JADWAL PELAKSANAAN

Periode Ke 1 Periode Ke 2 Periode Ke 3 Periode Ke 4 Periode Ke 5


NO URAIAN VOLUME SATUAN BOBOT KETERANGAN
10 Nov - 12 Nov 13 Nov - 19 Nov 20 Nov - 26 Nov 27 Nov - 3 Des 4 Des - 9 Des

PENGADAAN JASA PENAMBAHAN BENDUNGAN


LUMPUR COOLING TOWER DAN MATERIAL KAYU
SUPPORT UPK

100,00%
1 Jasa Penambahan Bendungan Basin 1,00 Lot 23,34% 2,33% 19,84% 1,17%
Dimensi Bendungan
Lebar : 30 cm
Tinggi : 40 cm
Panjang : 8 m

2 Material Kayu Support


1. Balok Kayu 30cm x 30cm x 100cm 22,00 Bh 37,61% 7,52% 30,09% 50,00%
2. Papan Kayu 4cm x 25cm x 4m 3,00 Bh 1,22% 0,24% 0,98%
3. Balok Kayu 6cm x 6cm x 4m 12,00 Bh 2,01% 0,40% 1,61%
4. Terpal Plastik 8m x 10m 2,00 Bh 2,51% 2,51%
5. Plat Shim 0,05mm x 25cm x 2m 3,00 Bh 5,39% 5,39%
6. Plat Shim 0,10mm x 25cm x 2m 3,00 Bh 4,13% 4,13%
7. Plat Shim 0,25mm x 25cm x 2m 3,00 Bh 6,46% 6,46%
8. Plat Shim 0,50mm x 25cm x 2m 2,00 Bh 4,55% 4,55%
9. Plat Shim 1,00mm x 25cm x 2m 2,00 Bh 2,25% 2,25%
10. Ventilator Fan 12" 2,00 Bh 10,53% 10,53% 0,00%

100,00% 2,33% 28,00% 59,13% 10,53% 0,00%


0,00% 2,33% 30,34% 89,47% 100,00% 100,00%

Palembang, 15 November 2023


CV. ASKARA WINNING

Rio Arrohim
Direktur