QC INFRA PROJECT
SCOPE OF WORK:
ITEM
WORK DESCRIPTION & SCOPE OF WORKS UNIT QTY. UNIT COST TOTAL COST
NO.
A. GENERAL REQUIREMENT
Temporary Lighting & Water Facilities days 60 P P
Steel Barricade with caution tape (Rental) each 41
Billboard pc 1
Direct Cost A P
Material Cost P
Labor Cost
Direct Cost B P
Material Cost P
Labor Cost
Direct Cost D P
Page 2 of 3
Name of Project: PROPOSED INSTALLATION OF ELECTRICAL SERVICE ENTRANCE OF LAGRO
SENIOR HIGH SCHOOL
SUMMARY
A. GENERAL REQUIREMENT P
B. INSTALLATION OF ELECTRICAL SYSTEM
Page 3 of 3
Name of Project: PROPOSED INSTALLATION OF ELECTRICAL SERVICE ENTRANCE OF LAGRO
SENIOR HIGH SCHOOL
BREAKDOWN OF COST
A. GENERAL REQUIREMENT
B.
INSTALLATION OF ELECTRICAL SYSTEM
C. FABRICATED PVC BRACKETS
D. CONSTRUCTION OF CONCRETE
DISTRIBUTION POLE
E. INSULATION RESISTANCE TEST
TOTAL