Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

RISK SCORE CALCULATOR Project Name: xxx


Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls RA Ref No.: xxx
What w ould be the
CONSEQUENCE Frequent/Almost certain (5) Rarely (1) Can the hazard be Elim inated or removed
Continuous or will happen
Often (4) Likely (3) Possible (2) Less than once every 5 RA compilation
of an occurrence be? 6 to 12 times a year 1 to 5 times a year Once every 5 years from the w ork place? Review date:
frequently years Date:
Catastrophic (5) Can the product or process be substituted for Date:
High 25 High 20 High 15 Medium 10 Medium 5
Multiple Fatalities a less hazardous alternative?
Serious (4) Can the hazard be engineered aw ay w ith
High 20 High 16 High 12 Medium 8 Low 4 Compiled by:
Class 1 single fatality guards or barriers?
Moderate (3)
Can Adm inistration Controls be adopted
Class2 (AWI or LTI) or Class 1 High 15 High 12 Medium 9 Medium 6 Low 3 Reviewed by:
Permanently disabling effects
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work Medium 10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipm ent & Approved by:
restrictions. MTI Clothing be w orn to safe guard against
Insignificant (1) hazards?
FAI
Medium 10 Medium 4 Low 3 Low 2 Low 1
Overall Task Details Relevant Applicable MAS:
Additional Training required: NOC’s Required for task:
Initial Project Site cabin installation and erection, including lifting operations,  00246 – Excavations;
blockwork, painting and welfare  01413 – Underground services; Temporary Works Coordinator to be designated Municipality
 00940 – Plant Operators;
 00939 – CoSHH;
 00238 – Portable electric tools;
 00237 – Temporary Electrics;
 00241 – Fire Fighting equipment.

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
i. Adhere to requirements in Project Safety Plan;
 Pedestrian conflict with adjacent live
ii. Ensure that where required a flagman is used to control site personnel and
traffic routes;
vehicles crossing traffic routes;
 Traffic incident due to incorrect traffic iii. Ensure that general road surfaces at plant/pedestrian crossings and
management; adjacent to site works are maintained, and free from material and debris ;
Working adjacent to Workers not
Working the vicinity of 9 iv. Work area adjacent to live traffic shall be protected with hard barrier All supervision to monitor
1 public areas  Uncontrolled entry by unauthorized 3 3 complying with LOW
public areas; MED protection to standards and specific to traffic speeds; operation;
personnel into ATC work areas; controls
v. Priority ensured regarding the protection of public pedestrians and cyclists, Regular topic in TBT’s
 Objects falling from site plant onto including overhead protection where required;
public and site roads; vi. Where works are undertaken at night, ensure that the works areas are well
provided with adequate lighting systems;
vii. Workers instructed on requirements at induction.

i. Only competent and authorised personnel with licence for the category of
 Unauthorised use of untrained or plant they are operating allowed to operate the machinery, reviewed by
unlicensed operators; logistics before commencing on site;
 Use of un-certificated plant and ii. All plant and equipment shall be Third Party Certificated by a Municipality
 Use of plant – approved assessor; Equipment to be well
equipment;
Vehicles/Plant excavators, graders, iii. Heavy equipment shall be equipped with audible reversing alarm; maintained and inspected
Machine
Equipment movements telehandlers etc.;  Striking against mobile and/or fixed 16
iv. A flagman to be present to signal reversing vehicles , reversing to be
frequently as per
2 4 4 breakdown manufacturer’s LOW
Groundworks / objects/vehicles; HIGH avoided where practicable;
 Use of flat-bed recommendations
excavations  Collision of plant; v. All plant / vehicles to be controlled by banks man;
delivery vehicles;
vi. Plant to be parked only in designated area, parking brake on, keys Hydraulic fluid spill
 Collision with operatives, including
removed with working parts lowered;
other contractors – high risk of
serious injury; vii. Protected access route(s) for pedestrians to be maintained where required;
viii. Effective Traffic Management System (TMS) to be set up and monitored

