Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 37

Apply Problem Solving Techniques in the Work Site

Analyses construction, environmental management, and energy conservation problems and applies
appropriate and compliant remedial solutions


Ensures processes that identify faults and required remedial action
 Develops strategies to address project delays
 Performs various complex calculations relating to cost-benefit analysis, rise and fall amounts,
pessimistic overdraft requirements, statistical analysis, costs, set out of construction work, structural
analysis and service installations
 Analyses reasons for cost variations and takes remedial action
 Establishes and implements dispute resolution procedures
 Maintains site safety and manages risks
 Provides advice on dispute resolution
 Uses and analyses data in decision making
Negotiation
Marketing and/or contract administration organizations distribute copies of customer
specifications and subsequent changes regarding technical, administrative, and quality
requirements to appropriate functional groups for review and comment prior to proposal submittal.
This review is performed to ensure that customer requirements are adequately defined and
understood, and that the capability exists to meet these requirements. During the review,
marketing and/or contract administration organizations coordinate all communication with the
customer. A record of the review is maintained.

Identify the problem


1. Construction Claims
 Claim is legally defined as an assertion to right.
 The nature of right may relate to time, financial, or other remedies.
 Claim is therefore a substantive demand, for example, by the Contractor against the
Employer.
 The Employer may have its own substantive demand against the Contractor. We can call
this a counterclaim.
 The basis of claim is either the contract and/or the applicable law.

Claims under the Contract

 These are of two types:


 Claims as a result of certain anticipated & specified events & for which a remedy is
designated in the contract; and

1
 Claims as a result of an event where a certain term of the contract is breached & for
which a remedy is designated in the contract.
 In both cases, the remedy is provided under the contract.
 However, the first related to non breach of the contract, whereas, the second does.
 The remedies in both cases may relate to financial compensation, time extension, &
other benefits or remedies.
 Illustrative of remedies under the FIDIC Conditions of Contract.
1. Financial compensation:
 With respect to Variation;
 Measurement Changes;
 Adverse Physical Conditions;
 The Employer’s Risks;
 Compliance with statutes, regulations, price fluctuations, currency & other
economic causes;
 Defects & unfulfilled obligations (NB: It relates to breach of the Contract);
 Failure to commence, critical or non critical delays, suspension of work, release
from performance, default & termination;
 Delay in certifying payments; etc
2. Time Extension
 Delay in supply of documents or drawings; ( see FIDIC Clause 6.3 & 6.4 )
 Adverse physical obstructions or physical conditions; ( see FIDIC Clause
12.2)
 Fossils & articles of value or antiquity; ( see FIDIC Clause 27.1)
 Tests required but not provided for; ( see FIDIC Clause 36.5)
 Suspension of the progress of the works; ( see FIDIC Clause 40.2)
 Failure to give possession of site; ( see FIDIC Clause 42.2) etc
3. Other Benefits or Remedies
 Termination of contract under the contract and/or the applicable law.
 Suspension of the execution of works;
 Reduction of the progress of the execution of works;

2
4. Remedy under the Law
 It relates to a claim arising out of the contract based on the grounds that a term of contract
had been breached but where the remedy is not designated in the contract.
 Under this circumstance, if the claim is valid, the remedy lies under the provisions of the
applicable law.
 This is specially related to the assessment of damages or specific performance or others.
 With respect to assessment of damages only courts or the arbitral tribunal or the
adjudicator is empowered to assess & determine/decide based on the principles of
damages or compensation.
 With respect to specific performance only courts or the arbitral tribunal is empowered to
decide or give an award based on the principles of the applicable law.
 In such a situation, the Engineer is not empowered to assess & determine any damages or
order specific performance of the construction contract under the applicable law.
 The remedy would be sought through adjudication, arbitration or litigation unless the
claim is settled amicably.
 The legal remedy in case of damages may extend to the determination of liability with
respect to the consequential damages & assessment of quantum of same, termination of
contract as provided under the law( in serious cases).

Determine fundamental causes of the problem


2. Causes for Claims
 Causes for claims may be the occurrences of deviations from the promises made under
the construction contract during the performance of the Construction Contract.
 These deviations( Dr. Wubishet) may reflect themselves in terms of or in relation to
 completion time;
 construction cost;
 quality performance; and
 Safety requirements.
 The following factors may also cause claims.
 Poor or unclear tender and/or contract documents;
 Poor or inadequate administration of responsibilities by stakeholders; and

3
 Unforeseen or uncertain situations during execution of the Construction Project;
 The following categories of factors may also contribute to the emergence of claims.

– Changed conditions;

– Additional works;

– Delay for cost overruns & time extension;

3. Requirements for Claims

– For the claim to be successful, it has to fulfill certain valid requirements.

– These requirements are related to:

A. Substantive requirements;

B.Procedural requirements; and

C.Proof requirements;

A. Substantive Requirements

 By substantive requirement we mean supporting or giving justification for the claim by


specifically citing or invoking the provisionsOf the Construction Contract; and/or Of the
applicable law.

• The provisions of contract mean the relevant clause in the contract, which has been
signed between the parties.

• The provisions of the applicable law means the relevant article of the law, which is
applicable to the contract, for ex. The Civil Code.

• The substantive requirement is also called the legitimacy requirement.

• Submitting a claim, without first establishing its legitimacy, under the Contract and/or
under the applicable law is a futile exercise with no guaranteed return.

• Pursuing claims costs money & also corporate time.

