Ajeng Ayu Tabel AHSP Dan Rab PDF
Ajeng Ayu Tabel AHSP Dan Rab PDF
= 17.6 x 15.8
= 278.65 m2
17.6
= 2 (19.6 + 17.8)
= 74.87 m'
17.6
= 3x5
= 15.00 m2
3.0
-1.30
-2.00
1.00
B
Galian tanah pondasi Batu Kali (A)
P.Galian = 87.97 m 114.36 m3
-0.3 L.Galian = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 114.36 m3
-1.30
1
C
Galian tanah pondasi Batu Kali (B)
P.Galian = 51.06 m 66.38 m3
-0.3 L.Galian = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 66.38 m3
-1.30
1
2.2 Urugan Tanah
A Galian footplat = 37.50 m3 37.08 m3
Urugan tanah kembali footplat
Total Vol.Footplat = 4.80 m
Total Vol.Kolom pendek = 1.80 m
Volume = {37.5-(5.57+2.09)}x 1.2
= 37.08 m3
B
Urugan tanah kembali Batu kali
Vol. Total galian = 180.74 m 109.41 m3
Vol. Total pondasi = 89.56 m
Volume = (180.74-89.16)x1.2
= 109.41 m3
D
Urugan tanah peninggi elevasi
Luas lt. teras = 10.54 m 2.53 m3
lantai teras, KM, dan gudang
Tinggi/Tebal = 0.20 m
Volume = (10.54x0.2) x 1.2
= 2.53 m3
B
Urugan pasir bawah anstamping
Lebar = 1.00 m 13.90 m3
Batu Kali A dan B
Tinggi/Tebal = 0.10 m
Panjang Pondasi = 139.03 m
Volume = (1 x 0.1 x 139.03)
= 13.90 m3
- Volume Bekisting
Jmlah footplat = 25.00 bh 24.00 m2
Panjang = 0.80 m
Tinggi/ Tebal = 0.30 m
Volume = 4 (0.8 x 0.3) x 25
= 24.00 m2
B Kolom Pendek
Jmlah Footplat = 25.00 bh 1.80 m3
Panjang kolom = 0.15 m'
Lebar kolom = 0.30 m'
Tinggi/Tebal = 1.60 m'
Volume = 25 (1.6 x 0.3 x 0.15)
= 1.80 m3
C
Balok Sloof Batu Kali A dan B
Lebar = 0.15 m 5.91 m2
Tinggi/Tebal = 0.30 m
Panjang sloof = 131.44 m
Volume = 131.44 (0.3 x 0.15)
= 5.91 m2
- Volume Bekisting
Panjang sloof = 131.44 m 78.86 m2
Tinggi/Tebal = 0.30 m
Volume = 2 (131.44 x 0.3)
= 78.86 m2
- Volume Bekisting
Jlmh Kolom induk = 25.00 bh 30.00 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.3) x 28
= 30.00 m2
- Volume Bekisting
Jlmh Kolom induk = 14.00 bh 16.80 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.15) x 14
= 16.80 m2
- Volume Bekisting
Jlmh bekisting = 2.00 bh 132.68 m2
Panjang Balok = 147.43
Tinggi = 0.30 m'
Lebar = 0.15 m'
Volume = 3 (147.43 x 0.3)
= 132.68 m2
- Volume Bekisting
Jlmh bekisting = 2.00 bh 24.34 m2
Panjang Balok = 54.08
Tinggi = 0.15 m'
Lebar = 0.15 m'
Volume = 3 (54.08 x 0.15)
= 24.34 m2
H Plat Tangga
Tebal plat tangga = 0.18 m' 2.25 m3
Panjang Sisi samping = 2.40 m'
Sudut tangga bawah A = 34 derajat
Pnjng plat tangga bawah = 2.4/cos 34
= 2.89 m'
Panjang sisi samping B = 4.895 m'
Pnjng plat tangga tengah = 4.895/cos 34
= 5.90 m'
Panjang sisi samping C = 1.95 m'
Panjang plat tangga atas = 1.95/cos 34
= 2.35 m'
Lebar tangga = 0.95 m'
Lebar bordes = 1.00 m'
Volume
- Plat tangga bawah = (2.89 x 0.95 x 0.18)
= 0.50 m3
- Plat tangga tengah = (5.90 x 0.95 x 0.18)
= 1.01 m3
- Plat tangga atas = (2.35 x 0.95 x 0.18)
= 0.40 m3
- Plat Bordes = 2x (0.18 x(0.95 x 1))
= 0.34 m3
Volume total = 2.25 m3
Volume Bekisting
Volume plat 15.34 m2
Bawah = 3.73 m2
Tengah = 7.62 m2
Atas = 3.03 m2
Jumlah = 14.39 m2
Volume bordes = 0.95 m'
Volume = (31.91+0.95)
= 15.34 m2
Volume Bekisting
Jumlah = 2.00 bh 64.53 m2
Panjang = 143.40 m
Lebar = 0.15 m
Volume Bekisting = 3 x (143.40 x 0.15)
= 64.53 m2
B Lantai 2 Granit Tile (60 x 60) Ruang Tidur 1 = 6.061 x 4.65 242.02 m2
= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
Ruang Keluarga = 16.975 x 10.037
= 170.38 m2
Total Luas Lantai Granit = 242.02 m2
C Lantai 1 Keramik (40 x 40) KM/WC 1 = 1.775 x 1.75 5.64 m2
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Total Luas Lantai Keramik = 5.64 m2
XI PEKERJAAN FINISHING
11.1 Pekerjaan Pengecatan dinding
Luas dinding Lt.1 = 129.21 m2 461.56 m2
Luas dinding Lt.2 = 153.32 m2
Luas Sopi-sopi = 13.14 m2
Luas kusen = 64.89 m2
Luas Total
= (2 sisi x ((129.21 + 153.32 + 13.14) - 64.89))
= 461.56 m2
12.8 Parabola
Jumlah = 1 bh 1 bh