Professional Documents
Culture Documents
Case Digest From Year 2000 Up To Present
Case Digest From Year 2000 Up To Present
Case Digest From Year 2000 Up To Present
9184
and its IRR from Year 2000 up to Present
J.C. LOPEZ & ASSOCIATES, INC., petitioner, vs. COMMISSION ON AUDIT and
NATIONAL POWER CORPORATION, respondents.
BUENA, J :
The Facts
Petitioner entered into a contract with NAPOCOR for the dredging of the vicinity of
the Intake Tower at the Ambuklao Hydroelectric Plant in Bokod, Benguet. Pursuant to the
contract, NAPOCOR paid petitioner P10,125,150.00 representing 15% of the total contract
price and subsequently, P7,694,850.00 representing the balance of the mobilization cost.
Upon audit, however, payment of the said amounts were suspended as the contract
provided P18M mobilization fee, which is 26% of the total contract cost
. Under PD 1594, the allowed mobilization fee is only 15% of the total contract price.
The contract also provided for advance payment in violation of Sec. 88 of PD 1445.
NAPOCOR ordered the petitioner to stop its dredging operations in preparation for the joint
survey to determine the actual volume of silt dredged by the petitioner.
On February 20, 1992, NAPOCOR entered into a negotiated contract with a
consortium led by Meralco Industrial Engineering Services Corporation (MIESCOR) to
rehabilitate, operate and lease back the Ambuklao Hydroelectric Plant, including the
dredging of silt within the vicinity of the Intake Tower.
Thereafter, petitioner filed a complaint for injunction with the Regional Trial Court of
Quezon City, assailing NAPOCOR's termination of its contract, and with prayer for the
issuance of a writ of preliminary injunction.
The trial court issued a writ of preliminary injunction enjoining NAPOCOR and
MIESCOR from interfering with petitioner's dredging operations and from proceeding with
the negotiated contract between them. The trial court agreed with the opinion of the
NAPOCOR SVP and General Counsel that "the dredging of the Ambuklao water reservoir is
not an infrastructure work envisioned in Section 1 of P.D. 1818 but a service contract or
undertaking." In addition, the trial court construed that "what the petitioner apparently seeks
from the Court is not to stop the dredging of the Ambuklao water reservoir but on the
contrary, to continue its dredging of the said reservoir pursuant to the contract between
plaintiff J.C. Lopez petitioner and defendant NAPOCOR.
Alleging that the trial court committed grave abuse of discretion amounting to lack or
excess of jurisdiction in issuing the aforestated writ of preliminary injunction, MIESCOR filed
a petition for certiorari with prayer for a temporary restraining order/preliminary injunction,
with the Court of Appeals. The Court of Appeals issued a writ of preliminary injunction
prohibiting the trial court from enforcing the writ of preliminary injunction which it had earlier
issued, and enjoining NAPOCOR and MIESCOR from undertaking further activities at the
Ambuklao water reservoir until further orders from the court.
In its Decision, the Court of Appeals dismissed, as being without basis, the
petitioner's allegation that the act of clearing or dredging the reservoir of a hydroelectric plant
may be considered as a mere maintenance work or service undertaking. Citing Executive
Order No. 380 which defines the term "infrastructure projects" as "construction, improvement
or rehabilitation of roads and bridges, railways, airports, seaports, communication facilities,
irrigation, flood control and drainage, water supply and sewerage systems, shore protection,
power facilities, national buildings, school buildings, hospital buildings, and other related
construction projects that form part of the government capital investment;" the Court of
Appeals ruled that "there should not be any iota of doubt" that the enumerated undertakings
which include the dredging of the reservoir, power intake, tailrace tunnel and tailrace channel
in the Memorandum of Agreement between NAPOCOR and MIESCOR, "fall under the
protection of P.D. No. 1818 and even within the definition of 'infrastructure project' under
Executive Order No. 380."
When the matter was brought to the Commission on Audit, it ruled that the contract
involved government infrastructure project as defined by EO No. 380 and thus covered by
PD 1594 and its implementing rules and regulations. At any rate, the provision on
mobilization cost of P18M partook of advances on the contract price rather than a separate
"pay item."
Issue
Whether or not the dredging contract between the petitioner and NAPOCOR involves
an infrastructure project thus covered by PD 1594?
Ruling of the Court
Yes, in the instant case, the issue of whether the dredging contract between the
petitioner and NAPOCOR involves an "infrastructure project" as defined in Executive Order
No. 380, was already passed upon and resolved by the Court of Appeals in Meralco
Industrial Engineering Services Corporation vs. Hon. Romeo F. Zamora and J.C. Lopez.
Consequently, upon attaining finality, the said decision became the law of the case and
constituted a bar to any re-litigation of the same issue in any other proceeding under the
principle of res judicata.
We agree with the Solicitor General further that "the mobilization lump sum as
provided in the dredging contract is, and should be, considered an advance-payment item
which forms part of the contract price and not an addition thereto" and "subject to the
conditions provided under CI 4 of the Implementing Rules and Regulations for P.D. No. 1594
which reads in part, thus:
"1. The Government shall, upon a written request of the contractor which shall be
submitted as a contract document, make an advance payment to the contractor in an
amount equal to fifteen percent (15%) of the total contract price,to be made in lump sum or
the most two installments according to a schedule specified in the Instructions to Bidders
and other relevant Tender Documents.
"4. The advance payment shall be repaid by the contractor by deducting 20% from
his periodic progress payments, with the first repayment to be made when the contract value
of the work executed and material delivered shall equal or have exceeded twenty percent
(20%) of the contract price and further refunds shall be done thereafter at monthly intervals."
Having established that petitioner's dredging contract with NAPOCOR involves an
"infrastructure project," pursuant to the aforestated Court of Appeals decision, the said
contract is governed by the provisions of Presidential Decree No. 1594 and its implementing
rules and regulations. CI-4 of the implementing rules and regulations of Presidential Decree
No. 1594 clearly provides that upon the written request of the contractor, the government
shall make an advance payment in an amount equal to fifteen percent (15%) of the total
contract price, subject to recoupment from periodic progress billings submitted by the
contractor. Indeed, in compliance with Presidential Decree No. 1594 and its implementing
rules and regulations, it is provided under Article III of petitioner's contract with NAPOCOR
that fifteen percent (15%) of the total contract price shall be paid within thirty (30) calendar
days from the signing of the contract against the submission of a refund bond in the form of
an irrevocable standby letter of credit in the equivalent amount. And pursuant to the said
provision in the contract, in a letter dated January 10, 1991, and addressed to NAPOCOR,
petitioner requested for the "fifteen percent (15%) Advance Payment of our contract price."
However, the provision in the contract regarding the payment of the mobilization cost
as a "pay item" has gone beyond the requirements of the law, and should
consequently, be struck down.
While indeed, as asserted by the petitioner, contracting parties may establish such
stipulations, clauses, terms and conditions as they may deem convenient, however, such
stipulations should not be contrary to law. Realizing the need to adopt a comprehensive,
uniform, and updated set of policies, guidelines, rules and regulations covering government
contracts for infrastructure and other construction projects in order to achieve a more
efficient and effective implementation of these projects, Presidential Decree No. 1594 was
enacted to prescribe policies, guidelines, rules and regulations for government infrastructure
contracts.
In resume, as a government infrastructure contract, petitioner's contract with
NAPOCOR is subject to the provisions of Presidential Decree No. 1594 and
its implementing rules and regulations.
WHEREFORE, premises considered, the instant petition is hereby DISMISSED for
lack of merit.
SO ORDERED.
Republic of the Philippines
SUPREME COURT
Manila
FIRST DIVISION
YNARES-SANTIAGO, J :
The Facts
Feeling aggrieved, petitioner resorted to a judicial action with the Regional Trial Court
for specific performance claiming that a binding and legally enforceable contract had been
established between petitioner and SBMA. During the pendency of the case, SBMA opened
the rebidding of the project. This was sought to be enjoined by petitioner, but the trial court
denied the same. It ruled that under Section 21 of R.A. No. 7227, the implementation of
projects shall not be restrained or enjoined except by an order from the Supreme Court.
Hence, the present recourse, with petitioner seeking to obtain a prohibitory injunction against
re-bidding, arguing that there was already a perfected contract since it was the winning
bidder in the first bidding. During the pendency of the case, a re-bidding was ultimately
conducted where ICTSI was declared as the winning bidder. ||
In the petition for issuance of injunction, aside from the legality of the re-bidding,
HPPL’s standing to file the case was questioned due to the lack of license to engage in
business in the Philippines.
Issues
(a) That the petitioner/applicant must have a clear and unmistakable right;
(c) That there is an urgent and permanent necessity for the writ to prevent serious
damage.
To our mind, petitioner HPPL has not sufficiently shown that it has a clear and
unmistakable right to be declared the winning bidder with finality, such that the SBMA can
be compelled to negotiate a Concession Contract. Though the SBMA Board of Directors,
by resolution, may have declared HPPL as the winning bidder, said award cannot be said
to be final and unassailable. The SBMA Board of Directors and other officers are subject to
the control and supervision of the Office of the President. All projects undertaken by SBMA
require the approval of the President of the Philippines under Letter of Instruction No. 620,
which places the SBMA under its ambit as an instrumentality, defined in Section 10 thereof
as an "agency of the national government, not integrated within the department framework,
vested with special functions or jurisdiction by law, endowed with some if not all corporate
powers, administering special funds, and enjoying operational autonomy, usually through
a charter. This term includes regulatory agencies, chartered institutions and government
owned and controlled corporations."
As a chartered institution, the SBMA is always under the direct control of the
Office of the President, particularly when contracts and/or projects undertaken by the
SBMA entail substantial amounts of money. Specifically, Letter of Instruction No. 620
dated October 27, 1997 mandates that the approval of the President is required in all
contracts of the national government offices, agencies and instrumentalities, including
government-owned or controlled corporations involving two million pesos
(P2,000,000.00) and above, awarded through public bidding or negotiation. The
President may, within his authority, overturn or reverse any award made by the SBMA
Board of Directors for justifiable reasons. It is well-established that the discretion to
accept or reject any bid, or even recall the award thereof, is of such wide latitude that the
courts will not generally interfere with the exercise thereof by the executive department,
unless it is apparent that such exercise of discretion is used to shield unfairness or
injustice. When the President issued the memorandum setting aside the award
previously declared by the SBMA in favor of HPPL and directing that a rebidding be
conducted, the same was within the authority of the President and was a valid exercise
of his prerogative. Consequently, petitioner HPPL acquired no clear and unmistakable
right as the award announced by the SBMA prior to the President's revocation thereof
was not final and binding.
There being no clear and unmistakable right on the part of petitioner HPPL, the
rebidding of the proposed project can no longer be enjoined as there is no material and
substantial invasion to speak of. Thus, there is no longer any urgent or permanent
necessity for the writ to prevent any perceived serious damage. In fine, since the
requisites for the issuance of the writ of injunction are not present in the instant case,
petitioner's application must be denied for lack of merit.
(2) No, petitioner HPPL has no legal capacity to even seek redress from this
Court.
SUPREME COURT
Manila
FIRST DIVISION
PERALTA, C.J:
The Facts
An Invitation to Apply for Eligibility and to Bid (IAEB) was published twice in Romblon
Sun, a local newspaper, on September 25 to October 1, 2007, and on October 2 to 8, 2007.
Another IAEB was posted on Looc's Municipal Bulletin Board from October 15, 2007, to
November 20, 2007.
The opening of bids was conducted on November 12, 2007, and R.G. Florentino
Construction and Trading (R.G. Florentino) was the lone bidder with the bid amount of Eight
Million Nine Hundred Ninety-Nine Thousand Five Hundred Pesos (P8,999,500.00). The BAC
accepted and recommended R.G. Florentino's bid after determining that it was compliant
with the eligibility, technical and financial requirements.
On November 20, 2007, a Notice of Award was published in favor of R.G. Florentino,
followed by the issuance of the SWIP contract on November 29, 2007, and a Notice to
Proceed on December 4, 2007.
On September 2, 2008, a Certificate of Acceptance and Turn Over was issued by the
Municipality of Looc in favor of R.G. Florentino, indicating therein that the SWIP was
completed in accordance with the guidelines and specifications under the contract
agreement.
On May 4, 2009, Regional Office No. IV of the Commission on Audit (COA)
forwarded an Annual Audit 12 Report on the Municipality of Looc for the Year Ended
December 31, 2008 to Fiel. The COA observed that pertinent provisions of RA 9184 and its
Implementing Rules and Regulations-A (IRR-A) were violated when the BAC awarded the
SWIP to R.G. Florentino, to the detriment of Looc.
On August 26, 2009, Manuel Arboleda (Respondent) filed a Complaint before the
Office of the Ombudsman against Fiel and the BAC members for the following irregularities:
e. The BAC was not able to rate the bid as "failed" due to the
incompleteness and insufficiency of the bid security, contrary to
Section 30.1 of RA 9184 IRR-A.
The Ombudsman found untoward bias towards R.G. Florentino when: (1) the BAC
allowed Romeo Florentino of R.G. Florentino to pay for the publication of the IAEB in
Romblon Sun; (2) the BAC declared R.G. Florentino's bid as "eligible" even if the bid security
was not present at the opening of bids; and (3) the SWIP was not posted on the Philippine
Government Electronic Procurement System (PhilGEPS) website.
On April 28, 2015, herein petitioners, Jomadiao and Pastor filed a Motion for
Reconsideration, by themselves, and submitted therein that they never underwent any
training and were never informed of the procedures, duties, and responsibilities of the BAC.