B.Procedural Requirements

4
 By procedural requirement we mean the serving of the required prior written notice to the
designated party under the contract.
 This is called intention to claim.
 This prior written notice shall also be given within the contractually designated time
scale.
 The time scale might be specific or reasonable
 The contract under consideration may specify such time scale in either way.
 Clause 53 of FIDIC is illustrative in this instance. There are also other clauses, which
specify other (lesser or subjective) time scales depending up on the specific type of
claims.
 The non observance of the procedural requirement may result whole or partial loss of the
substantive claim.

C.Proof Requirements

• By proof requirement we mean the submission of the relevant documentation, which


supports/corroborates the claims under consideration.
• The relevant documentation may relate, for example, to:-

• time (delay & disruption) claims;

• cost (additional payment) & profit claims;

• variations claims; and

• Other construction claims;

 They may contain a form of letters, notices or otherwise.


 In case of disputes the proof requirement, in addition to the relevant
documentation, may also include:-

• Factual Witnesses;

• Expert Opinion;

• Site Visit or Inspection;etc

4.Process of Claims

5
– The claims process generally classified in to the following three phases:

I Claim Submittal;

II Claim Processing;

III Claim Enforcement;

I Claim Submittal

 This is a process by which the claimant is obliged to claim within a reasonable period of
time ( 28-30 days in most contracts) followed by the claimant’s preparation for all
substantial documents & legal aspects supporting its entitlements for an official
submittal.
 This constituted that a claim has been filed for its consideration if all the three sub-
processes called Claim Notification, Claim Preparation & Claim Submittal are fully
undertaken by the claimant.

II Claim Processing

• This phase is classified further in to the following three sub-processes,

A. Claim Handling;

B. Dispute Resolution;

C. Claim Approval;

A.The Claim Handling, this sub-process initiates checking of the claim whether, it is
legally or contractually supported or not, documents provided are valid and reliable to
substantiate the claim for consideration or not, and overall procedural requirements have
been followed or not. After verifying the validity of the claim proper computations &
evaluations will be carried out to present the proposed compensation for the contractual
parties the claim is applicable to.

B. Dispute Resolution, the contractual parties will pass through different dispute
resolution system depending on their acceptance over the proposed compensation varying

6
from the simplest mediation by the consulting engineer to the final court ruling in the
form of litigation. Three types of dispute resolution systems are well recognized. These
are,

 Preventive Dispute Resolution System; ( by use of partnering, dispute resolution


advisors, facilitators, …)
 Amicable Dispute Resolution System; ( through negotiation, mediation, conciliation,
mini-trial, …)
 Judgmental Dispute Resolution System; (through Dispute Adjudication Board,
Arbitration, Litigation…)

Where dispute was handled in any form of its resolution System,


it is termed as Dispute Resolution

C.Claim Approval, once the contractual parties agree on the final outcome of the claim process,
then they have reached in to a stage where the claim is approved.

III Claim Enforcement

 This phase is sub-divided in to the following two sub-processes.

– Claim Enforcement;

– Claim Closure;

 The claim enforcement sub-process will entertain the inclusion of the approved claim in
to payment certificates where their enforcement is due.
 Once this compensation or entitlement is due in accordance with the approved claim and
its enforcement requirements, then it is concluded for its closure.
 In order to account for such an administration process contracts provide claim clauses
within their provisions in their conditions of contract.

5.Construction Disputes

 Construction dispute may take different forms: dispute in relation to time or cost, time &
cost or otherwise.

I Disputes relative to Time

7
 With respect to dispute relative to time or delay the following aspects shall be considered.
 With respect to delay the contractor or the employer may have their own respective
claims
 The employer’s claim is related to liquidated damages.
 The contractor’s claim mostly related to prolongation and/or disruption claims.
 Prolongation may be defined as a critical delay which results when the time necessary to
complete a critical activity is prolonged, thus extending the time for completion of the
whole of the works.
 Delays in completion of the works might result in a number of added costs to the
contractor & if such delay is determined by the engineer to be the responsibility of the
employer, then a number of claims for financial compensation can be pursued by the
contractor.

– These time claims may include:

 Direct costs in relation to plant, equipment & labour;

 On-site Establishment costs

These are referred to as site over heads & consist of the costs of an administrative & supervisory
staff including but not limited to:

• Site staff, Trades foremen, Plant & tools, Welfare including cleaning…,Lighting &
power, Storage, workshops, temporary works, Contractor’s site office including its
equipment & communication charges;

• Accommodation for the employer’s representatives;

• Sanitary accommodation;

• Scaffolding;

• Transport;

 Off-site Overhead:
 The off-site overheads cover contributions by individual contracts to the cost of
maintaining the contractor’s head office. They are difficult to establish & especially in

8
respect of a period of delay & disruption or prolongation of a particular contract, where a
specific allocation of time to the various contracts is difficult to assess.
 Adverse weather conditions: A claim may arise if as a result of a change in the timing of
the execution of the works attributable to the employer, adverse weather conditions are
encountered.
 Increased costs of labour, materials or equipment;
 Finance charges & interest;
 Profit on direct costs;
 Loss of profit;
 Interest on late payment
 Disruption may be defined as the effect of an event or a number of events on the
efficiency of execution of the works, irrespective of whether or not there had been a delay
to a critical activity.
– Continuous, extensive & cumulative disruption, however, may end in critical delay &
prolongation of the time for completion.
 Inefficiency, loss of productivity of labour & uneconomic use of equipment comes under
the heading of disruption when they are caused by an event which is not the
responsibility of the contractor.

-A proper evaluation of a claim for disruption requires the following pre-requisites.

