JOB SAFETY ANALYSIS

Installation of precast manholes JSA NO./ REVISION:JSA SGDP 02/ 00

JOB TITLE / AIM: JSA for Hydro Testing for domestic water piping system ( Hot and Cold pipe)
JSA DATE: 15/02/2013

Brief description about the job:


SGDP EPC10, UNIT77
Tools &Equipment to be used: Manpower: 1 Project Engineer, 1 Site Engineer, 1 Supervisor, 5 workers, I HSEO
Job Safety Analysis - Sequence of Job Steps:

JSA No: JOB TITLE: excavation for manhole and catch basin pit
Step Describe Job Step Hazards Hazard Controls
No

1. Preparation / mobilization  Permit to work obtain as per project procedure.


of equipment at site for Hydro testing equipment  All hydro testing shall be carried out as per approved method statement.
hydro testing. failure  All equipments and pressure gauze shall have valid third party
calibration/inspection certificate.
 Trained and competent operatives shall be engaged during testing.
 Appointment of competent person to execute the testing.
 Ensure all valves, joints, gauze are fixed securely.
 Adequate manpower deployed at site with adequate resource to rectify the
defects.
 Method statement and job safety analysis to be communicated to the workers
involved.
 First aid facility provided while hydro testing hot water supply system.
 HSE Coverage for hydro testing is required.
2. Hydro testing execution Incompetent operatives ,  Hydro Testing to be executed under strict compliance to material verification
pressure exceeding the record (MRV) and approved hydraulic calculation of the respective area.
capacity of the pipes,  Area has been cordon off, appropriate signage posted and others worker
Pipe failure leading to physical communicated about the testing activity.
injury
 .Ensure operatives wear appropriate personnel protective equipments while
carrying out hydro testing.
 Appropriate hand protection are used while handling hot surface for hot water
hydro testing
 Adequate illumination is provided inside the room for hydro testing.
 First aider with first aid facility shall be deployed for hot line hydro testing.
JSA No: JOB TITLE: excavation for manhole and catch basin pit
Step Describe Job Step Hazards Hazard Controls
No

 Authorised operatives shall be allowed to stand in safe distance from the


affected area.
 Movement of other contractor shall be restricted by deploying stand bye person
from the working party.
 Tighting, Repairing loosening of bolts, nuts, flange and other fittings shall not be
carried out until pipe has been de-pressured by drain out.
 Electrical cable to be taken care to avoid coming in contact with water.
 Any spillage shall be clean up immediately.

3. Use of working platform for Inadequate working platform  Only scaffolds inspected, tagged shall be used for repair works.
rectification.  All operatives shall wear full body harness, with harness hooked.
 Mobile scaffolds safe work practices shall be implemented.
 Closed supervision for the activity.

4. Restoration of site Unintentional exposed to over  Restore work area after completion of testing.
pressured pipe, Hot Surface  Hot surface shall not leave unattended until normal temperature is reached for
hot pipe hydro testing.
 Area to be made safe and Permit to be closed

Site Engineer John Philip

MEP Coordinator Joseph Antony

Testing Supervisor Kareem

HSE Engineer

HSE Manager

Construction manager