PLAN PREPARATION PM

Air Plan Schedule MANPOWER Spare part


Group Machines Task Duration (h) PIC Tools Material Remark Status
Code PM TBM IMP Piece Work Contractor helper Part Stock Order
A. Cement packaging Belt conveying
P2J41 - Check and test safety device Belt conveyor (RS,SS,SW1,SW2)
- Cleaning and tightning local panel
- Check operation and interlocking
P2J42 - Check and test safety device Belt conveyor (RS,SS,SW1,SW2) 8 Nizar v Ready Ready Not Ready v
- Cleaning and tightning local panel
- check operation and interlocking
P2J43 - Check and test safety device Belt conveyor (RS,SS,SW1,SW2) 2 v Ready Ready Ready v
- Cleaning and tightning local panel
- check operation and interlocking 4 Ready Ready Not ready v

B. Bag filter and Cement conveying P2P07 - Check purging system of bagfilter Ready Ready N/A
- Check and cleaning rotary airlock motor 8 Dikdik
- Cleaning, tighten panel local 2 Ready Ready Ready
- Check local operation and interloacking of bagfilter 4 Ready Ready Not Ready
P2P08 - Cleaning and tigtning motor fan 4 v Ready N/A N/A
- Check ampere and voltage load by run local Ready Ready N/A
P2S27 - Check operation and interlocking vibrating screen 8 Fattah v Ready Ready Ready
- Check function limit P2L28LS1 and P2L28W1 2
P2J26 - Cleaning and tightning terminal motor bucket elevator 4
- Check Function Speed Switch (SS) and Level switch (LS) 4 Ready Ready
- Check opertion and interlocking Ready Ready
P2J40 - Check function speed switch (SS) of Screw conveyor 8 Imam Ready Ready
- Cleaning and tightning terminal motor 2
P2P09 - Check purging system of bagfilter 4 Ready Ready Not ready
- Check and cleaning rotary airlock motor 4 Ready Ready Not ready
- Cleaning, tighten panel local Ready Ready Not Ready
- Check local operation and interloacking of bagfilter 4 Arian Ready Ready Not Ready
P2P20 - Cleaning and tigtning motor fan 2 v v Ready Ready Ready
- Check ampere and voltage load by run local 4 v Ready Ready Ready
4
C. Cement Silo P2P03 - Check purging system of bagfilter 4 v Ready Ready Ready
- Check and cleaning rotary airlock motor 4
- Cleaning, tighten panel local 2
- Check local operation and interloacking of bagfilter v Ready Ready Ready
P2P04 - Cleaning and tigtning motor fan 4 Nizar
- Check ampere and voltage load by run local 2 Ready Ready Ready
P2J061b - Check operation and interlocking valve 4 Ready Ready
- Calibration valve 4 Ready Ready
P2J06 - Check operation and interlocking Root Blower 4 Ready Ready
- Check ampere and voltage load by run local
P2J171b - Check operation and interlocking valve 4
- Calibration valve 2 Ready Ready Ready
P2J17 - Check operation and interlocking Root Blower Ready Ready Not Rady
- Check ampere and voltage load by run local 4 Dikdik Ready Ready Ready
2 Ready Ready Not ready
D. Rotary Packer and Bag Placer 1 P2N31 - Cleaning and tighning local panel Roto Packer 4 Ready Ready Ready
- Calibration weighing bag 4 Ready Ready Ready
- Check operation and interlocking Roto packer 4
- Check Carbon brush 2
P2N32 - Check operation and interlocking Radimat
- Cleaning and tighning local panel Radimat 4 Imam
P2J33 - Check operation and interlocking 2
4
E. Palletizer loading channel - Check operation and interlocking bag transport 4
- Cleaning local panel 4
- Check safety device (RS,SS)

F. Jumbo Bag Loading channel - Check operation and interlocking 4 Fattah


- Cleaning local panel 4
- Calibration weighing zero span

G Truck scale Rawmat and Packing - Check operation of weighing system


- Calibration weighing zero span

G. Electrical Room Packing - Cleaning + tighten MCC, panel DCS 1d RTN Ready Ready
- Cleaning Change filter transformer 8h RTN Ready Ready