 An identification & analysis of each of the operations claimed to have been disrupted. It
is not sufficient simply to state that the execution of the works has been disrupted.
 The cause & the manner in which disruption has occurred should be established.
 The figures for the anticipated output. The resources planned & the time required to
achieve the completion of the disrupted operations as calculated in the tender have to be
shown to be achievable.
 The effect of any inefficiency on the part of the disrupted party in carrying out the works
should be properly calculated & its effect included in the calculations of disruption
suffered.
 The number of hours actually logged in the time sheets for the disrupted operation has to
be shown to be accurate.

9
 When records are available & are correct, then the cost of disruption can be simply
calculated as the number of hours actually worked less that originally anticipated in the
tender, with the result being multiplied by the cost of the particular resources disrupted
per hour.

– When acceleration of the progress of the works is required, the cost may include
the expense of,

• Working additional hour;

• Providing additional labour;

• Providing additional or different equipment;

• Advancing the date of delivery of manufactured elements;

 Programming
 In relation to monitoring the progress of the works, program is an indispensable guiding
tool.
 Programming involves introducing the parameters of time & resources into the work
activities & ultimately into the project itself.
 The traditional method of presenting a programme for the construction contract has been
through a bar chart.
 The bar chart gives an outline plan of the time scale of a project broken down into a
relatively small number of components, each made up of a collection of many activities.
Each component may have its own bar chart.
 The bar chart also provides the start date & completion date for each of the component or
activities shown.
 For the purpose of project control, the bar chart can show the progress actually achieved
at any particular time but it is only useful at the lower level of management.

10
 The bar chart does not show how the various activities are connected except through
sequence of listing & therefore the constraint imposed by the completion of one activity
on the start of another cannot be accurately indicated or assessed.
 As delay is costly to both the employer & the contractor, a more sophisticated method
which can handle various details of each activity & the interrelationships between them
should be used in all but the simplest of civil engineering projects.
 Network planning & control is such a method.

– A project network analysis should be carried out in at least eight phases.

 Planning phase where a network of all activities necessary for the completion of a project
is planned & drawn up. An activity is an operation where time & resources are
consumed.
 Project timing where estimates of duration of activities are calculated to determine as
accurately as possible the project duration & to identify the activities which may prove to
be critical.
 Resource allocation where information is added to each activity duration to show the
resources required to complete that activity within the projected duration.
 Allocation of work to sub-contractors & a programme of appointment to be followed
with a schedule for production & approval of sub-contractors’ design, if any, and
drawings.
 Pricing of the various elements of the works.
 Procurement of materials.
 Commencement of works on site.
 Project control where the actual progress on site is periodically measured against the
network plan. The network must then be updated in accordance with the actions taken,
and a report can be periodically compiled to highlight the status of each activity at the
particular time.

The report may show:

 Delay in an activity & its effect on other activities & on the time for completion;
 New activities due to variation & the effect on others & on the time for completion;

11
 Resources which must be drafted to redress any new situations;
 Any other change in the critical path network;
 Network analysis is, therefore, critical in delay claims of the contractor.

Determine corrective actions


6.Dispute Resolution

 Dispute resolution may have the following aspects/ dimensions, namely,

1.Preventive dimension;

2.Amicable settlement dimension; and

3.Judgmental dimension;

 In relation to this there is also the concept of ADR: Alternative Dispute Resolution.
Alternative to what?
 The concept of ADR is related to alternative to litigation or sometimes alternative to all
binding decision making process (including the decision of the arbitrator & adjudicator).
 Both preventive & amicable dispute resolution systems may be categorized under
Alternative Dispute Resolution (ADR). There is no any binding or imposed decision by a
third party in them.
 In this respect, except with respect to the preventive aspect, the Ethiopian law recognizes
both the amicable & the judgmental aspect of dispute resolution systems.
 The scope of the Ethiopian law may be limited in this regard. Because not all amicable &
judgmental forms of dispute resolution systems are recognized.
 From the amicable settlement both:-
 Negotiation (Compromise: See Article 3307-Article 3317 of the Civil Code); and
 Conciliation: See Article 3318-Article 3324 of the Civil Code);are recognized.

 From the judgmental forms of dispute resolution both:-

• Litigation ( the Court System or the Judiciary System: See Article 78-Article 82 of the
FDRE Constitution); and

12
• Arbitration (See Arbitral Submission: Article 3325-Article 3346 of the Civil Code &
Article 315-Article 319, Article 350-Article 357 & Article 461(for foreign arbitral
awards) of the Civil Procedure Code) are recognized.

1. Preventive Aspect

 To prevent construction disputes, there are a host of factors to be considered.


 The following aspects may contribute to the prevention of construction disputes. To
mention few of them:-

– To have a well planned project;

– To have a well studied project;

– To have a well designed project;

– To have a clear, accurate & complete tender dossier & document;

– To have a clear, accurate & complete contract document;

– To have a balanced (in terms of allocation & distribution of risks,


rights & obligations) contract document;

– To discharge the expected contractual & legal obligations by the


contracting parties;

– To have a good project governance;

– To have a well thought & suitable dispute prevention system;

 The following are some of the internationally recognized dispute prevention systems.