Page 1 of 6 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
i. Temporary Works Coordinator / Construction Team to ensure Permit to
Excavate has been issued, communicated and signed by personnel prior
to any excavation work;
ii. Excavation safety buffer, protection, design and traffic signs to be to ATC
Minimum Acceptable Standard, RTA Manual Chapter 3 requirements (as
applicable) and DM Code of Practice -Section 9;
iii. Any exposed services to be protected and adequately supported to avoid
damage; Any unidentified services discovered to be immediately
communicated to management and work stopped;
 Damage to exposed existing live iv. All spoil to be maintained at least 2m from excavation;
 Excavation in underground services; v. Trench boxes to be used where practicable, backfilled behind;
working areas with
live traffic  Trench/excavation collapse; vi. All shoring, trench sheet supports etc. to be as per approved design, Emergency services called,
movements and following correct working procedures; Vehicle entering area cleared
pedestrians;  Falling/slipping into trenches; vii. Temporary Works Coordinator to ensure excavation design adhered to at excavation
all times;
Excavation in site area  Overturning of Truck / machinery into viii. Provide access ladders or ramps that suitable to the size and location of
 Unprotected excavation; 16 excavation. Access and egress ladders/steps to be secured, every 20m Excavation Secure area
3 4 4 LOW
Trial trenches, septic excavation area; High on long runs, or steps dug into soil, suitably supported; collapse
tank excavation etc.  Incident due to poor illumination;
ix. All excavations below 1.2m depth to be benched/battered back to MAS No removal of protection
 Excavation not to  Incident due to hazardous gas/fumes standards; barriers without prior approval
entering excavation; Incident due to
approved design; x. Excavation to be inspected daily with written inspection report weekly by from management.
 Collapse/damage of structures due to barrier removal
Temporary Works Supervisor; Daily briefings to workers on working in
undermining; excavations requirements by supervision;
 Difficulty rescuing injured or collapsed xi. Use of stop blocks, barriers and other suitable means of protection used
worker from deep excavation; to prevent vehicles entering excavations , warning tape is not to be used
as primary protection;
xii. Where practicable, access roads and pedestrian walkways to be
established away from excavations; Suitable and sufficient signage
introduced to excavations;
xiii. Backfilling of trenches/excavations to be undertaken as soon as possible
after verification or completion of works;
xi v. Excavation to be suitably illuminated during night times;
xv. No changes to excavations without re-submittal of design reviewed by
the TWC, NOC and Permits;

i. Edge protection to be erected at all work areas where the potential of


injury from fall exists, regardless of height but compulsory above 2m;
ii. Where due to the constraints of the work area fall protection is not
possible safety harness and lanyard are to be used and hooked off to a
 Injury from Fall from Heights;
secure anchor point;
 Injury from falling objects; iii. No shock lanyard to be used below 6m in height;
 Unsafe use of ladder; iv. All hand tools to be tied off when working at height;
Supervision to constantly
v. Ensure good standard of lighting, at night, for the work area;
 Not securing ladder properly; monitor workers;
Works at Height vi. Employees are to be given training in the use of ladders;
4  Working at height;  Unsuitable handhold at the top of 4 4
16 vii. Supervisors must ensure that all ladders are correctly angled, tied or Regular TBT’s & Trainings to Low
(Office cabin set-up)
the ladder or at landing; High footed. A suitable base must also be provided for ladders; be given on working Confined
Use of Ladders and
viii. A ladder must extend at least 1 meter above the landing unless a space;
stepladders  Using defective ladders;
suitable handhold is present;
 Inadequate planning of task to be ix. All defective ladders are to be removed off site once defect has been
completed; observed; Painting of ladders is prohibited;
x. Ladders should be checked before being put into use and on a regular
basis thereafter;
xi. Ladders only be used where the duration of the use is short and where
other methods cannot be used due to physical constraints on site;
xii. Do not stand on top three rungs of ladders.