Their participation, as BAC members, only included attending the public bidding on
November 12, 2007, and they alleged that they were no longer privy to any transaction that
occurred thereafter. They also averred that the publication of the IAEB in the Romblon Sun
was made without their knowledge nor consensus and that the non-posting of the SWIP
project on the PhilGEPS website was not their direct duty. The Order dated May 15, 2015, of
the Office of the Ombudsman however upheld the November 14, 2014 Decision.
The CA noted that the BAC must duly ensure faithful compliance to the provisions of
R.A. 9184 and its IRR-A during the bidding process. Allowing R.G. Florentino to pay for the
IAEB was, therefore, a blatant disregard of R.A. 9184, particularly Section 21 thereof.
Issue
Yes, the basic rule in public bidding that bids should be evaluated on the basis
of the required documents submitted before and not after the opening of bids must be
strictly observed in order to safeguard a fair, honest and competitive public bidding. A
bid security is one of the documents that Section 25.3 and its IRR-A mandates to be
included at the opening of bids.
The Ombudsman determined that R.G. Florentino did not submit a bid security at the
time of bidding on November 12, 2007, because the Acknowledgment on the Bidder's Bond
was dated 2008 and the Official Receipt of Eastern Assurance & Surety Company (EASC),
the bonding company, was issued on March 8, 2008. Hence, the Ombudsman held that the
BAC violated RA 9184 for declaring R.G. Florentino as eligible even in the absence of a Bid
Security at the time of bidding.
On the other hand, attached on record is a Bidder's Bond dated November 11, 2007,
and valid until February 11, 2008, on which R.G. Florentino was named as the principal and
EASC as the surety. It also provides that "THIS BOND IS CALLABLE ON DEMAND UNDER
R.A. 9184" for the amount of Two Hundred Twenty-Five Thousand Pesos (P225,000.00), the
condition of which states:
NOW THEREFORE, the conditions of this obligation are such that if the
above-bounded principal shall, in the event of his becoming successful
bidder in the above proposal (1) fails to guarantee the true and faithful
performance in case of the award; (2) shall refuse to accept the same or
(3) shall not answer for any delay and/or default in the execution of the
contract as provided in the proposal; then the MUNICIPALITY OF LOOC
shall be entitled to be indemnified of any loss or damage it may suffer by
reason thereof not to exceed the sum of TWO HUNDRED TWENTY-FIVE
THOUSAND PESOS (P225,000.00) PESOS (sic), Philippine Currency,
otherwise this obligation shall be void and without effect.
A reading of the Bidder's Bond would show that it satisfied the required form of a Bid
Security as provided for in Sections 27.2 29 27.3 30 and 28 31 and its IRR-A which must be:
(a) Two and a half percent (2 1/2%) of the approved budget for the contract to be bid; (b)
callable upon demand issued by a reputable surety or insurance company; (c) in Philippine
Peso; and (d) not valid for more than 120 days from the opening of the bid.
Furthermore, the Bidder's Bond was notarized on November 11, 2007 which
contradicts the complaint and the finding of the Ombudsman.
Hence, the BAC did not err in accepting the bid offer of R.G. Florentino because the
bid security shows that it had been issued regularly and for purposes only of securing R.G.
Florentino's performance on the SWIP. The Court cannot contradict the BAC's finding on
record that a Bid Security was included in the technical proposal during the opening of bids
and, thus, upholds its presumption of regularity.
Section 21 of RA 9184 mandates that the procuring entity, in this case the Municipality
of Looc, shall cause the advertisement of the invitation to bid, thus:
It is undisputed that the IAEB was published in the Romblon Sun, a newspaper of
general local circulation. The charge against petitioners, on the other hand, was centered on
the seemingly partial action of the BAC in allowing R.G. Florentino to pay for the publication
of the IAEB.
At the onset, the duty of publication falls upon the BAC Secretariat, and his or her
certification as to the fact of posting refutes allegations to the contrary.
The petitioners, as provisional BAC members, are not responsible for the actual
posting of the IAEB and the corresponding payment, if any, of the same. Be that as it may,
the Court is of the view that allowing a prospective bidder to pay for any advertisement or
publication will not give him or her a leverage in public bidding. Such act is actually against
any bidder's interest because it publicizes the existence of a bidding and persuades
competition.
On the issue of non-posting of the IAEB on the PhilGEPS website, respondent did
not show that the Municipality of Looc had an electronic registry with the PhilGEPS nor that it
had access to the internet. Posting on the PhilGEPS website requires not only prior
coordination with the G-EPS but also a stable network of the procuring entity. Since the
viability of posting on the PhilGEPS website had not been duly proven during trial, the Court
could not postulate on the assumption that the lack of posting on PhilGEPS was deliberate.
Nonetheless, the BAC still fell short in the publication requirement when it failed to
advertise the IAEB in a newspaper of general nationwide circulation, or a newspaper that is
published nationally. The minutes of the September 24, 2007 meeting uncovers that the
BAC acceded to forego publication in a newspaper of general nationwide circulation
because the breakdown per project was below P5,000,000.00. This reveals that the BAC
was still ascribing to the posting requirements of P.D. 1594, or otherwise known as
Prescribing Policies, Guidelines, Rules and Regulations for Government Infrastructure
Contracts, the IRR of which provides:
This has already been superseded by Section 21.2.3 and its IRR-A which states that:
21.2.3. For contracts to be bid with an ABC costing two million pesos
(P2,000,000.00) and below for the procurement of goods, and five million pesos
(P5,000,000.00) and below for the procurement of infrastructure projects, the
Invitation to Apply for Eligibility and to Bid shall be posted at least in the website of
the procuring entity concerned, if available, the website of the procuring entity's
service provider, if any, as provided in Section 8 of this IRR-A the G-EPS, and
posted at any conspicuous place reserved for this purpose in the premises of the
procuring entity concerned, as certified by the head of the BAC Secretariat of the
procuring entity concerned, during the same period as above.
Yet, the BAC gave an incorrect interpretation of the law because the easing of the
posting requirement refers to contracts that are below P5,000,000.00. The SWIP contract
was for the entire amount of P9,000,000.00 and it was without regard to the value of the
infrastructure project per barangay.
The Court has been consistent in holding that the functions of BAC members are not
merely ceremonial. Theirs is the obligation to ensure the proper conduct of public bidding,
because it is the policy and medium adhered to in Government procurement and
construction contracts under existing laws and regulations. It is the accepted method for
arriving at a fair and reasonable price and ensures that overpricing, favoritism and other
anomalous practices are eliminated or minimized.
Petitioners are charged for the less grave offense of simple neglect of duty, which is the
failure to give attention to a task, or the disregard of a duty due to carelessness or
indifference. They are hereby penalized for six (6) months suspension, considering that this
is their first offense after several years in public service.
WHEREFORE, the petition is PARTLY GRANTED. The Decision dated July 21, 2016
and the Resolution dated March 1, 2017 of the Court of Appeals in CA-G.R. SP No. 142029
are hereby SET ASIDE. A new one is ENTERED finding petitioners Jessie L. Jomadiao and
Wilma F. Pastor GUILTY of SIMPLE NEGLECT OF DUTY and the penalty of six (6) months
suspension is hereby imposed unto them.
SO ORDERED.
Republic of the Philippines
SUPREME COURT
Manila
EN BANC
PERALTA, J.:
The Facts
On July 10, 2009, the Comelec and Smartmatic-TIM entered into a Contract for the
Provision of an Automated Election System for the May 10, 2010 Synchronized National and
Local Elections,(AES Contract). The contract between the Comelec and Smartmatic-TIM
was one of “lease of the AES with option to purchase (OTP) the goods listed in the contract.”
In said contract, the Comelec was given until December 31, 2010 within which to exercise
the option. In September 2010, the Comelec partially exercised its OTP 920 units of PCOS
machines with corresponding canvassing/consolidation system (CCS) for the special
elections in certain areas in the provinces of Basilan, Lanao del Sur and Bulacan. In a letter
dated December 18, 2010, Smartmatic-TIM, through its Chairman Flores, proposed a
temporary extension of the option period on the remaining PCOS machines until March 31,
2011, waiving the storage costs and covering the maintenance costs. The Comelec did not
exercise the option within the extended period. Several extensions were given for the
Comelec to exercise the OTP until its final extension on March 31, 2012.
Petitioners assail the constitutionality of the Comelec Resolutions on the grounds that
the option period provided for in the AES contract had already lapsed; that the extension of
the option period and the exercise of the option without competitive public bidding
contravene the provisions of RA 9184; and that the Comelec purchased the machines in
contravention of the standards laid down in RA 9369.
On the other hand, respondents argue on the validity of the subject transaction based
on the grounds that there is no prohibition either in the contract or provision of law for it to
extend the option period; that the OTP is not an independent contract in itself, but is a
provision contained in the valid and existing AES contract that had already satisfied the
public bidding requirements of RA 9184; and that exercising the option was the most
advantageous option of the Comelec.
Claiming that the foregoing issuances of the Comelec, as well as the transactions
entered pursuant thereto, are illegal and unconstitutional, petitioners come before the Court
in four separate Petitions for Certiorari, Prohibition, and Mandamus imputing grave abuse of
discretion amounting to lack or excess of jurisdiction on the part of the Comelec in issuing
the assailed Resolutions and in executing the assailed Extension Agreement and Deed.
Issue
Whether or not there was grave abuse of discretion amounting to lack or excess of
jurisdiction on the part of the Comelec in issuing the assailed Resolutions and in executing
the assailed Extension Agreement and Deed?
No, A reading of the other provisions of the AES contract would show that the parties
are given the right to amend the contract which may include the period within which to
exercise the option. There is, likewise, no prohibition on the extension of the period, provided
that the contract is still effective.
In this case, the extension of the option period means that the Comelec had more
time to determine the propriety of exercising the option. With the extension, the Comelec
could acquire the subject PCOS machines under the same terms and conditions as earlier
agreed upon. The end result is that the Comelec acquired the subject PCOS machines with
its meager budget and was able to utilize the rentals paid for the 2010 elections as part of
the purchase price.
It must be pointed out that public biddings are held for the best protection of the
public and to give the public the best possible advantages by means of open competition
between the bidders, and to change them without complying with the bidding requirement
would be against public policy. What are prohibited are modifications or amendments which
give the winning bidder an edge or advantage over the other bidders who took part in the
bidding, or which make the signed contract unfavorable to the government. In this case, as
thoroughly discussed in our June 13, 2012 Decision, the extension of the option period and
the eventual purchase of the subject goods resulted in more benefits and advantages to the
government and to the public in general.
The "advantage to the government," time and budget constraints, the application of
the rules on valid amendment of government contracts, and the successful conduct of the
May 2010 elections are among the factors looked into in arriving at the conclusion that the
assailed Resolutions issued by the Comelec and the agreement and deed entered into
between the Comelec and Smartmatic-TIM, are valid.
WHEREFORE, premises considered, the petitions are DENIED for lack of merit.
SO ORDERED.
Republic of the Philippines
SUPREME COURT
Manila
SECOND DIVISION
Undaunted, Martel and Guiñares appealed before the CA under Rule 43 of the
Rules of Court.
Court of Appeals Ruling
In its assailed decision, dated February 4, 2015, the CA found that the PBAC
members committed a violation when they resorted to a negotiated purchase even without
a prior public bidding. Under Republic Act (R.A.) No. 9184 and R.A. No. 7160, negotiated
procurement can only be resorted to when there are two (2) failed biddings. The CA ruled
that there was no failure of bidding because no public bidding was ever conducted. It also
observed that the PBAC violated (1) Section 18 of R.A. No. 9184 prohibiting the reference
of brand names for the purpose of procurement; and (2) COA Circular No. 75-6 precluding
government officials or employees from using more than one motor vehicle.
The CA disposed the appeal in this wise:
WHEREFORE, foregoing premises considered, the 25 February 2011 Decision of
the Office of the Ombudsman is AFFIRMED with MODIFICATION. The penalty of
dismissal meted upon petitioners RICHARD T. MARTEL and ABEL A. GUIÑARES is
hereby lowered to ONE YEAR SUSPENSION WITHOUT PAY.
SO ORDERED.
The Ombudsman moved for reconsideration, but its motion was denied by the CA.
Hence, this petition.
Issue
Whether or not the procurement of five (5) vehicles violated R.A. 9184?
Yes, the procurement of the vehicles violated R.A No. 9184 and R.A No. 7160
and CO A Circular No. 92-386.
Section 10 of R.A. No. 9184 provides that “all procurement shall be done through
Competitive Bidding, except as provided for in Article XVI of this Act." Likewise, Section 27
of COA Circular 92-386 provides that “except as otherwise provided herein, acquisition of
supplies or property by local government units shall be through competitive public bidding."
Hence, there is a clear mandate by R.A. No. 9184 and COA Circular 92-386 that public
bidding is the primary process to procure goods and services for the government.
A competitive public bidding aims to protect public interest by giving it the best
possible advantages thru open competition. It is precisely the mechanism that enables the
government agency to avoid or preclude anomalies in the execution of public contracts.
Strict observance of the rules, regulations, and guidelines of the bidding process is the
only safeguard to a fair, honest and competitive public bidding.
Only in exceptional circumstances that R.A. No. 9184 and R.A No 7610 allow the
procuring entity to forego the strict requirement of a public bidding. Section 53 of R.A. No.
9184 provides that negotiated procurement may be availed by the procuring entity only in
specific occasions, such as when there are two (2) failed biddings. Similarly, Section 369
of R.A. No. 7160 provides that negotiated purchase may be availed in case where public
bidding has failed for two (2) consecutive times. Section 35 of R.A. No. 9184 provides,
among others, that there is a failure to bid if no bids are received.
