THANH PHONG Wind Power Plant (29.

7 MW)

WTG COMMISSIONING CONCERNS


Date 28-Aug-23
No. Scope of Work . Turbine No. Issued Date Status Description Goldwind' s Clarify Target Date Revised Actual Remarks
- Communication State : PLC Interrupt -> Need to update program and software.
- GW forgot to remove link cable at converter cabinet, the PLC detected not real
1 GW WTG 1 to 9 25-Aug Closed 25-Aug-23 Closed
warning and stop WTGs running -> Already removed link cable at converter
cabinet
2 GW WTG9 25-Aug Closed Alam type custom, Program, Device commstate 25-Aug-23 Closed

3 GW WTG9 25-Aug Closed Operation Condition abnomal Protection 25-Aug-23 Closed


Large Deviation among three Pitch Position
4 GW WTG5 25-Aug Closed (Due to the signal wiring cable of Pitch's Brake was loosen, has to reconnect 25-Aug-23 26-Aug-23 Closed
firmly again)
Outer Race Temp. Of Generator front Bearing
5 GW WTG5 27-Aug Closed (Not enough grease, when generator running full capacity and speed, the great 27-Aug-23 Closed Keep monitoring
friction make the temperature increase high)
6 GW WTG4 27-Aug Closed CVT_Inveter_Cab_Over_Temp 27-Aug-23 Closed Keep monitoring
GW discussed with their R&D
7 GW WTG3 28-Aug Open CVT_Inveter_Cab_Over_Temp ( Again ) 28-Aug-23 Opened team. 29 Aug, GW stop WTG4
to update software/program
Turbine WTG2 Reached 3.516 MW at 12:28 a.m over 6% with max 3.3 MW.
8 GW General 28-Aug Open Request to Goldwind to clarify the capicity of generator during running & time to TBC Open Keep monitoring
over Rated Capacity accept.

9 GW General N/a Open Abnormal Nosie TBC Open Keep monitoring

10

11
Urgent

WTG INSTALLATION CONCERNS Normal


On Schedule

WTG PREPARATION WORK


No. Scope of Work . Area Issued Date Status Description PCC ' Reply for Solution Target Date Revise Actual TE P.I.C Owner Contact No. Remarks

A. INTERNAL ROAD

>> PCC to move Piling material for Crane 150 Tons Parking
1 PCC- Subcon JETTY 16-Jul-21 - Piling material need to move for Crane 150 Tons ( TAGI) location TBC Mr. Khoi Mr. Xe
-> PCC confirm the date./ ( Tagi to inform PCC to move befor 5days )

- Leveling elevation between jetty and main road suface all need to
2 PCC- Subcon JETTY 16-Jul-21 >> PCC to make slope below 3% TBC Mr. Khoi Mr. Xe
make sam level and logitudinal slope require below 3%

- Main yard is very bad condition with serious and sinking & quite
defined Space. ( Storage layout must be stored at lease 3 full sets of
3 PCC- Subcon Main Storage 16-Jul-21 >> PCC to provide Crane & Lifting Plan for unloading EQ TBC Mr. Khoi Mr. Xe
WTG)
- 02 Crawle Crane 100Tons ) - Lifting Radius

- At main gate of Yard :


Request to remove fence and site containers to enlarge & get >> PCC to move Piling material before Tagi moving Blade Material
4 PCC- Subcon Main Storage 16-Jul-21 TBC Mr. Khoi Mr. Xe
sufficient turning radius for Blade trailer as our simulation ( Targi to inform site before 10 days )
accordingly

- There are 03 Steel Bridge which we request all longitudinal


gradients here must be from 2.5% to max 3% for safe operations
trailer moving pass these bridges . Bridges are also requested - To make Slope as request and caculation one more time to check
Mr.Chen / Mr.
5 PCC- Subcon Bridge 16-Jul-21 strength enough to impose wind component weight up to 100T plus - Tagi to provide Trailer /Truck dim & to show SUMULATION that TBC Mr. Khoi Mr. Xe
Nie
with trailer weight. Blade on Trailer
- Request all sharp curves to be widen as sufficient turning radius
we will submit simulation at later stage

B. SUBMIT DOCUMENT

PCC- SINOTRANS - Crane 150 Tons ( 2 Pcs) document to submit ( Lifting Plan ,
1 JETTY 16-Jul-21 -> Tagi to provide Certificate of Crane TBC Mr. Khoi
TAGI Certificate ,,, ) before Start work

PCC- SINOTRANS - Tagi to Provide Lifting duration time for each EQ / Each Barge - > To make detail schedule ( Date / Barge / Time offloading for each
2 JETTY 16-Jul-21 TBC Mr. Khoi
TAGI ( Detail schedule for Duration lifting ) Barge )

- PCC to provide Crawler Crane 800Tons Location , Assembly Plan


3 PCC-PCShanxi WTG3 16-Jul-21 - Lifting Plan / Loadtest Certificate TBC Mr. Khoi
, LoadTest Plan , Certificate

4 PCC-PCShanxi WTG3-Main Storage 16-Jul-21 - PCC will Provide Truck Crane 500 Tons Certificate - Crane Certificate TBC Mr. Khoi

5 PCC ALL 16-Jul-21 - Delivery detail list ( Invoice No : THPH -001 to 005 ) - Parking List ??/ TBC Mr. Khoi

6 PCC ALL 16-Jul-21 - MS Revise -> PCC Have Submited MS Rev : B on 20/Jul TBC Mr. Khoi

7 PCC ALL 16-Jul-21 - TE request to PCC to submit ITP of WTG inspection TBC Mr. Khoi