Professional Documents
Culture Documents
Show Files
Show Files
Show Files
Technical Specification
1|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
Table of content
II part - current situation at SCMS Central System of Substation “Navtlugi 220 kV”................................... 7
IV part - Technical specifications for preparation “Navtlugi 220kv” substation control and monitoring
system.………............................................................................................................................................... 20
2|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
Name of Project: Upgrade of SS Navtlugi-220 Station Control and Monitoring System (SCMS)
Scope of Project: The substation Navtlugi 220 kV shall be equipped with a fully redundant substation
control and monitoring system (SCMS).
The scope of supply and work for the central system is shown in the table below:
3|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
Payment terms:
After installation of equipment.
After SCMS tests (based of SAT signed report).
After avaılabılıty Test (AvT)
Delivery dates:
Equipment must be delivered maximum in 2 months after signing the contract.
The project must be finished maximum in 6 months after signing the contract. Detailed schedule must
be agreed with GSE.
Documentation to be submitted:
Information about company (document from official business register of the Public Registry of Georgia)
Contender must submit minimum 2 coworkers certificates or documentations confirming their
experience in corresponding field.
4|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
5|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
6|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
7|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
8|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
9|Page
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
The full system of HMI WorkStation with its backup system must be arranged. Real time
controlling and monitoring software must be installed. The working backup must be uploaded and
tested fully.
It is critically necessary to change and update, equipment and software for proper functioning
substation control and monitoring system HMI WorkStation.
Current situation of Substation ‘Navtlugi 220kv” is critically dangerous and needs updating and
changing as software as hardware parts. A new HMI WorkStation place must be arranged, as well as
GATEWAY system. Current relay software versions must be checked and updated if necessary. All
current and new signals must be integrated and tested in new system. Important part is that new
system must be installed and updated parallelly to the old control and monitoring system, and all
information must be transferred step by step.
Pretender must provide:
Complete set for fully functionalizing substation control and monitoring system HMI
WorkStation.
On provided computers must be installed maintenance software for substation control and
monitoring system.
Integration in SCMS system all 46 relays (including 7SD, SEL411 relays and new 7SA and REC650 relays).
On provided systems must be installed corresponding license with unlimited possibility of
adding new signals.
On job 5 days training of SCMS system configuration
On Request, As in GSE Substation mainly are implemented SICAM230 and Zenon, SEL
Architect, RTAC, Toolbox II Softwares and GSE engineers have good knowledge of them, If
new SCMS system Software will be other then above mentioned ones, supplier must provide
additional manufacturer Training for Configuration in SCMS System (In Georgia or Factory).
McAfee Application Control Software antivirus must be installed on both as main as backup
servers.
Contractor must provide equipment (GATEWAY) with reserve backup for information
transfer with central dispatching center.
Contractor must provide NAS equipment (Minimum 4TB Capacity) for archiving reports and
events.
Before installation following services must be provided on server:
Server Image for Restoration
Installed and configured McAfee antivirus.
The system should be scanned and provided with a report where no secondary vulnerabilities are detected.
The system must have latest security updates by the date of installation.
10 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
Redundant substation computers (SCMS servers) providing supervising and control functions, archiving
functions and engineering tools. The human machine interface (HMI) might also be implemented on these SCMS
servers.
• Audible alarm system
• Redundant communication gateway computers for the connection to the SCADA/EMS systems in NCC/BCC via
the Operational Telecommunication System (hybrid system based on optical Ethernet and Ethernet over SDH.
• Two workplace computers, connected to both SCMS servers (core computers), in case the HMI is not running
on the SCMS servers
• Redundant GPS time system (Master Clock) with IRIG-B or NTP time synchronization. ±100 ns average timing
accuracy.
• Engineering laptop (notebook) computer as Emergency HMI
NAS –Network Archiving System
11 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
12 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
The master clock shall be synchronized by a satellite receiver (GPS). While running without GPS signal
maximum time deviation shall be less than 50 ms per day. The master clock in Substation shall be battery buffered.
Data transmission between the devices on station and bay level shall take place via station bus, realized by
using fiber-optic cables, thereby guaranteeing disturbance free communication.
SCMS shall include the following main functional parts:
• Station Computer System
• Human Machine Interface (HMI) with process data base
• gateways for remote supervision and control through two control centers with parameterizable
interlocking of control authority
• master clock
• protection fault processing
• service, analysis and engineering system
• data exchange between the different system components via LAN
• collection of relevant data from the substation and distribution of data wherever needed
• bay and station level devices for control, monitoring and protection
• process interface parallel wired or connected by a process bus
15 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
2 Functional Requirements
All control and monitoring functions necessary for a secure and reliable operation of the Substation shall
be provided.