In this case, no public bidding was conducted in the procurement of the service
vehicles for the Governor and Vice-Governor. The absence of public bidding was a glaring
violation of R.A. No. 9184 and R.A. No. 7160 and COA Circular No. 92-386, unless the
respondents could prove that the resort to a negotiated bidding, as approved by the PBAC,
was proper.
The respondents, however, reasoned out that it was upon the recommendation of
the PGSO that they resorted to the direct purchase of the vehicles and the PBAC merely
approved the recommendation of the PGSO.
The argument utterly lacks merit. Accordingly, as members of the PBAC, the
respondents were not bound by the recommendation of the PGSO to determine the mode
of procurement. As an independent committee, the PBAC was solely responsible for the
conduct of the procurement and could not pass the buck to others. As correctly stated by
the CA, the PBAC had control over the approval of the mode of procurement and the
respondents could not wash their hands from liability thereof. Their role in choosing the
mode of procurement was clearly an active action, and not a passive one as the
respondents would want to convey.
In this case, respondents Martel and Guiñares, as members of the PBAC, being
the Provincial Treasurer and the Provincial Auditor, respectively, committed the following
transgressions:
(1) They failed to conduct a public or competitive bidding as a mode of procurement;
(2) Without any basis in law, they allowed the resort to negotiated procurement in
violation of Sections 35, 48, 50 and 53 of R.A. No. 9184; Sections 356, 366 and
369 of R.A. No. 7160; and COA Circular No. 92-386;
(3) In the direct purchase of the vehicles, they specified the brand name of the units
they wanted to procure, instead of technical descriptions only, which violated
Section 18 of R.A. No. 9184;
(4) They approved the purchase of more than one service vehicle for the use of the
governor, in violation of COA Circular No. 75-6;
(5) They signed and issued the disbursement vouchers for the vehicles despite their
illegal procurement.
Notwithstanding these glaring violations of the procurement laws and the illegal
approval of the vehicles' procurement by the PBAC, Martel and Guiñares actively
participated in the acquisition of the same by signing the disbursement vouchers as
Provincial Accountant and Provincial Treasurer, respectively. Hence, due to the acts of the
respondents, the government disbursed public funds for illegally procured service vehicles.
WHEREFORE, the petition is GRANTED. The February 4, 2015 Decision and the
October 16, 2015 Resolution of the Court of Appeals in CA-G.R. SP No. 05473-MIN are
REVERSED and SET ASIDE. The February 28, 2013 Order of the Ombudsman in OMB-
M-A-05-450-L, is hereby REINSTATED.
SO ORDERED.
SUPREME COURT
Manila
THIRD DIVISION
REYES, J.:
The Facts
The petitioners and Danilo C. Castro and George F. Inventor (respondents) are all
officials and employees of the Davao City Water District (DCWD). Engr. Yamson, Engr.
Chavez, Navales and Atty. Guillen occupied concurrent membership in its Pre-Bidding and
Awards Committee-B (PBAC-B). Almonte, meanwhile, was the Division Manager of
DCWD's Engineering and Construction Department, while Laid was the Assistant General
Manager for Administration.
In Board Resolution No. 97-2488 adopted on November 21, 1997, the DCWD
Board of Directors approved the recommendation of DCWD General Manager
Carbonquillo to undertake the Cabantian Water Supply System Project stage by stage,
with a budgetary cost of Thirty-Three Million Two Hundred Thousand Pesos
(P33,200,000.00). Initial activities for the project were the simultaneous drilling of two wells
separately located in Cabantian (identified as VES 15 Project) and Communal (identified
as VES 21 Project) in Davao City, both estimated at Four Million Pesos (P4,000,000.00)
each. Included in Carbonquillo's recommendation was the direct negotiation of the well
drilling phase of the project to Hydrock Wells, Inc. (Hydrock).
Thereafter, in Resolution No. 05-9711, the PBAC-B resolved to dispense with the
advertisement requirement in the conduct of the bidding and instead, opted to send letters
to accredited well drillers and invited their participation in the VES 15 and VES 21 well
drilling projects. Invited were Hydrock, AMG Drilling and Construction, Inc. (AMG) and Drill
Mechanics Incorporated (DMI).
Thereafter, in Resolution No. 06-9714 dated December 16, 1997, the PBAC-B
resolved, "due to the urgency, importance and necessity of the well drilling project," to
endorse the matter to the head of agency for approval, with a "recommendation that the
project be pursued by a negotiated agreement contract with HYDROCK taking into
account its track record, efficiency of performance, and quoted price."
For the VES 21 Project, the administrative case against the petitioners was
docketed as OMB-M-A-05-093-C, while the administrative case for the VES 15 Project
was docketed as OMB-M-A-05-104-C.
The Ombudsman did not accept the petitioners' explanation as regards the PBAC-
B's resort to a "simplified bidding", finding that the circumstances of the project do not call
for the application of the exception to the general rule on competitive public bidding, viz.:
(3) there was no adjacent or continuous project being undertaken by Hydrock; and
Thus, the Ombudsman found the petitioners guilty of Grave Misconduct, ruling that:
(2) the project was implemented by Hydrock ahead of the contract award, with the
knowledge and approval of Carbonquillo, and with the cooperation of the petitioners;
(3) the petitioners' justification that Carbonquillo was responsible for the
mobilization of Hydrock prior to contract award is self-serving considering that the
petitioners hold managerial positions and should not follow orders blindly; and
(4) the change order was allowed even before proper documentation was
accomplished, among others.
The CA rejected the petitioners' argument that the filing of the separate complaints
filed against them in the Ombudsman constituted forum shopping. According to the CA,
the rule on forum shopping applies exclusively to judicial cases/proceedings and not to
administrative cases, and as such, the filing of the identical complaints with the
Ombudsman does not violate the rule.
The CA also found no reversible error in the Ombudsman's ruling that the
petitioners are liable for grave misconduct, finding that they violated the mandatory
provisions of P.D. No. 1594, particularly the absence of a public bidding on the award of
the VES 15 and VES 21 Projects to Hydrock. The CA ruled that the attendant
circumstances do not justify dispensing with, the public bidding and entering into a
negotiated contract with Hydrock as trie conditions set in P.D. No. 1594 were not met.
xxxx xxxx xxxx xxxx
Thus, the petitioners are now before this Court, arguing that the CA Decision dated
December 6, 2010 was not in accord with law or with the applicable decisions of the Court.
Issue
Whether or not petitioners are liable for administrative sanction by violating the
provisions of P.D. No. 1594, particularly the absence of a public bidding on the award of
the VES 15 and VES 21 Projects to Hydrock?
Yes, petitioners are liable for simple neglect of duty and simple misconduct.
P.D. No. 1594, and even the subsequent laws on procurement, set the order of
priority in the procurement of government construction projects. First, by competitive public
bidding and second, by negotiated procurement (or by administration or force account, as
the case may be).62 Its Implementing Rules and Regulation (IRR),63 meanwhile, provide
for the specific instances when a negotiated contract may be entered into, viz.:
(1) in times of emergencies arising from natural calamities where immediate action
is necessary to prevent imminent loss of life and/or property;
(2) when there is a failure to award the contract after competitive bidding for valid
cause or causes, in which case bidding is undertaken through sealed canvass
of at least three (3) contractors; and
But as correctly concluded by both the Ombudsman and the CA, such "public
outcry for water" does not qualify as an emergency arising from natural calamities,
as required by both P.D. No. 1594 and E.O. No. 164. Natural calamities, as opposed to
man-made calamities, usually refer to catastrophic events that result from the natural
processes of the earth and which give rise to loss of lives or property or both. These
include floods, earthquakes, storms and other similar natural events. Water shortage,
clearly, does not belong to the list of natural calamities. In fact, the "public outcry for water"
relied upon by the petitioners was brought about by insufficient water supply connections
in the affected areas.
Records also show that as early as May 1997, residents of the affected area have
already been demanding for the improvement in their water supply system; yet, it was only
in November 1997 that DCWD started to act on the matter and apparently, only after the
clamour has been publicized in the local newspapers. This contradicts the petitioners'
claim of urgency given the lapse of time that it took the DCWD to address the situation.
The petitioners, clearly, had no justifiable reason to dispense with the public bidding of the
VES 21 Project.
(2) Petitioners Wilfred G. Yamson, Rey C. Chavez and Arnold D. Navales are
found GUILTY of Simple Neglect of Duty, aggravated by Simple Misconduct and are
imposed the penalty of six (6) months suspension;
(3) Petitioner William V. Guillen is found GUILTY of Simple Neglect of Duty and is
imposed the penalty of three (3) months suspension;
(4) Petitioners Rosindo J. Almonte and Alfonso E. Laid are found GUILTY of
Simple Misconduct and are imposed the penalty of three (3) months suspension;
(5) Petitioners Rey C. Chavez, Arnold D. Navales, Rosindo J. Almonte and Alfonso
E. Laid are hereby ordered REINSTATED to their former or equivalent positions without
loss of seniority rights, but without backwages/back salaries; and cralawlawlibrary
(6) Let a copy of this Decision be reflected in the permanent employment records of
petitioners Wilfred G Yamson and William V. Guillen.
SO ORDERED.
EN BANC
GESMUNDO, J:
The Facts
In 2009, SBMA procured special and field uniforms for its employees through regular
public bidding, and the winning bidder with the lowest price was Topnotch Apparel
Corporation (Topnotch Apparel). However, SBMA claimed that the quality and craftsmanship
of the uniforms of the employees were compromised due to the current procurement laws.
Thus, in a memorandum dated December 10, 2009, Lolita S. Mallari, then Human
Resource Management Officer of the SBMA, provided several recommendations to the
SBMA Administrator and CEO regarding the acquisition of special and field uniforms for the
SBMA employees under the supervision of a Uniform Committee.
Notice of Disallowance
On March 26, 2012, the Special Audit Team of the SBMA issued Special Audit ND No.
2012-001-(2011) against several SBMA officers, department heads and suppliers regarding
the procurement of special and field uniforms of the SBMA employees. The Special Audit
Team stated that the total disallowed amount was P2,420,603.99 because several
requirements of R.A. No. 9184 and its Implementing Rules and Regulations (IRR) were
violated, to wit:
The COA-Region III issued a decision denying the appeal made by the petitioner. It
held that petitioners neither considered public bidding as the mode for procurement nor
secured the recommendation of the Bids and Awards Committee (BAC) in resorting to the
alternative method of negotiated procurement. The COA-Region III highlighted that the
procurement of the uniforms did not comply with the requirements set forth by R.A. No. 9184
and its IRR. The fallo of the decision states:
In its decision dated December 29, 2015, the COA dismissed the petition because it
was filed out of time. It observed that petitioners only had six (6) months or 180 days to file the
petition before the COA. As the petition was filed beyond the 180-day period, the COA denied
it outright. The dispositive portion of the COA decision reads:
Petitioners filed a motion for reconsideration, but it was dismissed by the COA in its
resolution dated December 21, 2016.
Petitioners argue that the 180-day period to file the petition for review before the
COA fell on May 31, 2014, a Saturday, hence, it timely filed the petition on the next working
day or June 2, 2014; that COA did not even consider the weekends in its computation of time;
that on the substantial aspect, their petition has merit; and that they properly complied with the
alternative method of procurement because it was approved by the head of the procuring
authority and the procurement of the uniforms was justified by the conditions provided by R.A.
No. 9184 to promote economy and efficiency.
Issue
Whether or not the petitioner exercised good faith and transparency in procuring the
uniforms of their employees; and that they still acquired the most advantageous price for the
government based on R.A No. 9184?
Alternative methods of procurement, however, are allowed under R.A. No. 9184,
which would enable dispensing with the requirement of open, public and competitive bidding,
but only in highly exceptional cases and under the conditions set forth in Article XVI thereof.
In this case, petitioners admit that they did not conduct public bidding to procure the
uniforms of their employees. However, they argue that they properly used the alternative
modes of procurement to obtain the uniforms with the most advantageous price for the
government through negotiation with accredited SBMA suppliers subject to the control
measures provided for by the uniform committee. They further assert that they negotiated with
the accredited SBMA suppliers to obtain the uniforms with the most advantageous price for
the government.
The Court finds that petitioners exercised good faith. As to the first requisite,
petitioners acted in good faith when they disbursed public funds to procure the uniforms of
their employees. They merely wanted to address their problem regarding their previous
procurement of uniforms because the lowest bidder considerably compromised the quality of
the said uniforms. Also, SBMA has as many as twenty-six (26) different uniforms, thus, they
resorted to a Uniform Committee to devise a procurement method specifically for the varied
uniforms of their employees.
Notably, petitioners resorted to their chosen procurement method for the benefit of its
employees — to ensure that they will receive the uniform with superior quality based on the
budget provided by the government — and not for some selfish or ulterior motive. Evidently,
while there may be irregular expenditure because petitioners did not strictly comply with the
IRR of R.A. No. 9184, they may not be held personally liable under the ND based on their
exercise of good faith.
While the disbursement of funds for the procurement of the employees' uniforms
must be disallowed because it particularly contravenes the provisions of IRR of R.A. No.
9184, the good faith exercised by petitioners exempts them from liability under the ND. The
COA committed grave abuse of discretion when it did not properly appreciate the
circumstance of good faith on petitioners' part.
In conclusion, it is unfair to penalize public officials based on overly stretched and
strained interpretations of rules which were not that readily capable of being understood at the
time such functionaries acted in good faith. If there is any ambiguity, which is actually clarified
years later, then it should only be applied prospectively. A contrary rule would be
counterproductive. It could result in paralysis, or lack of innovative ideas getting tried. In
addition, it could dissuade others from joining the government. When government service
becomes unattractive, it could only have adverse consequences for society.