1.1 Disputes Potential Index (DPI);

1.2 Intelligent Allocation of Project Risks;

1.3 Incentives to Encourage Cooperation;

1.4 Partnering;

1.5 Others;

1.1 Dispute Potential Index

13
– The Construction Industry Institute, as the result of a study into the causes of construction
disputes & the characteristics of construction projects that are more likely than others to
generate disputes, has developed a predictive tool called the Dispute Potential Index or
DPI.
– DPI identifies the presence of dispute-prone characteristics on a project, evaluates them,
and reports the results to project team members so they can take action to correct them
before they actually generate problems.
 The DPI is in effect a “cholesterol test” of the health of a construction project. The results
of such analysis can be used to take action to eliminate potential problems & to design
dispute resolution systems that will be suited to resolve particular kinds of problems that
are likely to occur.

1.2. Intelligent Allocation of Risks


– The most efficient & cost-effective way to structure project relationship is to assign each
risk to the party who is best able to manage or control the risk.
– Unrealistic shifting of risks to a party who is unable to manage the risk can increase bid
prices, sow the seeds of countless potential disputes, create distrust & resentment, and
establish adversarial relationship that can interfere with the success of the project.
– The specific studies made in relation to the subject conclude the following.
 Owners should avoid dictating preferential contract language through superior bargaining
power;
 Owners should not attempt to shift inordinate risks to the contractor through one-sided
contract language;
 The ideal contract is one that assigns each risk to the party that is best equipped to
manage & minimize that risk, recognizing the unique circumstances of the project;
 Some owners believe that the best contract is one that forces the contractor to hold the
owner harmless against all possible risks. The owner ultimately must pay the costs of
project risk-either by assuming them or by requiring the contractor to include the
insurance costs in the bid. If the particular risk is one that the contractor is ill-equipped to
avoid or manage, the insurance cost may be excessive.

14
 Project cost benefit can be realized when risk allocation is tailored to the circumstances
of the individual project. Owners who routinely force maximum assumption of risk on
the contractor are likely to incur higher project costs. Contract preparation that allocates
risk with a balanced input from all parties will be most cost-effective.

1.3. Incentive to Encourage Cooperation


– Incentive techniques are available to encourage cooperation among all participants in the
construction project.
– By temporarily subordinating their individual interests to the legitimate needs & success
of the project as a whole, they achieve a greater ultimate benefit for all project
participants, including themselves.
– An example of such an incentive is the establishment by a construction manager or
general contractor of a bonus pool.
– Upon attainment of specific project goals, the bonus will be shared among all sub-
contractors on the project.

1.4.Partnering

 Partnering is a team-building effort in which the parties establish cooperative working


relationships through a mutually developed, formal strategy of commitment and
communication.
 It can be used for long-term relationships or on project-specific basis.
 When used on a project-specific basis, partnering is usually instituted at the beginning of
the construction process after the contractor has been selected, by holding a retreat among
all project personnel who have leadership & management responsibilities.
 The participants, assisted by an independent facilitator, become acquainted with &
understand each other’s project objectives & expectations recognize common aims,
initiate open communications, and establish nonadversarial processes for resolving
potential problems.
 The basic premise of partnering is that the success of every project relies upon good faith,
not legal enforcement. It therefore, seeks to create an environment of good faith, where

15
open & free communication, mutual trust & respect, and team work take the place of
adversarial, competitive relations.
 The first cornerstone of partnering is recognizing & developing common goals.
 The second cornerstone of partnering is issue resolution. Of course, partnering first aims
to prevent conflict.
 The third cornerstone of partnering is continuous improvement throughout the life of the
project.
2. Amicable Aspect
 The very feature of amicable settlement is that the disputing parties shall have full control
both over the process & the outcome.
 There is no third party imposition of solution on the parties to the dispute.
 The following are some of the highly recognized amicable settlement methods.
2.1.Negotiation;
2.2.Mediation;
2.3.Conciliation;

2.1 Negotiation

• Negotiation is a give & take process, a serious attempt to reach a


settlement agreement.
• Negotiation could be:-
A.Direct negotiation; or
B.Assisted negotiation;

A.Direct negotiation is held directly between the very parties to the dispute. The parties may, of
course, be assisted by their own internal advisors.

• In case of assisted negotiation, mediation & conciliation come in to


picture.
• Negotiation requires two qualities or skills:
• knowledge on substance or the subject matter to be negotiated; and
• knowledge on the art & skill or process of negotiation.
• There are two types of negotiation:

16
• Interest based negotiation; and
• Rights based (positional) negotiation;
• Alternatively they may also be called:
• Competitive or hard-bargaining (for rights based); and
• Cooperative or soft-bargaining (for interest based) negotiation;
The principled negotiation has seven elements.
1. Alternatives;
2. Interests;
3. Options;
4. Legitimacy;
5. Communication;
6. Relationship; and
7. Commitment;
 A good deal in negotiation is, therefore:-
– One that is better than your Best Alternative to a Negotiated Agreement (BATNA);
– One that satisfies your interests & the other person’s interests;
– One that has been achieved after you have brainstormed & explored numerous options;
– Based on a standard of legitimacy that is fair, persuasive for you, and the other
negotiator;
– One that has been achieved through effective communication, where you have
interactively listened to the other negotiator;
– One where the relationship has been maintained, if not improved, and certainly not
destroyed; and
– One where the appropriate level of commitment is made at the end of the negotiation, not
at the beginning;

• Negotiation helps to save time & money for the parties in dispute.

• It maintains also relationship between the parties.

• It creates a win-win-situation.

• The settlement is also easily implement able.

