Hitech City Srinivas Centering Agreement
Hitech City Srinivas Centering Agreement
1. Footing Measurement :
Mode of Payment :
1. Mobilization advance Rs.150000/- shall be paid after placing the centering material at site
and it will be deducted proportionately in each running bill.
2. Retention amount Rs.25000/- on each bill against after completion of each slab.
3. First bill shall be made against the works executed after completion of plinth beams.
4. Payment for retaining wall shall be release after completion itself.
5. Payment shall be released after completion of each slab.
Note : Incase of any urgency labour payment shall be released against works.