SO ORDERED.
PUBLIC ESTATES AUTHORITY and MANUEL R. BERINA, JR., in his capacity as the
Acting General Manager of the Public Estates Authority, Petitioners v. BOLINAO
SECURITY AND INVESTIGATION SERVICE, INC., Respondent.
CARPIO MORALES, J.
The Facts
The report, noting that Integrated Security submitted the highest bid in terms of
liquidated damages but had no SSS clearance, and Bolinao Security submitted the next
highest bid but had no current license to operate, recommended that Masada Security
which proffered the third highest bid be considered the winning bidder.
Bolinao Security filed with the Regional Trial Court of Makati a complaint for
annulment of bid award, damages, injunction with special prayer for the issuance of a
temporary restraining order against PEA, and Masada Security, averring that, among other
things, the attempt of Masada Security to take over the Cavite City premises from it based
on the result of the bidding was improper, illegal, criminal and violative of the provisions of
the Anti-Graft and Corrupt Practices Act.
The trial court issued a writ of preliminary injunction enjoining the defendants from
terminating the contract with Bolinao Security covering PEA's Cavite City property
"WHEREFORE, premises considered, judgment is rendered in favor of the plaintiff
with the following dispositions:
1) The writ of preliminary injunction issued in this case, which enjoins defendants
from terminating the existing contract for security services with plaintiff, and from
implementing the questioned contract in favor of Masada Security Agency effective
September 17, 1991, and from ejecting plaintiff from the Villa Porta Vaga Subdivision,
Canacao, Cavite City, is made permanent.
2) The award of the bid in favor of defendant Masada Security Agency is declared
null and void and plaintiff Bolinao is declared as the winning bidder during the public bidding
held on April 10, 1991.
3) Directing the defendants to jointly and severally pay to the plaintiff the amount of
P50,000.00 as nominal damages, P50,000.00 as exemplary damages; attorney's fees; and
the costs of suit.
The Court of Appeals affirmed the decision of the trial court. In affirming the trial
court's decision, the appellate court held that disqualifying Bolinao Security for the simple
reason that on the day of the bidding its application for renewal of its license was still being
processed was "most unfair, arbitrary and has no legal basis" as the period for processing
thereof "is a bureaucratic requirement which should not work against the interest of Bolinao
Security, absent any badge of fraud or negligence.
Issues
(1) Whether or not Bolinao Security is a qualified bidder, despite its non-compliance
with the bidding requirements?
(2) Whether or not the stipulation "right to reject any or all bids" in the Invitation to
Bid valid?
Ruling of the Court
As priorly stated, the contract for security services between Bolinao Security
and PEA took effect on February 1, 1990 until January 31, 1991. As its license to
operate was to expire on March 31, 1991, Bolinao Security filed an application for a
new license which was granted and issued only on May 16, 1991, after the April 10,
1991 bidding. Evidently, at the time of the bidding, Bolinao Security had no "current
license to operate" as required by the TOR.
The basic rule in public bidding that bids should be evaluated on the basis of
the required documents submitted before and not after the opening of bids must be
strictly observed in order to safeguard a fair, honest and competitive public bidding.
At all events, as PEA argues, assuming arguendo that Bolinao Security was
deemed to have complied with the current license requirement, since the Invitation to
Bid expressly provided that "PEA reserves the right to reject any proposal or waive
any defects or formality, impose additional terms and conditions and accept the
proposal most advantageous to the Government," Bolinao Security voluntarily
submitted itself to the terms and conditions thereof and acknowledged the said right
of the government.
In fine, the PEA did not commit grave abuse of discretion in selecting the bid
of Masada Security as the most advantageous to the government.
WHEREFORE, the decision of the Court of Appeals dated May 30, 2002 is
REVERSED and SET ASIDE and the complaint of respondent, Bolinao Security and
Investigation Service, Inc. is DISMISSED.
SO ORDERED.
SUPREME COURT
Manila
FIRST DIVISION
VILLARAMA, JR., J:
Before the Court are the consolidated petitions for review filed by Ruby P. Lagoc
(Lagoc) and Limuel P. Sales (Sales) which seek to reverse and set aside the Decision dated
January 24, 2008 of the Court of Appeals (CA) — Cebu City in CA-G.R. SP No. 00837
affirming the Decision dated September 18, 2002 of respondent Deputy Ombudsman for the
Visayas in OMB-VIS-ADM-2001-0408, and Resolution dated September 8, 2008 denying
their motion for reconsideration.
The Facts
On July 20, 2001, private respondent Maria Elena Malaga filed a Complaint-Affidavit
before the Office of the Ombudsman-Visayas (OMB-Visayas) against Wilfredo Agustino
(Regional Director), Vicente M. Tingson, Jr. (OIC District Engineer), Reynold Soldevilla (Bids
and Awards Committee [BAC] Chairman), Assistant District Engineer Sales (BAC Chairman
for materials and equipment), Rodney Gustilo (BAC Member),Elizabeth H. Gardose (BAC
Member),Project Engineer Ruby P. Lagoc (BAC Member), Fema G. Guadalupe (Supply
Officer) and Blanca O. Pagal (Accountant III).
On his part, Sales together with Gardose, contended that the decision to implement
the skywalk projects by administration was made after evaluation of the provision of the law
(R.A. No. 8760) where the funds therefor were provided, and also to generate savings with
the elimination of "contractor's profit" in the preparation of the program of work. He likewise
averred that the invitation to bid was duly published in The Visayan Tribune and The Visayas
Examiner on March 5-11, March 12-18, 2001 and February 19 and 26, 2001, respectively,
attaching photocopies of these publications to his counter-affidavit. The fact of publication
was supported by Publisher's Affidavit, contrary to Malaga's insinuations. He further claimed
that when the bids were opened, IBC's tendered offer was below the AAE; IBC passed the
post-evaluation/qualification made by the BAC; and it is not unusual that the bid of the
winning bidder may jibe with the AAE because the cost reflected therein is based on the
rental rates prescribed by the Association of Carriers and Equipment Lessor (ACEL) in
relation compliance with Department Order No. 58, Series of 1999 issued by the DPWH
Secretary. He stressed that Malaga filed her complaint in retaliation against Tingson who
filed a criminal complaint for falsification of public documents against her.
During the preliminary conference held on May 9, 2002, the parties through their
respective counsel, agreed to submit the case for decision on the basis of the evidence on
record and position papers/memoranda.
In a Decision dated September 18, 2002, the public respondent Deputy Ombudsman
for Visayas Primo C. Miro found substantial evidence of Misconduct against Tingson, Sales,
Gardose and Lagoc, and accordingly recommended that the penalty of one year suspension
without pay be imposed on them. On the other hand, the complaint against Agustino,
Soldevilla and Gustilo were recommended to be dismissed for lack of sufficient evidence.
Then Ombudsman Simeon V. Marcelo approved the recommendation but modified the
offense and penalty to Grave Misconduct and dismissal from the service for Tingson, Sales,
Gardose and Lagoc.
Petitioners along with Gardose appealed to the CA which affirmed the Ombudsman's
findings of fact and conclusions. The CA held that the Ombudsman correctly concluded that
petitioners committed grave misconduct when they conducted the bid process of and
awarded the subject contracts without compliance with the mandatory twin-publication
requirement. It likewise disagreed with petitioners' claim that the Ombudsman failed to
consider their evidence as they could have presented whatever evidence they had during
the preliminary conference or attach it to their memorandum.
Issue to be Resolved
Whether the Ombudsman correctly concluded that petitioners conspired to rig the
bidding in favor of IBC, the winning bidder?
Yes, we affirm the CA in ruling that Ombudsman's finding that there was no
compliance with the requirement of publication of the Invitation to Bid is well
supported by substantial evidence.
By its very nature and characteristic, a competitive public bidding aims to protect the
public interest by giving the public the best possible advantages thru open competition.
Another self-evident purpose of public bidding is to avoid or preclude suspicion of favoritism
and anomalies in the execution of public contracts.
Presidential Decree (PD) No. 1594 established a set of rules and regulations to
ensure competitive public bidding for construction projects. The Implementing Rules and
Regulations (IRR) of said law mandates the publication of the invitation to pre-qualify/bid.
In this case, the Ombudsman found discrepancies in the evidence presented by the
complainant (Malaga) and petitioners to prove compliance with the publication requirement.
That petitioners submitted mere photocopies of the issues of The Visayan Tribune and The
Visayas Examiner added credence to the Ombudsman's conclusion that petitioners were
covering up for their omission as the invitation to bid for the materials and equipment was
actually never published.
Sales suggests there could have been errors in the printing of the pages in the
newspapers by the publisher which were beyond the control of petitioners and should not be
blamed on petitioners. He contends that the fact that the publishers of The Visayan Tribune
and The Visayas Examiner executed an affidavit of publication clearly established that the
invitations to bid were indeed published. And assuming arguendo that petitioners presented
mere photocopies of the said newspaper issues, he asserts that it is no proof that they had
knowledge and participation in the manipulation of the publication of the Invitation to Bid.
Sales maintains that as BAC Chairman, his authority is limited to recommending the
Program of Work prepared by Lagoc and it was his ministerial duty to approve the award to
the winning bidder (IBC) after the Technical Committee had submitted their
recommendation.
Similarly, Lagoc assails the CA in sustaining the Ombudsman's finding that she
conspired in rigging the bidding in favor of IBC, as she quoted portions of the comment filed
by private respondent (Malaga) herself before this Court asserting that she (Lagoc) was not
even present during the opening of the bids and that she was not in fact in good terms with
the District Engineer but being the Project Engineer she had to sign the Abstract of Bids as it
was "SOP" in their office. To Lagoc, said admission by complainant practically absolved her
(Lagoc) from any participation in the publication of the Invitation to Bid.
We find in this case clear and convincing evidence that petitioners colluded in the
rigging of the bidding process to favor IBC, the winning bidder. Petitioners signed the
Abstract of Bids and approved the award to IBC of the contract for the materials and
equipment needed for the skywalk projects despite the absence of an Invitation to Bid duly
published in accordance with the IRR of PD 1594. They cannot simply feign ignorance of
such non-compliance with a basic requirement because as Chairman (Sales) and Member
(Lagoc) of the BAC, they are responsible for the conduct of pre-qualification, or eligibility
screening, bidding, evaluation of bids, post qualification, and recommending award of
contract. As such, it is their duty to ensure that the rules and regulations for the conduct of
bidding for government projects are faithfully observed. They may thus be held liable for
collective acts and omissions as when they affixed their signatures in official documents as
BAC Chairman/Members, and recommended approval of the bids, in effect certifying to
compliance with the aforesaid rules.
Petitioner Lagoc claimed that even the complainant acknowledged that she simply
signed the Abstract of Bids in her capacity as Project Engineer and provisional member of
the BAC. Such excuse is flimsy and unacceptable. Indeed, the affixing of signatures by the
committee members are not mere ceremonial acts but proofs of authenticity and marks of
regularity. Moreover, there is nothing in the IRR that exempts a provisional BAC member
from liability in case of violation of its provisions.
We stress that the Ombudsman's finding of collusion to rig the bidding was based not
only on the non-publication of the Invitation to Bid but also the highly suspicious
circumstance that the bid submitted by IBC contained the unit prices of items/rental rates
exactly similar to those listed in the Program of Work. This unexplained fact, along with the
deliberate disregard of the requisite publication of the Invitation to Bid, convinced the
Ombudsman that the BAC Chairman and Members acted in conspiracy in committing a
misconduct.
Section 52 (A) (3), Rule IV of the Revised Uniform Rules on Administrative Cases in
the Civil Service provides that the penalty for grave misconduct is dismissal from the service,
which was correctly imposed by the Ombudsman on petitioners, along with OIC District
Engineer Tingson, Jr. and the other BAC Member Elizabeth H. Gardose.
WHEREFORE, the consolidated petitions are DENIED for lack of merit. The Decision
dated January 24, 2008 and Resolution dated September 8, 2008 of the Court of Appeals —
Cebu City in CA-G.R. SP No. 00837 AFFIRMING the Decision of the Office of the
Ombudsman in OMB-VIS-ADM-2001-0408 finding the petitioners GUILTY of Grave
Misconduct and imposing upon them the severe penalty of DISMISSAL from office are
UPHELD.
SO ORDERED.
SECOND DIVISION
The Facts
On March 1, 1990, the DECS Secretary received a letter from the Parents Teachers
Association of the Panabo High School regarding the investigation of Principal Oani and
Bonifacio Roa, the Resident Auditor regarding, among other things, the alleged overpricing
of 12 fire extinguishers for P15,000.00 each. The Regional Office of the COA then issued
Assignment Order No. 90-137 dated March 2, 1990 to a team of auditors, composed of
Jaime P. Naranjo, as Chairman, and Bienvenido Presilda and Carmencita Enriquez, as
members.
The team discovered that, Oani had approved a Requisition and Issue Voucher for
the acquisition of 15 units of fire extinguishers for the use of the high school as mandated by
Presidential Decree No. 1185, also known as the Fire Code of the Philippines. The amount
of P55,000.00 was certified as available for the purpose. Instead of conducting a public
bidding, Oani decided to purchase the fire extinguishers from the Powerline Manufacturing
Industry for P54,747.00.
The Auditing Team conducted a review of the prices of the stereo set and school and
office supplies, and discovered that they could be purchased for only P144,621.51 instead of
the P227,857.45 paid by the school. The Auditing Team recommended the filing of
administrative and criminal complaints for violations of Rep. Act No. 3019 against Oani and
Roa.
On March 30, 1993, Informations were filed against Oani and Roa in the
Sandiganbayan for violation of Section 3(e) of Rep. Act No. 3019.