2.2.Mediation

17
 Mediation describes the process of a neutral & disinterested person helping disputing
parties to negotiate a resolution to their dispute.
 Mediation is simply a facilitated or assisted negotiation. To agree or not to agree is left to
the decision of the parties.
 The mediator helps disputing parties to understand the dispute in a way that will
maximize their chances to reach a mutually acceptable & lasting solution.
 A mediator facilitates the discussion or negotiation. He will never propose a solution for
the settlement of the dispute. He is a mere facilitator.
 He simply performs the task of persuading the parties in dispute to change their
respective positions in the hope of reaching a point where those positions coincide,
without actively initiating any ideas as to how the dispute might be settled.
 The advantages of mediation include informality, speed & economy, but more
importantly perhaps, it often leads to an agreed settlement between the parties rather than
an imposed award or judgment.

• The process of mediation is described as follows.

A . Setting the Table;

B . Story Telling;

C . Determining Interests;

D .Setting out the Issues;

E . Brainstorming Options;

F . Selecting the Durable Options; and

G . Closure;

A.Setting the Table

• Setting the Table is the first step in mediation.

• Under this step the following actions are undertaken by the mediator.

• The mediator shall:-

18
• introduce himself to the parties (if not done previously);

• introduce to the parties about the process of the mediation;

• explains his role as mediator;

• reminds the parties as to their decisive role in resolving their disputes, that the parties
shall endeavor to persuade each other not the mediator;

• explain their right to use their own advisor (ex. Legal advisor);

• explain to the parties to follow certain procedures during the mediation;

• explain that the process is confidential;

• explain that he can not appear as a witness nor the documentation kept by the mediator be
admitted as evidence in the possible next(arbitral or judicial) proceeding;

• explain to the parties as to the possibility of holding discussions separately (caucusing);

• explain the right of the parties to walk out from the mediation process at any stage of the
mediation;

• explain the objective of the mediation being to save time & cost by reaching settlement
by their own, and the role of the mediator being assisting the parties to reach such
settlement;

B.Story Telling

 At this stage the parties are encouraged directly to tell to the mediator about the
background & contents of the dispute. The mediator is advised not to interrupt the
parties about the telling of their story. In construction mediation a written summary of the
dispute shall be sent to the mediator, before the mediator meets the parties.

C.Determining Interest,

 At this stage the mediator asks the parties more about the contents of their dispute to
determine their interests.
 Without determining their interests the mediator can not frame the issues nor seek
legitimate & durable solutions.

D.Setting out the Issue,

19
 After the interests of the parties have been figured out, issues shall be framed to
deliberate on.
 The role of the mediator is carefully framing the very issues to the dispute.
 The issues so framed help parties to conduct a purposeful discussion & to recommend
solution in respect thereof.

F.Brainstorming Options,

 At this stage of the mediation process the parties to the dispute brainstorming possible
options to resolve the dispute.
 The mediator may, according to the circumstances, assist the parties by suggesting some
possible solution either by discussing with the parties jointly or separately.

G.Selecting the Durable Solution (s),

 At this stage the mediator, on the basis of the brainstormed potential solutions, help the
parties by indicating which solution is legitimate & durable to resolve the dispute under
consideration.

I Closure,

 Closure is the last stage in the mediation process.


 The mediation process may be culminated either by resolving or not resolving the very
dispute between the parties.
 If the mediation process is successful, there is a settlement agreement reached between
the parties.
 The mediator has to make sure that the contents of the settlement reached by the parties
have been fully understood by same.
 The mediator is not expected to draft or formulate the settlement agreement.
 It is advisable to leave such task to the parties or to their respective advisors.
 The role of the mediator still may be needed in modifying or concretizing the contents of
the settlement already reached.
 If the mediation process culminated by not resolving the dispute, the mediator declares
that his role has been terminated here.

20
Construction Mediation

 The construction sector/industry fully shares the basic framework of the mediation
process.
 The construction mediation has its own peculiarities, however.
 The peculiarity may emerge due to:-
– multitude of stakeholders;
– the multi-dimensionality of the issues involved;
– the specificity of the legal & contractual framework & the industry practice &
norms being unique;that the contractual relationship between the Contracting
parties to the construction contract being along term, complex, involving high
financial stake &risky;

2.3.Conciliation

 Similar to mediation, conciliation is a voluntary form of dispute resolution where a


neutral party, the Conciliator, is appointed to facilitate negotiation between the parties in
dispute & to act as a catalyst for them to reach a resolution of their dispute.
 Unlike the mediator, the conciliator under the conciliation process, takes a more active
role probing the strengths & weaknesses of the parties’ case,
 Making suggestions;
 Giving advice;
 Finding persuasive arguments for & against each of the parties’ positions; and
 Creating new ideas which might induce them to settle their dispute;
 Under the mediation method of dispute resolution, if the parties to the dispute
fail to reach agreement, the neutral party himself is then required to draw up &
propose a solution which represents what, in his view, is a fair & reasonable
compromise of the dispute.
 The conciliator cannot decide the dispute for the parties. This is the difference
between conciliation & arbitration.
 Conciliation is sometimes called evaluative mediation.

21
 Conciliation is a more formal process than mediation & it generally involves
the engagement of legal representatives, thus making it a more expensive
process than mediation.

The conciliation process may contain the following:

 During the conciliation process, it is necessary for each party carefully to prepare a
document containing the following material.

 The Facts:

• The facts mean the factual narrative of the events leading to the issues in the conciliation.

• One of the parties, usually the party initiating the process, should prepare a bundle
containing documents which can be submitted jointly, such as

– The contract document;

– The Technical Specification;

– any drawings necessary for understanding the issues involved,

– And other relevant documentation;

 The Issues:

• It is necessary to identify the issues between the parties as clearly as possible.

