Professional Documents
Culture Documents
Module 2 - Deep Foundation - 3
Module 2 - Deep Foundation - 3
DEEP FOUNDATION
BMC II MODULE 2 S3
CAISSONS
• The term caisson is derived from Latin, which means box or case.
• Caissons are hollow inside and usually constructed at site and sunk in place into
a hard bearing stratum.
• Often the caissons have high construction cost and their construction is
restricted to major foundation works.
• Caissons are used for bridge piers, abutments in rivers and lakes, docks and
wharves, break water and other shore protections works, and large water front
structures such as pump houses subjected to very heavy vertical and horizontal
loads.
BMC II MODULE 2 S3
• Caissons denote watertight structures which are constructed in connection with
the excavation for foundations of bridges, piers, abutments in river and lake dock
structure, foreshore protection, etc.
• The caisson remains in its position and thus ultimately becomes as integral parts of
the permanent structure. It can be made up of wood, steel or reinforced concrete,
etc.
BMC II MODULE 2 S3
MATERIALS USED IN THE CONSTRUCTION OF CAISSONS
1) Cast iron
3) Steel
4) Timber
BMC II MODULE 2 S3
CAISSONS
BMC II MODULE 2 S3
BOX CAISSON
BMC II MODULE 2 S3
BOX CAISSON
• The caisson is sunk by filling sand, gravel, or concrete in the empty space inside.
• The place where the caisson base is to rest must be levelled and as such box
caissons are used in places where the strata of sufficient bearing capacity is
available near the ground.
• In normal practice, the soft natural bottom soil of the river bed is dredged out to
some depth and the trench thus formed is filled with sand to have a levelled base.
• The function of the sand layer is to uniformly distribute the superimposed loads
over the soil below and thus avoid tilting of the caisson.
BMC II MODULE 2 S3
OPEN OR WELL CAISSON
BMC II MODULE 2 S3
a) Single Wells
This is a box type structure having no top or bottom(during construction) and mainly
consists of vertical walls.
Well Components:
BMC II MODULE 2 S3
a) Single Wells
BMC II MODULE 2 S3
b) Multiple Wells or Monoliths
BMC II MODULE 2 S3
b) Multiple Wells or Monoliths
Each individual well has a separate cutting edge and dredging in each of the
well can be done separately.
The monoliths are bigger in dimension, so they cannot be built on site in water.
BMC II MODULE 2 S3
b) Multiple Wells or Monoliths
Construction Of Monoliths
BMC II MODULE 2 S3
b) Multiple Wells or Monoliths
• The gate of dry dock is opened. The monolith is then floated and located in its
correct position.
• After dredging to the required depth, the whole monolith is gradually sunk
uniformly up to the required level.
• The bottom is provided with a concrete seal, the wells are filled-with the
concrete and cap is provided at the top to finish up the construction of monolith.
• USE:
-Used for the foundation work of bridge piers,quay walls etc.
BMC II MODULE 2 S3
c) Cylinders:
An open cylinder can be conveniently used for the foundation of bridge piers.
• The cylinder is a light shell which invariably becomes the part of the permanent
structure.
• Cylinders are used as a foundation when depth of water is more than 12 m or when
it becomes essential to go deep to avoid exposure of foundations due to scouring
action of flowing water
BMC II MODULE 2 S3
c) Cylinders:
Disadvantages :-
(1)As the diameter of cylinder is small, it’s load carrying capacity is less.
(2)There are more chances of lifting of the cylinders.
(3)They require additional weight for sinking as their self weight is less.
(4)The thickness is less and hence, they are not suitable for the high bridges.
(5)When water is flowing with high velocity of flow, it is difficult to sink the
cylinders.
Advantages :-
(1)The construction is simple.
(2) The cost is low.
(3)As the diameter of cylinder is small, the obstruction the water flow is less.
(4)The quantity of excavation is less.
(5)They do not require expensive and complicated lifting devices.
BMC II MODULE 2 S3
PNEUMATIC CAISSON
BMC II MODULE 2 S3
BMC II MODULE 2 S3
PNEUMATIC CAISSON
• Each caisson has two air locks. Through one air lock workmen go down for
working while through the other excavated material is taken out.
• An air lock essentially consists of a steel chamber having two air- tight doors.
• One door of this chamber serves as an entry for men and material from outside into
the steel chamber and the other door leads to the air shaft.
• When a workman enters the airlock from outside, the pressure inside the airlock is the
same as that of outside atmosphere.
• Thereafter the outside door is closed and the pressure inside the airlock is raised slowly.
When the pressure inside the airlock becomes equal to the pressure in the caisson, the
door of the airlock which leads to the air shaft is opened and the workman goes down
the air-shaft with the help of a ladder installed therein.
• Exactly reverse procedure is followed when the workman comes out of the caisson. Air-
shaft provides means of access for the worker from airlock down to the working
chambers
BMC II MODULE 2 S3
PNEUMATIC CAISSON
Disadvantages:
• This method of providing foundation is complicated, expensive and very slow.
Advantages:
• In places where it is rather difficult to use bulky equipment required for alternative
method, pneumatic caissons appear to be the only choice.
• The chief advantage of this method is that entire operation of sinking the caisson
can be carried out under controlled conditions.
• This method provides better facilities for removing obstructions, inspection of work
and concreting of foundations bed
BMC II MODULE 2 S3
TIMBERING AND TRENCHING OF FOUNDATIONS
BMC II MODULE 2 S3
TIMBERING PROCESS
1.Sheething:
2.Waling or wale:
3.Strut:
4.Bracing:
METHODS OF TIMBERING
1.Stay bracing
2.Box sheeting
3.Vertical sheeting
4.Runners
5.Sheet piling
BMC II MODULE 2 S3
TIMBERING PROCESS
1.Stay bracing
BMC II MODULE 2 S3
TIMBERING PROCESS
2.Box sheeting
BMC II MODULE 2 S3
3.Vertical sheeting
BMC II MODULE 2 S3
4.Runners
BMC II MODULE 2 S3
5.Sheet piling
BMC II MODULE 2 S3