Sandiganbayan’s Ruling
After trial, the Sandiganbayan promulgated a decision acquitting Roa, but convicting
Oani of the crimes charged. The fallo of the decision reads:
WHEREFORE, judgment is hereby rendered CONVICTING accused LEOPOLDO E.
OANI of the crime[s] charged in both Criminal Cases Nos. 18885 and 18886, his guilt having
been proven beyond reasonable doubt. Accordingly, in Criminal Case No. 18885, Leopoldo
E. Oani is hereby sentenced to suffer an indeterminate penalty of SIX (6) YEARS and ONE
(1) MONTH as minimum, to EIGHT (8) YEARS as maximum, and to suffer perpetual
disqualification from public office. He is ordered to restitute to the treasurer of the Panabo
National High School the amount of TWENTY-THREE THOUSAND FORTY PESOS
(P23,040.00).
Oani, now the petitioner, filed the instant Petition for Review on Certiorari with this
Court.
The petitioner avers that the trial court erred in finding him guilty of violating Section
3(e) of Rep. Act No. 3019 for the purchase of the fire extinguishers without any public
bidding. He maintains that since Powerline was the exclusive manufacturer of the fire
extinguishers and had not designated any dealer or subdealer of its products as evidenced
by the Certification of Cunanan, he was justified in dispensing with a public bidding and to
purchase the fire extinguishers on a negotiated basis with Powerline.
Issue
COA Circular No. 78-84 dated August 1, 1978, provides that negotiated contracts
may be entered into where any of the following conditions exist:
1. Whenever the supplies are urgently needed to meet an emergency which may
involve the loss of, or danger to life and/or property;
5. In cases where it is apparent that the requisition of the needed supplies through
negotiated purchase is most advantageous to the government as determined by the head of
agency;
None of the foregoing conditions existed when the petitioner purchased the
fire extinguishers on a negotiated basis from Powerline.
The petitioner did not require Cunanan to submit any certification from the
Department of Trade and Industry that he was the exclusive distributor or manufacturer of
fire extinguishers. Neither did he require Cunanan to certify or execute an affidavit that no
subdealer had been designated to sell the said product at a lower price. The petitioner failed
to ascertain whether a suitable substitute could be obtained elsewhere, under terms more
advantageous to the government. It turned out that as declared by the trial court, another
business enterprise, Systems Products Industries, was selling the same brand and
specifications at only P2,900.00 per unit.
Finally, accused Oani failed to present proof that "no suitable substitute can be
obtained elsewhere at more advantageous terms to the government," as thus, required
by COA Circular 78-84, series of 1978. In consciously allowing the suppliers to violate the
requirements of bidding and canvass, accused Oani brazenly undermined the objective of
the process, namely, "To protect the public interest by giving the public the best possible
advantage thru open competition." Hence, not only did he act in a "wantonly careless
manner" but also in an unspeakable "breach of duty in a flagrant and palpable" way. In full
contemplation of the law, his acts constitute gross inexcusable negligence.
As occasioned by the lack of bidding and canvass, unqualified and non-bona fide
entities that only served as brokers, gained entry and participation to the transaction. Not
only did this burden the government with additional costs, as a result, but also exposed it to
unnecessary risks and disadvantages
By its very nature and characteristic, a competitive public bidding aims to protect the
public interest by giving the public the best possible advantages thru open competition.
Another self-evident purpose of public bidding is to avoid or preclude suspicion of favoritism
and anomalies in the execution of public contracts. Public bidding of government contracts
and for disposition of government assets have the same purpose and objectives. Their only
difference, if at all, is that in the public bidding for public contracts the award is generally
given to the lowest bidder while in the disposition of government assets the award is to the
highest bidder.
In the present case, the petitioner purchased the fire extinguishers and office and
school supplies without the benefit of a public bidding, in gross and evident bad faith,
resulting in the considerable overpricing of the fire extinguishers and the supplies, to the
gross prejudice of the government.
In sum then, the decision of the trial court is in accord with the law and the evidence.
IN LIGHT OF ALL THE FOREGOING, the petition is DENIED. Cost against the
petitioner.
SO ORDERED.
SUPREME COURT
Manila
FIRST DIVISION
G.R. No. 213500, March 15, 2017
OFFICE OF THE OMBUDSMAN AND THE FACT-FINDING INVESTIGATION BUREAU
(FFIB), OFFICE OF THE DEPUTY OMBUDSMAN FOR THE MILITARY AND OTHER
LAW ENFORCEMENT OFFICES (MOLEO), Petitioners, v. PS/SUPT. RAINIER A.
ESPINA, Respondent.
PER CURIAM:
The Facts
Petitioner the Fact-Finding Investigation Bureau (FFIB) of the Office of the Deputy
Ombudsman for the Military and Other Law Enforcement Offices (MOLEO) filed before the
Ombudsman an affidavit-complaint and a supplemental complaint, respectively, charging
Espina and several other PNP officers and private individuals for:
(a) violation of Republic Act No. (RA) 7080, RA 3019, RA 9184 and its
Implementing Rules and Regulations (IRR), and Malversation of Public Funds through
Falsification of Public Documents under Article 217 in relation to Article 171 of the Revised
Penal Code (RPC); and
(b) Grave Misconduct and Serious Dishonesty; arising from alleged anomalies that
attended the Philippine National Police's (PNP) procurement of 40 tires, and repair,
refurbishment, repowering, and maintenance services of a total of 28 units of V-150 Light
Armored Vehicles (LAVs), and the related transportation and delivery expenses of 18 units
of LAYs between August and December 2007.
It averred that the PNP did not comply with the bidding procedure prescribed
under RA 9184 and its IRR, in that:
(a) copies of the bid documents were not furnished to possible bidders;
(b) no pre-procurement and pre-bid conferences were held;
(c) the invitation to bid was not published in a newspaper of general circulation;
(d) the procuring agency did not require the submission of eligibility requirements
as well as the technical and financial documents from the bidders; and
(e) no post qualification was conducted.
Further, it claimed that there were "ghost deliveries," i.e., the tires were never
delivered to the PNP and no repair and refurbishment works were actually performed on
the LAVs.
Espina was impleaded in the complaints for noting/signing the Inspection Report
Forms (IRFs), which confirmed the PNP's receipt of the tires and other supplies, and the
performance of repair and refurbishment works on the LAYs. According to the FFIB-
MOLEO, by affixing his signature on the IRFs, Espina supposedly facilitated the fraudulent
disbursement of funds amounting to P409,740,000.00 when no goods were actually
delivered and no services were actually rendered.
In defense, Espina denied any participation in the bidding and/or procurement
process and maintained that he belonged to the Management Division which is
responsible for the inspection of deliveries made to the PNP after the bidding and
procurement process. He also pointed out that pursuant to the Standing Operating
Procedure, his only duty, was to note the reports. According to him, it was not his
responsibility to personally inspect and confirm deliveries and go beyond the contents of
the IRFs submitted by his subordinates, absent any irregularity reported by the property
inspectors who are tasked to check and examine deliveries.
Ombudsman’s Ruling
In a Joint Resolution dated December 19, 2012, the Ombudsman found probable
cause to indict Espina and several other PNP officers for violation of Section 3 (e) of RA
3019, Section 65 (b) (4) of RA 9184, and for Malversation of Public Funds through
Falsification under Article 217 in relation to Article 171 of the RPC. The Ombudsman also
found them guilty of Grave Misconduct and Serious Dishonesty and, accordingly,
recommended their dismissal from government service.
Aggrieved, Espina filed a petition for review before the CA, impleading both the
Ombudsman and the FFIB-MOLEO.
Court of Appeals Ruling
The CA found Espina guilty, instead, of Simple Misconduct, a less grave offense
punishable with suspension for one (1) month and one (1) day to six (6) months for the first
offense, and dismissal for the second offense. It rejected Espina's defense of reliance in
good faith on the acts of his subordinates, holding that he had the obligation to supervise
them and ensure that the IRFs and Work Orders they prepared, as well as every
procurement-related document released by his division, were regular, lawful, valid, and
accurate, considering the significance of the transaction related to the disbursement of
public funds over which great responsibility attached.
xxxx xxxx xxxx xxxx
Dissatisfied, petitioners moved for reconsideration which was, however, denied by
the CA in a Resolution dated July 15, 2014; hence, the present petition.
Issue
Whether or not Espina should be held administratively liable for the charges
imputed against him?
Yes, Espina should be liable for Gross Neglect of Duty by failing to exercise
due diligence in government transactions dealing with procurement.
Here, the CA correctly observed that while Espina may have failed to personally
confirm the delivery of the procured items, the same does not constitute dishonesty of any
form inasmuch as he did not personally prepare the IRFs but merely affixed his signature
thereon after his subordinates supplied the details therein.
Neither can Espina's acts be considered misconduct, grave or simple. The records
are bereft of any proof that Espina was motivated by a premeditated, obstinate or
deliberate intent of violating the law, or disregarding any established rule, or that he
wrongfully used his position to procure some benefit for himself or for another person,
contrary to duty and the rights of others. However, after a circumspect review of the
records, the Court finds Espina administratively liable, instead, for Gross Neglect of Duty,
warranting his dismissal from government service. Notably, the FFIB-MOLEO's
supplemental complaint accused Espina with failure to exercise due diligence in signing
the IRFs, which is sufficient to hold him liable for Gross Neglect of Duty.
As aptly observed by the CA, Espina had the obligation to supervise his
subordinates and see to it that they have performed their respective functions in
accordance with law. To recall, Espina was the Acting Chief and Head of the PNP's
Management Division and, as such, had supervisory powers over the departments or
sections which comprise it, namely:
(a) the Internal Control and Inspection Section (ICIS);
(b) the Accountability and Assistance Section;
(c) the Management Improvement Section; and
(d) the Claims and Examination Section (CES).
Espina himself admitted that the property inspectors who were tasked to
personally inspect deliveries to the PNP belong to the ICIS which was under his
management and stewardship. The Court pointed out that the nature of the public officers'
responsibilities and their role in the procurement process are compelling factors that
should have led them to examine with greater detail the documents which they are made
to approve.
Here, while SOP No. XX4, which Espina cited does not expressly require the Head
of the Management Division to physically re-inspect, re-check, and verify the deliveries to
the PNP as reported by the property inspectors under him, his duty was not simply to
"note" or take cognizance of the existence of the IRFs, but to reasonably ensure that they
were prepared in accordance with law, keeping in mind the basic requirement that the
goods allegedly delivered to and services allegedly performed for the government have
actually been delivered and performed. As aptly pointed out by the Ombudsman in its Joint
Order, "it was incumbent upon Espinal to affix his signature only after checking the
completeness and propriety of the documents."
More so, considering the sheer magnitude of the amount in taxpayers' money
involved, i.e., P409,740,000.00, Espina should have exercised utmost care before signing
the IRFs. It is of no moment that the disbursement of the P409,740,000.00 was spread
over several transactions and not through a single payment or that only the IRFs relating to
the delivery of supplies were allegedly presented; the fact remains that taxpayers' money
was spent without the corresponding goods and services having been delivered to the
government.
Given the amounts involved and the timing of the alleged deliveries, the
circumstances reasonably impose on Espina a higher degree of care and vigilance in the
discharge of his duties. Thus, he should have been prompted to make further inquiry as to
the truth of his subordinates' reports. Had he made the proper inquiries, he would have
discovered the non-delivery of the procured items and the non-performance of the
procured services, and prevented the unlawful disbursement. However, he did not do this
at all. Instead, he blindly relied on the report and recommendation of his subordinates and
affixed his signature on the IRFs. Plainly, Espina acted negligently, unmindful of the high
position he occupied and the responsibilities it carried, and without regard to his
accountability for the hundreds of millions in taxpayers' money involved.
WHEREFORE, the petition is PARTLY GRANTED. The Decision dated February
27, 2014 and the Resolution dated July 15, 2014 of the Court of Appeals in CA-G.R. SP
No. 131114 are hereby SET ASIDE. A new one is ENTERED finding respondent Rainier
A. Espina GUILTY of GROSS NEGLECT OF DUTY. Accordingly, he is DISMISSED from
government service with all the accessory penalties.
SO ORDERED.
Topic: Delegation of Authority
FIRST DIVISION
PARDO, J :
The Facts
In 1993, the Secretary of Health appointed Dr. Baylon as the Program Manager of
the Government's National Voluntary Blood Donation Program. The National Kidney and
Transplant Institute (NKTI) was the lead agency of the blood program. On February 3, 1994,
the DOH called a meeting of all the managers of the department's several programs. During
the meeting, a comprehensive work plan for a new project "STOP D.E.A.T.H.: Hospitals for
Philippines 2000" was discussed. The blood program was one of the six (6) new programs
included in the project. A week later, the DOH allotted two million pesos (P2,000,000.00) to
the NKTI as start-up money for the blood program.
On February 18, 1994, the DOH issued Department Order Nos. 73-f and 73-g, series
of 1994. Department Order No. 73-f launched the project. The sum of fifty-one million pesos
(P51,000,000.00) was allocated for the blood program. Department Order No. 73-g created
an Executive Committee and a National Secretariat for the Project.
||| On February 24, 1994, Secretary of Health Juan M. Flavier revealed to the public
the results of the USAID study, to wit:
(a) the blood transfusion service of the country failed to adequately meet the public
demand for safe blood; and
(b) the blood sourced from commercial blood banks had a contamination rate of 4%.
On March 3, 1994, in view of the afore-quoted findings, Secretary Flavier issued a
closure order on the provincial retail outlets of commercial blood banks. The events led to an
acute shortage of blood available to the public as the commercial blood banks intentionally
refused to sell blood in retaliation to the closure order. Thus, Secretary Flavier instructed the
immediate implementation of the voluntary blood donation system as the only alternative
source of blood.