The following are the minimum functions required:
• acquisition of binary signals (single and double-pole indication)
• acquisition of analogue signals
• initiation and monitoring of execution of commands and set points to the process
• automatic chronological control of standard switching routines
• station and bay interlocking
• tap changer control of power transformers inclusive automatic voltage regulator AVR
• supervision of the entire Substation
• station control via operator workstations
• alarm handling
• sequence of event recording
• tagging
• analogue value processing
• display of trend values
• archiving display and evaluation of historical data
• fault indication
• disturbance analysis
16 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
17 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
18 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
19 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
20 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
21 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
3. Other Requirements
3.1 Engineering
The specific functionality and boundary conditions of the SCMS shall be adapted to the requirements which
are related to the particular voltage level and specific substation layout.
During the engineering phase, at least the following items are very important and shall be supplied for
approval by the Employer:
• general system architecture of the entire SCMS • functional design specification of SCMS, which describes
in detail the equipment and the functionalities • layouts of the displays at station level and bay level as single-line
diagram, event list, alarm list, etc. • lists of events and alarms (including their names) with the indication of the
particular signal to be sent (station event list, remote, etc.) • signal list for data transmission towards and from
the remote-control centers including mapping towards and from the individual addressing given by the higher
level two Control Centers and the applied standard telecommunication profile (IEC60870-5-104) • IT security risk
assessment according to IEC 62351 and the IEC 27000 group of standards including appropriate recommendations
for mitigation measures. The IT security measures applied shall be fully compliant with any requirement generated
from outside systems, like the SCADA system in the connected National Control Center.
3.2 SAT
3.2.1 General
The supplier shall submit a test specification for site acceptance tests (SAT) of the SCMS for approval. For the
individual devices applicable type test certificates shall be submitted.
The general philosophy shall be to deliver a SCMS to site only after it has been thoroughly tested and its
specified performance has been verified, as far as site conditions can be simulated in a test lab.
3.3 SAT requirements
All materials and equipment used in the Contract Works are subject to inspection by the Employer /
Engineer in order to determine whether the material and equipment comply with the required properties.
The Contractor shall at his own cost and expense execute shop and field tests of all materials and
equipment supplied by him or his Subcontractor required in accordance with the applicable IEC standards. This
shall not preclude the Employer’s/Engineer’s right to call for further tests if he considers them necessary.
All equipment and materials necessary for execution of the tests shall be furnished by the Contractor.
Measuring apparatus and their calibration certificates shall be subject to approval by the Employer/Engineer.
The Contractor shall submit to the Employer/Engineer for approval the test results showing conditions
of tests performed.
22 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
5. Documentation
The hardware and software documentation shall comprise but is not limited to the following: • list of drawings •
single line diagram • list of apparatus • test plan and specification of Site Acceptance Test (SAT) • product
manuals • operator’s manuals • Updated system architecture drawings. • Acceptance Test (SAT) report. •
Availability Test (AvT) report.
All system hard- and software documentation, the application hard- and software documentation and the
operating instructions shall be provided in English language. In addition, the operating instructions shall be
provided in Georgian language.
23 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
6. Availability Requirements for the Substation Control and Monitoring System (SCMS) and Trial
Operation
Availability Requirements for the Substation Control and Monitoring System (SCMS) is applicable
6.1 Guaranteed availabilities of the systems: • availability of Station Monitoring and Control System (Central
System and Substation LAN) 99.95% The SCMS shall have an availability of 99.95% which is equivalent to a
statistical outage time of 4.4 hours per year. System availability means in this case: • The substation can be
controlled from at least one operator workplace in the control – room and remotely from the NCC. • no loss of
information occurs • continuous archive management.
24 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
25 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
26 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
No. Description
1 General -
Manufacturer
Type / designation -
MTBF h >8760
MTTR h <12 h
Spare parts % 20
2 Station Bus
redundant star
connection to the P&C
Redundancy of station buses -
containers or two ring
topology
IEC 61850
Protocol -
MBit/
Transmission rate
s
3 Ethernet Switches
27 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
No. Description
Manufacturer -
Type -
Manufacturer -
Type -
CPU -
Working memory -
Hard disk -
RAID-System -
External memory -
Operating system -
28 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
No. Description
Manufacturer -
Type -
Quantity - 1
Manufacturer -
Type -
Operating system -
Software -
29 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
30 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
31 | P a g e
Project of SS Navtlugi-220
Georgia Station Control and Monitoring System (SCMS) Upgrade
32 | P a g e