Professional Documents
Culture Documents
Standard Time Calculation
Standard Time Calculation
0ccur at the end of the shift. e.g. cleaning allowance is given while an operator has s
repeatedly for cleaning his machine or workplace. Atool allowance is given to to give
funing and repairs of tools. COver up the fine. attention
I is generally preferedto give allthese allowances as aperiod of ftime per day
them withinthestandard times. Typically. it is better asit has an advantage ofrather than
drawing therepresenting
of the managementtowards the amount of time being given to these
will be effort to reduce the same. activities: consequentlatyt,entthioeren
Some of the allowances are usually set perchance or per lot, e.g., set-up
up the time needed to set up a machine, cquipment or production allowanceis
i
given to cover
process, a necessary
start the production of abatch of a new product or component. This set-up time
is operation
to
as make-ready time: its contrary is called as tear-down or sometimes
dismantling time, which iS given, totermed
up the time required for doing adjustments and changesto machine or cover
production run. e.g..changing adie. Extremely alike is the change-overprocesS settingssafter finishing a
provided to the allowance, which is normalu
operators who are not truly occupied in setting-up or dismantling. Hence it is to
reimburse operators for the time spent on necessary activities or may be
the given
and/or the ending of a job or batch. These allowances are termed as waiting time at beginnino
There is another allowance, called as learning job/batch change-over allowances
allowances, which is
occupied in activities or jobs having set standard times. It is provided as agiven to the trainee workers
trainees can develop their skills. Similarly we have a training temporary benefit while the
worker to compensate his training period. These are given asallowance
some
which given to an experienced
scale so that the allowances taper off to zero over the minutes per hour, on a declining
Very similar is an implementation allowance, given to
expected learning period.
workers asked to adopt a new ways and
prevent their loss of earnings by doing so. In fact, it is sometimes
actually be increased during the change-over period, so as to enablearranged that their earnings will
the new method to encourage
them to implement enthusiastically and prevent their down
earnings. For example, one system of
implementation allowances credits the workers with ten minutes per hour on the first day, nine on
the second, and so on, down to zero.
BT (or NT) = 0T x OR
i.e. OT x OR = BTx SR
SR(100)
Dacie(Normal) Time can be
represented as = (Observed Time) x Rating factor in %
100
Pating factor (RF) is in percentage like if observed rating is 90
per cent, RF =0.9, if rating is 110
per cent then R.F = 1.10
where, BT:Basic time
NT: Normal time
0T: the observed time with the
OR: Observed rating
stopwatch
SR: Standard rating
Allowed Time
Standard Time
90 107 125
2 145
155 175 195
210
240 260
4 225 280
310 330
290 350
110 120
Average Rating 110 90
Solution: The initial stopwatch reading is taken as zero, the observed time for each elenmens :.
determined from the continuous readings taken at the end of each element by subtracting the initisl
from the final, therefore observed timings for each element is shown in Table 4.9.
Therefore normal time for the operation = 14.3+ 20.24+ 23.52 + 17.1 = 75.16 sec
Table 4.9: Calculation of average observed time and basic time for each element.
3 4
Element No.
Cycle No. Stopwatch Reading in Seconds
20 20 20
10
20
2 20 17 18
20
10 20 20
15
15 15 20
20
10 20 20
92 98 = 19.6 95- 19
Average 6513 5
= 18.4
5
5
90
Average Rating 110 110 120
19x 90 = 17.1
Normal Time 13 x 110 18.4 × 1 10 19.6 x 120 = 23.52
= 14.3 = 20.24 100
I00 100 100