The NKTI expedited the installation of the blood program. On March 8 and 17, 1994,
requisition vouchers for the initial purchase of containers for blood were issued.13 NKTI
decided to purchase Terumo blood bags for immediate distribution to the regional hospitals
and medical centers. NKTI obtained a quotation of the prices of blood bags (Terumo brand)
from FVA-Exim Trading. FVA is the exclusive distributor of Terumo blood bags and the only
supplier which could supply all sizes of the blood bags.
In March 1995, the Commission on Audit (COA) disallowed in post audit the sale
transactions entered into by the NKTI with FVA on the ground that the blood bags were
purchased without public bidding, contrary to the applicable laws or rules, thereby allegedly
resulting to overpricing. The COA found that FVA sold "Terumo" blood bags to the Philippine
National Red Cross (PNRC) and to blood banks Our Lady of Fatima and Mother Seaton at
prices lower than those at which it sold to the NKTI, leading to a consequent total loss to the
government in the amount of P1,964,304.70.
A complaint-affidavit for violation of Section 3 (e) and (g) of R.A. 3019 was filed with
the Ombudsman against Dr. Baylon and other DOH officials. The Special Prosecutor found
probable cause to indict the petitioner and her co-accused. Thus, the Ombudsman filed with
Sandiganbayan 33 an information for violation of Section 3(e), R.A. No. 3019 34 against Dr.
Baylon and her co-accused.
Issue
Whether or not the Ombusman acted with grave abuse of discretion in finding
probable cause against Dr. Baylon and her co-accused for violation of Section 3(e), R.A. No.
3019?
Yes, the Ombudsman acted with grave abuse of discretion amounting to lack
or excess of jurisdiction in finding probable cause against Dr. Baylon and co-accused
for violation of Section 3(e), R.A. No. 3019, as amended, and in ordering their
prosecution before the Sandiganbayan.
In order to be held guilty of violating Section 3(e), R.A. No. 3019, the act of the
accused that caused undue injury must have been done with evident bad faith or with gross
inexcusable negligence. Bad faith per se is not enough for one to be held liable under the
law, the "bad faith" must be "evident.
We note the absence of some essential elements of the offense charged, to wit:
(2) Even assuming there was injury to the Government, there was no bad faith or
inexcusable negligence on the part of petitioner.
Here, there is no evident bad faith on the part of petitioner and her co-accused
neither is there gross negligence.
We cannot discount the fact that a sense of urgency drove petitioner to purchase the
Terumo blood bags. The project could not be delayed without causing detriment to the public
service. There was a shortage in the blood supply available to the public. To determine
whether there was bad faith, these essential facts should not have been ignored. When the
Ombudsman did not take these facts into consideration in the determination of probable
cause, he gravely abused his discretion.
The petitioner was merely doing her job and only acted in response to an emergency
brought about by the shortage in the blood supply available to the public. The shortage in
the blood supply available to the public was a matter recognized and addressed by
Secretary of Health Juan M. Flavier. Secretary Flavier attests that he "directed the NKTI to
do something about the situation and immediately fast-track the implementation of the
Voluntary Blood Donation Program of the government in order to prevent further deaths
owing to the lack of blood." In fact, more than finding fault in petitioner's quick action, she
and her co-accused, should be commended for acting "promptly" and "diligently" in response
to a crisis.
The facts of the case also readily show that the circumstances surrounding the
purchase of Terumo blood bags exempted it from the requirement of a public bidding
as per Executive Order No. 301, Section 1 paragraph (b), (c) and (e).
Sec. 1. Guidelines for Negotiated Contracts. Any provision of law, decree, executive
order or other issuances to the contrary notwithstanding, no contract for public services or
for furnishing supplies, materials and equipment to the government or any of its branches,
agencies or instrumentalities shall be renewed or entered into without public bidding, except
under any of the following situations:
xxx xxx xxx|
b. Whenever the supplies are to be used in connection with a project or activity
which cannot be delayed without causing detriment to the public service;
c. Whenever the materials are sold by an exclusive distributor or manufacturer
who does not have subdealers selling at lower prices and for which no suitable
substitute can be obtained elsewhere at more advantageous terms to the
government;
xxx xxx xxx|
e. In cases where it is apparent that the requisition of the needed supplies
through negotiated purchase is most advantageous to the government to be
determined by the Department Head concerned;
SUPREME COURT
Manila
FIRST DIVISION
The Facts
This case against petitioner arose when Lilia Cadores who was the Acting
Property Officer of the Land Transportation Commission – National Capital Region
(LTC-NCR) from 1984 to 1988 was called by Director Andres Sajul to his office
sometime in April 1985. She was shown certain documents such as the Request to
Issue Voucher (RIV), Purchase Order (PO), Certification, etc. She was told to sign the
RIV and the PO for the purchase of the 23 units of fire extinguishers from Bato-Bato
Enterprises. She refused to sign the request forms on the ground that the previous
deliveries of Bato-Bato Enterprises were defective and the price exorbitant.
She proposed/suggested to Director Sajul to subject the transaction to a public
bidding or open canvass so they will be able to purchase the same at a lower price.
Director Sajul, however, got mad and even slammed shut his attaché case in front of
her, uttering bad words such as “bullshit” and similar words. Cadores got out of the room
and proceeded to the comfort room and cried.
She reported the incident to Ms. Edna Garvida, the chief of Administrative
Division. The matter was referred for consultation to the Regional Accountant, Resident
Auditor, Asst. Regional Director and the Chief of Administrative Division and all the
members thereof agreed that the transaction be subjected to public bidding and open
canvass.
Issue
Whether or not the transaction or contract entered into was manifestly or grossly
disadvantageous to the government?
No, given the circumstances of the case, we do not see how the contract
entered into by the petitioners would cause obvious or glaring injury to the government
when petitioner merely continued the purchase from a regular supplier which he had
authority to do so.
The Supreme court ruled that the Petitioner is ACQUITTED of violating Section 3
(g) of R.A 3019. Manifest," meaning evident to the senses, open, obvious, notorious,
unmistakable etc. while "gross" is defined as glaring, reprehensible, culpable, flagrant,
shocking etc.
It must be noted that Bato-Bato Enterprises had long been supplying the Central
Office since 1982 after winning in a competitive bidding. Its price in 1982 and that in
1985 remained the same. No evidence was adduced to show that there were other fire
extinguishers which cost less than that of Bato-Bato Enterprises in 1982. In order to
show that there was an overpricing in the subject transaction, a canvass of different
suppliers with their corresponding prices should have been procured which could readily
show the differences in the price quotations.
Absent this competent evidence, it is rather unfair to conclude that the price of
Bato-Bato Enterprises was exorbitant on the basis alone of a submitted quotation of one
company and to further rule that the contract was grossly injurious to the government.
Following from this disquisition, we do not see how the disadvantage allegedly
caused by the subject transaction to the government was gross and manifest as to
warrant petitioner's conviction under this section given the facts and circumstances of
the case. To justify a conviction, a man's guilt must be established to a moral certainty,
that is, precluding all reasonable doubt as to his guilt. Regrettably, the respondent
court's decision failed in this respect.
SO ORDERED.
SUPREME COURT
Manila
THIRD DIVISION
LEONEN, J :
|||
The Facts
Sometime in 2001, the Philippine Postal Corporation entered into a contract with
Aboitiz Air Transport Corporation (Aboitiz Air) for the carriage of mail at a rate of P5.00
per kilogram. This contract would expire on December 31, 2002.
Sometime in October 2003, or after the expiry of its contract with Aboitiz Air, the
Philippine Postal Corporation purchased 40 vehicles for mail deliveries in Luzon. It also
hired 25 drivers for these vehicles on a contractual basis. All of these drivers' contracts
would expire on March 31, 2004, except that of a certain Oliver A. Cruz.
The Central Mail Exchange Center of the Philippine Postal Corporation conducted
a post study of the delivery system and found that the expenses for the salaries and
maintenance of its vehicles for Luzon deliveries were higher than its previous system of
outsourcing deliveries to Aboitiz Air. On April 15, 2004, it submitted a recommendation
that the Philippine Postal Corporation would save P6,110,152.44 per annum if deliveries
were outsourced instead at the cost of P8.00 per kilogram.
On April 29, 2004, the Board of Directors of the Philippine Postal Corporation held
a Special Board Meeting where De Guzman, the Officer-in-Charge, endorsed for
approval the Central Mail Exchange Center's recommendation to outsource mail delivery
in Luzon.
On May 7, 2004, De Guzman sent a letter to Aboitiz Air, now Aboitiz One, Inc.
(Aboitiz One), through its Chief Operating Officer, Efren E. Uy.
Aboitiz One accepted the proposal and commenced its delivery operations in
Luzon on May 20, 2004. When Postmaster General Diomedo P. Villanueva (Postmaster
General Villanueva) resumed work, the Aboitiz One contract had already been fully
implemented. Thus, the Postmaster General approved payments made to Aboitiz One
for services rendered.
On October 20, 2005, Atty. Sim Oresca Mata, Jr. filed an administrative complaint
with the Office of the Ombudsman against De Guzman. He alleged that the Aboitiz One
contract renewal was done without public bidding and that the rate per kilogram was
unilaterally increased without the Philippine Postal Corporation Board of Directors'
approval.
In his Counter-Affidavit, De Guzman alleged that the Office of the Ombudsman no
longer had jurisdiction over the case since it was filed one (1) year and five (5) months
after the commission of the act complained of, or after he sent his May 7, 2004 letter to
Aboitiz. He also alleged that the contract renewal was approved by the Board of
Directors in the April 29, 2004 Special Meeting. He maintained that the expiration of the
employment contracts of the drivers caused a delay in the delivery of mail, which justified
the approval of the outsourcing of deliveries.
On August 31, 2007, the Office of the Ombudsman rendered its Decision finding
De Guzman guilty of grave misconduct and dishonesty.
Petitioner argues that respondent committed grave misconduct since he was not
authorized to enter into a contract with Aboitiz One or to allow the rate increase per
kilogram of mail considering that in the April 29, 2004, Special Board Meeting,
respondent was merely instructed to provide more information on Aboitiz One and to
submit a copy of the proposed contract. It insists that the approval of the contract was
contingent upon respondent's compliance with the conditions set by the Board of
Directors and that the Board of Directors was not fully apprised of the details during the
meeting. Petitioner likewise submits that negotiated procurement was not applicable. It
alleges that Aboitiz One took over only two (2) months after the expiration of the mail
delivery drivers' employment contracts, showing no urgency in the situation. It also avers
that the Board of Directors could only exercise negotiated procurement when there are
substantiated claims of losses.
Respondent counters that he obtained the Board of Directors' approval of his
request for authority to enter into the outsourcing contract with Aboitiz One after a full
disclosure to the Board of Directors of the cost-benefit analysis submitted by the Central
Mail Exchange Center. Respondent likewise contends that he had no legal duty to
conduct a public bidding since he was not the procuring entity. The Board of Directors,
as the procuring entity, did not direct or suggest the conduct of a public bidding. He
insists that negotiated procurement was necessary, arguing that the non-renewal of the
mail delivery drivers' employment contracts would cause delay or stoppage of mail
delivery to various parts of the country.
Respondent explains that the Philippine Postal Corporation had been incurring
costs of P21.00 per kilogram and that if services were outsourced at P8.00 per kilogram,
it could save P13.00 per kilogram or a total of P6,110,152.44 per annum. He alleges that
this price would have been the most advantageous for the government since no other
company offered a rate lower than P8.00 per kilogram for its Luzon mail deliveries.
Respondent further asserts that a public bidding was conducted in 2005, and Airfreight
2100, Inc., the winning bidder, refused the award and did not sign the contract. He states
that due to the cancellation of Aboitiz One's contract on January 31, 2006, the Philippine
Postal Corporation has incurred costs of more than P25.00 per kilogram in Luzon mail
deliveries. Respondent contends that if he was the only official of the Philippine Postal
Corporation found liable of grave misconduct and dishonesty, it would violate his right to
due process since he merely endorsed for approval a recommendation by the Central
Mail Exchange Center.
Issue
Whether or not respondent acted without authority when he procured Aboitiz One’s
services in outsourcing mail deliveries in Luzon?
SO ORDERED.
SUPREME COURT
Manila
SECOND DIVISION
Issue
Whether the procurement of the iPad units without conducting public bidding is
lawful?
SECOND DIVISION
PEREZ, J.:
The Facts
In 1986, Pozzolanic Australia won the public bidding for the purchase of the fly ash
generated by NPC's power plant in Batangas. Pozzolanic Australia then negotiated with
NPC for a long-term contract for the purchase of all fly ash to be produced by NPC's future
power plants. NPC accepted Pozzolanic Australia's offer and they entered into a long-term
contract, dated 20 October 1987, denominated as "Contract for the Purchase of Fly Ash of
Batangas Coal-Fired Thermal Power Plant Luzon" (the Batangas Contract). Under Article I
of the contract, NPC, referred to therein as the "CORPORATION," granted Pozzolanic
Australia, the "PURCHASER," a right of first refusal to purchase the fly ash generated by the
coalfired plants that may be put up by NPC in the future.
The specific provision of the contract states: PURCHASER has first option to
purchase Fly Ash under similar terms and conditions as herein contained from the second
unit of Batangas Coal-Fired Thermal Plant that the CORPORATION may construct.
