5 Pekerjaan Pembuatan Beton Support Piperack Unit 2.00 1.48% 0.00 2.00 2.00 1.48% 100%
6 Pekerjaan Piperack Jembatan Pipa Unit 1.00 3.41% 0.00 1.00 1.00 3.41% 100%
7 Pekerjaan Pengangkatan Pipa diatas Support Pipa 0.00 0.00 0.00
Diameter 1"- 4" ( Lumpsum ) Meter 405.00 2.16% 210.00 166.00 376.00 2.01% 93%
8 Pekerjaan Penjajaran Pipa Baja 0.00
Diameter 1"- 4" ( Lumpsum ) Meter 405.00 3.33% 210.00 166.00 376.00 3.09% 93%
9 Pekerjaan Pengelasan Line Up Pipa Baja
Diameter 1" Joint 45.00 2.07% 0.00 0.00 0.00 0.00% 0%
Diameter 2" Joint 56.00 3.44% 15.00 22.00 37.00 2.27% 66%
Diameter 4" Joint 47.00 3.89% 20.00 11.00 31.00 2.56% 66%
10 Pekerjaan Pengelasan Tie In Pipa Baja 0.00
Diameter 2" Joint 3.00 0.19% 0.00 2.00 2.00 0.13% 67%
Diameter 4" Joint 2.00 0.22% 0.00 0.00 0.00 0.00% 0%
11 Pekerjaan Pengelasan Venting Pipa Baja 0.00
Dia 3/4", 1", 2" Joint 6.00 0.47% 1.00 1.00 2.00 0.16% 33%
12 Pemasangan Ball Valve 0.00
Diameter 1" Unit 5.00 0.16% 0.00 0.00 0.00 0.00% 0%
Diameter 2" Unit 4.00 0.21% 0.00 1.00 1.00 0.05% 25%
Diameter 4" Unit 3.00 0.24% 0.00 2.00 2.00 0.16% 67%
13 Pekerjaan Galian Tanah Pipa Baja 0.00
Subgrade Tanah Keras Diameter 2", 4", 6" M' 7.00 0.25% 0.00 0.00 0.00 0.00% 0%
Boring Diameter 2", 4", 6" M' 26.00 1.95% 0.00 26.00 26.00 1.95% 100%
14 Pekerjaan Proteksi Katodik 0.00
Pekerjaan Pembuatan Test Box Unit 2.00 0.24% 0.00 2.00 2.00 0.24% 100%
Pekerjaan Pemasangan Test box Unit 2.00 0.03% 0.00 1.00 1.00 0.01% 50%
Pekerjaan Pemasangan Anoda Korban Unit 1.00 0.15% 0.00 0.00 0.00 0.00% 0%
Pekerjaan Instalasi Test Box dan Anoda Dengan Las Exotermic
Titik 4.00 0.68% 0.00 0.00 0.00 0.00% 0%
Pekerjaan Pengujian Proteksi Katodik Unit 2.00 0.03% 0.00 1.00 1.00 0.02% 50%
15 Pekerjaan Pemasangan Marker Tape M' 7.00 0.01% 0.00 0.00 0.00 0.00% 0%
16 Pekerjaan Wrapping Pipa Baja 0.00
Diameter 2 , 4 " M' 33.00 1.47% 0.00 22.00 22.00 0.98% 67%
JUMLAH III 24.74%
IV Pekerjaan Pengujian
1 Pekerjaan Pengujian NDT Radiography Pipa Baja
Diameter 1" Joint 45.00 2.01% 0.00 0.00 0.00 0.00% 0%
Diameter 2" Joint 56.00 2.72% 0.00 23.00 23.00 1.12% 41%
Diameter 4" Joint 47.00 3.76% 0.00 32.00 32.00 2.56% 68%
2 Pekerjaan Pengujian NDT Dye Penetran - Pengelasan
Dia 3/4", 1", 2" Joint 6.00 0.28% 0.00 0.00 0.00 0.00% 0%
3 Pekerjaan Flushing N2 Pipa Baja
Diameter 2 " - 4 " Ls 1.00 0.37% 0.00 0.00 0.00 0.00% 0%
4 Pekerjaan Pneumatic Tes Pipa Baja
Diameter 2 " - 4 " Ls 1.00 0.74% 0.00 0.00 0.00 0.00% 0%
5 Pekerjaan Pengisian Nitrogen Pipa Baja (Gas In)
Diameter 2 " - 6 " Ls 1.00 0.34% 0.00 0.00 0.00 0.00% 0%
JUMLAH IV 3.68%
V Pekerjaan Rekondisi
1 Pekerjaan Urugan Tanah Pipa Baja
Tanah Keras Diameter 2", 4", 6 " M' 17.00 0.55% 6.00 0.00 6.00 0.20% 35%
2 Pengecatan Pipa Baja Dia. 2 "
- Pengecatan Dasar & Finish Coat (warna kuning) M' 246.00 1.47% 0.00 0.00 0.00 0.00% 0%
3 Pengecatan Pipa Baja Dia. 4''
- Pengecatan Dasar & Finish Coat (warna kuning) M' 156.00 1.50% 0.00 0.00 0.00 0.00% 0%
Jumlah V 0.20%
VI Laporan dan Dokumentasi
1 Laporan Dokumentasi Ls 1.00 0.09% 0.00 0.00 0.00 0.00% 0%
2 Pembuatan Gambar Terlaksana Ls 1.00 0.16% 0.00 0.00 0.00 0.00% 0%
JUMLAH VI 0.00%
JUMLAH TOTAL PROGRESS 80.64%