• The possible issues could be:-

• Technical issues; and Legal issues;

 The Legal Principle:

• The legal basis supporting the case made by each of the parties should be set out in as
clear a language as possible.

 The Remedy or Remedies

• What to demand from the other party at the end of the process.

 The Time Frame:

22
• That is within which the conciliation process may or should be conducted.

• There are internationally recognized specific Conciliation Rules. Like

• International Chamber of Commerce (ICC) Conciliation Rules;

• The UNCITRAL Conciliation Rules;

• The ICE Conciliation Procedure;

• Others;

• The conciliation service is regulated by specific contract agreement signed between the
parties in dispute & the conciliator.

• There is also a fee to be paid by the parties to the Conciliator.

3. Judgmental Dimension
– The very feature of judgmental form of dispute resolution is that the third party known as
the court judge, the arbitrator or the adjudicator decides the case before him for the
parties.
– The parties to the dispute shall have no control over the process (especially in case of the
court system) and/or the outcome of same in all the three cases.
– Under the judgmental forms of dispute resolution the following are recognized.

3.1. Adjudication ;

3.2. Arbitration; and

3.3. Litigation;

3.1.Adjudication

 Adjudication can be defined as a process whereby an appointed neutral & impartial party
is entrusted to take the initiative in ascertaining the facts & the law relating to a dispute &
to reach a decision within a short period of time.
 Under the FIDIC Conditions of Contract Dispute Board is suggested.
 Dispute Board can, according to ICC, be of three types, namely,

3.1.1.Dispute Review Board (DRB);

3.1.2.Dispute Adjudication Board (DAB);

23
3.1.3.Combined Dispute Board(CDB);

3.1.1.Dispute Review Board (DRB)

 The DRB issues ‘Recommendations’ with respect to any dispute referred to it &
constitutes a relatively consensual approach to dispute resolution.
 If no party expresses dissatisfaction with a recommendation within a stated time period,
the parties contractually agree to comply with the Recommendation.
 If a party expresses dissatisfaction with the Recommendation within such time period,
that party may submit the dispute to arbitration, if the parties have so agreed, or the
courts. Pending a ruling by the arbitral tribunal or the court, the parties may voluntarily
comply with the Recommendation but are not bound to do so.

3.1.2.Dispute Adjudication Board (DAB)

 The DAB issues ‘Decisions’ with respect to any dispute referred to it & constitutes a less
consensual approach to dispute resolution.
 By contractual agreement, the parties must comply with a Decision without delay as soon
as they receive it.
 If a party expresses dissatisfaction with a Decision within a stated time period, it may
submit the dispute to final resolution by arbitration, if the parties have so agreed, or the
courts, but the parties meanwhile remain contractually bound to comply with the
Decision unless & until the arbitral tribunal or the court rules otherwise.
 If no party expresses dissatisfaction with a Decision within the stated time period, the
parties contractually agree to remain bound by it.

3.1.3.Combined Dispute Board (CDB)

 The CDB normally issues Recommendations with respect to any dispute referred to it but
may issue a Decision if a party so requests & no other party objects.

24
 In the event of an objection, the CDB will decide whether to issue a Recommendation or
a Decision on the basis of the criteria set forth in the Dispute Board Rules.
 The CDB thus offers an intermediate approach between the DRB & the DAB.
 The essential difference between a Decision & a Recommendation is that the parties are
required to comply with the former without delay as soon as they receive it, whereas a
Recommendation must be complied with only if no party expresses dissatisfaction within
a stated time limit.
 The DB’s determination (Recommendation or Decision) is admissible in any such further
proceedings, arbitral or judicial.

Types of Adjudication

 Adjudication could be:-

A.permanent adjudication; or

B.ad hoc adjudication;

 The permanent one is normally set up at the course of the contract & remains in place &
the members are remunerated throughout its duration.
 An ad hoc one only established after the dispute has been arisen & its existence comes to
an end after it gives is determination, Recommendation or Decision.
 The Adjudication could also be composed of:-

A.sole member; or

B.three members;

 In case of single or sole member DB, the member may be called a Dispute Review
Expert. Such member only gives Recommendation & not a Decision.
 The parties to the dispute & the member(s) of the DB shall jointly sign a common
contract document, called Three Party Agreement.
 The professional fee & the costs of the members of the DB shall be shared & paid equally
by the parties to the dispute, i.e. the employer & the contractor.

I Features

• The key distinguishing features of the DB are as follows:

25
• Formation of a review panel before the construction process begins, usually shortly after
contract award;

• Selection of board members highly qualified in the particular type of construction;

• The board’s ability to monitor construction as it progresses, including periodic site visit;

• The board’s awareness of & readiness to review a dispute at the time it arises, when
witnesses(present at the signing of contract) are present & memories are fresh, rather
than months or years latter;

• A keen awareness by all parties that a highly qualified DRB is monitoring their actions
closely & that serious claims or deliberate delays will be both unsuccessful & potentially
embarrassing;

• Information submittals to the board that are mostly documentary with only a short
“meeting” for oral presentation of claims & questions by the panel, in lieu of such
traditional but protracted processes as witness examination & cross-examination.