Page 2 of 6 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
i. Logistics and construction team to ensure the correct type and size
of crane for the task is ordered;
 Unauthorised operation of the ii. Crane Supervisor / HSE Officer to undertake visual checks of
mobile crane; crane and operator certificates when arriving on site;
iii. All cranes to be Third Party Certificated by a DM approved inspector;
 Failure due to use of un-certificated
crane; iv. Minimum Acceptable Standard ATC/OHS/MAS/00941 to be adhered to;
v. Ensure crane is set up/rigged out correctly, is on firm level ground as per
 Overturning due to incorrect siting; crane plan with outriggers fully extended with spreader pads;
 Incident due to use of defective lifting vi. Ensure all lifting equipment have valid test certificate before use (6
gear / equipment; monthly 3 rd party insp.); Mechanical failure
Daily visual inspection and
Mobile Crane operation of crane;
vii. Method statements and risk assessments to be submitted and adhered to Pre- start check of the lifting
Use of Mobile Crane  Load striking moving and/or 16
5 4 4 for technical and/or non-routine lifts; Lift Plan to be completed prior to any Failure of lifting equipment & lifting gears to be Low
(Cabin/unit placing) stationary structures; High
lift taking place by crane supervisor and engineer; equipment during conducted.
 Crane collapse due to lifting loads viii. Riggers to undertake visual inspection of all lifting equipment daily; operation;
beyond SWL;
ix. Crane load indicator to be functioning, not to be overridden;
 Persons underneath load struck by x. Operator to adhere to crane safe working load limits , weight of load
materials; established before lifting;
 Load swinging / spinning xi. Lift controlled by designate rigger/banks man using approved hand
uncontrolled. signals;
xii. Tag lines shall be used to guide materials while lifting, 2 lines minimum
10m in length;
xiii. No personnel under loads, avoid over-sailing of personnel if practicable;
xi v. No lifts when wind speed exceeds 40kph;

i. All electricians to be suitably trained and experienced in the works;


ii. All wiring, connections and terminations inspected prior to connection to
live supply;
 Use of untrained electricians for iii. All wiring to follow colour coding standards; All fuses shall be to correct
electrical works; rating for electrical system or equipment;
iv. All junction boxes and sockets fixed securely to structure; All electrical
 Use of substandard electrical fixtures
junction boxes, sockets and fittings to be of suitable quality;
and fittings;
v. Insulation tape shall not be used for cable connections, correct junction
 Use of substandard connections; boxes to be used;
Temporary electrics -  Electrical 12 Rain entering
6 connections and  Non-adherence to colour coding of 3 4 vi. All earth connections shall be to standards; Remove from site Low
offices High DB’s
terminations wiring; vii. No cables shall trail on the floor; all securely clipped clear of damage or
posing a trip hazard;
 Incorrect earthing;
viii. Armoured cable used for cables set below ground; Armoured cable shall
 Tripping hazard; Damage to be correctly fitted and protected at junction boxes; All cables to be fed
unprotected cables; through securely fixed conduit;
ix. SMDB’s and DB’s used on site shall be sound, minimum IP54 rated, and
 Use of incorrectly rated fuses;
mounted on secure frames. Doors shall be lockable with correct warning
signage;
x. SMDB’s and DB’s shall be subject to regular inspections, any damaged
units removed from service;

i. Generators to be suitable size and capacity for the task, with maintenance
record;
 Generator fires; ii. Generators to have suitable earth rod connected at all time;
 Incident due to incorrect earthing; iii. Fire extinguishers to be located close to generators;
Site generators –
7 offices and site  Temporary supply  Fuel leakage – environmental risk; iv. Generators to be fitted with drip trays; Low
v. Fuel tanks to be bunded to 110% capacity, bunds to be sealed with
 Fuel storage;
delivery hoses retained inside bund;
 Noise; vi. Generators to be subject to regular inspection regime; Units monitored for
excessive exhaust fumes;

