How to Create Baseline Summary Bar
In this Lesson, I am going to show how to create Baseline Summary Bar and present
it in the Gantt chart.
At the first please go to the Gantt chart area and right-click for the “Bar” dialog box
Then please push “ADD”, a new bar line added to your Bars, so please use to below
setting
www.globalprojectcontrol.com Page 1 of 6
How to Create Baseline Summary Bar
www.globalprojectcontrol.com Page 2 of 6
How to Create Baseline Summary Bar
• Assign the time scale, for instance, “Primary baseline Bar”. Please look at the
below picture
www.globalprojectcontrol.com Page 3 of 6
How to Create Baseline Summary Bar
• Modify the new Bar style for Bar’s Shape, color, pattern, and Row. It is
important to select it properly!
www.globalprojectcontrol.com Page 4 of 6
How to Create Baseline Summary Bar
• On the Bar Setting use to checkmark “Show bar for grouping bonds”
Notice: if you use to correct setting “filter” column change from “all activities” to
“summary”
www.globalprojectcontrol.com Page 5 of 6
How to Create Baseline Summary Bar
Now you can find the Summary Baseline Bar in your Gantt Chart
Note 1
Note 2
Result: Now, if we collapse the WBS, we can present the Summary Duration
Variance (note 1) by Baseline Summary Bar. Also, we can expand the project to show
both activity and summary duration variance together (note 2).