II Procedure

 Each DB shall have its own rules of procedure for submittal of claims & conduct of
claims presentations at the meetings.
 It is important that these ground rules expedite the process but remain flexible enough to
be responsive to changing circumstances that characterize most construction projects.
• The following is the general procedure of a DB.
 Notice of intention to submit a claim & the manner & form of submission.
 All participants at DB meetings should be identified in advance with notification sent to
all parties.
 Discussions during DB meetings should be informal & focus on the issues in dispute.
 Participants in DB meetings should be limited to individuals directly involved in the
dispute or their immediate supervisors.
 During a meeting, each party should be given a fair opportunity to explain its claim or
defense without interruption by the opposing party.
 If a construction site review is determined to be beneficial by the DB, it should be
conducted with advance notice & with all parties present.

26
 Stenographic(writing) transcription of proceedings does not occur but meeting minutes
are kept by the DB chairperson, in writing, and distributed to the parties promptly
following each meeting. The DB shall always inform itself about every development of
the project in terms of :

• Contract documentation;

• Correspondences;

• Progress project reports;

• Project site visit;

• Periodic meetings;

3.2.Arbitration

 Arbitration is a process whereby parties in dispute agree to submit the matter in dispute to
the decision of a person or persons in whom they have confidence & trust & undertake to
abide by that decision.According to Article 3325(1) of the Civil Code:-
 The arbitral submission is the contract whereby the parties to a dispute entrust its solution
to a third party, the arbitrator, who undertakes to settle the dispute in accordance with the
principles of law.
 The very nature of arbitration is that it is fundamentally consensual. Arbitration is based
on contract between the parties to the construction contract & the dispute:
 The contract to resolve a construction dispute is known as agreement to arbitrate.
 Agreement to arbitrate or the “Arbitration Clause” is independent from the substantive
contract. It is called severability or autonomy of the arbitration agreement from the rest of
the construction contract.

The construction dispute shall also be arbitrable.

 Arbitrability is a matter of public policy. For example, tax matters are not arbitrable.
Administrative contracts are “not arbitrable”. Please, see Article 315(2) of the Civil
Procedure Code of Ethiopia relative to Administrative Contracts.
 The parties to the dispute control the process but not the outcome i.e. the decision called
the award.

27
 The pre-requisite to a valid arbitration are the following:

• The existence of a dispute;

• Agreement to refer the dispute to arbitration when the dispute arises;

• Agreement to be bound by the award;

• Initiation of the arbitration;

The arbitration agreement could be:-

• an ad hoc agreement; or

• an existing agreement;

 An ad hoc agreement is an agreement where the parties in dispute agree to refer already
existing disputes to arbitration.
 An existing agreement is one where the parties to a certain contract, usually called the
substantive contract, have already agreed to refer any & all of their future disputes to
arbitration (Arbitration Clause).

Advantages of Arbitration

In relative terms, the following may be taken as advantages of arbitration.

• Neutrality; (of the arbitrators)

• Confidentiality; (no publicity of both the process & the outcome)

• Procedural flexibility; (the parties in dispute are capable of designing their own process)

• Expert arbitrators;

• Speed & cost;

• Finality of awards; (no appeal, if not always)

• Enforcement of awards; (recognition of the award by national courts)

• Limited powers of arbitrators; ( no coercive power)

• Multi-party disputes; (no joinder & no consolidation of third parties without their
express consent)

28
• Awards not binding on third parties;

• Others;

Types of Arbitration

 Arbitration could be voluntary or compulsory, binding or non-binding, international or


domestic, institutional or ad hoc, and so forth.
 The most known types of arbitration are:-

A.institutional arbitration; and

B. ad hoc arbitration;

A.Institutional arbitration is an administered type of arbitration. The process of


arbitration is backed by the management support of a given institution. It has its own
Rules of Arbitration & institution.

The following institutions are, for example, internationally recognized in administering


international arbitrations.

• International Court of Arbitration of the International Chamber of Commerce (ICC)


Paris;

• The London Court of International Arbitration (LCIA) London;

• The American Arbitration Association (AAA) New York;

• The International Center for Settlement of Investment Disputes (ICSID) Washington.


DC;

B. Ad hoc type of arbitration has no administering institution behind the arbitration process.
Both the management of the case including financial issues has been left to the arbitrators
& the parties.

In case of disagreement between the parties on:-

• the setting in motion of the arbitration process;

• the appointment of the arbitrators;

• the challenge of arbitrators; and

29
• Other issues the role of the court is also highly essential.

• Ad hoc arbitration could be managed by the following Rules:

• By devising special arbitration rules prepared by the parties to the dispute to that effect;
or

• By adoption of the UNCITRAL Arbitration Rules;

• Some international arbitration institutions provide some services in case of ad hoc


arbitration.

• The Arbitration Institute of the Stockholm Chamber of Commerce may also provide
services to the parties to an ad hoc type of arbitration against payment of costs for its
services.

• The possible services are provided under the UNICTRAL Arbitration Rules since 1 April
1999.

• The Institute has its own Rules to regulate the provision of the services.

• The services are;-

A. Services as an Appointing Authority; and

B. Administrative Services;

A.Services as an Appointing Authority :-The services are:-

• Appointment of sole or presiding arbitrator; Art. 1;

• Appointment of a “Second” arbitrator in three-arbitration cases; Art. 2;

• Decisions on challenges to arbitrators; Art. 3;

• Appointment of substitute arbitrators; Art. 4;

• Consultation on fees of arbitrators & deposit of costs; Art. 5;

B.Administrative Services :-The services are:-

• Providing, or arranging for, meeting rooms for hearings or deliberations of the arbitral
tribunal;

• Providing secretarial or clerical assistance;

30
• Forwarding of written communications of a party or the arbitrators;

• Arranging for stenographic transcriptions of hearings;

• Arranging for services of interpreters at hearing;

• Up on request, other services;

The following points are important in formulating or drafting an arbitration clause.

