = 22.98 m'
Volume
= [1.21 - (1/4 x 3.14 x 0.089 x 0.089 x 22.98)]
= 1.04 m3

12.5 Railing tangga dan void


Panjang tangga = 7.42 m 16.21 m
Panjang void = 8.79 m
Total = 7.42+8.79
16.21 m

12.6 Tandon air atau toren


Jumlah = 1 Unit 1 Unit

12.7 Set Wifi


Jumlah = 1 bh 1 bh

12.8 Parabola
Jumlah = 1 bh 1 bh