PURCHASER may also exercise the right of first refusal to purchase fly ash from any new
coal-fired plants which will be put up by CORPORATION. In 1988, while the necessary
clearances and approvals were being obtained by Pozzolanic Australia in connection with
the operation of its fly ash business in the Philippines, its major stockholders decided that it
would be more advantageous for the company to organize a Philippine corporation and to
assign to such corporation Pozzolanic Australia's rights to the commercial use of fly ash in
the Philippines.
WHEREAS, NPC intends to bid out the long term contract for the Fly Ash that may
be produced by the Masinloc Coal Fired Thermal Power Plant subject to the second
paragraph of Article I of the original contract between the parties which was signed on 20
October 1987 giving PURCHASER the right of first refusal. In October 1999, the Sual Coal-
Fired Power Plant started providing electricity in the Luzon region. NPC thereafter caused to
be published in the Philippine Star and the Manila Bulletin an "Invitation to Pre-Qualify and to
Bid," inviting all interested buyers to pre-qualify for the purchase of fly ash from the Masinloc
and/or Sual Power Plants.
As a result, respondent sent letters to NPC calling its attention to respondent's right
of first refusal under the Batangas Contract. It also demanded that any tender documents to
be issued in connection with the bidding on the right to purchase the Masinloc and Sual
Plants' fly ash include notices informing prospective bidders of respondent's right of first
refusal.
In a letter dated 7 March 2000, NPC informed respondent that it had decided to defer
indefinitely the bidding on the right to purchase the Masinloc Plant's fly ash and to proceed
first with the bidding on the right to purchase the Sual Plant's fly ash. Thus, on 7 April 2000,
NPC released the tender documents for the bidding on the Sual Plant's fly ash, which tender
documents made no reference to respondent's right of first refusal.
This prompted respondent to file a complaint with the trial court praying that NPC be
ordered to allow Pozzolanic to exercise its right of first refusal by permitting it to match the
price and terms offered by the winning bidder and by awarding the contract for the purchase
of the Sual Plant's fly ash to Pozzolanic if it matches the price and terms offered by said
winning bidder.
This complaint was dismissed by the trial court on the ground of forum shopping, it
appearing that the Province of Zambales, et al. had previously filed a case against
respondent and NPC, claiming exclusive right to withdraw the fly ash of the Masinloc Plant.
Respondent appealed the order of dismissal to the Court of Appeals. CA affirmed the
decision of the trial court.
Issue
Whether or not the right of first refusal is invalid for being contrary to public policy?
Yes, the right of first refusal granted to respondent in the Batangas Contract
invalid for being contrary to public policy as the same violates the requirement of
competitive public bidding in the award of government contracts, for the following
reasons:
(1) The grant to respondent of the right of first refusal constitutes an unauthorized
provision in the contract that was entered into pursuant to the bidding.
By respondent's own admission, the right of first refusal granted to it was
"contractually bargained for and acquired from NPC after it won the public bidding for
the purchase of the fly ash produced by the Batangas Power Plant. This clearly
indicates that the right of first refusal was not included in the bid documents
presented to the other bidders who participated in the bidding. As a result, the
contract signed by NPC and respondent is different from that which was bidded out.
As pointed out by the Court in Agan, if the winning bidder is allowed to later
include or modify certain provisions in the contract awarded such that the contract is
altered in any material respect, then the essence of fair competition in the public
bidding is destroyed. A public bidding would be a farce if, after the contract is
awarded, the winning bidder may modify the contract and include provisions which
are favorable to it that were not previously made available to the other bidders. The
government cannot enter into a contract with the highest bidder and incorporate
substantial provisions beneficial to him, not included or contemplated in the terms
and specifications upon which the bids were invited.
The grant of the right of first refusal in this case did not only substantially
amend the terms of the contract bidded upon, so that resultantly, the other bidders
thereto were deprived of the terms and opportunities granted to respondent after it
won the public auction, it so altered the bid terms - the very admission by all parties
that the disposal of fly ash must be through public bidding - by effectively barring any
and all true biddings in the future. The grant of first refusal was a grant to respondent
of the right to buy fly ash in all coal-fired plants of NPC. Proceeding from the afore-
cited jurisprudence, the Batangas Contract is, consequently, a nullity.
(2) The right to buy fly ash precedes and is the basis of the right of first refusal,
and the consequent right cannot be acquired together with and at the same
time as the precedent right.
The right of first refusal has long been recognized, both legally and
jurisprudentially, as valid in our jurisdiction. It is significant to note, however, that in
those cases where the right of refusal is upheld by both law and jurisprudence, the
party in whose favor the right is granted has an interest on the object over which the
right of first refusal is to be exercised. In those instances, the grant of the right of first
refusal is a means to protect such interest.
In the case at bar, however, there is no basis whatsoever for the grant to
respondent of the right of first refusal with respect to the fly ash of NPC power plants
since the right to purchase at the time of bidding is that which is precisely the bidding
subject, not yet existent much more vested in respondent.
It is significant to note that, in the tender documents for the bidding of the fly
ash of the Masinloc Power Plant, NPC gave respondent the opportunity to top the
highest bid by fifteen percent (15%). Respondent protested this, however, as an
infringement upon its alleged right of first refusal to purchase the Masinloc fly ash, as
supposedly guaranteed by the Batangas Contract.
(3) The right of first refusal is against the public policy that contracts must be
awarded through public bidding.
The right of first refusal of respondent being invalid, it follows that it has no
binding effect. It does not create an obligation on the part of petitioner to
acknowledge the same. Neither does it confer a preferential right upon respondent to
the fly ash of NPC's power plants.
As adverted to above, the disposal of NPC power plants' fly ash is governed
by COA Circular Nos. 86-264 and 89-296.These circulars direct that public auction
shall be the primary mode of disposal of assets of the government and sale through
negotiation shall be resorted to only in case of failure of public auction. For failure to
abide by the requirement of a public bidding in the disposal of government assets,
this Court is left with no option but to likewise declare the Sual and Masinloc
Contracts null and void.
WHEREFORE, we GRANT the petition for review on certiorari. The Decision dated
30 April 2008 and Order dated 27 June 2008 of the Regional Trial Court of Quezon City,
Branch 96 in Civil Case No. Q-00-40731 are hereby REVERSED AND SET ASIDE. Further,
the Batangas, Sual and Masinloc Contracts are hereby declared NULL AND VOID for being
contrary to law and public policy. Petitioner is hereby ordered to conduct a bidding of the
right to purchase the fly ash produced by the Batangas, Masinloc and Sual Power Plants
within thirty (30) days from the finality of this Decision.
SO ORDERED.
SECOND DIVISION
PERLAS-BERNABE, J:
The Facts
At the time material to this case, Andaya was Acting Director of the National Printing
Office (NPO) while Atty. Banda was Chairman, Samson was Vice Chairman, and Sillona,
Lagumen, and Enriquez were Members of the Bids and Awards Committee (BAC).
On December 13, 2010, however, the BAC passed a Resolution stating that it
would resort to negotiated procurement for the following reasons: (a) the delay in the
elevator's repair would hamper the NPO's operations which will result in considerable losses
on the part of the government; and (b) the allocated budget for the elevator's repair must be
disbursed before the end of the fiscal year for it not to revert to the general fund. The
Resolution was approved by Andaya and the Notice of Award was thereafter issued to EPI,
having the lowest quotation in the amount of P665,000.00.
This prompted respondent Field Investigation Office (FIO) of the Ombudsman to file
a complaint against petitioners for Serious Dishonesty, Gross Neglect of Duty, Grave
Misconduct, and Conduct Prejudicial to the Interest of the Service, alleging that the BAC
failed to justify the recourse to negotiated procurement under emergency cases pursuant to
Section 53 (b) of Republic Act (RA) No. 9184 for the repair of an unserviceable elevator. The
FIO alleged that an unserviceable elevator did not pose any imminent danger to life or
property nor was immediate action necessary to prevent damage to or loss of life and
property, or to restore vital services, infrastructure facilities, and other public utilities. Further,
the contract was awarded to EPI despite the latter being a printing company and not a
contractor for elevator repair and maintenance. As for Andaya, the FIO added that he acted
with gross inexcusable negligence in allowing the BAC to adopt negotiated procurement
without complying with the formalities under RA 9184.
In defense, petitioners claimed that their resort to negotiated procurement was
justified as the elevator in question was used to transfer heavy rolls and pallets of paper, as
well as printed forms from one floor to another. Moreover, they believed in good faith that the
repair was urgent and necessary to restore public services and infrastructure facilities and
they had no intent to circumvent RA 9184 or to cause any damage to the government or the
NPO. Finally, they maintained that EPI is a qualified contractor, as the company's secondary
purpose is "to engage in general construction business."
Ombudsman Ruling
In a Decision dated June 27, 2016, the Ombudsman found petitioners guilty of
Gross Neglect of Duty and Grave Misconduct, and accordingly, dismissed them from
service. In ruling that petitioners were guilty of Grave Misconduct, the Ombudsman found
that they violated the rules of procurement under RA 9184 when they resorted to negotiated
procurement instead of conducting a public bidding, taking into account that the cost of the
contract was P665,000.00, which is beyond the threshold for alternative modes of
procurement. Likewise, the project was hastily awarded to EPI, a contractor engaged in
printing, not in elevator repair and services. Moreover, it observed that the public was not
duly notified of the award to EPI for failure to comply with the required publication of the
procurement in the Philippine Government Electronic Procurement System.
Section 10, Article IV, in relation to Section 5, paragraphs (n) and (o), Article I of RA
9184, mandates that all acquisition of goods, consulting services, and the contracting for
infrastructure projects by any branch, department, office, agency, or instrumentality of the
government, including state universities and colleges, government-owned and/or -controlled
corporations, government financial institutions, and local government units shall be done
through competitive bidding. This is in consonance with the law's policy and principle of
promoting transparency in the procurement process, implementation of procurement
contracts, and competitiveness by extending equal opportunity to enable private contracting
parties who are eligible and qualified to participate in public bidding.
Public bidding is the primary process to procure goods and services for the
government. A competitive public bidding aims to protect public interest by giving it the best
possible advantages through open competition. It is precisely the mechanism that enables
the government agency to avoid or preclude anomalies in the execution of public contracts.
Strict observance of the rules, regulations, and guidelines of the bidding process is the only
safeguard to a fair, honest, and competitive public bidding.
In this case, competitive public bidding was dispensed with by petitioners for
the checkup, repair, and supply parts of Elevator II in the NPO building. However, as
correctly found by the Ombudsman and affirmed by the CA, petitioners' resort to
negotiated procurement as an alternative mode of procurement was not proper and
justified. Their reasons do not satisfy any of the highly exceptional
circumstances enumerated in Section 53 as above-quoted, particularly
paragraph (b), as records are bereft of evidence to show that the immediate
repair of the subject elevator was necessary to prevent damage to or loss of
life or property, or to restore vital public services, infrastructure facilities, and
other public utilities.
First, the alleged urgency of the repair of the subject elevator is belied by the fact that
the purchase request therefor was made only in September 2010, whereas it supposedly
became non-operational in July 2010. The delay in the submission of the purchase request
is inconsistent with the immediate nature of the service required and negates the existence
of an emergency.
Second, the elevator, which was merely used for carrying loads of paper and other
printed materials, is not indispensable to the NPO's mandate to provide printing services for
the government. To be sure, the NPO can continue with its day-to-day operations even
without the elevator, albeit, perhaps, with some inconvenience. Such inconvenience,
however, does not warrant a complete disregard of the required public bidding.
Finally, the adoption of negotiated procurement in order to utilize the funds allocated
for the repair and service of the elevator before the end of the fiscal year lest the amount
revert to the general fund is likewise devoid of legal justification. Clearly, therefore,
petitioners utterly failed to justify the negotiated procurement in this case.
All told, substantial evidence exists to hold petitioners guilty for Grave Misconduct
and Gross Neglect of Duty.
The petitioners grossly disregarded the law and were remiss in their duties in strictly
observing the directives of RA 9184, which resulted in undue benefits to EPI. Such gross
disregard of the law is so blatant and palpable that the same amounts to a willful intent to
subvert the clear policy of the law for transparency and accountability in government
contracts, thereby warranting the penalty of dismissal from the service pursuant to Section
46, Rule 10 of the Revised Rules on Administrative Cases in the Civil Service, with
accessory penalties. Considering that both Grave Misconduct and Gross Neglect of Duty are
of similar gravity and that both are punished by dismissal under the pertinent civil service
laws and rules applicable to petitioners, they are thus punished with the said ultimate
penalty, together with the attending disabilities.
Verily, it must be stressed that serious offenses, such as Grave Misconduct and
Gross Neglect of Duty, have always been and should remain anathema in the civil service.
They inevitably reflect on the fitness of a civil servant to continue in office. When an officer or
employee is disciplined, the object sought is not the punishment of such officer or employee,
but the improvement of public service and the preservation of the public's faith and
confidence in the government. Indeed, public office is a public trust, and public officers and
employees must at all times be accountable to the people, serve them with utmost
responsibility, integrity, loyalty and efficiency, act with patriotism and justice, and lead
modest lives. This high constitutional standard of conduct is not intended to be mere
rhetoric and taken lightly as those in the public service are enjoined to fully comply with this
standard or run the risk of facing administrative sanctions ranging from reprimand to the
extreme penalty of dismissal from the service, as in this case.
WHEREFORE, the petition is DENIED. The Decision dated August 31, 2017 and the
Resolution dated February 23, 2018 rendered by the Court of Appeals in CA-G.R. SP No.
149420 are AFFIRMED.
SO ORDERED.
Republic of the Philippines
SUPREME COURT
Manila
THIRD DIVISION
Issue
Whether or not the Sandiganbayan gravely abused its discretion amounting to lack
or want of jurisdiction when it denied petitioner’s demurrer to evidence?