 The type of arbitration;

– Institutional vs. ad hoc;

– International vs. national/domestic;

– Binding vs. non-binding;

 The language of the arbitration;

• One or two, if two, ruling language

• The applicable rules of the arbitration;

• The place of arbitration or otherwise

 The number of arbitrators;

• Sole or three,

• Appointing authority, in case of disagreement & in case of ad hoc arbitration;

• The place of enforcement

• Home or neutral or otherwise, if to be agreed;

 Rules of evidence

• factual witness;

• expert witness; (party and/or tribunal appointed)

• documentary proof;

• project site visit or inspection;

 Special power of the arbitrators

31
• Assessment of special damages;

• Award on interest;

• Award on costs of arbitration;

• Granting injunctive relief; and Other issues;

 Number & Appointment of Arbitrators

• The number of arbitrators could be one or three.

• In case of one arbitrator the arbitrator being called as sole arbitrator.

• In case of three arbitrators, they are called collegiate.

• In both cases the organ, if constituted, is called the Arbitral Tribunal.

• The following may have a role in the selection, appointment or


confirmation of arbitrators.

• The parties to the dispute;

• An agreed arbitration institution;

• A designated appointing authority;

• A competent court;

 This may depend on the type of arbitration being either institutional or ad hoc and/or the
number of arbitrators being either sole or collegiate.
 In case of institutional arbitration both the parties & the arbitration institution have a
direct role to play.
 In case of ad hoc arbitration the parties, and, if they fail to agree, the appointing
authority, if any , or the parties, and, if they fail to agree, the court, if no appointing
authority has been designated, play a direct role in the appointment process.

• For example, in case of institutional arbitration under the Arbitration Rules of the
Ethiopian Arbitration & Conciliation Center, the appointment process resembles as
follows.

32
The Arbitral Proceeding

 The arbitral proceeding covers the period from the constitution of the arbitral tribunal up
to the rendition of the final award by the arbitral tribunal.
 The arbitral proceeding is at the heart of the arbitration process.
 The arbitral proceeding is the process by which the arbitral tribunal discharges its
function for which it is established.
 The form of arbitral proceeding may be dependent upon the type of arbitration being
either institutional or ad hoc, or being international or domestic.
 The arbitral proceeding is specifically designed both by the parties & the arbitral tribunal
without prejudice to the mandatory provisions of the law.

Procedure

The following is the procedure under Clause 67(Settlement of Disputes) of FIDIC for
international construction arbitration.

• Claims made but rejected;

• Construction dispute arises;

• Dispute referred to the Engineer’s decision;

• Decision of the Engineer becomes final unless referred to arbitration;

• Notice of intention to commence arbitration;

• Introduction of procedure for amicable settlement before arbitration but after notice in
respect thereof;

• Amicable settlement becomes unsuccessful;

• The Framework of Arbitration

The following six points constitute the framework of (international & institutional)
arbitration.

• These are:

• The arbitration agreement;

• The arbitration rules;


33
• The Arbitration institution;

• The arbitration law;

• The arbitration treaty;

• The court;

3.3.Litigation

 Litigation takes place at the court of law having jurisdiction over the case.
 The courts play here their dispute resolution role.
 Litigation is the most serious & adversarial(need evidence) method of dispute resolution.
 The procedure before the court is so rigid & not tailor made to the construction dispute
resolution.
 The courts are following the standard procedure established under the civil procedure
code, which applies for all types of disputes brought to them.
 The advantages of arbitration are all missing under litigation.
 The clear disadvantage of litigation is that it being the most time consuming.
 The clear advantage of litigation is that the court itself enforces its own orders &
judgments.
 The role of courts, however, very important in terms of:
 Enforcing an agreement to arbitrate;
 Recognizing & enforcing domestic arbitral award;
 Recognizing & enforcing foreign arbitral award;
 Rendering judicial assistance to the arbitration process or to the settlement
agreement;
 Hearing appeals against the arbitral award, if not final & appeal able; and
 Setting aside of an arbitral award, if, legally qualified to be set aside;

34
Self check

1. In case of disputes the proof requirement, in addition to the relevant documentation, may also
include:-

a. Factual Witnesses;

b. Expert Opinion;

c, Site Visit or Inspection; etcd.all

2. The following points are important in formulating or drafting an arbitration clause.

35
a. The type of arbitration;

b. The language of the arbitration;

c. a&b

d. none

3. The clear disadvantage of----------- is that it being the most time consuming.

a. arbitration
b. Litigation

c. Negotiation

d.all

4. ---------is legally defined as an assertion to right.

a. Claim
b. time extensions
c. cost overrun
d. all

5. The Requirements for Claimare related to:

A. Substantive requirements;

B. Procedural requirements; and

C. Proof requirements

d.all

6. Which one of the ff are the internationally recognized dispute prevention systems.

a.Intelligent Allocation of Project Risks;

36
b. Incentives to Encourage Cooperation;

c. Partnering;

d. all

7. One of the ffs are highly recognized amicable settlement methods.

a.Arbitration; and

b. Litigation;

c. Negotiation;

d. none

8. One of the ffs are recognized judgmental forms of dispute resolution.

a. Adjudication

b. Negotiation

c. Litigation;

d.a&c

9. Explain the Advantages of Arbitration?

10.State and explain the aspects/ dimensions of Dispute resolution?

11. State and explain the three phases of Claim Process?

12. State at least four causes of claim?

37

You might also like