Page 3 of 6 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR

i. All electrical equipment, drills, grinders, cutters etc., to be tested,


inspected and sound, no damaged leads, connectors etc. To be
removed from service and quarantined if damaged;
ii. No guards to be removed from grinders or cutting equipment at any time;
iii. No handles shall be removed from electrical hand tools at any time;
iv. No electrical hand tools shall be adapted for use other than as designed
by the manufacturer;
 Electric shock due to damaged
v. Manufacturers power tool speed rating and cutting disc max speed to be
equipment;
matched to prevent bursting of wheels;
 Ear damage through excessive noise; vi. Grinding / cutting wheels shall only be changed by trained personnel;
 Use of untrained operators resulting vii. 110v tools to be used, unless exempted by risk assessment;
in incident; viii. Splitter boxes shall not be used for multiple connections;
 Electrical equipment ix. All Emergency Stop buttons to be present and working on all machinery, Sub-contractors will be
 Hand Arm Vibration injury through 9 Use of sub-
8 Office installation – grinders, cutters, 3 3 if not, machine will be quarantined until repaired to standards; informed at tender stage Low
prolonged use of equipment; Med contractors
drills etc. regarding site requirements
x. Equipment to be subject to regular electrical inspection regime, and
 Eye injury from flying debris; especially when returned to the stores ;
 Incident due to adapted/modified xi. Hot works permit required if cutting through steel, aluminum etc. where a
equipment; spark can be formed, fire extinguishers and fire watch in place as per
 incident due to machine guard permit requirement;
removal; xii. Ear protection and face mask to be worn by all workers in area, not just
tool operators. Eye protection to be worn;
xiii. When using vibrating tools such a jack-hammers etc., workers shall be
rotated to avoid Hand Arm Vibration. Refer to chart for recommended
use in 8hour period;
xi v. Workers shall be advised of the symptoms of HAV via briefings, toolbox
talks etc.;
xv. Works from ladders, see section 4;

i. Offices to be fitted with smoke detectors;


ii. Hose reels to be installed before personnel allowed to occupy, fire
pumps subject to inspection regime;
iii. Extinguishers to be placed in clear areas and subject to weekly
inspections;
iv. Emergency exits to be established and clearly marked with signage. To
be communicated at Induction;
v. Fire drills to be routinely undertaken, at least every 6 months;
Site offices  Poor emergency response vi. Muster points also clearly identified at induction, and kept clear of
procedures; storage areas; Muster points New muster points to be
16
9.  Fire 4 4 vii. Reverse parking deployed in parking areas; relocated due to effectively communicated to Low
Fire prevention and  Insufficient fire-fighting equipment; High site development site staff
emergency procedures viii. Designated smoking areas established, clear of the offices, with sand
 Poor housekeeping; trays and fire extinguishers;
ix. Waste skips to be at least 10m from offices, and not allowed to overflow.
Regular removal from site by licensed contractor;
x. Double stacked offices to be fitted with steel emergency exit stairs, at
least 2 at opposing ends;
xi. Flammable liquids, fuel, paints, chemicals shall not be stored in offices;
xii. No gas cylinders to be stored inside offices, but in area clear of offices in
signed cages;
xiii. Waste paper etc. to be removed daily and not allowed to build up;

Page 4 of 6 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
i. Walkway to be available for access around area. Rubbish to be cleared
regularly to prevent slip/trips;
ii. Do not lift over people with truck Hiab or fork lift; Hiab outriggers fully
extended and Third Party test available for review;
 Slip, trip or fall; iii. When handling components wear gloves, cover all exposed body parts;
iv. Follow correct Manual Handling procedures, use aids if available;
 Fall from ladder;
v. Stored materials to be laid on flat ground and not stacked more than 2
 Fall from trailer bed; pallets high;
 Blockwork (cabin vi. Access to trailer beds to be via footed ladder. When lifting do not climb
Loading out blocks /  Manual Handling strain injury to body;
10 supports, septic tank over trailer bed on unsecured materials; Low
materials in work area
walls etc.);  Cuts to exposed body parts; vii. Blocks to be stored on pallets if they are to be moved to another location.
Blocks to be positioned as close as possible to the work area;
 Hit by vehicle;
viii. Loading out can be done by stacking on pallet and placing with fork lift of
 Use of electrical cutting equipment; manually stacking individual blocks adjacent to the work station;
ix. Care must be taken to prevent overloading of any work platform with
blocks. Supervision will monitor loading out, ensuring blocks are loaded
safely, and distributed along the length of work platform, no point
loading;
x. Blocks will be stacked on platforms no more than 3 high and never
above the height of installed hand rails;