SO ORDERED.
SUPREME COURT
Manila
THIRD DIVISION
The Facts
On November 20, 2007, the Department of Public Works and Highways (DPWH)
Region VI Director, Rolando M. Asis , submitted the approved Program of Works and
Estimates for the proposed Asphalt Overlay Project in Iloilo City to the DPWH Secretary. In
the program, it was estimated that the amount of P54,500,000.00 is necessary to
implement the project, which intends to repair about 2.4 kilometers of the Iloilo-Jaro
Diversion Road, starting from the Iloilo-Antique Road up to Dungon Bridge.
Former Iloilo City Mayor Jerry P. Treñas requested Director Asis to immediately
implement the project, in time for the upcoming Dinagyang Festival. Director Asis, thus,
requested then DPWH Secretary Ebdane for clearance to implement the project through
negotiated procurement. He reasoned that the project is urgent because this was the
primary route for the Dinagyang Festival, and there is a need to further promote tourism in
the region. On November 29, 2007, Secretary Ebdane approved the request.
On January 2, 2008, the BAC unanimously approved an unnumbered Resolution,
which recommended the direct negotiation of the contract for the Asphalt Overlay Project
to International Builders' Corporation (IBC). Director Asis approved the Resolution. Thus,
BAC Chairman Berna sent an invitation to the President of IBC, requesting them to submit
a quotation for the project, together with the other bid requirements. IBC's bid offer was
opened and negotiated at the DPWH Regional Office. The following day, the BAC
unanimously approved another unnumbered Resolution recommending the award of the
project to IBC, with an Approved Budget for the Contract in the amount of
P54,308,803.44.
Director Asis informed IBC of BAC's recommendation, with the caveat that the
Notice to Proceed cannot be issued until the funds to cover the contract cost are released.
In light of the unavailability of funds, Director Asis asked the IBC President whether they
were willing to take the risk of proceeding with the project, pending the release of an
appropriation. He likewise guaranteed to process the payment as soon as the funds for the
project are released. In response, the IBC President agreed to take on the risk, and
committed to immediately proceed with the implementation of the Asphalt Overlay Project.
Meanwhile, the Assistant Ombudsman for Visayas sent a letter to the Commission
on Audit (COA) Region VI, requesting the conduct of a special audit examination on the
Asphalt Overlay Project. The State Auditor reported that there were no entries in the books
showing that allotments were received, and that obligation requests were made for the
implementation of the project. Moreover, the DPWH Region VI informed the State Auditor
that there was no project contract submitted for certification as to the availability of
allotments and availability of funds.
Subsequently, the OMB Region VI Field Investigation Office (FIO) filed their
Complaint-Affidavit, charging the respondents and several other officials and employees of
the DPWH Region VI with violating Republic Act (R.A.) No. 9184 and R.A. No. 3019, and
holding them liable for Grave Misconduct. It was specifically alleged that the application of
negotiated procurement was unwarranted under the circumstances. There was also no
available appropriation at the time of the execution of the contract for the Asphalt Overlay
Project.
In light of their participation in the procurement and implementation of the Asphalt
Overlay Project, the OMB Region VI FIO alleged that the respondents were guilty of Grave
Misconduct for patently intending to violate or disregard the procurement law, and for
violating Section 3(e) of R.A. No. 3019.
Ombudsman’s Ruling
In a Joint Resolution28 dated October 6, 2015, the OMB found probable cause to
charge the respondents with a violation of Section 3(e) of R.A. No. 3019. The OMB,
likewise, found all of them guilty of Grave Misconduct, and meted the penalty of dismissal
from the service, thus:
WHEREFORE, let the attached Information for Violation of Section 3(e) of RA No.
3019 be FILED against respondents Rolando M. Asis, Berna C. Coca, Luvisminda H.
Narciso, Fernando S. Tuares, Danilo M. Peroy and Marilyn H. Celiz.
Respondents Rolando M. Asis, Berna C. Coca, Luvisminda H. Narciso, Fernando
S. Tuares, Danilo M. Peroy and Marilyn H. Celiz are found GUILTY OF GRAVE
MISCONDUCT and hereby meted the penalty of DISMISSAL from the service, which shall
carry with it cancellation of eligibility, forfeiture of retirement benefits and the perpetual
disqualification from re-employment in the government service.
Court of Appeals Ruling
In the event that the penalty of dismissal can no longer be imposed due to their
separation from the service, it shall be converted into FINE amounting to respondents'
salary for ONE (1) YEAR, payable to the Office of the Ombudsman, and may be deducted
from their accrued leave credits or any receivable from their office. It is understood,
however, that the accessory penalties of forfeiture of retirement benefits, cancellation of
eligibility and perpetual disqualification to hold public office shall still be applied.
No, the respondents violated R.A. No. 9184 and P.D. No. 1445 in the
procurement of the Asphalt Overlay Project.
Generally, all government procurement must be done through competitive
bidding.44 Alternative methods of procurement, however, are available under the
conditions provided in R.A. No. 9184. For infrastructure projects in particular, the only
alternative mode is negotiated procurement.
In negotiated procurement, the procuring entity directly negotiates the contract with
a technically, legally and financially capable supplier, contractor or consultant. It may be
resorted to in the following cases:
(a) when there has been a failure of public bidding for the second time;
(b) when there is imminent danger to life or property during a state of calamity, or
when time is of the essence arising from natural or man-made calamities or other causes
where immediate action is necessary to prevent damage or loss of life or property, or to
restore vital public services, infrastructure facilities and other public utilities;
(c) in take-over of contracts that were rescinded or terminated for cause and
immediate action is necessary;
(d) where the contract is adjacent or contiguous to an on-going infrastructure
project, the original contract of which was the result of a competitive bidding; or
(e) under other instances specified in the implementing rules and regulations of
R.A. No. 9184.
xxxx xxxx xxxx xxxx
As aptly held by the CA, there must be an immediate and compelling need to justify
negotiated procurement other than that provided by the respondents. The requirement of
urgency is qualified under the law as "arising from natural or man-made calamities or other
causes where immediate action is necessary to prevent damage to or loss of life or
property. As such, it does not cover situations outside this qualification.
Section 53(b), Article XVI of R.A. No. 9184 evidently does not contemplate a yearly
occasion and the promotion of tourism to justify resort to negotiated procurement. Since
the Dinagyang Festival is an annual event that has always been scheduled to take place in
the middle of January, there was plenty of time for the preparation of the necessary
infrastructure. Furthermore, aside from the promotion of tourism, there was no showing
that the repairs were necessitated by a calamity, that there was imminent danger to life or
property, or that there was a loss of vital public services and utilities.
Sufficient appropriation is also required before the government enters into a
contract. While Sections 85 and 86 of the Government Auditing Code requires an
appropriation prior to the execution of the contract, the enactment of R.A. No. 9184
modified this requirement by requiring the availability of funds upon the commencement of
the procurement process.
The requirement of availability of funds before the execution of a government
contract, however, has been modified by R.A. No. 9184. The said law presents a novel
policy which requires, not only the sufficiency of funds at the time of the signing of
the contract, but also upon the commencement of the procurement process.
Clearly, the respondents and the other DPWH officials intended to circumvent the
requirement that there should be prior appropriation. The execution of the contract with
IBC, as well as the issuance of the Notice of Award, was delayed until such time that the
SARO was issued. By the time the funds for the project were released, the award of the
contract to IBC was already a foregone conclusion. IBC had commenced construction
activities as early as January 10, 2008, almost a year prior to the execution of the contract
for the project.
WHEREFORE, premises considered, the present petition is GRANTED. The
Decision dated September 15, 2017 and the Resolution dated December 11, 2017 of the
Court of Appeals in CA-G.R. CEB-SP. No. 10438 are hereby REVERSED and SET
ASIDE. A new judgment is entered finding respondents Marilyn H. Celiz and Luvisminda
H. Narciso GUILTY of GRAVE MISCONDUCT. As such, they are DISMISSED from the
government service with all the accessory penalties of cancellation of eligibility, forfeiture
of leave credits and retirement benefits, and disqualification for re-employment in the
government service.
SO ORDERED.
SUPREME COURT
Manila
SECOND DIVISION
MENDOZA, J.:
The Facts
First, the contract completion dates were unjustifiably revised several times to
delay the project;
Ombudsman’s Ruling
In its decision, dated February 28, 2005, the Ombudsman held that the
respondents committed grave misconduct. On the issue of improper extension of contract
completion, it stated that the "Time Suspension Orders/Reports" of Caligan prevailed over
the bare allegations of Cabana. Similarly, on the issue of subcontracting, the Ombudsman
held that it needed more than mere presence of heavy equipment of Timberland
Construction to conclude that Roma Construction indeed had the project illegally
subcontracted.
On the issue of the solid rock excavation under Item No. 102 (3) of the project
contract, however, the Ombudsman found that there was manifest irregularity. Because of
Change Order No. 1, the solid rock excavation with a volume of 15,275.50 cu. m. costing
P6,248,443.28, in the original project contract, was increased to 28,404.36 cu. m. at
P11,618,803.46. Caligan even testified before the Sangguniang Panlalawigan of Iloilo on
July 1, 2002 that the 28,404.38 cu. m. of solid rocks were actually excavated from the
mountainside and pushed down the ravine as excess materials.
The respondents moved for reconsideration but their motion was denied by the
Ombudsman-Visayas in its April 21, 2005 order, which was approved by Acting
Ombudsman Orlando C. Casimiro on March 6, 2008.
Aggrieved, the respondents filed a petition for review under Rule 43 of the Rules of
Court before the CA.
In its assailed November 23, 2011 Decision, the CA granted the petition. It
reversed and set aside the Ombudsman's finding of administrative liability against the
respondents. The CA was of the view that the evidence presented to prove the
respondents' culpability for grave misconduct was insufficient. It found that the
Ombudsman erroneously concluded that P11,618,803.46, the amount allotted for
28,404.38 cu. m. of rock excavation under Change Order No. 1, was the actual amount
expended, when Change Order No. 2 decreased the volume to 16,518.00 cu. m. costing
P6,738,894.23. The CA further stated that Change Order No. 2 should not be considered
as a mere afterthought absent proof that it was issued to circumvent the law. It held that "
[u]nless it can be shown cogently and clearly that Change Order No. 2 was issued to
circumvent the law, [it] will always uphold the presumption of regularity in the performance
of official functions, and authenticity of official documents."
The Ombudsman filed its motion for reconsideration, but it was denied by the CA in
the assailed September 27, 2012 Resolution. Hence, this petition.
Issue
The government allotted a portion of the public funds for the blasting activities and,
yet, the respondents failed to faithfully apply those funds for its intended purpose. Such
omission without any justification cannot be dismissed. If the Court were to overlook this
questionable incident, then it would set a perilous precedent that detailed estimates for
government construction projects could be treated as mere scraps of paper. It defeats the
purpose of properly delineating the cost of the project for greater accountability.
Several circumstances demonstrate that Change Order No. 2 was indeed issued
as a mere afterthought, following the July 2002 investigation of the Sangguniang
Panlalawigan of Iloilo. First, Caligan during the investigation, only mentioned Change
Order No. 1 and blasting as the method for solid rock excavation. As the Ombudsman
correctly observed, Caligan could have then easily mentioned Change Order No. 2 to
remove the clouds of doubt surrounding the project.
Second, Change Order No. 2 did not contain the required detailed estimate of the
unit cost of the project. Notably, unlike Change Order No. 1 which was issued after an "as-
staked survey," Change Order No. 2 simply emerged without any technical survey therein.
Third, the undated Change Order No. 2 was forwarded to the office of respondent
Agustino only on July 19, 2002, after the investigation of the Sangguniang Panlalawigan.
Surprisingly, even the DPWH itself, through its own Fact-Finding Committee, which was
tasked to conduct its investigation on the incident of irregularities over the project, never
mentioned Change Order No. 2.
The Court holds all the respondents administratively liable for grave misconduct. As
stated in the Ombudsman decision, Caligan and Edward Canastillo had direct knowledge
of the day-to-day activities in the project site, they being the acting assistant head and
acting head of the Iloilo Sub-Engineering District, respectively. Being in the frontline, they
had actual knowledge that there were no blasting activities of that magnitude in the area.
Rudy Canastillo and Agustino did not have a direct hand in the implementation of
the project, but the questionable change orders were recommended and approved by
them. Following the IRR of P.D. No. 1594 Agustino, as Regional Director, did not only
approve the change orders, but also sent his technical staff to conduct an on-the-spot
investigation to verify the need for the work to be prosecuted.This should have allowed him
to discover the irregularities in the project. The IRR would also indicate that the change
order was recommended for approval by Rudy Canastillo, as Assistant Regional Director,
and that he was empowered to review and evaluate the change orders. Yet, he kept silent
on the anomalies of the project. Their deliberate failure to prevent the questionable
occurrences in the implementation of the project indicated that they had knowledge of the
misdeeds and were in conspiracy with Caligan and Edward Canastillo.
WHEREFORE, the petition is GRANTED. The November 23, 2011 Decision and
the September 27, 2012 Resolution of the Court of Appeals in CA-G.R. SP No. 03526 are
REVERSED and SET ASIDE. The Decision, dated February 28, 2005, and the Order,
dated April 21, 2005, of the Office of the Ombudsman in Administrative Case No. OMB-V-
A-03-0204-D, finding Wilfredo Agustino, Rudy Canastillo, Edward G. Canastillo and Cecil
C. Caligan GUILTY of GRAVE MISCONDUCT and ordering their DISMISSAL from
government service, are hereby REINSTATED. The respondents are also perpetually
disqualified for reemployment in the government service.