i.
Washing facilities shall be provided; Contact with the skin is to be
minimized and eye protection is to be worn, soaked overalls to be
removed immediately;
ii. Chemical resistant gloves shall be worn by anyone whose hands may
contact with the wet concrete mixes; Wellington boots to be worn when
pouring concrete;
iii. Guards to be in place over moving machinery, cover is to be kept over
hopper during operation and cleaning activities;
iv. Mortar is to be delivered from the mixer in a bucket or wheel barrow and
placed on spot boards next to the work station;
v. Used cement bags are to be disposed of as produced in designated area
and not left to blow around site;
 Use of cement mixer and mechanical vi. Glasses or goggles and dust mask may be required to be worn when
saw, entanglement or shock; loading the mixer to prevent cement particles from blowing into eyes,
mouth/nose;
 Splash from concrete into eyes; vii. Exposed body parts are to be kept covered, if cement/mortar splashes
 Dermatitis and skin burns to body; occur they are to be washed off immediately;
 Use of Concrete; viii. Cement mixer and mechanical block saw to be operated by trained
11 Blockwork.  Concrete soaking boots, overalls, and competent persons only, all guards present on machines always, Low
 Laying blocks; other clothing. electrical connections/wiring sound and undamaged;
 Vibration. - Cement burns; ix. At no time, will personnel use hands, shovels etc. inside rotating
machine, mixer will be isolated and stopped rotating before cleaning out
 Waste build up;
machine; Lay blocks at a comfortable level. Do not over reach or build
higher than the working platform either on the ground or from hop ups
and scaffold;
x. Blockwork will be laid with stability in mind, mortar will be allowed to cure
in sections before proceeding too high. Engineers and Supervision will
monitor blockwork tie rods are fitted and secured during the task as
specified;
xi. Block saw blades only to be changed by trained personnel;
xii. Wear PPE at all time especially nitrile gloves to protect hands from sharp
corners and cement burns. Wash any spillage off hands or clothing
immediately;
xiii. Care must be taken to prevent overloading of any work platform with
blocks. Supervision will monitor loading out, ensuring blocks are loaded
safely, and distributed along the length of work platform, no point
loading;

Page 5 of 6 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Initial Project Site Office Set-up
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
xi v. Clear up waste regularly, do not allow to build up;

i. Ensure that Material Safety Data Sheets (MSDS) are made available at
the site and users are aware of the hazards involved while using and
storing these chemicals;
CoSHH ii. Personnel must be issued with required P.P.E. and work to be carried out
 Fire; under supervision;
 Storing, handling and iii. Where practicable water based paints to be used;
using Hazardous  Environmental hazard;
iv. Thinners and cleaners to only be used in well ventilated areas;
materials (Paints and
 Exposure of chemicals with skin, risk v. Ensure all painting equipment is cleaned in designated area; Spill kits to be available in all
Painting task offices Thinners); of dermatitis etc. 9 vi. Area to be well ventilated; Paint or chemical areas where a risk exists.
12 etc. 3 3 Low
 Cleaning of Med spillage
 Accidental ingestion of hazardous vii. All wash-off to be stored in designated tanks for removal by licens ed Staff trained in environmental
equipment and contractor;
liquids; actions in the event of a spill
disposal of cleaning
agents and  Inhalation of harmful vapour; viii. Strict no smoking policy enforced;
hazardous liquids ix. Use of disposable equipment where practicable. Nitrile gloves to be worn;
 Poor disposal of waste;
x. Operatives to be instructed on identifying symptoms of skin disease and
related illness;
xi. All empty paint cans to be removed from site using designated skips;
All paint, thinner and other hazardous liquids to be stored in designated,
marked containers, plastic bottles etc. are not to be used;

 Inadequate welfare facilities; i. All welfare facilities will be established as per approved Worker Welfare
 Risk of poor health to workers; 9 Plan for the duration of the project;
13 Welfare facilities Workers on site requiring 3 3 Low
Welfare Med
 Non-compliance with requirements; ii. Welfare areas shall be kept clean at all time, regular housekeeping,
removal of waste and ablution cleaning daily;

Page 6 of 6 HSEQ -Rev-01(Aug-2018)

You might also like